CN106032692A - Integral pouring molding construction method for reinforced concrete column - Google Patents

Integral pouring molding construction method for reinforced concrete column Download PDF

Info

Publication number
CN106032692A
CN106032692A CN201510752765.5A CN201510752765A CN106032692A CN 106032692 A CN106032692 A CN 106032692A CN 201510752765 A CN201510752765 A CN 201510752765A CN 106032692 A CN106032692 A CN 106032692A
Authority
CN
China
Prior art keywords
template
steel
stirrup
construction method
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510752765.5A
Other languages
Chinese (zh)
Other versions
CN106032692B (en
Inventor
刘付钧
李盛勇
黄忠海
郭伟亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RBS Partners S&T Co Ltd
Original Assignee
RBS Partners S&T Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by RBS Partners S&T Co Ltd filed Critical RBS Partners S&T Co Ltd
Priority to CN201510752765.5A priority Critical patent/CN106032692B/en
Publication of CN106032692A publication Critical patent/CN106032692A/en
Application granted granted Critical
Publication of CN106032692B publication Critical patent/CN106032692B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses an integral pouring molding construction method for reinforced concrete columns. The integral pouring molding construction method for the reinforced concrete column comprises the steps that a column reinforcing cage is composed of a plurality of stirrups and column reinforcing cage vertical reinforced bars, outer-side formworks are fixed by forming outer threads in the ends of framework reinforced bars of the stirrups forming the column reinforcing cage and enabling the outer threads to penetrate through the formworks, all the side face formworks are fixed separately to form an integral formwork splicing structure with the self-balancing performance, and the spliced integral formwork structure is conveniently lifted to a construction site for construction. According to the construction method, the site construction procedures of the concrete columns are simplified, the structural integrality is good, and the construction method is applied to the building construction field.

Description

The integral type of a kind of reinforced column pours molding construction method
Technical field
The present invention relates to the realm of building construction, the integral type particularly relating to a kind of reinforced column pours molding construction method.
Background technology
Ordinary reinforced concrete post first colligation vertical reinforcement and stirrup form post steel reinforcement cage, then support template around column section, after-pouring concrete, after concrete setting reaching some strength requirement, then remove the template around column section.Site operation step is many, and flow process is complicated, and site operation is long in time limit.
Tradition prefabricated reinforced concrete column completes above-mentioned steps in factory, and after the most prefabricated reinforced column is transported to job site, then lifting installation, the weight transporting and lifting installation is bigger, and the connecting structure between prefabricated components is complicated, and stress performance and the globality of structure be not good enough.
Summary of the invention
For solving the problems referred to above, the present invention provides the integral type of a kind of reinforced column that can be rapidly completed construction by concreting after formwork structure assembly completes to pour molding construction method.
The technical solution adopted for the present invention to solve the technical problems is:
The integral type of a kind of reinforced column pours molding construction method, comprises the following steps:
1, post steel reinforcement cage and monoblock type template assembly structure are made;
A), along concrete column length direction the some stirrups being set parallel to each other along concrete column length direction of some post steel reinforcement cage Vertical bar connection are set and form post steel reinforcement cage, be equipped with two ends in each stirrup and stretch out to outside and carry externally threaded skeleton reinforcing steel bar;
B), in the periphery of post steel reinforcement cage installing some templates arranged along concrete column length direction, each template is connected realization by the nut penetrated from outside with the external screw thread of skeleton reinforcing steel bar and fixes, and the termination of template is stretched out at the two ends of each post steel reinforcement cage vertical reinforcement;
C), the shaped steel of vertically putting more energy into being fixedly connected with two side templates is set between two adjacent templates, and passes, by the skeleton reinforcing steel bar termination passed from template, shaped steel of vertically putting more energy into, and fixed by nut from outside;
D), mounting ring be wound on the sash shaped steel arranged outside each template, and by the skeleton reinforcing steel bar termination that passes from template through sash shaped steel, and fixed by nut from outside, the concrete column reinforcing bar cage template assembly structure of formation self-balancing;
2, the transport of described concrete column reinforcing bar cage template assembly structure to job site and is lifted in place;
3, the post steel reinforcement cage vertical reinforcement of post steel reinforcement cage is connected;
4, the shaped steel of putting more energy into of suspension column template and suspension column template and column template connecting portion is installed;
5, casting concrete inside template, concrete and template one coagulation forming form reinforced column;
6, after concrete setting reaches predetermined strength, remove vertically put more energy into shaped steel and the sash shaped steel of temperature pier template, move to floor above and recycle.
Being further used as the improvement of technical solution of the present invention, stirrup includes some skeleton reinforcing steel bar overlapped in length and breadth, stirrup is additionally provided be connected with multiple spot on stirrup separately add stirrup.
Be further used as the improvement of technical solution of the present invention, separately add stirrup include some longitudinally of one another or horizontal reinforcement welding fixes the entirety of formation, separately add the junction point of stirrup and skeleton reinforcing steel bar by welding or colligation is fixed.
Being further used as the improvement of technical solution of the present invention, separately adding stirrup is one to be fixed on stirrup by the steel ring of reinforcing bar bending, the dislocation of steel ring and each skeleton reinforcing steel bar, and steel ring passes through with the junction point of each skeleton reinforcing steel bar to weld or colligation is fixed.
It is further used as the improvement of technical solution of the present invention, periphery along template is equidistant is provided with some sash shaped steel, each sash shaped steel is close to template and shaped steel of vertically putting more energy into, and nut is through sash shaped steel, vertically put more energy into shaped steel and template is connected with the skeleton reinforcing steel bar ends screw of stirrup both sides.
Being further used as the improvement of technical solution of the present invention, in step 1, described template is connected formation self-balancing entirety by the two ends of skeleton reinforcing steel bar to drawing with post steel reinforcement cage.
It is further used as the improvement of technical solution of the present invention, in step 1, is combined formation entirety, whole Transporting and lifting after concreting with template and installs.
Beneficial effects of the present invention: the integral type of this reinforced column pours molding construction method, post steel reinforcement cage is formed by some stirrups and post steel reinforcement cage vertical reinforcement, and external screw thread is set by the termination of the skeleton reinforcing steel bar of the stirrup of composition post steel reinforcement cage, through template, outboard template is fixed, each Side shuttering forms the monoblock type template assembly structure with self-balancing performance after fixing respectively, convenient monoblock type formwork structure lifting assembly completed is constructed to job site, this construction method simplifies the site operation flow process of concrete column, and the globality of structure is good.
Accompanying drawing explanation
The invention will be further described below in conjunction with the accompanying drawings:
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is first embodiment of the invention overall structure top view;
Fig. 2 is second embodiment of the invention overall structure top view;
Fig. 3 is embodiment of the present invention overall structure front view;
Fig. 4 is that construction process of the present invention sets up process the first status architecture schematic diagram;
Fig. 5 is that construction process of the present invention sets up process the second status architecture schematic diagram.
Detailed description of the invention
With reference to Fig. 1~Fig. 5, the present invention is that the integral type of a kind of reinforced column pours molding construction method, comprises the following steps:
1, post steel reinforcement cage and monoblock type template assembly structure are made;
A), along concrete column length direction arrange some post steel reinforcement cage vertical reinforcements 7 to connect some stirrups 4 being set parallel to each other along concrete column length direction and form post steel reinforcement cage, be equipped with two ends in each stirrup 4 and stretch out to outside and carry externally threaded skeleton reinforcing steel bar 41;
B), in the periphery of post steel reinforcement cage installing some templates arranged along concrete column length direction, each template is connected realization by the nut 5 penetrated from outside with the external screw thread of skeleton reinforcing steel bar 41 and fixes, and the termination of template is stretched out at the two ends of each post steel reinforcement cage vertical reinforcement 7;
C), the shaped steel of vertically putting more energy into being fixedly connected with two side templates is set between two adjacent templates, and passes, by skeleton reinforcing steel bar 41 termination passed from template, shaped steel 6 of vertically putting more energy into, and fix from outside by nut 5;
D), mounting ring is wound on the sash shaped steel 8 arranged outside each template, and passes sash shaped steel 8 by skeleton reinforcing steel bar 41 termination passed from template, and fixes from outside by nut 5, the concrete column reinforcing bar cage template assembly structure of formation self-balancing;
2, the transport of described concrete column reinforcing bar cage template assembly structure to job site and is lifted in place;
3, the post steel reinforcement cage vertical reinforcement of post steel reinforcement cage is connected;
4, the shaped steel of putting more energy into of suspension column template and suspension column template and column template connecting portion is installed;
5, casting concrete inside template, concrete and template one coagulation forming form reinforced column;
6, after concrete setting reaches predetermined strength, remove vertically put more energy into shaped steel and the sash shaped steel of temperature pier template, move to floor above and recycle.
The integral type of this reinforced column pours molding construction method, post steel reinforcement cage is formed by some stirrups 4 and post steel reinforcement cage vertical reinforcement 7, and external screw thread is set by the termination of the skeleton reinforcing steel bar 41 of the stirrup 4 of composition post steel reinforcement cage, through template, outboard template is fixed, each Side shuttering forms the monoblock type template assembly structure with self-balancing performance after fixing respectively, convenient monoblock type formwork structure lifting assembly completed is constructed to job site, this construction method simplifies the site operation flow process of concrete column, and the globality of structure is good.
As the preferred embodiment of the present invention, stirrup 4 includes some skeleton reinforcing steel bar 41 overlapped in length and breadth, stirrup 4 is additionally provided with and separately adds stirrup 42 with multiple spot on stirrup 4 is connected.
As the preferred embodiment of the present invention, separately add stirrup 42 include some longitudinally of one another or horizontal reinforcement welding fixes the entirety of formation, separately add the junction point of stirrup 42 and skeleton reinforcing steel bar 41 by welding or colligation is fixed.
As the preferred embodiment of the present invention, separately adding stirrup 42 is one to be fixed on stirrup 4 with the dislocation of each skeleton reinforcing steel bar 41 by the steel ring of reinforcing bar bending, steel ring, and steel ring passes through with the junction point of each skeleton reinforcing steel bar 41 to weld or colligation is fixed.
Each stirrup 4 is overlapped in length and breadth by skeleton reinforcing steel bar 41 before being assembled into post steel reinforcement cage and is welded, each stirrup 4 is arranged and separately adds stirrup 42, each stirrup 42 that separately adds primarily serves the auxiliary potentiation of the intensity to stirrup 4 entirety, and the setting separately adding stirrup 42 can be realized by above various ways.
As the preferred embodiment of the present invention, periphery along template is equidistant is provided with some sash shaped steel 8, each sash shaped steel 8 is close to template and shaped steel 6 of vertically putting more energy into, and nut 5 is through sash shaped steel 8, vertically put more energy into shaped steel 6 and template is connected with skeleton reinforcing steel bar 41 ends screw of stirrup 4 both sides.
Shaped steel 6 of vertically putting more energy into is arranged between two adjacent templates, and be fixedly connected with the template of both sides, monoblock type template can be made to form the entirety that a surrounding seals, prevent concrete in concreting process from revealing, meanwhile, the connectivity robustness of monoblock type template can be strengthened.
The template of surrounding threaded is fixed by what termination was provided with between externally threaded skeleton reinforcing steel bar 41 and nut 5, by being attached by shaped steel 6 of vertically putting more energy between adjacent template, the template that can make post steel reinforcement cage and periphery forms the entirety of self-balancing, having more preferable stability, convenient reinforced column integrated template structure assembly completed carries out transporting, shift and lifting.
As in the preferred embodiment of the present invention, step 1, described template is connected formation self-balancing entirety by the two ends of skeleton reinforcing steel bar to drawing with post steel reinforcement cage, can whole Transporting install with lifting, and job site is not required to arrange template temporary support.
As in the preferred embodiment of the present invention, step 1, be combined formation entirety after concreting with template, after having constructed, be not required to form removal.
Certainly, the invention is not limited to above-mentioned embodiment, those of ordinary skill in the art also can make equivalent variations or replacement on the premise of spirit of the present invention, and modification or the replacement of these equivalents are all contained in the application claim limited range.

Claims (7)

1. the integral type of a reinforced column pours molding construction method, it is characterised in that comprise the following steps:
1, post steel reinforcement cage and monoblock type template assembly structure are made;
A), along concrete column length direction the some stirrups being set parallel to each other along concrete column length direction of some post steel reinforcement cage Vertical bar connection are set and form post steel reinforcement cage, be equipped with two ends in each described stirrup and stretch out to outside and carry externally threaded skeleton reinforcing steel bar;
B), some templates arranged along concrete column length direction are installed in the periphery of described post steel reinforcement cage, each described template is connected realization by the nut penetrated from outside with the external screw thread of skeleton reinforcing steel bar and fixes, and the termination of template is stretched out at the two ends of each described post steel reinforcement cage vertical reinforcement;
C), the shaped steel of vertically putting more energy into being fixedly connected with two side templates is set between two adjacent described templates, and passes, by the skeleton reinforcing steel bar termination passed from template, shaped steel of vertically putting more energy into, and fixed by nut from outside;
D), mounting ring be wound on the sash shaped steel arranged outside each template, and by the skeleton reinforcing steel bar termination that passes from template through sash shaped steel, and fixed by nut from outside, the concrete column reinforcing bar cage template assembly structure of formation self-balancing;
2, the transport of described concrete column reinforcing bar cage template assembly structure to job site and is lifted in place;
3, the post steel reinforcement cage vertical reinforcement of post steel reinforcement cage is connected;
4, the shaped steel of putting more energy into of suspension column template and suspension column template and column template connecting portion is installed;
5, casting concrete inside template, concrete and template one coagulation forming form reinforced column;
6, after concrete setting reaches predetermined strength, remove vertically put more energy into shaped steel and the sash shaped steel of temperature pier template, move to floor above and recycle.
The integral type of reinforced column the most according to claim 1 pours molding construction method, it is characterised in that: described stirrup includes some skeleton reinforcing steel bar overlapped in length and breadth, described stirrup is additionally provided be connected with multiple spot on stirrup separately add stirrup.
The integral type of reinforced column the most according to claim 2 pours molding construction method, it is characterized in that: described separately add stirrup include some longitudinally of one another or horizontal reinforcement welding fixes the entirety of formation, the described junction point separately adding stirrup and skeleton reinforcing steel bar is by welding or colligation is fixed.
The integral type of reinforced column the most according to claim 2 pours molding construction method, it is characterized in that: the described stirrup that separately adds is a steel ring bent by reinforcing bar, the dislocation of described steel ring and each skeleton reinforcing steel bar is fixed on stirrup, and described steel ring passes through with the junction point of each skeleton reinforcing steel bar to weld or colligation is fixed.
The integral type of reinforced column the most according to claim 1 pours molding construction method, it is characterized in that: periphery along described template is equidistant is provided with some sash shaped steel, each described sash shaped steel is close to template and shaped steel of vertically putting more energy into, and described nut is through sash shaped steel, vertically put more energy into shaped steel and template is connected with the skeleton reinforcing steel bar ends screw of stirrup both sides.
The integral type of reinforced column the most according to claim 1 pours molding construction method, it is characterised in that: in described step 1, described template is connected formation self-balancing entirety by the two ends of skeleton reinforcing steel bar to drawing with post steel reinforcement cage, and whole Transporting and lifting are installed.
The integral type of reinforced column the most according to claim 1 pours molding construction method, it is characterised in that: in described step 1, after concreting, be combined formation entirety with template.
CN201510752765.5A 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column Active CN106032692B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510752765.5A CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510752765.5A CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Publications (2)

Publication Number Publication Date
CN106032692A true CN106032692A (en) 2016-10-19
CN106032692B CN106032692B (en) 2018-01-09

Family

ID=57148999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510752765.5A Active CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Country Status (1)

Country Link
CN (1) CN106032692B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288261A (en) * 2017-07-03 2017-10-24 广州容联建筑科技有限公司 A kind of construction method of reinforced column cavity
CN107313554A (en) * 2017-08-10 2017-11-03 滨州学院 A kind of reinforced column constructing device of free removal template
CN107435415A (en) * 2017-07-03 2017-12-05 广州容联建筑科技有限公司 A kind of reinforced column and construction method for building industrialization
TWI661109B (en) * 2017-08-17 2019-06-01 Ruentex Engineering & Construction Co., Ltd. Method of assembling column stirrups
CN110206230A (en) * 2019-06-10 2019-09-06 上海建工四建集团有限公司 Concrete column framework of steel reinforcement and template system integral structure and construction method
CN110206229A (en) * 2019-06-10 2019-09-06 上海建工四建集团有限公司 A kind of concrete column splicing structure and its construction method
CN110206227A (en) * 2019-05-10 2019-09-06 中天建设集团有限公司 A kind of superelevation column template reinforcing bar integral hoisting construction method
CN110512860A (en) * 2019-09-19 2019-11-29 武汉悉道建筑科技有限公司 A kind of reinforcing bar integrated template system and preparation method thereof
CN110552497A (en) * 2019-09-19 2019-12-10 武汉悉道建筑科技有限公司 light steel keel building template and manufacturing method thereof
CN114482550A (en) * 2021-12-31 2022-05-13 华能国际电力股份有限公司上海石洞口第一电厂 Concrete ultrahigh column pouring construction method
CN115110576A (en) * 2022-07-26 2022-09-27 中铁广州工程局集团有限公司 Integral forming construction method for underground garage frame column and base layer
CN115288507A (en) * 2022-07-25 2022-11-04 中建八局深圳科创发展有限公司 Cast-in-situ river stone landscape column and construction method thereof
CN115492309A (en) * 2022-10-31 2022-12-20 中国十九冶集团有限公司 Steel reinforcement cage expansion structure and construction method for installing box steel column in steel reinforcement cage

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1876996A (en) * 2006-07-04 2006-12-13 朱秦江 Integrally-cast mould-detachment-free concrete structure system and construction method thereof
US20080282634A1 (en) * 2006-05-18 2008-11-20 Ping Qu Composite Concrete Shear Wall for Heat Insulation
CN101818539A (en) * 2010-06-04 2010-09-01 北京万科企业有限公司 Assembled integral building and construction method thereof
CN201649631U (en) * 2010-04-07 2010-11-24 南通建工集团股份有限公司 T-shaped pole template system protruding from the exterior wall
CN201826439U (en) * 2010-10-18 2011-05-11 清华大学 Assembled self-compaction steel tube concrete combined structure
CN103938797A (en) * 2014-04-04 2014-07-23 北京工业大学 Heat-preserving recycled concrete rectangular column with dismantling-free high performance cement mortar mold plate and manufacturing method
CN105019600A (en) * 2015-08-04 2015-11-04 万保金 Disassembly-free precast concrete frame column template

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080282634A1 (en) * 2006-05-18 2008-11-20 Ping Qu Composite Concrete Shear Wall for Heat Insulation
CN1876996A (en) * 2006-07-04 2006-12-13 朱秦江 Integrally-cast mould-detachment-free concrete structure system and construction method thereof
CN201649631U (en) * 2010-04-07 2010-11-24 南通建工集团股份有限公司 T-shaped pole template system protruding from the exterior wall
CN101818539A (en) * 2010-06-04 2010-09-01 北京万科企业有限公司 Assembled integral building and construction method thereof
CN201826439U (en) * 2010-10-18 2011-05-11 清华大学 Assembled self-compaction steel tube concrete combined structure
CN103938797A (en) * 2014-04-04 2014-07-23 北京工业大学 Heat-preserving recycled concrete rectangular column with dismantling-free high performance cement mortar mold plate and manufacturing method
CN105019600A (en) * 2015-08-04 2015-11-04 万保金 Disassembly-free precast concrete frame column template

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288261A (en) * 2017-07-03 2017-10-24 广州容联建筑科技有限公司 A kind of construction method of reinforced column cavity
CN107435415A (en) * 2017-07-03 2017-12-05 广州容联建筑科技有限公司 A kind of reinforced column and construction method for building industrialization
CN107313554A (en) * 2017-08-10 2017-11-03 滨州学院 A kind of reinforced column constructing device of free removal template
TWI661109B (en) * 2017-08-17 2019-06-01 Ruentex Engineering & Construction Co., Ltd. Method of assembling column stirrups
CN110206227A (en) * 2019-05-10 2019-09-06 中天建设集团有限公司 A kind of superelevation column template reinforcing bar integral hoisting construction method
CN110206230A (en) * 2019-06-10 2019-09-06 上海建工四建集团有限公司 Concrete column framework of steel reinforcement and template system integral structure and construction method
CN110206229A (en) * 2019-06-10 2019-09-06 上海建工四建集团有限公司 A kind of concrete column splicing structure and its construction method
CN110552497A (en) * 2019-09-19 2019-12-10 武汉悉道建筑科技有限公司 light steel keel building template and manufacturing method thereof
CN110512860A (en) * 2019-09-19 2019-11-29 武汉悉道建筑科技有限公司 A kind of reinforcing bar integrated template system and preparation method thereof
CN114482550A (en) * 2021-12-31 2022-05-13 华能国际电力股份有限公司上海石洞口第一电厂 Concrete ultrahigh column pouring construction method
CN114482550B (en) * 2021-12-31 2024-03-22 华能国际电力股份有限公司上海石洞口第一电厂 Concrete ultra-high column pouring construction method
CN115288507A (en) * 2022-07-25 2022-11-04 中建八局深圳科创发展有限公司 Cast-in-situ river stone landscape column and construction method thereof
CN115288507B (en) * 2022-07-25 2023-09-12 中建八局深圳科创发展有限公司 Cast-in-situ river stone landscape column and construction method thereof
CN115110576A (en) * 2022-07-26 2022-09-27 中铁广州工程局集团有限公司 Integral forming construction method for underground garage frame column and base layer
CN115110576B (en) * 2022-07-26 2024-03-01 中铁广州工程局集团有限公司 Integral forming construction method for frame column and base layer of underground garage
CN115492309A (en) * 2022-10-31 2022-12-20 中国十九冶集团有限公司 Steel reinforcement cage expansion structure and construction method for installing box steel column in steel reinforcement cage
CN115492309B (en) * 2022-10-31 2023-06-13 中国十九冶集团有限公司 Reinforcement cage expansion structure and construction method for installing box-type steel column in reinforcement cage

Also Published As

Publication number Publication date
CN106032692B (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN106032692A (en) Integral pouring molding construction method for reinforced concrete column
CN106906955B (en) Shear wall integral prefabricated reinforcement mesh structure and construction method thereof
CN112900619B (en) Fabricated concrete beam-column joint and construction method thereof
CN104088397B (en) A kind of prefabricated post and precast construction method thereof
CN106032706A (en) Integrated casting molding construction method of reinforced concrete shear wall
CN109537810B (en) Manufacturing method of prefabricated column and assembling method of column beam
CN101979791B (en) Ring beam and annular corbel column reinforced connection joint construction method
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
CN103614967A (en) Stiff framework and method for constructing bridge tower column by means of same
CN103850363A (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN104831818A (en) Connection node of precast reinforced concrete beam and laminated column
CN112922231A (en) Fabricated concrete beam-column joint and construction method thereof
CN205153536U (en) Structure is assembled to self -balancing integral template of reinforced concrete roof beam
CN105155841A (en) External bone prefabricated thin wall component and assembled construction reinforced concrete pier and column and construction method thereof
CN106049719A (en) Self-balance whole formwork assembly structure of reinforced concrete shear wall
CN205153535U (en) Structure is assembled to reinforced concrete column's self -balancing integral template
CN106894544B (en) Embedded single-layer steel plate-concrete combined shear wall and construction method thereof
CN106032701A (en) Self-balance integral template assembling structure of reinforced concrete column
CN106032705B (en) A kind of integral type pouring molding construction method of reinforced concrete floor
CN104453228A (en) Construction method of large-span super-large-section steel plate wall beam
CN111576620A (en) Construction method for beam-column core area of stiffened concrete structure
CN212405468U (en) Stiff concrete structure beam column core area structure
CN103993671A (en) Joint of concrete-filled steel-tubular column and steel beam and architectural structure system
CN211473348U (en) Scaffold wall connecting piece
CN205153221U (en) Structure is assembled to self -balancing integral template of reinforced concrete shear force wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant