EP3527752A1 - Construction method for constructing towers - Google Patents
Construction method for constructing towers Download PDFInfo
- Publication number
- EP3527752A1 EP3527752A1 EP19382077.6A EP19382077A EP3527752A1 EP 3527752 A1 EP3527752 A1 EP 3527752A1 EP 19382077 A EP19382077 A EP 19382077A EP 3527752 A1 EP3527752 A1 EP 3527752A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- profiles
- tower
- pillars
- foundations
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000010276 construction Methods 0.000 title claims abstract description 11
- 230000008878 coupling Effects 0.000 claims abstract description 11
- 238000010168 coupling process Methods 0.000 claims abstract description 11
- 238000005859 coupling reaction Methods 0.000 claims abstract description 11
- 238000000034 method Methods 0.000 claims abstract description 11
- 230000002787 reinforcement Effects 0.000 claims abstract description 10
- 238000005553 drilling Methods 0.000 description 2
- 206010073306 Exposure to radiation Diseases 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/04—Structures made of specified materials of wood
- E04H12/06—Truss-like structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
- E04H12/10—Truss-like structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/20—Side-supporting means therefor, e.g. using guy ropes or struts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2292—Holders used for protection, repair or reinforcement of the post or pole
Definitions
- the present invention relates to a construction method for constructing towers, columns, and other vertical bearing devices. It is designed to facilitate refurbishing and updating the bearing capacity of towers, columns, and posts, particularly of lattice towers, columns, and posts.
- the towers are designed under two possible criteria.
- the first criterion includes calculating the loads and conditions at that moment, and the second criterion includes oversizing the tower from the start.
- the initial cost is low, but the evolution of needs has meant that it may be necessary to modify the capacity. In that case, it costs time and resources to reinforce the tower, even more than the initial construction does.
- the tower may even be rendered useless for an extended time, which may exceed two weeks, according to tower dimensions.
- the operations for a new foundation work next to the old foundation can cause damage to same or cause unwanted movements of the tower.
- the profiles are replaced or duplicated, resulting in a structure with a much larger area for absorbing stress, and therefore having a higher bearing capacity.
- the foundation must be enlarged, assuring that the behavior is consistent with the behavior of the previous foundation.
- reinforcement profiles are adhered, for example by means of riveting or screwing, to the already existing profiles. This work is done by hand, by drilling or arranging coupling points in the profiles one by one. Therefore, the work lasts for several weeks or months, during which time the equipment can be shut down (due to problems relating to operator exposure to radiation, for example).
- the design that is provided is far superior to current needs.
- the fundamental problem lies in the need to make a high initial investment without being able to know the future need.
- the tower may require being enlarged, may be sufficient with the already installed capacity, or may increase the capacity without needing to modify tower dimensions resulting from the breakthroughs made by technology. Therefore, this second case may comprise a completely unnecessary expenditure of resources and time.
- the objective of the invention is to provide a tower construction method which allows for versatility (flexibility) in adapting the tower to current needs, such that neither huge investments nor service shutdowns are required.
- the invention consists of a construction method which facilitates modifying and refurbishing towers, posts, and the like.
- the claims show the preferred embodiments which solve the aforementioned problems.
- the invention particularly relates to a construction method for constructing towers, posts, columns, or the like based on the known method of preparing foundations, installing pillars therein, and fixing a series of profiles to the pillars to define the tower.
- the novel aspect is that these foundations are oversized and comprise respective additional pillars which are arranged close to each pillar. These additional pillars are configured for receiving adjacent reinforcement profiles fixed to the profiles which, however, are not arranged until reinforcement of the structure is required. If desired, the additional pillars can be replaced with embedded parts, with or without a cover, in the foundations, which parts are indeed configured for fixing the additional pillars.
- the profiles preferably comprise coupling points configured for fixing the adjacent profiles.
- the additional pillars or the embedded parts can be arranged on the outer side of the tower, on the inner side, or on both.
- the construction method for constructing the tower, post, column, etc. begins as it often does with the preparation of the foundations (1), which will have the pillars (2) of the tower (3) embedded therein.
- the profiles (4) defining the tower (3) will be arranged on these pillars, and the features of such profiles (4) will depend on the type of tower, post, or column.
- the profiles (4) are arranged in a vertical, transverse, and oblique manner to form the structure.
- the (generally cylindrical) profile will only be vertical.
- Other tower, post, or column designs are likewise possible.
- the entire tower (3) is designed and constructed for a fixed bearing capacity which will correspond to the original needs. If it were necessary, the upper part of the tower (3) will have a wide safety margin in order to reduce high above-ground operations during reinforcement. In that sense, for example, only the lower segment of the tower (3) may be reinforced when the increase in capacity is lower. In contrast, the lower part may have a smaller margin as it can be readily reinforced.
- the known method for reinforcing it comprises enlarging the foundation, embedding additional pillars (2') therein, and coupling to several or all of the profiles (4) an adjacent profile (4'), attached by a bar, clamp, or other fixing device.
- the method is performed in a first step in which the foundations (1) are oversized and comprise from the start the additional pillars (2') which, in this case, remain free and are not directly connected to any original profile (4) of the tower (3). It is possible, though less advisable, to replace the additional pillars (2') with an embedded part (5) where the additional pillars (2') will later be fixed when the capacity of the tower (3) is going to be increased.
- This embedded part (5) may have an inner thread, a space where there will be fixed by means of resin, concrete, or another method the lower part of the corresponding additional pillar (2') or another similar solution having the suitable strength.
- the embedded part (5) may have a cover for preventing dirt from getting into it and affecting the use thereof.
- This first modification therefore provides an advantage, in that there is a lower risk of the ground moving when enlarging the foundations (1). Moreover, if the additional pillars (2') are arranged from the start, it is possible to arrange them in the most effective position, without having to risk damaging the initial pillars (2) as they are arranged close-by (which may involve drilling the initial foundations (1) in a position close to the initial pillars (2)).
- the profiles (4) arranged during the construction of the tower (3) will have from the start coupling points (6) where the adjacent profiles could be fixed in a quick manner.
- the exact position of the coupling points (6) will mainly depend on the length of the profiles (4) and the maximum bearing capacity for which the tower (3) is to be reinforced.
- a first example of coupling points (6) will be by means of through boreholes for fixing a bar.
- This bar can be placed at the time of the original construction ( Figure 2B ) or when the tower (3) is reinforced ( Figure 2A ), and it can be placed towards the inside or towards the outside of the tower (3) or on both sides.
- Each additional pillar (2') can, however, be connected from the start to a first adjacent profile (4') in order to be correctly attached to the tower (3) and assure that all the adjacent profiles (4') will later be perfectly aligned with the coupling points (6).
- Reinforcement of the tower (3) is thereby simplified by reducing the necessary operations to the simple assembly of the adjacent profiles (4') at the coupling points (6).
Abstract
preparing foundations (1);
installing pillars (2) in the foundations (1);
fixing to the pillars (2) profiles (4) defining the tower (3);
such that
the foundations (1) are oversized and comprise respective additional pillars (2') located close to each pillar (2) and configured for receiving adjacent reinforcement profiles (4') fixed to the profiles (4). Embedded parts (5) can optionally be installed for the later arrangement of the additional pillars (2').
Description
- The present invention relates to a construction method for constructing towers, columns, and other vertical bearing devices. It is designed to facilitate refurbishing and updating the bearing capacity of towers, columns, and posts, particularly of lattice towers, columns, and posts.
- It can be applied in the industry for building and installing communications equipment.
- Over the years, high-rise infrastructures, such as towers, columns or posts (hereinafter simply "tower"), for example telecommunications towers, have been a basic necessity for raising system equipment up in height. The towers are designed under two possible criteria. The first criterion includes calculating the loads and conditions at that moment, and the second criterion includes oversizing the tower from the start.
- In the first case, the initial cost is low, but the evolution of needs has meant that it may be necessary to modify the capacity. In that case, it costs time and resources to reinforce the tower, even more than the initial construction does. The tower may even be rendered useless for an extended time, which may exceed two weeks, according to tower dimensions. Furthermore, the operations for a new foundation work next to the old foundation can cause damage to same or cause unwanted movements of the tower.
- For example, for the purpose of increasing the bearing capacity in a lattice tower the profiles are replaced or duplicated, resulting in a structure with a much larger area for absorbing stress, and therefore having a higher bearing capacity. To that end, the foundation must be enlarged, assuring that the behavior is consistent with the behavior of the previous foundation. Then reinforcement profiles are adhered, for example by means of riveting or screwing, to the already existing profiles. This work is done by hand, by drilling or arranging coupling points in the profiles one by one. Therefore, the work lasts for several weeks or months, during which time the equipment can be shut down (due to problems relating to operator exposure to radiation, for example).
- In many cases there are situations in which the need for reinforcement means that the tower is oversized after being reinforced. In other words, need for reinforcement "compels" making an investment, but one, however, which allows a bearing capacity that may never be needed.
- In the second case, the design that is provided is far superior to current needs. The fundamental problem lies in the need to make a high initial investment without being able to know the future need. The tower may require being enlarged, may be sufficient with the already installed capacity, or may increase the capacity without needing to modify tower dimensions resulting from the breakthroughs made by technology. Therefore, this second case may comprise a completely unnecessary expenditure of resources and time.
- The objective of the invention is to provide a tower construction method which allows for versatility (flexibility) in adapting the tower to current needs, such that neither huge investments nor service shutdowns are required.
- The invention consists of a construction method which facilitates modifying and refurbishing towers, posts, and the like. The claims show the preferred embodiments which solve the aforementioned problems.
- The invention particularly relates to a construction method for constructing towers, posts, columns, or the like based on the known method of preparing foundations, installing pillars therein, and fixing a series of profiles to the pillars to define the tower. The novel aspect is that these foundations are oversized and comprise respective additional pillars which are arranged close to each pillar. These additional pillars are configured for receiving adjacent reinforcement profiles fixed to the profiles which, however, are not arranged until reinforcement of the structure is required. If desired, the additional pillars can be replaced with embedded parts, with or without a cover, in the foundations, which parts are indeed configured for fixing the additional pillars.
- The profiles preferably comprise coupling points configured for fixing the adjacent profiles.
- The additional pillars or the embedded parts can be arranged on the outer side of the tower, on the inner side, or on both.
- Other variants will be described in other parts of the specification.
- To better understand the invention, the following figures are included.
-
Figure 1 : schematic depiction of a tower in its original state (A) and in it reinforced state (B), according to the state of the art. -
Figure 2 : schematic depiction of a tower in its recently constructed original state and prior to starting the reinforcement thereof in two embodiments. - An embodiment of the invention is very briefly described below as an illustrative and non-limiting example of said invention.
- The construction method for constructing the tower, post, column, etc. begins as it often does with the preparation of the foundations (1), which will have the pillars (2) of the tower (3) embedded therein. The profiles (4) defining the tower (3) will be arranged on these pillars, and the features of such profiles (4) will depend on the type of tower, post, or column.
- In the case of the drawing which corresponds to the most preferred example, the profiles (4) are arranged in a vertical, transverse, and oblique manner to form the structure. In one post, the (generally cylindrical) profile will only be vertical. Other tower, post, or column designs are likewise possible.
- The entire tower (3) is designed and constructed for a fixed bearing capacity which will correspond to the original needs. If it were necessary, the upper part of the tower (3) will have a wide safety margin in order to reduce high above-ground operations during reinforcement. In that sense, for example, only the lower segment of the tower (3) may be reinforced when the increase in capacity is lower. In contrast, the lower part may have a smaller margin as it can be readily reinforced.
- Once the tower (3) is constructed, the known method for reinforcing it comprises enlarging the foundation, embedding additional pillars (2') therein, and coupling to several or all of the profiles (4) an adjacent profile (4'), attached by a bar, clamp, or other fixing device.
- However, according to the invention, the method is performed in a first step in which the foundations (1) are oversized and comprise from the start the additional pillars (2') which, in this case, remain free and are not directly connected to any original profile (4) of the tower (3). It is possible, though less advisable, to replace the additional pillars (2') with an embedded part (5) where the additional pillars (2') will later be fixed when the capacity of the tower (3) is going to be increased. This embedded part (5) may have an inner thread, a space where there will be fixed by means of resin, concrete, or another method the lower part of the corresponding additional pillar (2') or another similar solution having the suitable strength. The embedded part (5) may have a cover for preventing dirt from getting into it and affecting the use thereof.
- This first modification therefore provides an advantage, in that there is a lower risk of the ground moving when enlarging the foundations (1). Moreover, if the additional pillars (2') are arranged from the start, it is possible to arrange them in the most effective position, without having to risk damaging the initial pillars (2) as they are arranged close-by (which may involve drilling the initial foundations (1) in a position close to the initial pillars (2)).
- In a simple tower (3), such as a post, this solution allows obtaining a sufficient advantage because the adjacent profiles (4') can be arranged in a sufficiently quick manner. However, in more complex towers (3), such as in lattice towers, adjacent profiles (4') must be placed parallel to all or part of the original profiles (4). Since the number can be high, it would be appropriate to make this task easier.
- Therefore, the profiles (4) arranged during the construction of the tower (3) will have from the start coupling points (6) where the adjacent profiles could be fixed in a quick manner. The exact position of the coupling points (6) will mainly depend on the length of the profiles (4) and the maximum bearing capacity for which the tower (3) is to be reinforced.
- A first example of coupling points (6) will be by means of through boreholes for fixing a bar. This bar can be placed at the time of the original construction (
Figure 2B ) or when the tower (3) is reinforced (Figure 2A ), and it can be placed towards the inside or towards the outside of the tower (3) or on both sides. - Each additional pillar (2') can, however, be connected from the start to a first adjacent profile (4') in order to be correctly attached to the tower (3) and assure that all the adjacent profiles (4') will later be perfectly aligned with the coupling points (6).
- Reinforcement of the tower (3) is thereby simplified by reducing the necessary operations to the simple assembly of the adjacent profiles (4') at the coupling points (6).
Claims (6)
- A construction method for constructing towers, posts, columns, or the like, said method comprising:preparing foundations (1);installing pillars (2) in the foundations (1);fixing to the pillars (2) profiles (4) defining the tower (3);characterized in that
the foundations (1) are oversized and comprise respective additional pillars (2') located close to each pillar (2) and configured for receiving adjacent reinforcement profiles (4') fixed to the profiles (4). - The method according to claim 1, the profiles (4) of which comprise coupling points (6) configured for fixing the adjacent profiles (4').
- The method according to claim 1, wherein the additional pillars (2') are replaced with embedded parts (5) in the foundations (1) configured for fixing the additional pillars (2').
- The method according to claim 3, the embedded parts (5) of which have respective covers.
- The method according to claim 1 or 4, having additional pillars (2') or embedded parts (5) both on the outer side and on the inner side of the tower (3).
- The method according to claim 2, the additional pillars (2') of which are fixed to a first adjacent profile (4') attached to a profile (4) by its coupling points (6).
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES201830107A ES2672256B2 (en) | 2018-02-08 | 2018-02-08 | Tower construction procedure |
Publications (1)
Publication Number | Publication Date |
---|---|
EP3527752A1 true EP3527752A1 (en) | 2019-08-21 |
Family
ID=62493766
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19382077.6A Withdrawn EP3527752A1 (en) | 2018-02-08 | 2019-02-04 | Construction method for constructing towers |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP3527752A1 (en) |
ES (1) | ES2672256B2 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1335083A1 (en) * | 2002-02-09 | 2003-08-13 | SAG Energieversorgungslösungen GmBH | Method for renovating power pylons consisting of steel lattices |
WO2009156827A1 (en) * | 2008-06-24 | 2009-12-30 | Hedinger, Johan | Upgradeable lattice tower and components thereof |
WO2017156582A1 (en) * | 2016-03-15 | 2017-09-21 | Piling And Concreting Australia (Pca) Pty Ltd | A steel cap for an electricity transmission tower |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5955963A (en) * | 1982-09-25 | 1984-03-31 | 中部電力株式会社 | Method and apparatus for raising power transmission tower |
JP3999625B2 (en) * | 2002-10-15 | 2007-10-31 | 東京電力株式会社 | Bottom structure of steel tower |
US20050001131A1 (en) * | 2003-07-03 | 2005-01-06 | Stevens James A. | Method and apparatus for tower reinforcement system |
JP6452349B2 (en) * | 2014-08-26 | 2019-01-16 | 株式会社竹中工務店 | Bending reinforcement structure of existing tower structure |
US9376830B1 (en) * | 2015-05-01 | 2016-06-28 | Thomas B. Watson, III | Tower reinforcement apparatus and methods |
CN105298205B (en) * | 2015-11-30 | 2017-09-19 | 国网山东省电力公司枣庄供电公司 | A kind of power network electric pole reinforces heightening device and its construction method |
-
2018
- 2018-02-08 ES ES201830107A patent/ES2672256B2/en active Active
-
2019
- 2019-02-04 EP EP19382077.6A patent/EP3527752A1/en not_active Withdrawn
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1335083A1 (en) * | 2002-02-09 | 2003-08-13 | SAG Energieversorgungslösungen GmBH | Method for renovating power pylons consisting of steel lattices |
WO2009156827A1 (en) * | 2008-06-24 | 2009-12-30 | Hedinger, Johan | Upgradeable lattice tower and components thereof |
WO2017156582A1 (en) * | 2016-03-15 | 2017-09-21 | Piling And Concreting Australia (Pca) Pty Ltd | A steel cap for an electricity transmission tower |
Also Published As
Publication number | Publication date |
---|---|
ES2672256A1 (en) | 2018-06-13 |
ES2672256B2 (en) | 2018-10-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3153627B1 (en) | Foundations system for towers and method for installing the foundations system for towers | |
EP2914790B1 (en) | Method for producing a tower construction from reinforced concrete | |
DE102012109860A1 (en) | Supply tower for a tower, tower with a utility scaffold and method for erecting a utility scaffolding inside a tower | |
US20160251856A1 (en) | Solid reinforced concrete column based on arrangement of triangular reinforcing bar networks and method of constructing the same | |
CN103711308A (en) | Tool type steel-column supporting steel platform climbing system and using method thereof | |
CN106032692A (en) | Integral pouring molding construction method for reinforced concrete column | |
KR101626428B1 (en) | Manufacturing Method for Hollow Precast Concret-encased Steel Column and Dry-splicing Methods for the Same | |
CN103912008A (en) | Unilateral formwork structure and construction method thereof | |
CN105442434A (en) | Slot type connecting structure for prefabricated stand column and prefabricated cover beam of bridge and splicing method for prefabricated stand column and prefabricated cover beam | |
JP2018024984A (en) | Method for constructing dome-like structure with linear member | |
US10655287B2 (en) | Reinforcement apparatus for reinforcing a structure comprising a pier and a cross-beam | |
KR100862005B1 (en) | Manufacturing method of segmental internally confined hollow concrete filled tube | |
CN106032706A (en) | Integrated casting molding construction method of reinforced concrete shear wall | |
CN107119698A (en) | A kind of prefabricated assembling type reinforced concrete side slope protection modular assembly and its construction method | |
EP3527752A1 (en) | Construction method for constructing towers | |
CN107363194A (en) | Reserved steel bar means for correcting and its application construction method | |
KR101538074B1 (en) | Pivot Joint Type Aseismatic Device and Method using thereof | |
KR101596259B1 (en) | Reinforcing System Of Reinforced Concrete Slab, Reinforced Concrete Slab Having The Same, Shear Reinforcing Unit Of Reinforced Concrete Slab, And Flat Plate Constructing Method | |
KR102281205B1 (en) | Extension arm and construction method of transmission tower | |
EP3208901A1 (en) | Retractable road cabinet | |
RU161629U1 (en) | DEVICE FOR PLACING A FILTERING CARTRIDGE | |
KR101958768B1 (en) | Structure for Constructing the Lagging Board using Strut Beam having Reinforcement Bar | |
CN209760830U (en) | Prevent framework of steel reinforcement skew structure | |
CN105544395B (en) | A kind of high pier vertical prestressing pipe installation method | |
CN205369874U (en) | Elevartor shaft outer wall cantilever frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20190204 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20220225 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20231109 |