Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP17185614.9A
Other languages
German (de)
French (fr)
Other versions
EP3306010A1 (en
Inventor
Armin Böser
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of EP3306010A1 publication Critical patent/EP3306010A1/en
Application granted granted Critical
Publication of EP3306010B1 publication Critical patent/EP3306010B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/17Comprising essentially pre-assembled three-dimensional elements, e.g. cubic elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/38Arched girders or portal frames
    • E04C3/40Arched girders or portal frames of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/22Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/007Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/302Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members
    • E04G7/306Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are fixed at several bars or members to connect
    • E04G7/308Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are fixed at several bars or members to connect without tying means for connecting the bars or members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/34Scaffolding bars or members with non-detachably fixed coupling elements with coupling elements using positive engagement, e.g. hooks or pins
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2406Connection nodes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2433Connection details of the elongated load-supporting parts using a removable key
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0486Truss like structures composed of separate truss elements
    • E04C2003/0495Truss like structures composed of separate truss elements the truss elements being located in several non-parallel surfaces

Definitions

  • the invention relates to a protective and / or work frame for overhead line construction.
  • JP H03 156065 A relates to the provision of a three-dimensional scaffolding structure which can be erected by a plurality of rod elements connected to one another, the scaffolding structure having a gate recess, the post bars of which vertically delimiting the gate recess are stabilized by a horizontally extending support element attached to it.
  • 5,390,463 relates to a modular framework system, comprising prefabricated cuboid modules, in particular for the design of a protective and / or work scaffold with at least two tower elements and at least one top chord carried by the tower elements, the tower elements having similar cuboid modules arranged one above the other and connected to one another and the top chord arranged next to one another and having similar cuboid modules connected to one another.
  • the cuboid modules can have four parallel round bars running in the longitudinal direction and four of the round bars at the ends, either diagonally or parallel to the sides of the cuboid modules, box-shaped cross bars.
  • the disclosure document JP 2004 270403 A relates to a protective scaffolding installation, comprising at least two tower elements and at least one upper chord carried by the tower elements, the tower elements having cuboid modules arranged one above the other and connected to one another and the upper chord comprising cuboid modules arranged next to one another and connected to one another, the connection between a tower element and the upper chord by means of one of these two common cube-shaped adapter module takes place and the tower elements are supported by foundation elements.
  • a large number of such frame elements can be used to design a support structure, for example to set up exhibition stands and shelves, and are used there in the same way for horizontal connections as well as for vertical constructions, the frame element being a simple suspension of parts in the parallel elongated elements when mounted vertically of the stiffening element.
  • a portal is assembled by using a plurality of such frame elements and associated node parts, comprising two tower elements and an upper chord carried by the tower elements, the tower elements having similar, cuboidal modules arranged one above the other and connected to one another, composed of the frame, and the upper chord Identical, cuboidal modules composed of the frame and arranged next to one another and connected to one another, and wherein the connection between a tower element and the upper chord is made by means of a cube-shaped adapter module common to these two.
  • the disclosure document US 2013/2917477 A1 relates to the connection of a plurality of structural supports with respective extension elements, which are connected via a connector block.
  • the structural supports and the respectively assigned expansion elements have connectors which are designed as brackets provided with holes.
  • a first and second structural layer are first built up by at least each respective connection of four horizontal beams with four connecting elements and two cover elements. Then one of the structural layers is raised relative to the other and both vertically spaced structural layers are attached to respective connecting elements by means of vertical supports connected. The interconnected structural layers are then raised together, and subsequently connected to a further structural layer assembled as described by means of vertical beams, this step being repeated until the desired framework structure is achieved.
  • the erection of the scaffolding according to the invention can be done in such a way that the upper chord composed of the cuboid modules and the adapter modules is first mounted on the floor, which is then raised by means of at least one lifting device by a distance, which the arrangement in each case one for the Tower elements provided module allows in a position in which it is connected to the top belt by fastening to the respective adapter module provided.
  • This can be done on the floor using, for example, small assembly scaffolding whose height does not need to exceed the length of a cuboid module.
  • the number of tower elements will depend on the length of the upper chord and possibly also on the load-bearing capacity of the at least one lifting element to be used. The latter also applies to the maximum height of the scaffolding to be erected, whereby its stability can be secured by guy ropes if necessary.
  • the top chord 12 and tower elements 14 are essentially composed of cuboid modules 18, one of which is shown in FIG Figure 3 is shown.
  • Each of the modules is designed as a framework and provided with four parallel rods 20 running in the longitudinal direction, which are connected to one another at the respective end of the cuboid by four transverse rods.
  • the longitudinal rods 20 have a significantly greater length than the transverse rods, so that in the exemplary embodiment shown in the drawings, a diagonal strut 28 is attached to at least two opposite sides 24, 26 of the module.
  • struts 28 are provided on each of the two sides, each extending from one end of the module and meeting in a plane dividing the module in half and being attached there to the opposite longitudinal rod.
  • another diagonal strut running in this plane is provided in the strut 30.
  • the number and arrangement of these struts depends on the particular circumstances, in particular also on the length of the modules, which can generally be about two meters, for example.
  • the connection between the upper chord 12 and the respective tower element 14 is made using an adapter module 32, which is composed of rods 34 of the same length and thus has the shape of a cube ( Figure 4 ).
  • the surfaces of the cube correspond in terms of dimensions and shape to the end faces 27 of the cuboid modules. Because at least the cuboid modules of the top chord and tower elements coincide with regard to their cross-sectional shape and size, both the modules 18 of the upper chord 12 adjoining the respective adapter module 32 and the corresponding modules of the tower elements 14 can thus be connected to the adapter module, as shown in particular from Figure 2 can be seen.
  • the adapter module 32 is connected to a cuboid module 18 on two of its opposite surfaces.
  • the uppermost cuboid module for the respective tower element 14 is attached to a further, to the two aforementioned surfaces of the vertical surface that delimits the adapter module on the underside.
  • fastening means that are designed as tabs.
  • the arrangement of the cuboid modules is such that alternating single tabs 36 and double tabs 38 are provided on each end face at the four corners thereof, the double tabs being arranged parallel to one another and at a distance from one another, such that between the two tabs of a double tab 38 of a module of a single tab of an adjacent module can be inserted.
  • All brackets are provided with a hole, the holes of all brackets being aligned with one another in the connection position so that they can receive a screw bolt or other suitable connecting means in order to connect the brackets of both adjacent modules and thus the modules to one another connect to.
  • the two tower elements 14 are each on a foundation element 41 ( Figure 5 ), which consists of two longitudinal beams, for example double-T beams 42 and some cross beams 44 connecting these longitudinal beams and is arranged and optionally anchored on the floor receiving the scaffolding.
  • the foundation elements 41 can, depending on the nature of the ground on which they are placed, be provided with extensions or the like on the underside, which provide a safeguard against displacement that may be required.
  • the cross members 44 located in the middle are also provided with single straps 36 and double straps 38 corresponding to the attachment of the straps to the cuboid module in such a way that the lower end of the respective lowermost module of the tower element is connected to the foundation element 41 in the manner described can be.
  • the frame shown is provided along the top chord with a work platform 46 to which a railing 48 is assigned.
  • the modules of the upper chord and the adapter modules are provided with corresponding additional components which, when the modules are installed, complement each other to form this work platform in the railing (s).
  • the right tower element of the scaffolding according to Figure 1c is provided with a vertical climb with back protection and resting platforms.
  • the modules of this tower element are provided with corresponding components that complement each other to the climbing gear, etc.
  • the scaffolding according to Figure 1a is secured with guy ropes 54 due to its greater height.
  • the framework according to the invention can also have more than two tower elements.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Description

Die Erfindung betrifft ein Schutz- und/oder Arbeitsgerüst für den Freileitungsbau.The invention relates to a protective and / or work frame for overhead line construction.

Bisher werden in den Bereichen Freileitungs- und Anlagenbau übliche Arbeitsgerüste verwendet, wie sie zum Beispiel im Baugewerbe an Gebäuden und anderen Bauwerken angebracht werden, um an diesen Arbeiten durchzuführen. Deren Errichtung ist zeitaufwändig und umständlich, wobei der Aufwand mit der Höhe der Gerüste überproportional steigt.So far, normal working scaffolding has been used in the fields of overhead line and plant construction, such as those attached to buildings and other structures in the construction industry, in order to carry out work on these. Erecting them is time-consuming and cumbersome, with the effort increasing disproportionately with the height of the scaffolding.

Die Offenlegungsschrift DE 21 09 088 A1 betrifft ein räumliches Bauelement zur Bildung von Trag- und Stützwerken, bestehend aus einem prismatischen Hohlkörper mit paarweise einander gegenüber liegenden, zueinander parallelen Begrenzungsebenen, von denen mindestens zwei zueinander parallele Begrenzungsebenen als Haupttrag- und Verbindungsebene zur Verbindung des Bauelements mit anderen Bauelementen gleicher oder ähnlicher Gestaltung ausgebildet sind. Das beschriebene Bauelement kann insbesondere zur Gestaltung eines Trag- und Stützwerkes verwendet werden mit wenigstens zwei Turmelementen und wenigstens einem von den Turmelementen getragenen Obergurt, wobei die Turmelemente übereinander angeordnete und miteinander verbundene gleichartige, quaderförmige räumliche Bauelemente aufweisen und der Obergurt nebeneinander angeordnete und miteinander verbundene gleichartige räumliche Bauelemente aufweist und die Turmelemente von Fundamentalelementen getragen sind. Die Offenlegungsschrift JP H03 156065 A betrifft die Bereitstellung einer dreidimensionalen Gerüststruktur, welche durch eine Vielzahl von miteinander verbundenen Stangenelementen errichtbar ist, wobei die Gerüststruktur eine Torausnehmung aufweist, deren die Torausnehmung vertikal begrenzenden Pfostenstangen durch ein daran befestigtes, horizontal verlaufendes Stützelement stabilisiert sind. Das Patent US 5,390,463 betrifft ein modulares Fachwerksystem, umfassend vorgefertigte quaderförmige Module, insbesondere zur Gestaltung eines Schutz- und/oder Arbeitsgerüstes mit wenigstens zwei Turmelementen und wenigstens einem von den Turmelementen getragenen Obergurt, wobei die Turmelemente übereinander angeordnete und miteinander verbundene gleichartige quaderförmige Module aufweisen und der Obergurt nebeneinander angeordnete und miteinander verbundene gleichartige quaderförmige Module aufweist. Die quaderförmigen Module können je nach Ausführungsform vier parallele in Längsrichtung verlaufende Rundstäbe und jeweils vier die Rundstäbe an den Enden entweder diagonal oder parallel zu den Seiten der quaderförmigen Module angeordnete, kastenförmige Querstäbe aufweisen. Die Offenlegungsschrift JP 2004 270403 A betrifft eine Schutzgerüstinstallation, umfassend wenigstens zwei Turmelemente und wenigstens einen von den Turmelementen getragenen Obergurt, wobei die Turmelemente übereinander angeordnete und miteinander verbundene quaderförmige Module aufweisen und der Obergurt nebeneinander angeordnete und miteinander verbundene quaderförmige Module umfasst, wobei die Verbindung zwischen einem Turmelement und dem Obergurt mittels eines diesen beiden gemeinsamen würfelförmigen Adaptermoduls erfolgt und die Turmelemente von Fundamentelementen getragen sind. Das Gebrauchsmuster DE 94 08 443.2 betrifft ein für den Laden- und/oder Ausstellungsbau dienendes Rahmenelement mit einem rechteckförmigen Rahmen, einem in diesem Rahmen etwa parallel zu einer Rahmenseite und in einem vorgegebenen Abstand von dieser vorgesehenen Aussteifungselement, das zwei im Wesentlichen parallele, durch einen Abstand voneinander getrennte längliche Elemente aufweist, die beide in einer gemeinsamen Ebene liegen, welche im Wesentlichen senkrecht zur Ebene des Rahmens verläuft, wobei die länglichen Elemente an beiden Enden mit dem dortigen Teil des Rahmens fest verbunden, insbesondere verschweißt sind. Eine Vielzahl derartiger Rahmenelemente kann zur Gestaltung eines Stützgerüsts, beispielsweise zum Aufbau von Messeständen und Regalen, verwendet werden und dient dort in gleicher Weise für waagerechte Verbindungen sowie für senkrechte Konstruktionen, wobei das Rahmenelement bei vertikaler Montage ein einfaches Einhängen von Teilen in den parallelen länglichen Elementen des Aussteifungselements ermöglicht. In einer Ausführungsform wird durch Verwendung einer Vielzahl von derartigen Rahmenelementen und zugeordneten Knotenpunktteilen ein Portal zusammengesetzt, umfassend zwei Turmelemente und einem von den Turmelementen getragenen Obergurt, wobei die Turmelemente übereinander angeordnete und miteinander verbundene gleichartige, quaderförmige, aus den Rahmen zusammengesetzten Module aufweisen und der Obergurt nebeneinander angeordnete und miteinander verbundene gleichartige, quaderförmige und aus den Rahmen zusammengesetzte Module umfasst, und wobei die Verbindung zwischen einem Turmelement und dem Obergurt mittels eines diesen beiden gemeinsamen würfelförmigen Adaptermoduls erfolgt. Die Offenlegungsschrift US 2013/2917477 A1 betrifft die Verbindung einer Mehrzahl von Strukturträgern mit jeweiligen Erweiterungselementen, die über einen Verbinderblock verbunden sind. Die Strukturträger und die jeweils zugeordneten Erweiterungselementen weisen Verbinder auf, die als mit Löchern versehene Laschen ausgebildet sind. Die Offenlegungsschrift EP 2 009 198 A2 betrifft ein Gerüstmodul zur Realisierung einer Gerüststruktur für Bauarbeiten an Gehäusen, Infrastrukturen oder Denkmälern. Beschrieben wird darüber hinaus ein Verfahren zur Errichtung eines Gerüstes, bei dem eine Mehrzahl von horizontal verlaufenden Gerüstabschnitten auf einem Untergrund fertiggestellt wird und nachfolgend die hergestellten horizontal verlaufenden Gerüstabschnitte mittels eines Krans aufeinander gestapelt werden. Die Offenlegungsschrift US20140026514 A1 betrifft eine portable Gerüststruktur, aufweisend eine Mehrzahl von Horizontalträgern und eine Mehrzahl von Vertikalträgern, jeweils umfassend eine erste Kupplungseinrichtung, und eine Mehrzahl von Verbindungselementen, die jeweils eine Mehrzahl von zweiten Kupplungseinrichtungen aufweisen. Die ersten Kupplungseinrichtungen und die korrespondierenden zweiten Kupplungseinrichtungen sind mittels eines jeweiligen Horizontalträgers starr in Eingriff bringbar zur Festlegung einer Strukturstufe oder -lage, umfassend zumindest vier Verbindungselemente, die in einem Rechteck angeordnet sind, wobei zwei benachbarte Verbindungselemente jeweils mittels eines Horizontalträgers verbunden sind, und wobei im Bereich der die Horizontalträger begrenzten Fläche zwei Deckelemente angeordnet sind. Eine Mehrzahl von derartigen Strukturlagen sind vertikal übereinander angeordnet, wobei vertikal benachbarte Strukturlagen mittels einer Mehrzahl von Vertikalträgern verbunden sind. Das Dokument offenbart darüber hinaus ein Verfahren zur Bereitstellung einer portablen Gerüststruktur und zum Zusammenbau/Demontieren einer solchen portablen Struktur. Dabei wird die portable Struktur durch Zusammenfügung einer Mehrzahl von Verbindungseinrichtungen, Horizontalträger, Vertikalträgern sowie Abdeckelementen erstellt. Hierzu werden zunächst durch zumindest jeweiliges Verbinden von vier Horizontalträgern mit vier Verbindungselementen und zwei Deckelementen eine erste und zweite Strukturlage aufgebaut. Danach wird eine der Strukturlagen gegenüber der anderen angehoben und beide vertikal beabstandeten Strukturlagen mittels Vertikalträgern an jeweiligen Verbindungselementen verbunden. Die miteinander verbundenen Strukturlagen werden alsdann zusammen angehoben, und nachfolgend mit einer weiteren, wie beschrieben zusammengesetzten Strukturlage mittels Vertikalträgern verbunden, wobei dieser Schritt solange wiederholt wird, bis die gewünschte Gerüststruktur erreicht ist.The disclosure document DE 21 09 088 A1 relates to a spatial component for the formation of supporting structures, consisting of a prismatic hollow body with mutually opposite, mutually parallel boundary planes in pairs, of which at least two mutually parallel boundary planes as the main support and connection plane for connecting the component with other components of the same or similar design are trained. The structural element described can be used in particular to design a supporting structure with at least two tower elements and at least one upper chord carried by the tower elements, the tower elements being arranged one above the other and have interconnected, similar, cuboid spatial components and the top chord has similar spatial components arranged next to one another and connected to one another, and the tower elements are supported by fundamental elements. The disclosure document JP H03 156065 A relates to the provision of a three-dimensional scaffolding structure which can be erected by a plurality of rod elements connected to one another, the scaffolding structure having a gate recess, the post bars of which vertically delimiting the gate recess are stabilized by a horizontally extending support element attached to it. The patent U.S. 5,390,463 relates to a modular framework system, comprising prefabricated cuboid modules, in particular for the design of a protective and / or work scaffold with at least two tower elements and at least one top chord carried by the tower elements, the tower elements having similar cuboid modules arranged one above the other and connected to one another and the top chord arranged next to one another and having similar cuboid modules connected to one another. Depending on the embodiment, the cuboid modules can have four parallel round bars running in the longitudinal direction and four of the round bars at the ends, either diagonally or parallel to the sides of the cuboid modules, box-shaped cross bars. The disclosure document JP 2004 270403 A relates to a protective scaffolding installation, comprising at least two tower elements and at least one upper chord carried by the tower elements, the tower elements having cuboid modules arranged one above the other and connected to one another and the upper chord comprising cuboid modules arranged next to one another and connected to one another, the connection between a tower element and the upper chord by means of one of these two common cube-shaped adapter module takes place and the tower elements are supported by foundation elements. The utility model DE 94 08 443.2 concerns a store and / or exhibition building serving frame element with a rectangular frame, a stiffening element provided in this frame approximately parallel to a frame side and at a predetermined distance therefrom, which has two essentially parallel elongated elements separated by a distance, both in a common The plane lies essentially perpendicular to the plane of the frame, the elongate elements being firmly connected, in particular welded, to the part of the frame there at both ends. A large number of such frame elements can be used to design a support structure, for example to set up exhibition stands and shelves, and are used there in the same way for horizontal connections as well as for vertical constructions, the frame element being a simple suspension of parts in the parallel elongated elements when mounted vertically of the stiffening element. In one embodiment, a portal is assembled by using a plurality of such frame elements and associated node parts, comprising two tower elements and an upper chord carried by the tower elements, the tower elements having similar, cuboidal modules arranged one above the other and connected to one another, composed of the frame, and the upper chord Identical, cuboidal modules composed of the frame and arranged next to one another and connected to one another, and wherein the connection between a tower element and the upper chord is made by means of a cube-shaped adapter module common to these two. The disclosure document US 2013/2917477 A1 relates to the connection of a plurality of structural supports with respective extension elements, which are connected via a connector block. The structural supports and the respectively assigned expansion elements have connectors which are designed as brackets provided with holes. The disclosure document EP 2 009 198 A2 relates to a framework module for realizing a framework structure for construction work on housings, infrastructures or monuments. In addition, a method for erecting a scaffold is described in which a plurality of horizontally running scaffolding sections are completed on a substrate and the horizontally running scaffolding sections produced are subsequently stacked on top of one another by means of a crane. The disclosure document US20140026514 A1 relates to a portable scaffold structure, having a plurality of horizontal beams and a plurality of vertical beams, each comprising a first coupling device, and a plurality of connecting elements, which each have a plurality of second coupling devices. The first coupling devices and the corresponding second coupling devices can be rigidly brought into engagement by means of a respective horizontal beam to define a structural step or layer, comprising at least four connecting elements which are arranged in a rectangle, with two adjacent connecting elements each being connected by means of a horizontal beam, and with two cover elements are arranged in the area of the surface bounded by the horizontal beams. A plurality of such structural layers are arranged vertically one above the other, with vertically adjacent structural layers being connected by means of a plurality of vertical supports. The document also discloses a method for providing a portable scaffolding structure and for assembling / disassembling such a portable structure. The portable structure is created by joining a plurality of connecting devices, horizontal beams, vertical beams and cover elements. For this purpose, a first and second structural layer are first built up by at least each respective connection of four horizontal beams with four connecting elements and two cover elements. Then one of the structural layers is raised relative to the other and both vertically spaced structural layers are attached to respective connecting elements by means of vertical supports connected. The interconnected structural layers are then raised together, and subsequently connected to a further structural layer assembled as described by means of vertical beams, this step being repeated until the desired framework structure is achieved.

Der Erfindung liegt die Aufgabe zugrunde, ein Gerüst der einleitend beschriebenen Art für den Freileitungsbau zu vereinfachen, um so den Aufwand und auch die für das Errichten und Abbauen des Gerüsts jeweils erforderliche Zeit zu verkürzen.The invention is based on the object of simplifying a scaffold of the type described in the introduction for overhead line construction in order to shorten the effort and also the time required for erecting and dismantling the scaffolding.

Zur Lösung dieser Aufgabe schlägt die Erfindung ein Schutz- und/oder Arbeitsgerüst für den Freileitungsbau mit den Merkmalen des Anspruchs 1 vor, mit wenigstens zwei Turmelementen und wenigstens einem von dem Turmelementen getragenen Obergurt, wobei die Turmelemente übereinander angeordnete und miteinander verbundene gleichartige quaderförmige und vorgefertigte Module aufweisen und der wenigstens eine Obergurt nebeneinander angeordnete und miteinander verbundene gleichartige quaderförmige und vorgefertigte Module aufweist und die Verbindung zwischen einem Turmelement und dem wenigstens einen Obergurt mittels eines diesen beiden gemeinsamen würfelförmigen Adaptermoduls erfolgt. Das Gerüst steht mit den Turmelementen auf jeweils einem Fundamentelement.To solve this problem, the invention proposes a protective and / or work scaffolding for overhead line construction with the features of claim 1, with at least two tower elements and at least one upper chord carried by the tower elements, the tower elements being arranged on top of one another and connected to one another, similar cuboid and prefabricated Have modules and the at least one top chord arranged next to one another and connected to one another has similar cuboid and prefabricated modules and the connection between a tower element and the at least one top chord is made by means of a cube-shaped adapter module common to these two. The scaffolding and the tower elements each stand on a foundation element.

Die Module für die Turmelemente und den wenigstens einen Obergurt sind vorgefertigt. Dabei können sie in gleicher Weise ausgebildet sein. Die Flächen des würfelförmigen Adaptermoduls können bezüglich ihrer Dimensionierung den Stirnflächen der quaderförmigen Module entsprechen, mit denen Turmelemente und Obergurt versehen sind.The modules for the tower elements and the at least one upper chord are prefabricated. They can be designed in the same way. The dimensions of the surfaces of the cube-shaped adapter module can correspond to the front surfaces of the cuboid-shaped modules with which the tower elements and the upper flange are provided.

Sowohl die quaderförmigen Module als auch die Adaptermodule sind als Stabwerk ausgebildet, wobei bei den quaderförmigen Modulen für Turmelemente und den wenigstens einen Obergurt die in Längsrichtung derselben verlaufenden Stäbe des jeweiligen Moduls länger sind als die quer dazu verlaufenden Stäbe. Im Bedarfsfall kann zur Stabilisierung der Module und somit des Gerüstes an wenigstens zwei aneinander gegenüberliegenden Seiten des Moduls und/oder des Adaptermoduls jeweils mindestens eine diagonale Strebe vorgesehen sein. Insbesondere bei den längeren, quaderförmigen Modulen kann in der Mitte der Längserstreckung gegebenenfalls wenigstens eine in einer Ebene quer zur Längsrichtung des Moduls verlaufende diagonale Strebe angebracht sein.Both the cuboid modules and the adapter modules are designed as a framework, with the cuboid modules for tower elements and the at least one upper chord extending in the longitudinal direction of the same rods respective module are longer than the transverse bars. If necessary, at least one diagonal strut can be provided on at least two mutually opposite sides of the module and / or the adapter module to stabilize the modules and thus the framework. In the case of the longer, cuboid modules in particular, at least one diagonal strut running in a plane transverse to the longitudinal direction of the module can optionally be attached in the middle of the longitudinal extent.

Verbindungselemente sind an den Enden der quaderförmigen Module der Turmelemente und des wenigstens einen Obergurts und an wenigstens drei Seiten der Adaptermodule vorgesehen. Die Verbindungselemente sind auf einfache Weise als mit Löchern versehene Laschen ausgebildet, wobei ein Teil der Verbindungselemente als Doppellasche ausgebildet und die Anordnung der Verbindungselemente an den Modulen so getroffen sein kann, dass im zusammengesetzten Zustand zweier Module eine Einzellasche des einen zwischen die beiden Laschen einer Doppellasche des anderen Moduls greift und ein gemeinsamer Schraubbolzen in die fluchtenden Löcher der eine Verbindungsanordnung darstellenden Laschen gesteckt ist.Connecting elements are provided at the ends of the cuboid modules of the tower elements and the at least one upper flange and on at least three sides of the adapter modules. The connecting elements are designed in a simple manner as tabs provided with holes, with some of the connecting elements being designed as double tabs and the arrangement of the connecting elements on the modules such that when two modules are assembled, a single tab of one is between the two tabs of a double tab of the other module engages and a common screw bolt is inserted into the aligned holes of the tabs constituting a connecting arrangement.

Die laschenförmigen Verbindungselemente sind an den Ecken der stirnseitigen Begrenzungsflächen der Module derart angebracht, dass die jeweils diagonal paarweise einander gegenüberliegenden Laschen einer Verbindung zwischen zwei Modulen sich zueinander parallelen Ebenen erstrecken und die Ebenen des einen Paares gegenüber den Ebenen des anderen Paares um 90° versetzt angeordnet sind. Auf diese Weise können auf die Module einwirkende Seitenkräfte besser aufgefangen werden.The tab-shaped connecting elements are attached to the corners of the front-side boundary surfaces of the modules in such a way that the tabs of a connection between two modules, diagonally opposite in pairs, extend planes parallel to one another and the planes of one pair are offset by 90 ° relative to the planes of the other pair are. In this way, the side forces acting on the modules can be better absorbed.

Die Module des zumindest einen Obergurtes können mit einer zusätzlichen Komponente versehen sein, wobei die Komponenten der Module sich in montiertem Zustand derselben zu einer in Längsrichtung des Obergurts verlaufenden begehbaren Fläche ergänzen, die mit einer Absturzsicherung versehen ist. Die für ein Turmelement vorgesehenen Module können ebenfalls mit einer zusätzlichen Komponente versehen sein, wobei diese Komponenten in montiertem Zustand des Turmelementes zu sich zu einem vertikalen Steiggang mit Rückenschutz und Ruheplattformen ergänzen.The modules of the at least one upper chord can be provided with an additional component, the components of the modules complementing each other in the assembled state of the same to form a walk-on area which runs in the longitudinal direction of the upper chord and is provided with a fall protection device. The Modules provided for a tower element can also be provided with an additional component, these components supplementing each other in the assembled state of the tower element to form a vertical access passage with back protection and resting platforms.

Das Errichten des Gerüstes gemäß der Erfindung kann in der Weise erfolgen, dass zunächst auf dem Boden der aus den quaderförmigen Modulen und den Adaptermodulen zusammengesetzte Obergurt montiert wird, der dann mittels wenigstens einer Hubeinrichtung um eine Wegstrecke angehoben wird, welche die Anordnung jeweils eines für die Turmelemente vorgesehenen Moduls in einer Position ermöglicht, in welcher es mit dem Obergurt durch Befestigung an dem jeweiligen dafür vorgesehenen Adaptermodul verbunden wird. Dies kann auf dem Boden unter Verwendung z.B. von kleinen Montagegerüsten geschehen, deren Höhe die Länge eines quaderförmigen Moduls nicht zu übersteigen braucht. Nach Anbringen des ersten quaderförmigen Moduls am Adaptermodul des Obergurtes wird letzteres in weiterer Folge mit den jeweils bereits montierten Modulen für die Turmelemente schrittweise um eine entsprechende Distanz angehoben, um so jeweils nacheinander weitere Module für die Turmelemente anzubringen und das Gerüst zu komplettieren und dann das Gerüst mit den Turmelementen auf entsprechend vorbereitete Fundamentelemente aufzusetzen und mit diesen zu verbinden.The erection of the scaffolding according to the invention can be done in such a way that the upper chord composed of the cuboid modules and the adapter modules is first mounted on the floor, which is then raised by means of at least one lifting device by a distance, which the arrangement in each case one for the Tower elements provided module allows in a position in which it is connected to the top belt by fastening to the respective adapter module provided. This can be done on the floor using, for example, small assembly scaffolding whose height does not need to exceed the length of a cuboid module. After the first cuboid module has been attached to the adapter module of the top chord, the latter is then connected to the modules that have already been installed for the tower elements gradually increased by a corresponding distance in order to attach further modules for the tower elements one after the other and to complete the scaffolding and then to place the scaffolding with the tower elements on appropriately prepared foundation elements and connect them to them.

Die Länge der quaderförmigen Module wird im Allgemeinen so bemessen sein, dass es ohne aufwendige Maßnahmen möglich ist, die Module für die Turmelemente jeweils bodennah zu montieren, sodass ein Betreten des Gerüstes während der Montage nicht unbedingt erforderlich ist. Im Allgemeinen wird ein kleines Arbeitsgerüst ausreichen, um das jeweils nächste Modul am zu komplettierenden Turmelement anzuhängen.The length of the cuboid modules will generally be dimensioned so that it is possible to assemble the modules for the tower elements close to the ground without complex measures, so that it is not absolutely necessary to step onto the scaffolding during assembly. In general, a small scaffold will be sufficient to attach the next module to the tower element to be completed.

Die Anzahl der Turmelemente wird von der Länge des Obergurtes und gegebenenfalls auch von der Tragfähigkeit des jeweils einzusetzenden wenigstens einen Hubelementes abhängen. Letzteres gilt auch für die maximale Höhe des zu errichtenden Gerüstes, wobei dessen Standfähigkeit im Bedarfsfall durch Abspannseile gesichert werden kann.The number of tower elements will depend on the length of the upper chord and possibly also on the load-bearing capacity of the at least one lifting element to be used. The latter also applies to the maximum height of the scaffolding to be erected, whereby its stability can be secured by guy ropes if necessary.

In der Zeichnung sind Ausführungsbeispiele der Erfindung dargestellt. Es zeigen

Figuren 1a - c
unterschiedliche Ausführungen eines Gerüstes,
Figur 2
einen Ausschnitt aus einem Gerüst gemäß Figur 1a - c, welcher die Verbindung zwischen Obergurt und Turmelement in größerem Maßstab zeigt.
Figur 3
die Seitenansicht und Draufsicht eines quaderförmigen Moduls,
Figur 4
Vorderansicht und Draufsicht eines Adaptermoduls.
Figur 5
Draufsicht und Seitenansicht eines Fundamentelementes.
Exemplary embodiments of the invention are shown in the drawing. Show it
Figures 1a - c
different versions of a scaffold,
Figure 2
a section of a framework according to Figure 1a - c which shows the connection between the top chord and the tower element on a larger scale.
Figure 3
the side view and top view of a cuboid module,
Figure 4
Front view and top view of an adapter module.
Figure 5
Top view and side view of a foundation element.

Die drei in Figur 1 dargestellten Gerüste weisen insoweit denselben Grundaufbau auf, als die jeweils mit einem Obergurt 12, zwei Turmelementen 14 und zwei Fundamentelementen 16 versehen sind. Auf letzteren sind die Turmelemente 14 aufgesetzt.The three in Figure 1 The frameworks shown have the same basic structure in that they are each provided with an upper chord 12, two tower elements 14 and two foundation elements 16. The tower elements 14 are placed on the latter.

Obergurt 12 und Turmelemente 14 sind im Wesentlichen aus quaderförmigen Modulen 18 zusammengesetzt, von denen eines in Figur 3 dargestellt ist. Jedes der Module ist als Stabwerk ausgebildet und mit vier parallelen in Längsrichtung verlaufenden Stäben 20 versehen, die am jeweiligen Ende des Quaders durch vier Querstäbe miteinander verbunden sind. Die Längsstäbe 20 weisen eine merklich größere Länge auf als die Querstäbe, sodass bei dem in den Zeichnungen dargestellten Ausführungsbeispiel an wenigstens zwei gegenüberliegenden Seiten 24, 26 des Moduls eine Diagonalstrebe 28 angebracht ist. In Figur 3 ist eine Anordnung dargestellt, bei welcher auf jeder der beiden Seiten Streben 28 vorgesehen sind, die jeweils von einem Ende des Moduls ausgehen und sich in einer das Modul hälftig unterteilenden Ebene treffen und dort am gegenüberliegenden Längsstab angebracht sind. Weiterhin ist eine weitere in dieser Ebene verlaufende Diagonalstrebe in der Strebe 30 vorgesehen. Die Anzahl und Anordnung dieser Streben hängt von den jeweiligen Gegebenheiten ab, insbesondere auch von der Länge der Module, die allgemein zum Beispiel etwa zwei Meter betragen kann.The top chord 12 and tower elements 14 are essentially composed of cuboid modules 18, one of which is shown in FIG Figure 3 is shown. Each of the modules is designed as a framework and provided with four parallel rods 20 running in the longitudinal direction, which are connected to one another at the respective end of the cuboid by four transverse rods. The longitudinal rods 20 have a significantly greater length than the transverse rods, so that in the exemplary embodiment shown in the drawings, a diagonal strut 28 is attached to at least two opposite sides 24, 26 of the module. In Figure 3 an arrangement is shown in which struts 28 are provided on each of the two sides, each extending from one end of the module and meeting in a plane dividing the module in half and being attached there to the opposite longitudinal rod. Furthermore, another diagonal strut running in this plane is provided in the strut 30. The number and arrangement of these struts depends on the particular circumstances, in particular also on the length of the modules, which can generally be about two meters, for example.

Die Verbindung zwischen Obergurt 12 und dem jeweiligen Turmelement 14 erfolgt unter Verwendung eines Adaptermoduls 32, welches aus Stäben 34 mit derselben Länge zusammengesetzt ist und somit die Form eines Würfels aufweist (Figur 4). Die Flächen des Würfels entsprechen bezüglich Dimensionen und Form den Stirnflächen 27 der quaderförmigen Module. Weil die quaderförmigen Module von Obergurt und Turmelementen zumindest bezüglich ihrer Querschnittsform und -größe übereinstimmen, können somit sowohl die an das jeweilige Adaptermoduls 32 angrenzenden Module 18 des Obergurtes 12 als auch die entsprechenden Module der Turmelemente 14 mit dem Adaptermodul verbunden werden, wie dies insbesondere aus Figur 2 ersichtlich ist. Das Adaptermodul 32 ist an zwei seiner einander gegenüberliegenden Flächen mit jeweils einem quaderförmigen Modul 18 verbunden. An einer weiteren, zu den beiden vorgenannten Flächen der senkrechten Fläche, die das Adaptermodul unterseitig begrenzt, ist jeweils das oberste quaderförmige Modul für das jeweilige Turmelementes 14 angebracht.The connection between the upper chord 12 and the respective tower element 14 is made using an adapter module 32, which is composed of rods 34 of the same length and thus has the shape of a cube ( Figure 4 ). The surfaces of the cube correspond in terms of dimensions and shape to the end faces 27 of the cuboid modules. Because at least the cuboid modules of the top chord and tower elements coincide with regard to their cross-sectional shape and size, both the modules 18 of the upper chord 12 adjoining the respective adapter module 32 and the corresponding modules of the tower elements 14 can thus be connected to the adapter module, as shown in particular from Figure 2 can be seen. The adapter module 32 is connected to a cuboid module 18 on two of its opposite surfaces. The uppermost cuboid module for the respective tower element 14 is attached to a further, to the two aforementioned surfaces of the vertical surface that delimits the adapter module on the underside.

Zur Herstellung der Verbindungen zwischen den einzelnen Modulen sind die quaderförmigen Module zumindest an ihren stirnseitigen Flächen mit Verbindungelementen versehen. Entsprechende Verbindungselemente befinden sich an wenigstens zwei aneinander gegenüberliegenden Flächen des Adaptermoduls 32 und wenigstens einer dazu senkrechten Fläche, die in montiertem Zustand des Gerüstes sich an der Unterseite des Adaptermoduls 32 befindet.To produce the connections between the individual modules, the cuboid modules are provided with connection elements at least on their end faces. Corresponding connecting elements are located on at least two mutually opposite surfaces of the adapter module 32 and at least one surface perpendicular thereto, which is located on the underside of the adapter module 32 in the assembled state of the frame.

Zur Befestigung der Module aneinander sind diese mit Befestigungsmitteln versehen, die als Laschen ausgebildet sind. An den quaderförmigen Modulen ist die Anordnung so getroffen, dass an jeder Stirnseite an den vier Ecken derselben abwechselnd Einzellaschen 36 und Doppellaschen 38 vorgesehen sind, wobei die Doppellaschen parallel zueinander und in einem Abstand voneinander angeordnet sind, derart, dass zwischen die beiden Laschen einer Doppellasche 38 eines Moduls einer Einzellasche eines benachbarten Moduls einsteckbar ist. Alle Laschen sind mit einem Loch versehen, wobei die Löcher aller Laschen in der Verbindungsposition miteinander fluchten, sodass sie einen Schraubenbolzen oder ein anderes geeignetes Verbindungsmittel aufnehmen können, um die Laschen beider benachbarten Module und damit die Module miteinander zu verbinden. Dabei ist die Anordnung so getroffen, dass die Laschen eines ersten Paares diagonal einander gegenüberliegender Verbindungen zu den Laschen der beiden anderen einander diagonal gegenüberliegenden Verbindungen um 90° um eine Achse verschwenkt angeordnet sind, welche parallel zu den Längsstäben 20 des jeweiligen Moduls verläuft, wie dies auch mit Draufsicht der Figur 5 erkennen lässt.To fasten the modules to one another, they are provided with fastening means that are designed as tabs. The arrangement of the cuboid modules is such that alternating single tabs 36 and double tabs 38 are provided on each end face at the four corners thereof, the double tabs being arranged parallel to one another and at a distance from one another, such that between the two tabs of a double tab 38 of a module of a single tab of an adjacent module can be inserted. All brackets are provided with a hole, the holes of all brackets being aligned with one another in the connection position so that they can receive a screw bolt or other suitable connecting means in order to connect the brackets of both adjacent modules and thus the modules to one another connect to. The arrangement is such that the tabs of a first pair of diagonally opposite connections to the tabs of the two other diagonally opposite connections are arranged pivoted by 90 ° about an axis which runs parallel to the longitudinal bars 20 of the respective module, like this also with top view of the Figure 5 reveals.

Die Adaptermodule 32 sind in entsprechender Weise mit derartigen Verbindungslaschen versehen mit dem Unterschied, dass diese sich nicht nur an zwei gegenüberliegenden Seiten 12 zur Verbindung mit den Modulen 18 des Obergurtes vorgesehen sind, sondern auch wenigstens an einer dritten Seite, die in montiertem Zustand der Teile nach unten, also dem zugehörigen Turmelement zugekehrt ist. Bei dem in der Zeichnung dargestellten Ausführungsbeispiel ist auch die Seite mit Verbindungslaschen versehen, welche im montierten Zustand nach oben gekehrt ist, also der unteren Seite gegenüberliegt. Dadurch kann die Handhabung des Adaptermoduls bei der Montage vereinfacht werden.The adapter modules 32 are provided in a corresponding manner with such connecting straps, with the difference that they are not only provided on two opposite sides 12 for connection to the modules 18 of the upper chord, but also at least on a third side, which is in the assembled state of the parts down, so facing the associated tower element. In the embodiment shown in the drawing, the side is also provided with connecting straps which, in the assembled state, is turned upwards, that is, opposite the lower side. This can simplify the handling of the adapter module during assembly.

Die beiden Turmelemente 14 sind auf jeweils einem Fundamentelement 41 (Figur 5) aufgesetzt, welches aus zwei Längsträgern, zum Beispiel Doppel-T-Trägern 42 und einigen diese Längsträger verbindenden Querträgern 44 besteht und auf dem das Gerüst aufnehmenden Boden angeordnet und gegebenenfalls verankert ist. Die Fundamentelemente 41 können in Abhängigkeit von der Beschaffenheit des Bodens, auf welchem sie aufgesetzt sind unterseitig mit Fortsätzen oder dergleichen versehen sein, die eine gegebenenfalls erforderliche Sicherung gegen Verschieben bewirken. Die in der Mitte befindlichen Querträger 44 sind ebenfalls mit Einzellaschen 36 und Doppellaschen 38 entsprechend der Anbringung der Laschen an dem quaderförmigen Modul derart versehen, dass das untere Ende des jeweils untersten Moduls des Turmelementes mit dem Fundamentelement 41 in der beschriebenen Weise verbunden werden kann. Insbesondere Figur 5 der Zeichnung lässt erkennen, wie die Laschen der Verbindungen gegeneinander versetzt angeordnet sind, derart, dass seitliche Kräfte besser aufgefangen werden können. Eine - gegebenenfalls zusätzliche - Sicherung jedes Fundamentelements kann gegebenenfalls zusätzlich durch an den beiden Enden desselben aufgelegte Gewichte 45, beispielsweise Betonelemente erfolgen, die oberseitig mit einer Öse 52 der gleichen versehen sind, damit sie mit einem Hubelement in die gewünschte Position gebracht bzw. aus dieser entfernt werden können.The two tower elements 14 are each on a foundation element 41 ( Figure 5 ), which consists of two longitudinal beams, for example double-T beams 42 and some cross beams 44 connecting these longitudinal beams and is arranged and optionally anchored on the floor receiving the scaffolding. The foundation elements 41 can, depending on the nature of the ground on which they are placed, be provided with extensions or the like on the underside, which provide a safeguard against displacement that may be required. The cross members 44 located in the middle are also provided with single straps 36 and double straps 38 corresponding to the attachment of the straps to the cuboid module in such a way that the lower end of the respective lowermost module of the tower element is connected to the foundation element 41 in the manner described can be. Especially Figure 5 The drawing shows how the tabs of the connections are offset from one another in such a way that lateral forces can be better absorbed. An - possibly additional - securing of each foundation element can also be done by means of weights 45, for example concrete elements, placed on both ends of the same, which are provided with an eyelet 52 of the same on the top so that they can be brought into the desired position with a lifting element or out of this can be removed.

Das in Figur 1c) dargestellte Gerüst ist entlang dem Obergurt mit einer Arbeitsplattform 46 versehen, der ein Geländer 48 zugeordnet ist. Die Module des Obergurts, sowie die Adaptermodule sind mit entsprechenden zusätzlichen Komponenten versehen, die sich im montierten Zustand der Module zu dieser Arbeitsplattform in dem oder den Geländer(n) ergänzen. Das rechte Turmelement des Gerüstes gemäß Figur 1c ist mit einem vertikalen Steiggang mit Rückenschutz und Ruheplattformen versehen. Die Module dieses Turmelementes sind mit entsprechenden Komponenten versehen sind, die sich zu dem Steiggang usw. ergänzen.This in Figure 1c ) The frame shown is provided along the top chord with a work platform 46 to which a railing 48 is assigned. The modules of the upper chord and the adapter modules are provided with corresponding additional components which, when the modules are installed, complement each other to form this work platform in the railing (s). The right tower element of the scaffolding according to Figure 1c is provided with a vertical climb with back protection and resting platforms. The modules of this tower element are provided with corresponding components that complement each other to the climbing gear, etc.

Das Gerüst gemäß Figur 1a ist aufgrund seiner größeren Höhe mit Abspannseilen 54 gesichert.The scaffolding according to Figure 1a is secured with guy ropes 54 due to its greater height.

Das Gerüst gemäß der Erfindung kann auch mehr als zwei Turmelemente aufweisen.The framework according to the invention can also have more than two tower elements.

Es besteht natürlich die Möglichkeit, zwei oder mehr Gerüste der vorbeschriebenen Art nebeneinander aufzubauen, beispielsweise zu beiden Seiten einer Straße oder dergleichen, um über die Straße geführte Hochspannungsleitungen abzuspannen.There is of course the possibility of building two or more scaffolding of the type described above next to one another, for example on both sides of a street or the like, in order to tension high-voltage lines running across the street.

BezugszeichenlisteList of reference symbols

1010
Gerüstframework
1212
ObergurtTop chord
1414th
TurmelementTower element
1818th
Quaderförmiges ModulCuboid module
2020th
LängsstabLongitudinal bar
1111
QuerstabCross bar
2424
Seite von 18Page of 18
2626th
Seite von 18Page of 18
2727
Stirnfläche von 18Face of 18
2828
Strebestrut
3030th
Strebestrut
3232
AdaptermodulAdapter module
3333
BegrenzungsflächeBoundary surface
3434
StabRod
3636
EinzellascheSingle tab
3838
DoppellascheDouble flap
4040
Loch in 36 bzw. 38Hole in 36 or 38
4141
FundamentelementFoundation element
4242
LängsträgerSide member
4444
QuerträgerCross member
4545
GewichteWeights
4646
ArbeitsplattformWorking platform
4848
Geländerrailing
5050
SteiggangAscent
5252
Öseeyelet
5454
AbspannseilGuy rope

Claims (10)

  1. Safety and/or work scaffold (10) for the overhead line construction with at least two tower elements (14) and at least one upper chord (12) carried by the tower elements, wherein the tower elements (14) have similar parallelepiped and prefabricated modules (18) that are arranged one above the other and connected with one another and the at least one upper chord has similar cuboid and prefabricated modules (18) that are arranged next to each other and connected with one another and the connection between one tower element (14) and the at least one upper chord is carried out by means of a cubic adapter module (32) common to these two elements and the tower elements (14) are carried by foundation elements (41), wherein the parallelepiped modules (18) of the tower elements (14) and of the at least one upper chord (12) as well as the adapter modules (32) are designed as a framework and the parallelepiped modules (18) of the tower elements (!4) and of the at least one upper chord (12) are designed with four parallel beams (20) extending in the longitudinal direction of the tower element (14) and/or of the at least one upper chord (12) and respectively four transverse beams (22) that connect the longitudinal beams at their ends, characterized in that the longitudinal beams, the transverse beams and the struts of the respective framework are designed as tubes and the tubes have a rectangular cross-section and that the parallelepiped modules (18) of the tower elements (14) and of the at least one upper chord (12) are provided at their ends, which ends constitute front faces (27), and the adapter modules at provided at least on three sides, which sides constitute boundary surfaces (33), with connecting elements (36, 38), wherein the connecting elements (36, 38) are designed as tabs provided with holes and wherein the tab-shaped connecting elements (36, 38) are fixed at corners of the boundary surfaces (33) provided therewith of the modules (18) of the tower elements (14) and of the at least one upper chord (12) and/or at corners of the front faces provided therewith of the adapter modules (32) in such a manner that the tabs respectively diagonally arranged in pairs of a connection between parallelepiped modules (18) and/or between the parallelepiped modules (18) and the adapter modules (32) extend in planes parallel to each other and the planes of the one pair is placed offset by 90° to the planes of the other pair.
  2. Scaffold according to claim 1, characterized in that the boundary surfaces (33) of the adapter modules (32) and the front faces (27) of the parallelepiped modules (18) of the tower elements and of the at least one upper chord (12) match.
  3. Scaffold according to claim 1, characterized in that the parallelepiped modules (18) of the tower elements (14) and the parallelepiped modules (18) of the at least one upper chord (12) are designed in a similar way.
  4. Scaffold according to one of the preceding claims, characterized in that the length of the beams (34) of the adapter modules (32) corresponds to the length of the transverse beams of the parallelepiped modules (18) of the tower elements (14) and/or of the at least one upper chord (12).
  5. Scaffold according to claim 1, characterized in that the beams (20) of a parallelepiped module (18) of the tower elements (14) and/or of the at least one upper chord (12) that extend in the longitudinal direction of the tower elements (14) and/or of the at least one upper chord (12) are longer than the beams (22) extending transversely thereto.
  6. Scaffold according to one of the preceding claims, characterized in that at least one diagonal strut (28) is respectively provided on at least two opposed sides of a parallelepiped module (18) of the tower elements (14) and/or of the at least one upper chord (12) and/or of the adapter modules (32).
  7. Scaffold according to one of the preceding claims, characterized in that the parallelepiped modules (18) of the tower elements (14) and/or of the at least one upper chord (12) are provided in the middle of their longitudinal extension with at least one diagonal strut (30) extending in a plane transversely to the longitudinal direction of the respective module.
  8. Scaffold according to one of the claims 1 to 7, characterized in that a part of the connecting elements is designed as double tabs (38) and the arrangement of the connecting elements is made in such a way that, the modules being assembled, a connecting element designed as a single tab (36) respectively engages between the two tabs of a connecting element designed as a double tab (38).
  9. Scaffold according to claim 1, characterized in that the modules of the at least one upper chord (12) are provided with an additional component and the components of the modules, the modules being mounted, complement each other to a walkable surface (46) extending in the longitudinal direction of the at least one upper chord, this surface being provided with a fall protection (48), and that the modules (18) provided for at least one tower element of a scaffold are provided with an additional component and, the tower element being mounted, these additional elements complete each other to a vertical climbing facility (50) with back protection and resting platforms.
  10. Scaffold according to one of the preceding claims, characterized in that the foundation elements (41) are provided with longitudinal and transverse beams on which connecting elements (36, 38) are fixed, the design and arrangement of which corresponds to that of the modules (18).
EP17185614.9A 2016-10-05 2017-08-09 Protection and/or work scaffolding and method for erecting it Active EP3306010B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102016118844.1A DE102016118844A1 (en) 2016-10-05 2016-10-05 Protective and / or work scaffold and method for its construction

Publications (2)

Publication Number Publication Date
EP3306010A1 EP3306010A1 (en) 2018-04-11
EP3306010B1 true EP3306010B1 (en) 2020-11-25

Family

ID=59579528

Family Applications (1)

Application Number Title Priority Date Filing Date
EP17185614.9A Active EP3306010B1 (en) 2016-10-05 2017-08-09 Protection and/or work scaffolding and method for erecting it

Country Status (2)

Country Link
EP (1) EP3306010B1 (en)
DE (1) DE102016118844A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442343A (en) * 2018-05-21 2018-08-24 中国水利水电第十四工程局有限公司 A kind of standard module combined support device
CN113323356A (en) * 2021-04-23 2021-08-31 宁波工程学院 A hanging device for construction of building outer wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140026514A1 (en) * 2012-07-25 2014-01-30 Tait Towers, Inc. Portable structure

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2109088C3 (en) * 1971-02-25 1978-03-09 Philipp Holzmann Ag, 6000 Frankfurt Spatial component for the formation of loadbearing structures and supporting structures that are multiple times the largest edge length of the component with regard to their extension
JPH0833074B2 (en) * 1989-11-14 1996-03-29 住金鋼材工業株式会社 Deep frame mounting structure of frame scaffold opening
JPH06248794A (en) * 1993-02-26 1994-09-06 Maeda Corp Large-sized assembled-type moving scaffold
DE9408443U1 (en) * 1993-05-25 1994-10-06 Leitner Gmbh Frame element for shop and / or exhibition construction
US5390463A (en) * 1993-11-24 1995-02-21 Penn Fabrication (U.S.A.) Inc. Modular truss structure
JP2004270403A (en) * 2003-03-12 2004-09-30 Miyaji Construction & Engineering Co Ltd Lightweight box truss system
ITTV20070114A1 (en) * 2007-06-25 2008-12-26 Euroedile S R L SCAFFOLDING MODULE FOR THE CONSTRUCTION OF A SCAFFOLDING STRUCTURE AND ASSEMBLY / DISASSEMBLY METHOD OF THIS STRUCTURE
DE202008009282U1 (en) * 2008-07-10 2009-11-12 Daas, Kamal Lattice structure with evacuation means
US8978338B2 (en) * 2012-05-02 2015-03-17 Les Enceintes Acoustiques Unisson Inc. Structural trusses with monolithic connector plate members

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140026514A1 (en) * 2012-07-25 2014-01-30 Tait Towers, Inc. Portable structure

Also Published As

Publication number Publication date
EP3306010A1 (en) 2018-04-11
DE102016118844A1 (en) 2018-04-05

Similar Documents

Publication Publication Date Title
EP2253764B1 (en) Frame-shaped truss
EP3488060B1 (en) Method for erecting a tower for a wind energy plant
DE19633092A1 (en) Removable facade scaffolding
EP1005598B1 (en) Trelliswork modular scaffolding system
DE102010000472A1 (en) Scaffolding and method for mounting or dismounting such scaffolding
EP3417121B1 (en) Truss system for building a supporting construction
EP2239398B1 (en) Tower
EP3208405B1 (en) Device and method for assembling tower-like structures from pre-fabricated elements
EP3306010B1 (en) Protection and/or work scaffolding and method for erecting it
EP4063588A1 (en) Connecting member
DE102010017803A1 (en) Scaffolding support for gabion-bracket scaffold for workers, has angular shaped bearing element arranged at wire mesh of gabion, and receiver provided with connection unit and hook, which are hung into wire of gabion
DE2146701A1 (en) Multi-storey building construction from prefabricated building units and methods for erecting the same
EP3147424B1 (en) Grid support and grid support system, in particular for universal use within a known work and protection frame
EP3405627B1 (en) Supporting framework
DE202015003670U1 (en) mast
DE102017114090B4 (en) Method of constructing a building
DE3933198C2 (en) Bar grating
WO2019076786A1 (en) Method for erecting a tower, tower segment, supply structure, and tower
WO2020193120A1 (en) Modular frame system for stacking assemblies in industrial system construction
EP3792430A1 (en) Tower
DE2801945A1 (en) STANDARD STEEL BRIDGES AND THEIR COMPONENTS
EP1288392B1 (en) Support structure for the bearing system of a stage, a podium, a scaffold construction or similar
WO2017127947A1 (en) Supporting structure for a hall, stage, stand or bridge construction which can be assembled and disassembled multiple times
CH718252A2 (en) Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times.
DE2057774A1 (en) Mast or tower construction

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20181011

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20181221

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20200727

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1338474

Country of ref document: AT

Kind code of ref document: T

Effective date: 20201215

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502017008340

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: NL

Ref legal event code: FP

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210226

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210225

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210225

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502017008340

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

26N No opposition filed

Effective date: 20210826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20210831

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20210809

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210325

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210809

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210809

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210809

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20170809

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20230823

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20230818

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20231025

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20201125