CH718252A2 - Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times. - Google Patents

Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times. Download PDF

Info

Publication number
CH718252A2
CH718252A2 CH00028/21A CH282021A CH718252A2 CH 718252 A2 CH718252 A2 CH 718252A2 CH 00028/21 A CH00028/21 A CH 00028/21A CH 282021 A CH282021 A CH 282021A CH 718252 A2 CH718252 A2 CH 718252A2
Authority
CH
Switzerland
Prior art keywords
framework
support structure
plane
scaffolding
support
Prior art date
Application number
CH00028/21A
Other languages
German (de)
Inventor
Della Ca Danilo
Original Assignee
Nuessli Switzerland Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nuessli Switzerland Ltd filed Critical Nuessli Switzerland Ltd
Priority to CH00028/21A priority Critical patent/CH718252A2/en
Publication of CH718252A2 publication Critical patent/CH718252A2/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/38Arched girders or portal frames
    • E04C3/40Arched girders or portal frames of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C3/08Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal with apertured web, e.g. with a web consisting of bar-like components; Honeycomb girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/242Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/28Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H3/00Buildings or groups of buildings for public or similar purposes; Institutions, e.g. infirmaries or prisons
    • E04H3/10Buildings or groups of buildings for public or similar purposes; Institutions, e.g. infirmaries or prisons for meetings, entertainments, or sports
    • E04H3/22Theatres; Concert halls; Studios for broadcasting, cinematography, television or similar purposes
    • E04H3/24Constructional features of stages
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0486Truss like structures composed of separate truss elements
    • E04C2003/0491Truss like structures composed of separate truss elements the truss elements being located in one single surface or in several parallel surfaces

Abstract

Die Erfindung betrifft eine Tragstruktur für einen Hallen-, Bühnen-, Tribünen- oder Brückenbau. Sie umfasst eine von zwei wandartigen Gerüststrukturen (1, 2) getragene Trägerstruktur (5), welche sich im Wesentlichen in einer horizontalen Ebene erstreckt und schubsteif in dieser Ebene ist. Die beiden Gerüststrukturen (1, 2), welche sich jeweils in vertikalen Ebenen erstrecken und schubsteif in diesen Ebenen sind, stehen sich mit einem Abstand gegenüber. Die Trägerstruktur (5) ist von untereinander verbundenen und sich zwischen der ersten (1) und der zweiten Gerüststruktur (2) erstreckenden Trägern (6) gebildet und über die Enden dieser Träger (6) derartig mit diesen beiden Gerüststrukturen (1, 2) verbunden, dass in Richtung der vertikalen Ebenen der Gerüststrukturen (1, 2) wirkende horizontale Schubkräfte von der Trägerstruktur (5) auf die Gerüststrukturen (1, 2) übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken. Zudem ist die Verbindung derartige, dass jeder der Träger (6) an einem ersten seiner beiden Enden in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (1; 2) übertragen kann und an seinem zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (2; 1) übertragen kann Auch umfasst die Tragstruktur eine wandartige weitere Gerüststruktur (3, 4), welche sich in einer vertikalen Ebene quer zu den beiden erstgenannten Gerüststrukturen (1, 2) erstreckt und schubsteif in dieser Ebene ist. Die Trägerstruktur (5) ist derartig mit dieser weiteren Gerüststruktur (3, 4) verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebene, in welcher sich diese weitere Gerüststruktur (3, 4) erstreckt, wirken, von der Trägerstruktur (5) auf diese weitere Gerüststruktur (3, 4) übertragbar sind, nicht jedoch Biegemomente, welche um eine parallel zu dieser vertikalen Ebene verlaufende Achse wirken. Durch die Erfindung wird es möglich, die Vorteile von Gerüstbau und Stahlbau zu vereinen und Tragstrukturen für sturmfeste temporäre Hallen-, Bühnen-, Tribünen- oder Brückenbauten zur Verfügung zu stellen, welche trotz der Verwendung von Gerüstwänden wenig Raum für die Struktur benötigen und entsprechend viel nutzbaren Raum zur Verfügung stellen.The invention relates to a support structure for a hall, stage, grandstand or bridge construction. It comprises a support structure (5) carried by two wall-like framework structures (1, 2), which essentially extends in a horizontal plane and is shear-resistant in this plane. The two framework structures (1, 2), which each extend in vertical planes and are shear-resistant in these planes, face one another at a distance. The support structure (5) is formed by supports (6) which are connected to one another and extend between the first (1) and the second framework structure (2) and are connected in this way to these two framework structures (1, 2) via the ends of these supports (6). that horizontal shear forces acting in the direction of the vertical planes of the framework structures (1, 2) can be transferred from the support structure (5) to the framework structures (1, 2), but not bending moments which act around axes running parallel to these planes. In addition, the connection is such that each of the girders (6) can transmit shear forces acting in the longitudinal direction of the girder at a first of its two ends to the scaffolding structure (1; 2) connected to this end, and no shear forces acting in the longitudinal direction of the girder can be transmitted at its second end to the scaffolding structure (2; 1) connected to this end. The support structure also comprises a wall-like further scaffolding structure (3, 4) which extends in a vertical plane transversely to the first two scaffolding structures (1, 2) and is shear-resistant in this plane. The support structure (5) is connected to this further framework structure (3, 4) in such a way that horizontal shearing forces which act in the direction of the vertical plane in which this further framework structure (3, 4) extends are transmitted from the support structure (5) can be transferred to this further framework structure (3, 4), but not bending moments which act about an axis running parallel to this vertical plane. The invention makes it possible to combine the advantages of scaffolding and steel construction and to provide supporting structures for storm-proof temporary halls, stages, grandstands or bridge constructions which, despite the use of scaffolding walls, require little space for the structure and accordingly a lot provide usable space.

Description

TECHNISCHES GEBIETTECHNICAL AREA

[0001] Die Erfindung betrifft Tragstrukturen für einen mehrfach auf- und abbaubaren Hallen-, Bühnen-, Tribünen- oder Brückenbau, sowie ein Verfahren zur Erstellung solcher Tragstrukturen gemäss den Oberbegriffen der unabhängigen Patentansprüche. The invention relates to supporting structures for a hall, stage, grandstand or bridge that can be built and dismantled several times, as well as a method for creating such supporting structures according to the preambles of the independent patent claims.

STAND DER TECHNIKSTATE OF THE ART

[0002] Hallen-, Bühnen-, Tribünen- oder Brückenbauten stellen oftmals temporäre Bauwerke dar, welche für einen einzigen Anlass errichtet und anschliessend wieder abgebaut werden. [0002] Hall, stage, grandstand or bridge constructions often represent temporary structures which are erected for a single occasion and then dismantled again.

[0003] Dabei ist es von herausragender Bedeutung, dass solche Bauwerke unter allen denkbaren Einsatzbedingungen und Belastungen absolut betriebssicher sind und in kürzester Zeit mit möglichst wenig (oftmals vor Ort rekrutiertem) Montagepersonal fachgerecht aufgebaut und wieder abgebaut werden können. Auch sollten die einzelnen Bauteile, aus denen solche Bauwerke erstellt werden, sich für den erneuten Einsatz bei einem anderen ähnlichen Bauwerk eignen, möglichst platzsparend zu lagern sein und ein möglichst geringes Gewicht aufweisen. Auch gibt es zunehmend Bedarf nach temporären Bauten für eine längere, z.B. mehrjährige Benutzung, z.B. als vorübergehende Ersatzlösung bei Neubau oder Sanierung von bestehenden Bauten wie Turnhallen oder Brücken. It is of paramount importance that such structures are absolutely reliable under all conceivable operating conditions and loads and can be professionally assembled and dismantled again in the shortest possible time with as few assembly personnel (often recruited on site). The individual components from which such structures are constructed should also be suitable for reuse in another similar structure, should be able to be stored in as little space as possible and have the lowest possible weight. There is also an increasing need for temporary structures for longer use, e.g. for several years, e.g. as a temporary replacement solution for new construction or the renovation of existing buildings such as gymnasiums or bridges.

[0004] Zum Erstellen von Hallen-, Bühnen-, Tribünen- oder Brückenbauten kommen heute zwei grundsätzlich verschiedene Konstruktionsprinzipien zum Einsatz, nämlich der Gerüstbau und der Stahlbau. To create halls, stages, grandstands or bridges, two fundamentally different construction principles are used today, namely scaffolding and steel construction.

[0005] Der Gerüstbau weist den Vorteil auf, dass sich Raum in Handmontage mit kleinen, standardisierten Bauteilen schnell mit Struktur füllen lässt und dass aufgrund der filigranen Struktur die Bodenbelastung gering ist und keine Fundation erforderlich ist. Zudem weist der Gerüstbau eine grosse Flexibilität bezüglich des Terrainverlaufs und des Anschlusses an angrenzende Bauwerke auf und benötigt ein kleines Lade- und Lagervolumen. Ein weiterer Vorteil besteht in der hohen Verfügbarkeit aufgrund der Verwendung von standardisierten Systemkomponenten. The scaffolding has the advantage that space can be quickly filled with structure in manual assembly with small, standardized components and that due to the filigree structure, the floor load is low and no foundation is required. In addition, the scaffolding has great flexibility with regard to the terrain and the connection to adjacent buildings and requires a small loading and storage volume. Another advantage is the high availability due to the use of standardized system components.

[0006] Ein weiteres, ganz wesentliches Merkmal des Gerüstbaus besteht zudem darin, dass er raumfüllend ist, was insbesondere bei der Erstellung von Hallenbauten, bei denen es darum geht, mit einem möglichst geringen Strukturvolumen einen möglichst grossen umbauten Raum zu schaffen, nachteilig ist und den Gerüstbau deshalb trotz seiner Vorteile in vielen Fällen ungeeignet oder unwirtschaftlich macht für den Bau von Hallen. Dies, weil bei einer sturmfesten Auslegung die Gerüststrukturen der Wände eine Dicke von mehreren Metern aufweisen würden und entsprechend viel Platz beanspruchen würden. Auch sind die heute im Gerüstbau erstellten temporären Bauten, insbesondere wenn sie grosse Spannweiten aufweisen, konstruktiv nicht für eine mehrjährige Benutzung, z.B. als vorübergehende Ersatzlösung bei Neubau oder Sanierung von bestehenden Bauten wie Turnhallen oder Brücken, ausgelegt. Another very important feature of scaffolding is that it fills the room, which is disadvantageous, especially when building halls where the aim is to create the largest possible enclosed space with the smallest possible structural volume Despite its advantages, scaffolding is therefore in many cases unsuitable or uneconomical for the construction of halls. This is because with a storm-proof design, the scaffolding structures of the walls would be several meters thick and would take up a correspondingly large amount of space. Also, the temporary structures constructed today using scaffolding, especially if they have large spans, are not designed for use over several years, e.g. as a temporary replacement solution for new construction or the renovation of existing buildings such as gymnasiums or bridges.

[0007] Im Gegensatz zum Gerüstbau ermöglicht der Stahlbau grosse Spannweiten und generiert mit wenig Strukturvolumen ein grosses umbautes Raumvolumen. Grundsätzlich ist er ideal für die Erstellung von raumschaffenden Bauten für lange Nutzungsdauern, insbesondere von Hallenbauten, weist jedoch den Nachteil auf, dass er unflexibel ist, weil jeder Bau individuell geplant und gefertigt werden muss, eine Fundation benötigt wird und zur Montage grosse Maschinen erforderlich sind. Auch ist eine Wiederverwertung der Bauteile am Nutzungsende aufgrund der individuellen Anfertigung der Bauteile eher die Ausnahme. In contrast to scaffolding, steel construction enables large spans and generates a large enclosed volume of space with little structural volume. In principle, it is ideal for creating space-creating buildings for long periods of use, especially hall buildings, but has the disadvantage that it is inflexible because each building has to be planned and manufactured individually, a foundation is required and large machines are required for assembly . Also, recycling the components at the end of their useful life is rather the exception due to the individual manufacture of the components.

DARSTELLUNG DER ERFINDUNGPRESENTATION OF THE INVENTION

[0008] Es stellt sich deshalb die Aufgabe, technische Lösungen zur Verfügung zu stellen, welche die zuvor genannten Nachteile des Standes der Technik nicht aufweisen oder zumindest teilweise vermeiden. The object is therefore to provide technical solutions which do not have the aforementioned disadvantages of the prior art or at least partially avoid them.

[0009] Diese Aufgabe wird durch die Gegenstände der unabhängigen Patentansprüche gelöst. [0009] This object is achieved by the subject matter of the independent patent claims.

[0010] Gemäss diesen betrifft ein erster Aspekt der Erfindung eine Tragstruktur für einen Hallen-, Bühnen-, Tribünen- oder Brückenbau, welcher mehrfach auf- und abgebaut werden kann bzw. dessen Bauteile ohne weitere Aufbereitung mehrfach verwendet werden können für identische oder ähnliche Bauwerke. Hierzu ist die Tragstruktur aus einer Vielzahl von Bauteilen aufgebaut, welche mittels normaler Transportfahrzeuge (LKW) auf dem Landweg transportiert werden können und untereinander über mehrfach herstellbare und lösbare Verbindungen miteinander verbunden sind. According to this, a first aspect of the invention relates to a support structure for a hall, stage, grandstand or bridge construction, which can be set up and dismantled several times or whose components can be used several times without further processing for identical or similar buildings . For this purpose, the support structure is made up of a large number of components, which can be transported overland using normal transport vehicles (trucks) and are connected to one another via connections that can be made and detached multiple times.

[0011] Die Tragstruktur weist eine wandartige erste Gerüststruktur auf, welche sich im Wesentlichen in einer vertikalen ersten Ebene erstreckt, und eine wandartige zweite Gerüststruktur, welche sich im Wesentlichen in einer vertikalen zweiten Ebene erstreckt. Diese Gerüststrukturen stehen sich mit einem Abstand gegenüber und verlaufen dabei bevorzugterweise parallel zueinander. The support structure has a wall-like first frame structure, which extends essentially in a vertical first plane, and a wall-like second frame structure, which extends essentially in a vertical second plane. These framework structures face one another at a distance and preferably run parallel to one another.

[0012] Weiter weist die Tragstruktur mindestens eine, bevorzugterweise genau zwei wandartige weitere Gerüststrukturen auf, welche sich im Wesentlichen in einer vertikalen Ebene erstreckt bzw. erstrecken, die quer, bevorzugterweise senkrecht zu der ersten und der zweiten Ebene verläuft, in denen sich die erste und die zweite Gerüststruktur erstrecken. Furthermore, the support structure has at least one, preferably exactly two wall-like further framework structures, which extends or extend substantially in a vertical plane, which runs transversely, preferably perpendicularly, to the first and the second plane, in which the first and extend the second framework structure.

[0013] Diese wandartigen Gerüststrukturen sind derartig ausgebildet, dass sie schubsteif in der jeweiligen Ebene sind, in welcher sie sich erstrecken. Dies wird mit Vorteil mittels sich parallel zu der jeweiligen Ebene verlaufende diagonale Verstrebungen zwischen den Gerüststandrohren der Gerüststrukturen bewirkt. These wall-like framework structures are designed in such a way that they are shear-resistant in the respective plane in which they extend. This is advantageously effected by means of diagonal struts running parallel to the respective plane between the standpipes of the scaffolding structures.

[0014] Des Weiteren weist die Tragstruktur mindestens eine Trägerstruktur auf, welche sich im Wesentlichen in einer horizontalen Ebene erstreckt. Diese Trägerstruktur ist derartig ausgebildet, dass sie schubsteif in dieser horizontalen Ebene ist, was bevorzugterweise durch parallel zu dieser Ebene verlaufende diagonale Verstrebungen bewirkt wird. [0014] Furthermore, the support structure has at least one support structure which extends essentially in a horizontal plane. This support structure is designed in such a way that it is shear-resistant in this horizontal plane, which is preferably brought about by diagonal struts running parallel to this plane.

[0015] Diese Trägerstruktur ist oder diese Trägerstrukturen sind von untereinander verbundenen und sich zwischen der ersten und der zweiten Gerüststruktur erstreckenden Trägern gebildet und über die Enden dieser Träger derartig mit diesen beiden Gerüststrukturen verbunden, dass sie von der ersten Gerüststruktur und der zweiten Gerüststruktur getragen wird bzw. werden. This support structure is or these support structures are formed by interconnected beams extending between the first and second framework structure and connected to these two framework structures via the ends of these beams in such a way that it is supported by the first framework structure and the second framework structure or become.

[0016] Dabei sind die Verbindungen zu der ersten und der zweiten Gerüststruktur derartig ausgebildet, dass zwar horizontale Schubkräfte, welche in Richtung der ersten Ebene wirken, in welcher sich die erste Gerüststruktur erstreckt, und/oder welche in Richtung der zweiten Ebene wirken, in welcher sich die zweite Gerüststruktur erstreckt, von der jeweiligen Trägerstruktur auf die erste und/oder die zweite Gerüststruktur übertragen werden können, nicht jedoch Biegemomente um parallel zu der ersten bzw. zweiten Ebene verlaufende Achsen herum. [0016] The connections to the first and the second frame structure are designed in such a way that horizontal shearing forces which act in the direction of the first plane, in which the first frame structure extends, and/or which act in the direction of the second plane, in which the second framework structure extends, can be transferred from the respective support structure to the first and/or the second framework structure, but not bending moments about axes running parallel to the first or second plane.

[0017] Die Verbindung der Trägerstruktur ist dabei derartig realisiert, dass jeder der Träger der Trägerstruktur an einem ersten seiner beiden Enden in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene erste oder zweite Gerüststruktur übertragen kann und an seinem zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene zweite oder erste Gerüststruktur übertragen kann. Auf diese Weise kann eine Biegebeanspruchung der ersten und zweiten Gerüststrukturen durch temperaturbedingte Längenänderungen oder lastbedingte Durchbiegungen der Träger wirkungsvoll vermieden werden und damit die Bauteilbelastung minimiert werden, insbesondere auch die Wechselbelastung durch Tag/Nacht- und Sommer/Winter-Temperaturunterschiede und Schnee- und Windlasten. The connection of the support structure is realized in such a way that each of the supports of the support structure can transfer shear forces acting at a first of its two ends in the longitudinal direction of the support to the first or second framework structure connected to this end and no shear forces acting in the longitudinal direction of the support at its second end can be transferred to the second or first framework structure connected to this end. In this way, flexural stress on the first and second scaffold structures due to temperature-related changes in length or load-related deflection of the beams can be effectively avoided and thus the component stress can be minimized, in particular the alternating stress caused by day/night and summer/winter temperature differences and snow and wind loads.

[0018] Dabei ist oder sind gemäss einer ersten erfindungsgemässen Konstruktionsvariante die Trägerstruktur oder die Trägerstrukturen derartig mit der oder den wandartigen weiteren Gerüststrukturen verbunden, dass zwar horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in welchen sich diese wandartigen weiteren Gerüststrukturen erstrecken, von der oder den Trägerstrukturen auf die wandartigen weiteren Gerüststrukturen übertragen werden können, nicht jedoch Biegemomente um parallel zu diesen vertikalen Ebenen verlaufende Achsen herum. According to a first design variant according to the invention, the support structure or structures is or are connected to the wall-like additional framework structure or structures in such a way that horizontal shearing forces, which act in the direction of the vertical planes in which these wall-like additional framework structures extend, of the support structure(s) can be transferred to the wall-like additional framework structures, but not bending moments about axes running parallel to these vertical planes.

[0019] Alternativ oder ergänzend zu der im zuvor genannten Abschnitt genannten Ausgestaltung der erfindungsgemässen Tragstruktur gemäss der ersten Konstruktionsvariante ist oder sind in einer zweiten Konstruktionsvariante die Trägerstruktur oder die Trägerstrukturen derartig mit der ersten Gerüststruktur und der zweiten Gerüststruktur verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in welchen sich die wandartigen weiteren Gerüststrukturen erstrecken, von der oder den Trägerstrukturen auf die erste und/oder die zweite Gerüststruktur übertragen werden können. As an alternative or in addition to the configuration of the support structure according to the invention mentioned in the aforementioned section according to the first design variant, the support structure or the support structures is or are connected to the first scaffolding structure and the second scaffolding structure in such a way that horizontal shearing forces which occur in Act in the direction of the vertical planes in which the wall-like further framework structures extend, from which the carrier structure(s) can be transferred to the first and/or the second framework structure.

[0020] Dabei sind die erste Gerüststruktur und/oder die zweite Gerüststruktur derartig mit der oder den wandartigen weiteren Gerüststrukturen verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in welcher sich diese wandartigen weiteren Gerüststrukturen erstrecken, von der ersten und/oder der zweiten Gerüststruktur auf die wandartigen weiteren Gerüststrukturen übertragen werden können. The first scaffolding structure and/or the second scaffolding structure are connected to the wall-like further scaffolding structure(s) in such a way that horizontal shear forces, which act in the direction of the vertical planes in which these wall-like further scaffolding structures extend, are released from the first and/or or the second framework structure can be transferred to the wall-like further framework structures.

[0021] Mit anderen Worten gesagt betrifft eine erste Konstruktionsvariante der Tragstruktur gemäss dem ersten Aspekt der Erfindung eine Tragstruktur für einen Hallen-, Bühnen-, Tribünen- oder Brückenbau, welche eine von zwei wandartigen Gerüststrukturen getragene Trägerstruktur aufweist, die sich im Wesentlichen in einer horizontalen Ebene erstreckt und schubsteif in dieser Ebene ist. Die beiden Gerüststrukturen, welche sich jeweils in vertikalen Ebenen erstrecken und schubsteif in diesen Ebenen sind, stehen sich mit einem Abstand gegenüber. Die Trägerstruktur erstreckt sich mit ihren Trägern zwischen diesen Gerüststrukturen und ist derartig über die Enden ihrer Träger mit diesen verbunden, dass in Richtung der vertikalen Ebenen der Gerüststrukturen wirkende horizontale Schubkräfte von der Trägerstruktur auf zumindest eine dieser Gerüststrukturen übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken. Dabei ist die Verbindung zwischen der Trägerstruktur und der ersten und zweiten Gerüststruktur derartig realisiert, dass keine in Längsrichtung der Träger der Trägerstruktur wirkenden Schubkräfte über die Trägerstruktur zwischen der ersten und der zweiten Gerüststruktur ausgetauscht werden können. In other words, a first design variant of the support structure according to the first aspect of the invention relates to a support structure for a hall, stage, grandstand or bridge construction, which has a support structure supported by two wall-like scaffolding structures, which is essentially in a extends horizontal plane and is shear-resistant in this plane. The two framework structures, which each extend in vertical planes and are shear-resistant in these planes, face one another at a distance. The carrier structure extends with its carriers between these scaffolding structures and is connected to them via the ends of their carriers in such a way that horizontal shear forces acting in the direction of the vertical planes of the scaffolding structures can be transferred from the carrier structure to at least one of these scaffolding structures, but not bending moments which axes running parallel to these planes act around. The connection between the support structure and the first and second framework structure is realized in such a way that no shearing forces acting in the longitudinal direction of the supports of the support structure can be exchanged via the support structure between the first and second framework structure.

[0022] Auch umfasst die Tragstruktur eine wandartige weitere Gerüststruktur, welche sich in einer vertikalen Ebene quer zu den beiden erstgenannten Gerüststrukturen erstreckt und schubsteif in dieser Ebene ist. Die Trägerstruktur ist derartig mit dieser weiteren Gerüststruktur verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebene wirken, in welcher sich diese weitere Gerüststruktur erstreckt, von der Trägerstruktur auf diese weitere Gerüststruktur übertragbar sind, nicht jedoch Biegemomente, welche um eine parallel zu dieser vertikalen Ebene verlaufende Achse wirken. [0022] The support structure also includes a wall-like further framework structure which extends in a vertical plane transversely to the first two framework structures and is shear-resistant in this plane. The support structure is connected to this further scaffolding structure in such a way that horizontal shearing forces, which act in the direction of the vertical plane in which this further scaffolding structure extends, can be transferred from the support structure to this further scaffolding structure, but not bending moments which are parallel to it axis running in the vertical plane.

[0023] Mit anderen Worten gesagt betrifft eine zweite Konstruktionsvariante der Tragstruktur gemäss dem ersten Aspekt der Erfindung eine Tragstruktur für einen Hallen-, Bühnen-, Tribünen- oder Brückenbau, welche eine von zwei wandartigen Gerüststrukturen getragene Trägerstruktur aufweist, die sich im Wesentlichen in einer horizontalen Ebene erstreckt und schubsteif in dieser Ebene ist. Die beiden Gerüststrukturen, welche sich jeweils in vertikalen Ebenen erstrecken und schubsteif in diesen Ebenen sind, stehen sich mit einem Abstand gegenüber. Die Trägerstruktur erstreckt sich mit ihren Trägern zwischen diesen Gerüststrukturen und ist derartig über die Enden ihrer Träger mit diesen verbunden, dass in Richtung der vertikalen Ebenen der Gerüststrukturen und quer dazu wirkende horizontale Schubkräfte von der Trägerstruktur zumindest auf eine dieser Gerüststrukturen übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken. Dabei ist die Verbindung zwischen der Trägerstruktur und der ersten und zweiten Gerüststruktur derartig realisiert, dass keine in Längsrichtung der Träger der Trägerstruktur wirkenden Schubkräfte über die Trägerstruktur zwischen der ersten und der zweiten Gerüststruktur ausgetauscht werden können. In other words, a second construction variant of the support structure according to the first aspect of the invention relates to a support structure for a hall, stage, grandstand or bridge construction, which has a support structure supported by two wall-like scaffolding structures, which is essentially in a extends horizontal plane and is shear-resistant in this plane. The two framework structures, which each extend in vertical planes and are shear-resistant in these planes, face one another at a distance. The carrier structure extends with its carriers between these scaffolding structures and is connected to them via the ends of their carriers in such a way that horizontal shear forces acting in the direction of the vertical planes of the scaffolding structures and transversely thereto can be transferred from the carrier structure to at least one of these scaffolding structures, but not bending moments , which act around axes parallel to these planes. The connection between the support structure and the first and second framework structure is realized in such a way that no shearing forces acting in the longitudinal direction of the supports of the support structure can be exchanged via the support structure between the first and second framework structure.

[0024] Auch umfasst die Tragstruktur eine wandartige weitere Gerüststruktur, welche sich in einer vertikalen Ebene quer zu den beiden erstgenannten Gerüststrukturen erstreckt und schubsteif in dieser Ebene ist. Die zuvor genannten zwei Gerüststrukturen, welche die Trägerstruktur tragen, sind derartig mit dieser weiteren Gerüststruktur verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebene wirken, in welcher sich diese weitere Gerüststruktur erstreckt, von den die Trägerstruktur tragenden Gerüststrukturen auf diese weitere Gerüststruktur übertragbar sind. [0024] The support structure also includes a wall-like further framework structure which extends in a vertical plane transversely to the first two framework structures and is shear-resistant in this plane. The aforementioned two scaffolding structures, which carry the support structure, are connected to this further scaffolding structure in such a way that horizontal shearing forces, which act in the direction of the vertical plane in which this further scaffolding structure extends, can be transferred from the scaffolding structures carrying the support structure to this further scaffolding structure are.

[0025] Durch die Erfindung wird es möglich, die Vorteile von Gerüstbau und Stahlbau zu vereinen und Tragstrukturen für sturmfeste temporäre Hallen-, Bühnen-, Tribünen- oder Brückenbauten zur Verfügung zu stellen, welche trotz der Verwendung von Gerüstwänden für eine mehrjährige Nutzung geeignet sind, wenig Raum für die Struktur benötigen und entsprechend viel nutzbaren Raum über einen längeren Zeitraum zur Verfügung stellen. So lassen sich mit der Erfindung mit handelsüblichem Gerüstmaterial bei Gerüstwanddicken von 1 Meter Hallenspannweiten von bis zu 40 Metern realisieren. The invention makes it possible to combine the advantages of scaffolding and steel construction and to provide supporting structures for storm-proof temporary halls, stages, grandstands or bridge structures which are suitable for use over several years despite the use of scaffolding walls , require little space for the structure and provide a correspondingly large amount of usable space over a longer period of time. With the invention, hall spans of up to 40 meters can be realized with commercially available scaffolding material with scaffolding wall thicknesses of 1 meter.

[0026] In einer ersten bevorzugten Ausführungsform der erfindungsgemässen Tragstruktur sind sämtliche Träger der Trägerstruktur mit ihren anspruchsgemässen zweiten Enden, also mit denjenigen Enden, mit denen sie keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur übertragen können, mit der gleichen Gerüststruktur verbunden, nämlich entweder mit der ersten Gerüststruktur oder mit der zweiten Gerüststruktur. Hierdurch bilden die Träger bezogen auf in Trägerlängsrichtung wirkende Schubkräfte mit ihren anspruchsgemässen ersten Ende ein Festlager an der mit diesen Enden verbundenen Gerüststruktur und mit ihren anspruchsgemässen zweiten Ende ein Loslager an der mit diesen Enden verbundenen Gerüststruktur, so dass über die Trägerstruktur keine Schubkräfte in Trägerlängsrichtung zwischen der ersten und der zweiten Gerüststruktur übertragen werden können. In a first preferred embodiment of the support structure according to the invention, all the supports of the support structure are connected to the same support structure with their second ends according to the claims, i.e. with those ends with which they cannot transmit any shear forces acting in the longitudinal direction of the support to the framework structure connected to this end , namely either with the first framework structure or with the second framework structure. As a result, the girders, based on shear forces acting in the longitudinal direction of the girder, form a fixed bearing on the scaffolding structure connected to these ends with their first end according to the claims and a floating bearing on the scaffolding structure connected to these ends with their second end according to the claims, so that no shearing forces in the longitudinal direction of the girder between the first and the second framework structure can be transferred.

[0027] In einer zweiten bevorzugten Ausführungsform der erfindungsgemässen Tragstruktur sind die Träger der Trägerstruktur mit ihren anspruchsgemässen zweiten Enden, also mit denjenigen Enden, mit denen sie keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur übertragen können, mit unterschiedlichen Gerüststrukturen verbunden, nämlich mal mit der ersten Gerüststruktur und mal mit der zweiten Gerüststruktur. In a second preferred embodiment of the support structure according to the invention, the supports of the support structure are connected to different support structures with their second ends according to the claims, i.e. with those ends with which they cannot transmit any shear forces acting in the longitudinal direction of the support to the framework structure connected to this end. namely sometimes with the first framework structure and sometimes with the second framework structure.

[0028] Dies ist mit Vorteil derartig realisiert, dass die Träger der Trägerstruktur mit ihren zweiten Enden abwechselnd oder gruppenweise abwechselnd mal mit der ersten Gerüststruktur und mal mit der zweiten Gerüststruktur verbunden sind. This is advantageously implemented in such a way that the carriers of the carrier structure are connected with their second ends alternately or in groups alternately to the first framework structure and to the second framework structure.

[0029] Hierdurch bilden die Träger bezogen auf in Trägerlängsrichtung wirkende Schubkräfte mit ihren anspruchsgemässen ersten Ende abwechselnd ein Festlager an der ersten und an der zweiten Gerüststruktur und mit ihren anspruchsgemässen zweiten Ende abwechselnd ein Loslager an der zweiten und an der ersten Gerüststruktur, so dass über die Trägerstruktur zwar Schubkräfte in Trägerlängsrichtung zwischen der ersten und der zweiten Gerüststruktur übertragen werden können, etwaige temperatur- oder lastbedingte Längenänderungen der Träger aber nur in starke reduziertem Masse auf die erste und zweite Gerüststruktur übertragen werden, weil diese Längenänderungen zu einem grossen Teil durch Längenänderungen der an der eigentlichen Tragfunktion nicht massgeblich beteiligten Verstrebungen zwischen den Trägern aufgefangen werden. As a result, the beams, based on the shear forces acting in the longitudinal direction of the beam, alternately form a fixed bearing on the first and second scaffolding structure with their first end according to the claims and a floating bearing on the second and first scaffolding structure with their second end according to the claims, so that over Although the support structure can transfer shear forces in the longitudinal direction of the support between the first and the second frame structure, any temperature or load-related changes in length of the support are only transferred to a greatly reduced extent to the first and second frame structure, because these changes in length are largely caused by changes in the length of the struts between the beams that are not significantly involved in the actual load-bearing function.

[0030] Die Verbindung der anspruchsgemässen zweiten Enden der Träger mit der jeweiligen diese tragenden Gerüststruktur erfolgt in einer ersten bevorzugten Variante derartig, dass die Träger mit einer an ihren zweiten Enden gebildeten Gleitfläche auf einer zugeordneten Gleitfläche an der dieses Ende tragenden Gerüststruktur aufliegen, so dass sich dieses Ende bei einer Längenänderung der Trägers gegenüber dieser Gerüststruktur verschieben kann. In a first preferred variant, the connection of the claimed second ends of the carriers to the respective framework structure carrying them is carried out in such a way that the carriers rest with a sliding surface formed at their second ends on an assigned sliding surface on the framework structure carrying this end, so that this end can shift in relation to this scaffolding structure when the length of the carrier changes.

[0031] In einer zweiten Variante erfolgt die Verbindung der anspruchsgemässen zweiten Enden der Träger mit der jeweiligen diese tragenden Gerüststruktur derartig, dass die Träger mit ihrem zweiten Ende jeweils über eine Lasche an der dieses Ende tragenden Gerüststruktur angehängt sind, so dass sich dieses Ende bei einer Längenänderung der Trägers unter einem Verschwenken der Lasche gegenüber dieser Gerüststruktur verschieben kann. In a second variant, the connection of the claimed second ends of the beams with the respective framework structure carrying them takes place in such a way that the beams are each attached with their second end via a lug to the framework structure supporting this end, so that this end a change in length of the carrier can move with a pivoting of the tab relative to this framework structure.

[0032] Typischerweise verlaufen die Längsachsen der die Träger der Trägerstruktur bei der erfindungsgemässen Tragstruktur horizontal. Es sind jedoch auch bevorzugte Ausführungsformen der Tragstruktur vorgesehen, bei denen die Längsachsen der Träger der Trägerstruktur nicht horizontal verlaufen. So kann die Trägerstruktur beispielsweise ein Pultdach bilden, von welchem Regenwasser in einer definierten Richtung ablaufen kann. Typically, the longitudinal axes of the supports of the support structure run horizontally in the support structure according to the invention. However, preferred embodiments of the support structure are also provided in which the longitudinal axes of the supports of the support structure do not run horizontally. For example, the support structure can form a pent roof from which rainwater can run off in a defined direction.

[0033] Die mindestens eine wandartige weitere Gerüststruktur der erfindungsgemässen Tragstruktur ist bevorzugterweise zwischen der ersten Gerüststruktur und der zweiten Gerüststruktur angeordnet. The at least one wall-like additional frame structure of the support structure according to the invention is preferably arranged between the first frame structure and the second frame structure.

[0034] Wenn genau eine solche wandartige weitere Gerüststruktur vorhanden ist, ist diese gemäss einer ersten bevorzugten Ausführungsvariante der Tragstruktur mittig zwischen den Enden der ersten und der zweiten Gerüststruktur angeordnet, so dass die Gerüststrukturen in der Draufsicht einen H-förmigen Grundriss bilden. Auf diese Weise lassen sich z.B. zwei spiegelbildliche angeordnete überdachte Bühnen mit einer gemeinsamen erfindungsgemässen Tragstruktur realisieren. Gemäss einer zweiten bevorzugten Ausführungsvariante ist diese wandartige weitere Gerüststruktur an einem Ende der ersten Gerüststruktur und der zweiten Gerüststruktur angeordnet, so dass die Gerüststrukturen in der Draufsicht einen U-förmigen Grundriss bilden. Auf diese Weise lässt sich z.B. ein einseitig offener Hallenbau mit der erfindungsgemässen Tragstruktur bilden. If exactly such a wall-like further scaffolding structure is present, according to a first preferred embodiment variant of the support structure, this is arranged centrally between the ends of the first and the second scaffolding structure, so that the scaffolding structures form an H-shaped plan when viewed from above. In this way, for example, two roofed stages arranged in mirror image can be realized with a common support structure according to the invention. According to a second preferred embodiment variant, this wall-like additional framework structure is arranged at one end of the first framework structure and the second framework structure, so that the framework structures form a U-shaped plan view from above. In this way, for example, a hall construction that is open on one side can be formed with the support structure according to the invention.

[0035] Weist die erfindungsgemässe Tragstruktur mindestens zwei wandartige weitere Gerüststrukturen auf, nämlich eine wandartige dritte Gerüststruktur, welche sich im Wesentlichen in einer vertikalen dritten Ebene erstreckt, und eine wandartige vierte Gerüststruktur, welche sich im Wesentlichen in einer vertikalen vierten Ebene erstreckt, so ist es bevorzugt, dass sich die dritte Gerüststruktur und die vierte Gerüststruktur mit einem Abstand gegenüberstehen, und zwar bevorzugterweise derart, dass die dritte Ebene und die vierte Ebene im Wesentlichen parallel zueinander verlaufen. If the support structure according to the invention has at least two further wall-like framework structures, namely a wall-like third framework structure which essentially extends in a vertical third plane, and a wall-like fourth framework structure which essentially extends in a vertical fourth plane it is preferred that the third skeletal structure and the fourth skeletal structure face each other at a distance, preferably such that the third plane and the fourth plane are substantially parallel to each other.

[0036] Die dritte und die vierte Gerüststruktur sind bevorzugterweise jeweils an einem Ende der ersten und der zweiten Gerüststruktur angeordnet, und zwar bevorzugterweise derart, dass diese Gerüststrukturen einen rechteckiger Raum begrenzen. Auf diese Weise kann z.B. eine umfangsmässig vollständig geschlossene Halle mit der erfindungsgemässen Tragstruktur gebildet werden. The third and fourth skeleton structures are preferably arranged at one end of the first and second skeleton structures, respectively, preferably in such a way that these skeleton structures define a rectangular space. In this way, for example, a hall that is completely closed in terms of circumference can be formed with the support structure according to the invention.

[0037] Die wandartigen weiteren Gerüststrukturen der erfindungsgemässen Tragstruktur können direkt mit der wandartigen ersten Gerüststruktur und der wandartigen zweiten Gerüststruktur verbunden sein, oder nur indirekt über die Trägerstruktur. The wall-like additional frame structures of the support structure according to the invention can be connected directly to the wall-like first frame structure and the wall-like second frame structure, or only indirectly via the support structure.

[0038] In einer weiteren bevorzugten Ausführungsform weist die erfindungsgemässe Tragstruktur mehrere, z.B. zwei, Trägerstrukturen auf, welche mit einem Abstand zueinander übereinander angeordnet sind und wie zuvor dargelegt ausgebildet und mit den Gerüststrukturen der Tragstruktur verbunden sind. Mit derartigen Tragstrukturen lassen sich z.B. mehrstöckige Hallen- oder Tribünenbauten erstellen. In a further preferred embodiment, the support structure according to the invention has several, e.g. two, support structures which are arranged one above the other at a distance from one another and are designed as explained above and are connected to the frame structures of the support structure. Such support structures can be used, for example, to create multi-storey halls or stands.

[0039] Die wandartigen Gerüststrukturen der Tragstruktur weisen mit Vorteil jeweils in horizontaler Richtung in der jeweiligen vertikalen Ebene, in welcher sie sich erstrecken, eine Erstreckung auf, die einem Vielfachen ihrer Erstreckung senkrecht zu dieser Ebene beträgt. Auf diese Weise kann mit wenig Gerüstvolumen ein grosses umbautes Raumvolumen zur Verfügung gestellt werden. The wall-like scaffolding structures of the support structure advantageously each have an extent in the horizontal direction in the respective vertical plane in which they extend, which is a multiple of their extent perpendicular to this plane. In this way, a large enclosed volume of space can be made available with little scaffolding volume.

[0040] Die Trägerstruktur der erfindungsgemässen Tragstruktur umfasst bevorzugterweise mehrere quer, mit Vorteil senkrecht zu den vertikalen Ebenen, in denen sich die erste und die zweite Gerüststruktur erstrecken, verlaufende Träger, welche sich mit einem Abstand zueinander und bevorzugterweise parallel zueinander im Wesentlichen in horizontaler Richtung erstrecken und derartig miteinander verbunden sind, z.B. durch senkrecht und diagonal zu diesen verlaufende Verstrebungen, dass sie zusammen eine in horizontaler Richtung schubsteife Struktur bilden. Die Träger sind bevorzugterweise gerade Träger und sind bevorzugterweise als Fachwerkträger ausgebildet. The support structure of the support structure according to the invention preferably comprises a plurality of supports running transversely, advantageously perpendicularly to the vertical planes in which the first and second framework structure extend, which are spaced apart from one another and preferably parallel to one another essentially in the horizontal direction extend and are connected to one another in such a way, e.g. by struts running perpendicularly and diagonally to them, that together they form a shear-resistant structure in the horizontal direction. The girders are preferably straight girders and are preferably designed as lattice girders.

[0041] Dabei ist es bevorzugt, dass die erste und die zweite Gerüststruktur jeweils eine Vielzahl von vertikalen Gerüststandrohre aufweisen und die Träger jeweils derartig mit diesen beiden Gerüststrukturen verbunden sind, dass die von den Trägern der Trägerstruktur in vertikaler Richtung auf die erste und die zweite Gerüststruktur übertragenen Kräfte jeweils im Wesentlichen gleichmässig auf vier, in der Draufsicht gesehen einen mit Vorteil rechteckigen oder quadratischen Gerüststrukturteil bildende Gerüststandrohre übertragen werden. Auf diese Weise kann die Tragfähigkeit der Gerüststruktur bestmöglich ausgenutzt werden. It is preferred that the first and the second scaffolding structure each have a plurality of vertical scaffolding standpipes and the carriers are each connected to these two scaffolding structures in such a way that the beams of the carrier structure in the vertical direction on the first and the second Forces transmitted by the scaffolding structure are in each case transmitted essentially uniformly to four scaffolding standpipes which, seen in plan view, advantageously form a rectangular or square scaffolding structure part. In this way, the load-bearing capacity of the scaffolding structure can be utilized as best as possible.

[0042] Weiter ist es dabei bevorzugt, dass zur Einleitung der vertikalen Kräfte in die vier Gerüststandrohre paarweise jeweils diejenigen dieser Gerüststandrohre, welche sich in einer Richtung quer bzw. senkrecht zu der vertikalen Ebene gegenüberstehen, in welcher sich die erste bzw. die zweite Gerüststruktur erstreckt, eine sich zwischen diesen Gerüststandrohre erstreckende erste Auflager-Tragstruktur tragen, welche bevorzugterweise als Fachwerkträger ausgebildet ist. Diese beiden ersten Auflager-Tragstrukturen tragen zusammen eine zweite Auflager-Tragstruktur, z.B. in Form eines T-Trägers oder Doppel-T-Trägers, welche sich zwischen diesen ersten Auflager-Tragstrukturen erstreckt in einer Richtung parallel zu der vertikalen Ebene, in welcher sich die erste bzw. die zweite Gerüststruktur erstreckt. Diese zweite Auflager-Tragstruktur trägt ein Ende des jeweiligen Trägers der Trägerstruktur. It is also preferred that for introducing the vertical forces into the four scaffolding standpipes, in pairs, those of these scaffolding standpipes which face each other in a direction transverse or perpendicular to the vertical plane in which the first and the second scaffolding structure extends, carry a first bearing support structure which extends between these standpipes and is preferably designed as a truss girder. These two first bearing structures together support a second bearing structure, e.g. in the form of a T-beam or I-beam, which extends between these first bearing structures in a direction parallel to the vertical plane in which the first and the second framework structure extends. This second bearing support structure supports one end of the respective beam of the support structure.

[0043] Der Ort der Einleitung der vertikalen Kräfte von dem Träger in die zweite Auflager-Tragstruktur liegt bevorzugterweise unterhalb von den Orten der Einleitung der vertikalen Kräfte von der zweiten Auflager-Tragstruktur in die beiden ersten Auflager-Tragstrukturen. Hierdurch ergibt sich eine selbststabilisierende Krafteinleitungssituation. The location of the introduction of the vertical forces from the beam into the second bearing structure is preferably below the locations of the introduction of the vertical forces from the second bearing structure in the first two bearing structures. This results in a self-stabilizing force application situation.

[0044] Ist der Träger von unten an die zweite Auflager-Tragstruktur angehängt, was ebenfalls bevorzugt ist, so ergibt sich der Vorteil, dass er für die Montage mittels eines Ketten- oder Seilzugs an der jeweiligen Gerüststruktur hochgezogen und an die bereits bestimmungsgemäss montierte zweite Auflager-Tragstruktur angehängt werden kann, ohne dass hierzu ein Kran erforderlich wäre. If the carrier is attached to the second support structure from below, which is also preferred, there is the advantage that it can be pulled up on the respective scaffolding structure for assembly by means of a chain or cable hoist and attached to the second support structure that has already been assembled as intended Bearing structure can be attached without the need for a crane.

[0045] Des Weiteren ist es vorteilhaft, dass die erste und die zweite Gerüststruktur ein bestimmtes Rastermass mit bestimmten Verbindungselementen (z.B. Pin zum Anschliessen eines weiteren Gerüststandrohrs, Lochscheibe am Gerüststandrohr, Keilkopf an Gerüststreben zur Befestigung der Streben an Lochscheibe) aufweisen und die ersten Auflager-Tragstrukturen dieselben Verbindungselemente mit demselben Rastermass oder einem zu dem Rastermass der ersten bzw. der zweiten Gerüststruktur kompatiblen Rastermass aufweisen. Hierdurch wird es möglich, die ersten Auflager-Tragstrukturen in ein Raumgerüst mit der ersten bzw. der zweiten Gerüststruktur zu integrieren, z.B. derart, dass die jeweilige Gerüststruktur unter Nutzung der ersten Auflager-Tragstrukturen nach oben fortgesetzt werden kann. Furthermore, it is advantageous that the first and the second scaffolding structure have a certain grid dimension with certain connecting elements (e.g. pin for connecting another scaffolding tube, perforated disk on the scaffolding tube, wedge head on scaffolding struts for fastening the struts to the perforated disk) and the first supports -Support structures have the same connecting elements with the same grid size or a grid size that is compatible with the grid size of the first or second framework structure. This makes it possible to integrate the first support structures into a spatial framework with the first or second framework structure, e.g. in such a way that the respective framework structure can be continued upwards using the first support structures.

[0046] Die Träger sind mit Vorteil im Bereich ihrer ersten Enden über jeweils genau eine Bolzenverbindung, deren Bolzenlängsrichtung parallel zu der jeweiligen vertikalen Ebene verläuft, in welcher sich die erste bzw. die zweite Gerüststruktur erstreckt, lösbar mit der ersten oder der zweite Gerüststruktur bzw. mit deren zweiten Auflager-Tragstrukturen verbunden, zur biegemomentfreien Übertragung der vertikalen Kräfte auf diese Gerüststruktur. In the region of their first ends, the supports are advantageously detachable with the first or second frame structure or .connected to their second supporting structures, for the bending moment-free transmission of the vertical forces to this scaffolding structure.

[0047] Dabei ist es weiter bevorzugt, dass die Neutralachse des jeweiligen Trägers im Wesentlichen durch das Zentrum der jeweiligen Bolzenverbindung verläuft. It is further preferred that the neutral axis of the respective carrier runs essentially through the center of the respective bolt connection.

[0048] Weiter ist es bevorzugt, dass die Träger jeweils aus mehreren, mit Vorteil über Bolzenverbindungen lösbar miteinander verbundenen Bauteilen aufgebaut sind, und zwar vorteilhafterweise aus zwei Kopfteilen, welche bevorzugterweise bezüglich ihrer Tragwerksgeometrie identisch sind, und einem oder mehreren zwischen diesen Kopfteilen angeordneten, bevorzugterweise identischen Trägergrundelementen. Hierdurch ergibt sich der Vorteil, dass die Träger in verschiedenen Längen aus wenigen standardisierten Bauteilen gebildet werden können, was die Lagerhaltung und Bereitstellung deutlich vereinfacht. [0048] Furthermore, it is preferred that the carriers are each constructed from a plurality of components which are advantageously connected to one another in a detachable manner by means of bolt connections, namely advantageously from two head parts which are preferably identical in terms of their supporting structure geometry, and one or more head parts arranged between these preferably identical carrier basic elements. This results in the advantage that the carriers can be formed in different lengths from a few standardized components, which significantly simplifies storage and provision.

[0049] Sind die Trägergrundelemente dabei als zweidimensionale Fachwerke ausgebildet, so benötigen diese nur relativ wenig Raum bei der Lagerung und dem Transport. Dabei ist es weiter bevorzugt, dass die Trägergrundelemente untereinander und mit den Kopfteilen jeweils über genau zwei Bolzenverbindungen verbunden sind. [0049] If the basic carrier elements are designed as two-dimensional frameworks, they only require relatively little space during storage and transport. It is further preferred that the basic carrier elements are connected to each other and to the head parts via exactly two bolt connections.

[0050] Mit Vorteil weisen die Trägergrundelemente eine Länge von weniger als 5 m auf, z.B. eine Länge von etwa 2 m oder etwa 4 m, so dass sie einfach zu transportieren und zu handhaben sind, z.B. mittels eines normalen Gabelstaplers für Euro-Paletten. Advantageously, the basic support elements have a length of less than 5 m, for example a length of about 2 m or about 4 m, so that they are easy to transport and handle, for example by means of a normal Euro pallet forklift truck.

[0051] Bei den aus zwei Kopfteilen und einem oder mehreren zwischen diesen Kopfteilen angeordneten Trägergrundelementen aufgebauten Trägern, bei denen die Kopfteile die vertikalen Kräfte jeweils über genau eine Bolzenverbindung auf die erste bzw. zweite Gerüststruktur übertragen, ist es weiter bevorzugt, dass die Kopfträger als dreieckige Tragstruktur ausgebildet sind, bei welcher an einer ersten Ecke die Bolzenverbindung zur Übertragung der vertikalen Kräfte auf die erste bzw. zweite Gerüststruktur angeordnet ist und an den übrigen zwei Ecken die Bolzenverbindungen zur Verbindung mit dem an dieses Kopfteil anschliessenden Trägergrundelement angeordnet sind. Derartige Kopfteile ermöglichen eine ideale Überleitung der Kräfte aus den Trägergrundelementen in die Gerüststruktur. In the case of girders made up of two head parts and one or more basic girder elements arranged between these head parts, in which the head parts transmit the vertical forces to the first or second frame structure via exactly one bolt connection, it is further preferred that the head girders as triangular support structure are formed, in which the bolt connection for transmitting the vertical forces to the first or second frame structure is arranged at a first corner and the bolt connections for connection to the support base element adjoining this head part are arranged at the other two corners. Head parts of this type enable an ideal transfer of the forces from the basic support elements into the scaffolding structure.

[0052] Weiter ist es bevorzugt, dass die Kopfteile, mit Vorteil an ihrer Oberseite, jeweils eine Körperlichkeit zur Ankopplung einer Hebevorrichtung, wie z.B. ein Ketten- oder Seilzug, aufweisen, bevorzugterweise eine nach oben wegstehende Lasche mit einer Befestigungsbohrung für eine solche Hebevorrichtung. Mit Vorteil ist diese Körperlichkeit in einem Bereich angeordnet, welcher zwischen dem an dieses Kopfteil angrenzenden Trägergrundelement und dem Ort liegt, an welchem das Kopfteil die vertikalen Kräfte auf die erste bzw. zweite Gerüststruktur überträgt. Hierdurch ergibt sich der Vorteil, dass der mit solchen Kopfteilen gebildete Träger für die Montage mit Hilfe von zwei Ketten- oder Seilzügen in einer wohldefinierten Position an der ersten und der zweiten Gerüststruktur hochgezogen werden kann. It is also preferred that the head parts, advantageously on their upper side, each have a body for coupling a lifting device, such as a chain or cable hoist, preferably a bracket protruding upwards with a fastening hole for such a lifting device. Advantageously, this physicality is arranged in an area which lies between the base support element adjoining this head part and the location at which the head part transfers the vertical forces to the first or second frame structure. This results in the advantage that the support formed with such head parts can be pulled up in a well-defined position on the first and second scaffolding structure for assembly with the aid of two chain or cable hoists.

[0053] Des Weiteren ist es vorteilhaft, dass die erste und die zweite Gerüststruktur ein bestimmtes Rastermass mit bestimmten Verbindungselementen (z.B. Pin zum Anschliessen eines weiteren Gerüststandrohrs, Lochscheibe am Gerüststandrohr, Keilkopf an Gerüststreben zur Befestigung der Streben an den Lochscheiben) aufweisen und die Träger dieselben Verbindungselemente mit demselben Rastermass oder einem zu dem Rastermass der ersten und zweiten Gerüststruktur kompatiblen Rastermass aufweisen. Furthermore, it is advantageous that the first and the second scaffolding structure have a certain grid dimension with certain connecting elements (e.g. pin for connecting another scaffolding tube, perforated disk on the scaffolding tube, wedge head on scaffolding struts for fastening the struts to the perforated disks) and the supports have the same connecting elements with the same grid size or a grid size that is compatible with the grid size of the first and second framework structure.

[0054] Hierdurch wird es möglich, die Träger in ein Raumgerüst mit der ersten bzw. der zweiten Gerüststruktur zu integrieren, z.B. derartig, dass diese Gerüststrukturen unter Nutzung der Träger über den Trägern fortgesetzt werden können. This makes it possible to integrate the carriers into a spatial frame with the first or the second frame structure, e.g. in such a way that these frame structures can be continued using the carriers over the carriers.

[0055] Entsprechend ist gemäss einer weiteren bevorzugten Ausführungsform der erfindungsgemässen Tragstruktur auf der Trägerstruktur ein Raumgerüst angeordnet, bevorzugterweise die Tragstruktur einer Tribüne oder eines insbesondere einseitig oder doppelseitig geneigten Daches, welches bevorzugterweise in die Raumgerüste der ersten und der zweiten Gerüststruktur übergeht. Correspondingly, according to a further preferred embodiment of the support structure according to the invention, a spatial frame is arranged on the support structure, preferably the support structure of a grandstand or a roof that is inclined in particular on one or both sides, which preferably merges into the spatial frames of the first and the second frame structure.

[0056] Die Träger für die Trägerstruktur der erfindungsgemässen Tragstruktur sind bevorzugterweise gebildet aus zwei Kopfteilen und einem oder mehreren zwischen den Kopfteilen angeordneten, bevorzugterweise identischen Trägergrundelementen, welche als zweidimensionale Fachwerke ausgebildet sind und untereinander und mit den Kopfteilen jeweils über genau zwei Bolzenverbindungen verbunden sind. Derartige Träger weisen den Vorteil auf, dass sie im demontierten Zustand sehr wenig Lager- und Transportraum benötigen. The supports for the support structure of the support structure according to the invention are preferably formed from two head parts and one or more preferably identical support basic elements arranged between the head parts, which are designed as two-dimensional frameworks and are connected to one another and to the head parts via exactly two bolt connections. Such carriers have the advantage that they require very little storage and transport space when dismantled.

[0057] Wie bereits erwähnt wurde, weisen die Trägergrundelemente bevorzugterweise eine Länge von weniger als 5 m auf, z.B. eine Länge von etwa 2 m oder etwa 4 m. So sind sie einfach zu transportieren und zu handhaben, z.B. mittels eines einfachen Gabelstaplers oder mittels untergesetzten Fahrgestellen. As already mentioned, the basic support elements preferably have a length of less than 5 m, for example a length of about 2 m or about 4 m lower chassis.

[0058] In einer bevorzugten Ausführungsform sind die Kopfteile der Träger jeweils als eine dreieckige Tragstruktur ausgebildet, welche im Bereich einer ersten Ecke eine Paarungshälfte einer Bolzenverbindung (z.B. eine Doppellasche) zur Übertragung der vertikalen Kräfte auf die erste bzw. zweite Gerüststruktur aufweist und im Bereich der übrigen zwei Ecken die Bolzenverbindungen zur Verbindung mit dem an dieses Kopfteil anschliessenden Trägergrundelement aufweist. Derartige Träger ermöglichen eine ideale Überleitung der Kräfte aus den Trägergrundelementen in die Bolzenverbindungen zur Übertragung der vertikalen Kräfte auf die erste und die zweite Gerüststruktur. In a preferred embodiment, the head parts of the carriers are each designed as a triangular support structure, which has a pairing half of a bolt connection (e.g. a double strap) in the area of a first corner for transferring the vertical forces to the first or second framework structure and in the area of the other two corners has the bolt connections for connection to the carrier base element adjoining this head part. Such girders enable an ideal transfer of the forces from the basic girder elements into the bolted connections for transferring the vertical forces to the first and second scaffolding structure.

[0059] In einer weiteren bevorzugten Ausführungsform des Trägers weisen die Kopfteile an ihrer Oberseite jeweils eine Körperlichkeit zur Ankopplung einer Hebevorrichtung, wie z.B. ein Ketten- oder Seilzug, auf, bevorzugterweise eine nach oben wegstehende Lasche mit einer Befestigungsbohrung für eine Hebevorrichtung. Mit Vorteil ist diese Körperlichkeit in einem Bereich angeordnet, welcher zwischen dem an dieses Kopfteil angrenzenden Trägergrundelement und dem Ort liegt, an welchem das jeweilige Kopfteil bei bestimmungsgemässer Verwendung die vertikalen Kräfte auf die erste bzw. zweite Gerüststruktur überträgt. Hierdurch ergibt sich der Vorteil, dass der Träger für die Montage mit Hilfe von zwei Ketten- oder Seilzügen in einer wohldefinierten Position an der ersten und der zweiten Gerüststruktur hochgezogen werden kann. In a further preferred embodiment of the carrier, the head parts each have a physical structure on their upper side for coupling a lifting device, such as a chain or cable hoist, preferably an upwardly protruding lug with a fastening hole for a lifting device. Advantageously, this physicality is arranged in an area which lies between the basic support element adjoining this head part and the location at which the respective head part transmits the vertical forces to the first or second frame structure when used as intended. This results in the advantage that the carrier can be pulled up in a well-defined position on the first and second scaffolding structure for assembly with the aid of two chain or cable hoists.

[0060] Ein zweiter Aspekt der Erfindung betrifft ein Verfahren zur Erstellung einer Tragstruktur, bevorzugterweise einer Tragstruktur gemäss dem ersten Aspekt der Erfindung. A second aspect of the invention relates to a method for creating a support structure, preferably a support structure according to the first aspect of the invention.

[0061] Gemäss dem Verfahren werden eine wandartige erste Gerüststruktur, welche sich im Wesentlichen in einer vertikalen ersten Ebene erstreckt und schubsteif in dieser Ebene ist, und eine wandartige zweite Gerüststruktur, welche sich im Wesentlichen in einer vertikalen, bevorzugterweise parallel zur ersten Ebene verlaufenden zweiten Ebene erstreckt und schubsteif in dieser Ebene ist, derartig bereitgestellt, dass sie sich mit einem Abstand gegenüberstehen. According to the method, a wall-like first scaffolding structure, which extends essentially in a vertical first plane and is shear-resistant in this plane, and a wall-like second scaffolding structure, which essentially extends in a vertical, preferably parallel to the first plane, second Plane extends and is shear-resistant in this plane, provided in such a way that they face each other at a distance.

[0062] Des Weiteren wird eine Trägerstruktur umfassend mindestens zwei Träger bereitgestellt, welche sich im Wesentlichen in einer horizontalen Ebene, bevorzugterweise in Bodennähe oder am Boden, zwischen der ersten Gerüststruktur und der zweiten Gerüststruktur erstreckt und schubsteif in dieser Ebene ist. Die Trägerstruktur dringt dabei mit den Enden ihrer Träger in die erste und in die zweite Gerüststruktur ein. Furthermore, a support structure is provided comprising at least two supports, which essentially extends in a horizontal plane, preferably near or on the ground, between the first framework structure and the second framework structure and is shear-resistant in this plane. The support structure penetrates with the ends of its supports into the first and into the second frame structure.

[0063] Sowohl zwischen der ersten Gerüststruktur und den Trägern der Trägerstruktur in dem Bereich oder nahe dem Bereich, in welchem die Enden der Träger in die erste Gerüststruktur eindringen, als auch zwischen der zweiten Gerüststruktur und den Trägern der Trägerstruktur im dem Bereich oder nahe dem Bereich, in welchem die Enden der Träger in die zweite Gerüststruktur eindringen, werden Hebevorrichtungen, bevorzugterweise Seil- oder Kettenzüge, angeordnet. Both between the first framework structure and the beams of the beam structure in the area or near the area in which the ends of the beams penetrate into the first framework structure, and between the second framework structure and the beams of the beam structure in the area or near the Lifting devices, preferably cable or chain hoists, are arranged in the area in which the ends of the girders penetrate into the second framework structure.

[0064] Sodann wird die Trägerstruktur mittels der Hebevorrichtungen unter einem vertikalen Verfahren der Enden der Träger innerhalb der ersten und der zweiten Gerüststruktur angehoben, bis sie sich in einer gewünschten Installationsposition zwischen der ersten und der zweiten Gerüststruktur befindet. Then, the truss structure is lifted by the hoists under vertical displacement of the ends of the trusses within the first and second truss structures until it is in a desired installation position between the first and second truss structures.

[0065] In dieser Installationsposition werden die Enden der Träger der Trägerstruktur derartig mit der ersten Gerüststruktur und der zweiten Gerüststruktur verbunden, dass die Trägerstruktur bei einem Entfernen oder Entlasten der Hebevorrichtungen von der ersten und der zweiten Gerüststruktur getragen wird und dass zwar in Richtung der ersten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur auf die erste Gerüststruktur übertragen werden können und/oder in Richtung der zweiten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur auf die zweite Gerüststruktur übertragen werden können, nicht jedoch Biegemomente, welche um parallel zu der ersten bzw. zweite Ebene verlaufende Achsen wirken. In this installation position, the ends of the beams of the support structure are connected to the first framework structure and the second framework structure in such a way that when the lifting devices are removed or relieved of load, the support structure is supported by the first and second framework structure, namely in the direction of the first Plane-acting horizontal shear forces can be transferred from the at least one support structure to the first framework structure and/or horizontal shear forces acting in the direction of the second plane can be transferred from the at least one support structure to the second framework structure, but not bending moments which are parallel to the first or axes running on the second plane.

[0066] Zudem erfolgt das Verbinden zwischen den Trägern der Trägerstruktur und der ersten Gerüststruktur und der zweiten Gerüststruktur derart, dass jeder der Träger an seinem anspruchsgemässen ersten Ende in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur übertragen kann und an seinem anspruchsgemässen zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur übertragen kann. In addition, the connection between the supports of the support structure and the first framework structure and the second framework structure takes place in such a way that each of the supports can transmit shear forces acting in the longitudinal direction of the support at its first end according to the claims to the framework structure connected to this end and at its second end according to the claims no shearing forces acting in the longitudinal direction of the beam can be transferred to the scaffolding structure connected to this end.

[0067] Mit dem erfindungsgemässen Verfahren ist es möglich, Tragstrukturen gemäss dem ersten Aspekt der Erfindung mit grossen Spannweiten ohne einen Kran zu Erstellen. With the method according to the invention it is possible to create support structures according to the first aspect of the invention with large spans without a crane.

[0068] In einer bevorzugten Ausführungsform des Verfahrens werden die Träger der Trägerstruktur mit einem oder mehreren Trägergrundelementen gebildet, die miteinander verbunden werden, wobei die Trägergrundelemente bei der Montage der Träger zwecks Bereitstellung der Trägerstruktur mittels untergestellten Fahrwerken in die gewünschte Montageposition gefahren werden, was bevorzugterweise mittels Muskelkraft erfolgt. In a preferred embodiment of the method, the supports of the support structure are formed with one or more basic support elements that are connected to one another, with the basic support elements being moved into the desired assembly position during assembly of the supports in order to provide the support structure by means of undercarriages, which is preferably done by muscle power.

[0069] Bevorzugterweise werden dabei höheneinstellbare Fahrwerke verwendet, deren Höhe bei der Montage eingestellt wird. Height-adjustable undercarriages are preferably used here, the height of which is adjusted during assembly.

[0070] Hierdurch werden Hilfsmittel, wie z.B. Gabelstapler, welche im Montagebereich relativ viel Platz benötigen und eine Gefahrenquelle für das Montagepersonal darstellen, nur noch für das Abladen der Trägergrundelemente vom LKW benötigt, während der Transport derselben vor Ort und das Positionieren und Ausrichten bei der Montage im Wesentlichen ohne Maschinenunterstützung erfolgen kann. As a result, tools such as forklifts, which require a relatively large amount of space in the assembly area and represent a source of danger for the assembly personnel, are only required for unloading the basic carrier elements from the truck, while transporting them on site and positioning and aligning them at the Assembly can be done essentially without machine support.

KURZE BESCHREIBUNG DER ZEICHNUNGENBRIEF DESCRIPTION OF THE DRAWINGS

[0071] Weitere Ausgestaltungen, Vorteile und Anwendungen der Erfindung ergeben sich aus den abhängigen Ansprüchen und aus der nun folgenden Beschreibung anhand der Figuren. Darin zeigen: Fig. 1 eine Seitenansicht einer ersten erfindungsgemässe Tragstruktur; Fig. 2 eine Draufsicht von oben auf die Tragstruktur aus Fig. 1; Fig. 3 eine Seitenansicht einer zweiten erfindungsgemässe Tragstruktur; Fig. 4 eine Draufsicht von oben auf die Tragstruktur aus Fig. 3; Fig. 5a eine Seitenansicht eines Trägers der Tragstrukturen aus den Figuren 1 bis 4; Fig. 5b eine Draufsicht von oben auf den Träger aus Fig. 5a; Fig. 6a eine Seitenansicht des Bereichs der Anbindung der anspruchsgemässen ersten Enden der Träger bei den Tragstrukturen aus den Figuren 1 bis 4 an die Gerüststruktur; Fig. 6b eine Seitenansicht des Bereichs der Anbindung der anspruchsgemässen zweiten Enden der Träger bei den Tragstrukturen aus den Figuren 1 bis 4 an die Gerüststruktur; Fig. 7a eine vergrösserte perspektivische Draufsicht auf den in Fig. 6a gezeigten Bereich der Anbindung der Träger an die Gerüststruktur; Fig. 7b eine vergrösserte perspektivische Draufsicht auf den in Fig. 6b gezeigten Bereich der Anbindung der Träger an die Gerüststruktur; Fig. 8 eine perspektivische Draufsicht auf einen teilmontierten Träger gemäss Fig. 5a; Fig. 9 eine Draufsicht von oben auf die Tragstruktur aus Fig. 1 während der Montage; und Fig. 10 eine Draufsicht von oben auf die Tragstruktur aus Fig. 3 während der Montage.[0071] Further configurations, advantages and applications of the invention result from the dependent claims and from the following description with reference to the figures. Therein: FIG. 1 shows a side view of a first support structure according to the invention; FIG. 2 is a top plan view of the support structure of FIG. 1; 3 shows a side view of a second support structure according to the invention; FIG. 4 is a top plan view of the support structure of FIG. 3; 5a shows a side view of a carrier of the support structures from FIGS. 1 to 4; Figure 5b is a top plan view of the carrier of Figure 5a; 6a shows a side view of the area of connection of the first ends of the beams according to the claims in the supporting structures from FIGS. 1 to 4 to the scaffolding structure; 6b shows a side view of the area of connection of the second ends of the beams according to the claims in the supporting structures from FIGS. 1 to 4 to the scaffolding structure; FIG. 7a shows an enlarged perspective plan view of the region of connection of the carrier to the framework structure shown in FIG. 6a; FIG. FIG. 7b shows an enlarged perspective plan view of the region of connection of the carrier to the framework structure shown in FIG. 6b; FIG. FIG. 8 shows a perspective plan view of a partially assembled carrier according to FIG. 5a; FIG. 9 shows a plan view from above of the support structure from FIG. 1 during assembly; FIG. and FIG. 10 shows a plan view from above of the support structure from FIG. 3 during assembly.

WEGE ZUR AUSFÜHRUNG DER ERFINDUNGWAYS TO CARRY OUT THE INVENTION

[0072] Fig. 1 zeigt eine Seitenansicht einer ersten erfindungsgemässen Tragstruktur für einen temporären rechteckigen Hallenbau. Fig. 2 zeigt eine Draufsicht von oben auf diese Tragstruktur. Bei fertiggestelltem Hallenbau ist diese Tragstruktur allseitig mit Planen oder anderen Flächengebilden eingedeckt. 1 shows a side view of a first support structure according to the invention for a temporary rectangular hall construction. Fig. 2 shows a top view of this support structure. When the hall construction is complete, this supporting structure is covered on all sides with tarpaulins or other flat structures.

[0073] Wie zu erkennen ist, umfasst die Tragstruktur zwei parallel mit einem Abstand zueinander verlaufende, sich jeweils in vertikalen Ebenen erstreckende Gerüstwände 1, 2 (anspruchsgemässe wandartige erste und zweite Gerüststrukturen), welche eine Dachtragstruktur 5 (anspruchsgemässe Trägerstruktur) tragen, die sich in einer horizontalen Ebene zwischen diesen erstreckt. As can be seen, the supporting structure comprises two parallel scaffolding walls 1, 2 (according to the claims, wall-like first and second scaffolding structures) which are spaced apart from one another and each extend in vertical planes and carry a roof supporting structure 5 (according to the claims). in a horizontal plane between them.

[0074] Die Gerüstwände 1, 2 sind aus konventionellem Gerüstmaterial aufgebaut, d.h. aus Gerüstelementen mit Gerüststandrohren 7 mit Lochscheiben 11 und endseitigen Pinnen 12 zum Anschliessen weiterer Gerüstelemente, welche über horizontale Streben 21 (Riegel) und diagonale Streben 10, die jeweils mit endseitigen Keilköpfen an den Lochscheiben 11 befestigt sind, miteinander verbunden sind und jeweils ein in der vertikalen Ebene seiner Erstreckung schubsteifes Raumgerüst bilden The scaffolding walls 1, 2 are constructed from conventional scaffolding material, i.e. from scaffolding elements with scaffolding standpipes 7 with perforated discs 11 and pins 12 at the ends for connecting further scaffolding elements, which are connected via horizontal struts 21 (bars) and diagonal struts 10, each with wedge heads at the ends are fastened to the perforated discs 11, are connected to one another and each form a spatial structure that is shear-resistant in the vertical plane of its extension

[0075] Die Dachtragstruktur 5 umfasst mehrere senkrecht zu den Gerüstwänden 1, 2 verlaufende Träger 6, welche sich parallel mit einem Abstand zueinander in horizontaler Richtung erstrecken und über diagonale Verstrebungen 18 und weitere Verstrebungen 24 zu einer in horizontaler Richtung schubsteifen Struktur miteinander verbunden sind. The roof support structure 5 comprises a plurality of girders 6 running perpendicularly to the scaffold walls 1, 2, which extend parallel to one another at a distance in the horizontal direction and are connected to one another via diagonal struts 18 and further struts 24 to form a shear-resistant structure in the horizontal direction.

[0076] Wie aus den Figuren 5a und 5b ersichtlich wird, welche eine Seitenansicht eines der Träger 6 zeigen (Fig. 5a) sowie eine Draufsicht von oben auf einen der Träger (Fig. 5b), handelt es sich bei den Trägern 6 um gerade Fachwerkträger 6, welche aus zwei Kopfteilen 14 und vier identischen, zwischen den Kopfteilen 14 angeordneten Trägergrundelementen 15 gebildet sind. Dabei sind sowohl die Trägergrundelemente 15 als auch die Kopfteile 14 als zweidimensionale Fachwerke ausgebildet und untereinander jeweils über genau zwei Bolzenverbindungen 13 miteinander verbunden. As can be seen from FIGS. 5a and 5b, which show a side view of one of the supports 6 (FIG. 5a) and a top view of one of the supports (FIG. 5b), the supports 6 are straight Truss girders 6, which are formed from two head parts 14 and four identical girder base elements 15 arranged between the head parts 14. Both the basic support elements 15 and the head parts 14 are designed as two-dimensional frameworks and are connected to each other via exactly two bolt connections 13 .

[0077] Wie insbesondere auch aus Fig. 8 ersichtlich ist, welche eine vergrösserte perspektivische Draufsicht auf einen teilmontierten Träger 6 zeigt, weisen die Kopfteile 14 an ihrer Oberseite eine nach oben wegstehende Lasche 16 mit einer Befestigungsbohrung für einen Ketten- oder Seilzug 17 auf. Diese Lasche 16 ist in einem Bereich des Kopfteils 14 angeordnet, welcher zwischen dem an dieses Kopfteil 14 angrenzenden Trägergrundelement 15 und der Bolzenverbindung 13 liegt, über welche das Kopfteil 14 die vertikalen Kräfte auf die Gerüstwand 1 überträgt. Die Trägergrundelemente 15 weisen dieselben Verbindungselemente 11, 12 mit demselben Rastermass auf wie die Gerüstwand 1 bzw. mit einem zu dem Rastermass der Gerüstwand kompatiblen Rastermass. As can be seen in particular from FIG. 8, which shows an enlarged perspective plan view of a partially assembled carrier 6, the head parts 14 have on their upper side a bracket 16 protruding upwards with a fastening hole for a chain or cable pull 17. This lug 16 is arranged in a region of the head part 14 which lies between the supporting base element 15 adjoining this head part 14 and the bolt connection 13 via which the head part 14 transfers the vertical forces to the scaffolding wall 1 . The carrier base elements 15 have the same connecting elements 11, 12 with the same grid dimensions as the scaffolding wall 1 or with a grid dimension that is compatible with the grid dimensions of the scaffolding wall.

[0078] Wie in Zusammenschau mit den Figuren 6a und 7a erkennbar ist, welche eine Seitenansicht des Bereichs der Anbindung des anspruchsgemässen ersten Endes der Träger 6 an die linke Gerüstwand 1 (Fig. 6a) sowie eine vergrösserte perspektivische Draufsicht auf diesen Bereich vor dem Einschieben des Bolzens 13a zur Herstellung der Bolzenverbindung 13 (Fig. 7a) zeigen, übertragen die Kopfteile 14 die vertikalen Kräfte am anspruchsgemässen ersten Ende der Träger 6 jeweils über genau eine Bolzenverbindung 13 auf die erste Gerüstwand 1. Die Bolzenlängsrichtung dieser Bolzenverbindung 13 verläuft parallel zu der vertikalen Ebene in der sich die erste Gerüstwand 1 erstreckt (anspruchsgemässe erste Ebene), so dass diese Bolzenverbindung keine Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken, übertragen kann. As can be seen in combination with FIGS. 6a and 7a, which show a side view of the area where the first end of the carrier 6 according to the claims is attached to the left-hand scaffolding wall 1 (FIG. 6a) and an enlarged perspective top view of this area before it is pushed in of the bolt 13a for producing the bolt connection 13 (Fig. 7a), the head parts 14 transmit the vertical forces at the first end of the beam 6 according to the claims via exactly one bolt connection 13 to the first scaffolding wall 1. The longitudinal direction of the bolt connection 13 runs parallel to the vertical plane in which the first scaffolding wall 1 extends (first plane according to the claims), so that this bolt connection cannot transmit any bending moments which act around axes running parallel to these planes.

[0079] Wie in Zusammenschau mit den Figuren 6b und 7b erkennbar ist, welche eine Seitenansicht des Bereichs der Anbindung des anspruchsgemässen zweiten Endes der Träger 6 an die rechte Gerüstwand 2 (Fig. 6b) sowie eine vergrösserte perspektivische Draufsicht auf diesen Bereich (Fig. 7b) zeigen, übertragen die Kopfteile 14 die vertikalen Kräfte am anspruchsgemässen zweiten Ende der Träger 6 jeweils über einen ersten Bolzen 13a auf eine Pendellasche 26, welche diese Kräfte über einen zweiten Bolzen 13b auf die erste Gerüstwand 1 überträgt. Die Bolzenlängsrichtung dieser Bolzenverbindungen verläuft parallel zu der vertikalen Ebene in der sich die zweite Gerüstwand 2 erstreckt (anspruchsgemässe zweite Ebene), so dass diese Bolzenverbindung keine Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken, übertragen kann. As can be seen in combination with Figures 6b and 7b, which show a side view of the area of the connection of the second end of the carrier 6 according to the claim to the right scaffolding wall 2 (Fig. 6b) and an enlarged perspective top view of this area (Fig. 7b) show, the head parts 14 transmit the vertical forces at the second end of the girders 6 according to the claims via a first bolt 13a to a pendulum bracket 26, which transmits these forces to the first scaffolding wall 1 via a second bolt 13b. The longitudinal direction of these bolted connections runs parallel to the vertical plane in which the second scaffolding wall 2 extends (second level according to the claims), so that this bolted connection cannot transmit any bending moments acting around axes running parallel to these planes.

[0080] Die Kopfteile 14 der Träger 6 sind jeweils als eine dreieckige Tragstruktur ausgebildet, an deren dem Träger 6 abgewandter Ecke (anspruchsgemässe erste Ecke) eine Doppellasche 19 (anspruchsgemässe Paarungshälfte einer Bolzenverbindung) angeordnet ist. Diese Doppellasche 19 bildet am ersten Ende des Trägers 6 zusammen mit einer starren Gegenlasche 25 an der ersten Gerüstwand 1 und dem Bolzen 13a eine Bolzenverbindung 13, welche in Trägerlängsrichtung wirkende Schubkräfte vom ersten Ende des Trägers 6 auf die erste Gerüstwand 1 übertragen kann. The head parts 14 of the carriers 6 are each designed as a triangular support structure, at the corner of which facing away from the carrier 6 (first corner according to the claims) is arranged a double bracket 19 (mating half of a bolted connection according to the claims). At the first end of the girder 6, this double lug 19 forms, together with a rigid counter lug 25 on the first scaffolding wall 1 and the bolt 13a, a bolt connection 13 which can transmit shear forces acting in the longitudinal direction of the girder from the first end of the girder 6 to the first scaffolding wall 1.

[0081] Am zweiten Ende des Trägers 6 bildet die Doppellasche 19 zusammen mit der Pendellasche 26 und dem ersten Bolzen 13a eine erste Bolzenverbindung und die Pendellasche 26 zusammen mit einer starren Gegenlasche 25 an der zweiten Gerüstwand 2 und dem zweiten Bolzen 13b eine zweite Bolzenverbindung, wodurch sich eine Verbindung zwischen dem zweiten Ende des Trägers 6 und der zweiten Gerüstwand 2 ergibt, welche keine in Trägerlängsrichtung wirkende Schubkräfte auf die zweite Gerüstwand 2 übertragen kann. At the second end of the beam 6, the double shackle 19 together with the pendulum shackle 26 and the first bolt 13a forms a first bolt connection and the pendulum shackle 26 together with a rigid counter-shackle 25 on the second scaffolding wall 2 and the second bolt 13b forms a second bolt connection. This results in a connection between the second end of the girder 6 and the second scaffolding wall 2 which cannot transmit shear forces acting in the longitudinal direction of the girder to the second scaffolding wall 2 .

[0082] Das Zentrum der Bolzen 13a liegt in der Neutralachse des Trägers 6. An den beiden anderen Ecken der dreieckigen Tragstruktur des Kopfteils 14 sind die Bolzenverbindungen 13 zu dem an dieses Kopfteil 14 anschliessenden Trägergrundelement 15 angeordnet. The center of the bolt 13a lies in the neutral axis of the carrier 6. At the other two corners of the triangular support structure of the head part 14, the bolt connections 13 to the base element 15 adjoining this head part 14 are arranged.

[0083] Wie weiter insbesondere in den Figuren 7a und 7b erkennbar ist, erfolgt die Einleitung der von den Enden der Träger 6 in vertikaler Richtung auf die Gerüstwände 1, 2 übertragenen Kräfte jeweils im Wesentlichen gleichmässig auf vier, in der Draufsicht gesehen einen quadratischen Gerüststrukturteil bildende Gerüststandrohre 7. Dies wird dadurch erreicht, dass die gerüstwandseitige Gegenlasche jeweils von einem Doppel-T-Träger 9 (anspruchsgemässe zweite Auflager-Tragstruktur) getragen wird, der die vertikalen Kräfte je hälftig auf zwei Fachwerkträger 8 (anspruchsgemässe erste Auflager-Tragstrukturen) überträgt, welche diese Kräfte wiederum je hälftig auf zwei sich gegenüberliegende Gerüststandrohre 7 verteilen. As can also be seen in particular in FIGS. 7a and 7b, the forces transmitted from the ends of the supports 6 in the vertical direction to the scaffolding walls 1, 2 are introduced essentially evenly over four scaffolding structural parts that are square when viewed from above forming scaffold standpipes 7. This is achieved in that the scaffolding wall-side counter-plate is each supported by a double T-beam 9 (second support structure according to the claims), which transfers the vertical forces in equal parts to two truss girders 8 (first support structures according to the claims). , which in turn distribute these forces in equal parts to two opposing scaffolding standpipes 7 .

[0084] Dabei ist der Träger 6 von unten an die Doppel-T-Träger 9 angehängt und der Ort der Einleitung der vertikalen Kräfte von den Enden des Trägers 6 in die Gegenlasche 25 des jeweiligen Doppel-T-Trägers 9 liegt unterhalb von den Orten der Einleitung der vertikalen Kräfte von dem Doppel-T-Träger 9 in die beiden Fachwerkträger 8. Dabei weisen die zwei Fachwerkträger 8 jeweils dieselben Verbindungselemente 11, 12 mit demselben Rastermass auf wie die Gerüstwände 1, 2 und sind in deren Raumgerüst integriert. The carrier 6 is attached to the I-beam 9 from below and the location of the introduction of the vertical forces from the ends of the carrier 6 into the counter-plate 25 of the respective I-beam 9 is below the locations the introduction of the vertical forces from the I-beam 9 in the two trusses 8. The two trusses 8 each have the same connecting elements 11, 12 with the same grid dimensions as the scaffolding walls 1, 2 and are integrated into their spatial framework.

[0085] Wie aus Fig. 2 hervorgeht, ist die Dachtragstruktur 5 zudem über diagonale Verstrebungen 22 und weitere Verstrebungen 23 derartig mit den beiden Gerüstwänden 1, 2 verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in denen sich diese Gerüstwände 1, 2 erstrecken, von der Dachtragstruktur 5 auf diese Gerüstwände 1, 2 übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken. 2, the roof support structure 5 is also connected to the two scaffolding walls 1, 2 via diagonal struts 22 and other struts 23 in such a way that horizontal shear forces acting in the direction of the vertical planes in which these scaffolding walls 1, 2 extend from the roof support structure 5 to these scaffolding walls 1, 2, but not bending moments which act around axes running parallel to these planes.

[0086] Weiter umfasst die Tragstruktur zwei weitere, parallel mit einem Abstand zueinander verlaufende und sich jeweils in vertikalen Ebenen erstreckende Gerüstwände 3, 4 (anspruchsgemässe wandartige weitere Gerüststrukturen bzw. anspruchsgemässe dritte und vierte Gerüststrukturen), welche keine Tragfunktion bezüglich der Dachtragstruktur 5 ausüben. The supporting structure also comprises two further scaffolding walls 3, 4 (further wall-like scaffolding structures according to the claims or third and fourth scaffolding structures according to the claims) which run parallel at a distance from one another and each extend in vertical planes and which do not have any supporting function with regard to the roof supporting structure 5.

[0087] Diese weitere Gerüstwände 3, 4 verlaufen unter einem Winkel von 90° (senkrecht) zu den Gerüstwänden 1, 2, welche die Dachtragstruktur 5 tragen, und sind wie diese aus konventionellem Gerüstmaterial aufgebaut, d.h. aus Gerüstelementen mit Gerüststandrohren 7 mit Lochscheiben 11 und endseitigen Pinnen 12 zum Anschliessen weiterer Gerüstelemente, welche über horizontale Streben 21 (Riegel) und diagonale Streben 10, die jeweils mit endseitigen Keilköpfen an den Lochscheiben 11 befestigt sind, miteinander verbunden sind. Auch sie bilden jeweils ein in der vertikalen Ebene seiner Erstreckung schubsteifes Raumgerüst. Diese weiteren Gerüstwände 3, 4 sind nicht mit den Gerüstwänden 1, 2 verbunden, welche die Dachtragstruktur 5 tragen. These further scaffolding walls 3, 4 run at an angle of 90° (perpendicular) to the scaffolding walls 1, 2, which carry the roof support structure 5, and like these are constructed from conventional scaffolding material, i.e. from scaffolding elements with scaffolding standpipes 7 with perforated discs 11 and pins 12 at the ends for connecting further framework elements, which are connected to one another via horizontal struts 21 (bars) and diagonal struts 10, which are each fastened to the perforated disks 11 with wedge heads at the ends. They also each form a spatial structure that is shear-resistant in the vertical plane of its extension. These further scaffolding walls 3, 4 are not connected to the scaffolding walls 1, 2 which carry the roof support structure 5.

[0088] Wie wiederum aus Fig. 2 hervorgeht, ist die Dachtragstruktur 5 auch mit diesen Gerüstwänden 3, 4 über diagonale Verstrebungen 22 verbunden, derart, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in denen sich diese Gerüstwände 3, 4 erstrecken, von der Dachtragstruktur 5 auf diese Gerüstwände 3, 4 übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken. 2, the roof support structure 5 is also connected to these scaffolding walls 3, 4 via diagonal struts 22 in such a way that horizontal shearing forces acting in the direction of the vertical planes in which these scaffolding walls 3, 4 extend, can be transferred from the roof support structure 5 to these scaffolding walls 3, 4, but not bending moments which act around axes running parallel to these planes.

[0089] Die in den Figuren 3 und 4 dargestellte zweite erfindungsgemässe Tragstruktur unterscheidet sich von der zuvor beschriebenen Tragstruktur lediglich dadurch, dass die weiteren Gerüstwände 3, 4 mit den Gerüstwänden 1, 2, welche die Dachtragstruktur 5 tragen, verbunden sind, derart, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen wirken, in welchen sich die weiteren Gerüstwände 3, 4 erstrecken, von den die Dachtragstruktur 5 tragenden Gerüstwänden 1, 2 auf die weiteren Gerüstwände 3, 4 übertragen werden können. Bei dieser Variante ist es als Variante auch vorgesehen, dass die Träger 6 mit der Pendellasche 26 abwechselnd mit der ersten Gerüstwand 1 und mit der zweiten Gerüstwand verbunden sind und an ihrem anderen Ende jeweils mit der festen Gegenlasche 25 mit der zweiten Gerüstwand 2 verbunden sind. The second support structure according to the invention shown in Figures 3 and 4 differs from the support structure described above only in that the further scaffolding walls 3, 4 are connected to the scaffolding walls 1, 2, which carry the roof support structure 5, in such a way that horizontal shear forces, which act in the direction of the vertical planes in which the further scaffolding walls 3, 4 extend, can be transferred from the scaffolding walls 1, 2 carrying the roof support structure 5 to the further scaffolding walls 3, 4. In this variant, it is also provided as a variant that the carriers 6 are connected alternately to the first scaffolding wall 1 and to the second scaffolding wall with the pendulum shackle 26 and are connected at their other end to the fixed counter shackle 25 to the second scaffolding wall 2.

[0090] Die Figuren 9 und 10 zeigen Draufsichten von oben auf die Tragstrukturen gemäss den Figuren 1 und 2 (Fig. 9) und gemäss den Figuren 3 und 4 (Fig. 10) im unfertigen Zustand während der Montage gemäss dem erfindungsgemässen Verfahren. 9 and 10 show top views of the support structures according to FIGS. 1 and 2 (FIG. 9) and according to FIGS. 3 and 4 (FIG. 10) in the unfinished state during assembly according to the method according to the invention.

[0091] Diese Draufsichten zeigen die am bestimmungsgemässen Ort bereitgestellten Gerüstwände 1, 2, 3, 4 (anspruchsgemässe erste und zweite Gerüststruktur und anspruchsgemässe mindesten eine weitere Gerüststruktur bzw. dritte und vierte Gerüststruktur) und, angeordnet auf dem Boden zwischen diesen, die aus den Trägern 6 und den zwischen diesen angeordneten Verstrebungen 18, 24 gebildete Dachtragstruktur 5 (anspruchsgemässe Trägerstruktur). These top views show the scaffolding walls 1, 2, 3, 4 provided at the intended location (first and second scaffolding structure according to the claims and at least one further scaffolding structure or third and fourth scaffolding structure according to the claims) and, arranged on the floor between these, the Beams 6 and the struts 18, 24 arranged between them and formed roof support structure 5 (support structure according to the claims).

[0092] Wie zu erkennen ist, dringt die Dachtragstruktur 5 mit den Enden ihrer Träger 6 in die Gerüstwände 1, 2 ein, welche zum Tragen der Dachtragstruktur 5 vorgesehen sind. As can be seen, the roof support structure 5 penetrates with the ends of its supports 6 into the frame walls 1, 2, which are provided for supporting the roof support structure 5.

[0093] Um die Träger 6 der Dachtragstruktur 5 bereitzustellen und für die Gesamtmontage der Dachtragstruktur 5 zu positionieren, wurden die Trägergrundelemente 15 direkt nach dem Abladen vom Transportfahrzeug auf höheneinstellbare Fahrwerke 20 gesetzt, vom Montagepersonal von Hand in die gewünschte Montageposition gefahren, in der Höhe eingestellt und sodann untereinander und mit den Kopfteilen 14 zu den jeweiligen Trägern 6 verbunden, wie dies in Fig. 8 dargestellt ist. In order to provide the carrier 6 of the roof support structure 5 and to position it for the overall assembly of the roof support structure 5, the basic carrier elements 15 were placed on height-adjustable chassis 20 immediately after unloading from the transport vehicle, and the assembly personnel manually moved them to the desired assembly position, at the height adjusted and then connected to each other and to the head parts 14 to the respective carriers 6, as shown in Fig. 8.

[0094] Ausgehend von der in den Figuren 9 und 10 dargestellten Ausgangssituation werden sodann Ketten- oder Seilzüge 17 zwischen den Gerüstwänden 1, 2 und den Trägern 6 der Dachtragstruktur 5 in dem Bereich oder nahe dem Bereich, in welchem die Enden der Träger 6 in die Gerüstwände 1, 2 eindringen, angeordnet und sodann die gesamte Dachtragstruktur 5 mittels der Ketten- oder Seilzüge 17 unter einem vertikalen Verfahren der Enden der Träger 6 innerhalb Gerüstwände 1, 2 in die gewünschte Installationsposition angehoben, so dass die Gegenlaschen 25 der jeweiligen Doppelt-T-Träger 9 der Gerüstwände 1, 2 bzw. die daran bereits mit den zweiten Bolzen 13b befestigten Pendellaschen 26 bestimmungsgemäss in die Doppellaschen 19 an den Kopfteilen 14 der Träger 6 einfahren und die Bolzen 13a gesetzt werden können. Diese Situation ist am Beispiel des ersten Endes eines der Träger 6 als Detail in Fig. 7a gezeigt. Starting from the initial situation shown in Figures 9 and 10, chain or cable hoists 17 are then installed between the scaffolding walls 1, 2 and the supports 6 of the roof support structure 5 in the area or near the area in which the ends of the supports 6 in penetrate the scaffolding walls 1, 2, arranged and then raised the entire roof support structure 5 by means of the chain or cable hoists 17 under a vertical displacement of the ends of the beam 6 within scaffolding walls 1, 2 in the desired installation position, so that the counter-plates 25 of the respective double T-beams 9 of the scaffolding walls 1, 2 or the pendulum lugs 26 already attached to them with the second bolts 13b can be inserted as intended into the double lugs 19 on the head parts 14 of the girders 6 and the bolts 13a can be set. This situation is shown as a detail in FIG. 7a using the example of the first end of one of the beams 6. FIG.

[0095] Nach dem Setzen der Bolzen 13a können die Ketten- oder Seilzüge 17 entlastet und gegebenenfalls auch demontiert werden. Die Dachtragstruktur 5 wird nun von den beiden Gerüstwänden 1, 2 getragen, an denen die Träger 6 befestigt sind, und wird anschliessend über diagonale Verstrebungen 22 und weitere Streben 23 derartig mit den Gerüstwänden 1, 2, 3, 4 verbunden, dass horizontale Schubkräfte, welche in Richtung der vertikalen Ebenen der jeweiligen Gerüstwände wirken, in denen sich diese erstrecken, von der Dachtragstruktur 5 auf diese Gerüstwände übertragbar sind, nicht jedoch Biegemomente, welche um parallel zu diesen Ebenen verlaufende Achsen herum wirken oder horizontale Schubkräfte, welche in Richtung quer zu den vertikalen Ebenen der jeweiligen Gerüstwände wirken. Nach dem Montieren der Verstrebungen 22, 23 liegt die in Fig. 1 bzw. in Fig. 3 dargestellte Situation vor. After setting the bolts 13a, the chain or cable hoists 17 can be relieved and possibly also dismantled. The roof support structure 5 is now carried by the two scaffolding walls 1, 2, to which the beams 6 are attached, and is then connected to the scaffolding walls 1, 2, 3, 4 via diagonal struts 22 and other struts 23 in such a way that horizontal shear forces, which act in the direction of the vertical planes of the respective scaffolding walls in which they extend, can be transferred from the roof support structure 5 to these scaffolding walls, but not bending moments, which act around axes running parallel to these planes, or horizontal shear forces, which act in the direction transverse to the vertical planes of the respective scaffolding walls. After the struts 22, 23 have been mounted, the situation shown in FIG. 1 or in FIG. 3 is present.

[0096] Während in der vorliegenden Anmeldung bevorzugte Ausführungen der Erfindung beschrieben sind, ist klar darauf hinzuweisen, dass die Erfindung nicht auf diese beschränkt ist und auch in anderer Weise innerhalb des Umfangs der nun folgenden Ansprüche ausgeführt werden kann. While the present application describes preferred embodiments of the invention, it is to be understood that the invention is not limited thereto and may be otherwise embodied within the scope of the following claims.

Claims (31)

1. Tragstruktur für einen mehrfach auf- und abbaubaren Hallen-, Bühnen-, Tribünen- oder Brückenbau, umfassend: a) eine wandartige erste Gerüststruktur (1), welche sich im Wesentlichen in einer vertikalen ersten Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; b) eine wandartige zweite Gerüststruktur (2), welche sich im Wesentlichen in einer vertikalen zweiten Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; c) mindestens eine wandartige weitere Gerüststruktur (3, 4), welche sich im Wesentlichen in einer vertikalen Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; d) mindestens eine Trägerstruktur (5), welche sich im Wesentlichen in einer horizontalen Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (18), dass sie schubsteif in dieser Ebene ist; wobei sich die erste Gerüststruktur (1) und die zweite Gerüststruktur (2) mit einem Abstand gegenüberstehen und insbesondere die erste Ebene und die zweite Ebene im Wesentlichen parallel zueinander verlaufen, wobei die vertikale Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, quer, insbesondere senkrecht, zu der ersten und der zweiten Ebene verläuft, wobei die mindestens eine Trägerstruktur (5) von untereinander verbundenen und sich zwischen der ersten (1) und der zweiten Gerüststruktur (2) erstreckenden Trägern (6) gebildet ist und über die Enden dieser Träger (6) derartig mit diesen beiden Gerüststrukturen (1, 2) verbunden ist, dass die mindestens eine Trägerstruktur (5) von der ersten (1) und der zweiten Gerüststruktur (2) getragen wird, dass in Richtung der ersten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die erste Gerüststruktur (1) übertragen werden können und/oder in Richtung der zweiten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die zweite Gerüststruktur (2) übertragen werden können, dass keine um parallel zu der ersten bzw. zweiten Ebene verlaufende Achsen wirkende Biegemomente von der mindestens einen Trägerstruktur (5) auf die erste (1) bzw. die zweite Gerüststruktur (2) übertragen werden können, und dass jeder der Träger (6) an einem ersten seiner beiden Enden in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (1; 2) übertragen kann und an seinem zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (2; 1) übertragen kann, und wobei die mindestens eine Trägerstruktur (5) derartig mit der mindestens einen weiteren Gerüststruktur (3, 4) verbunden ist, dass in Richtung der vertikalen Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, wirkende horizontale Schubkräfte von der mindestens einen Trägerstruktur (5) auf die mindestens eine weitere Gerüststruktur (3, 4) übertragen werden können, und dass keine um eine parallel zu der vertikalen Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, verlaufende Achse wirkenden Biegemomente von der mindestens einen Trägerstruktur (5) auf die mindestens eine weitere Gerüststruktur (3, 4) übertragen werden können.1. Supporting structure for a hall, stage, grandstand or bridge construction that can be assembled and disassembled multiple times, comprising: a) a wall-like first scaffolding structure (1) which essentially extends in a vertical first plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; b) a wall-like second scaffolding structure (2) which essentially extends in a vertical second plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; c) at least one wall-like additional scaffolding structure (3, 4) which essentially extends in a vertical plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; d) at least one support structure (5) which extends essentially in a horizontal plane, being designed in such a way, in particular by diagonal struts (18), that it is shear-resistant in this plane; wherein the first framework structure (1) and the second framework structure (2) face one another at a distance and, in particular, the first plane and the second plane run essentially parallel to one another, wherein the vertical plane, in which the at least one further framework structure (3, 4) essentially extends, runs transversely, in particular perpendicularly, to the first and the second plane, wherein the at least one support structure (5) is formed by supports (6) connected to one another and extending between the first (1) and the second framework structure (2), and via the ends of these supports (6) is connected to these two framework structures (1, 2) in such a way that that the at least one carrier structure (5) is carried by the first (1) and the second frame structure (2), horizontal shear forces acting in the direction of the first level can be transferred from the at least one support structure (5) to the first framework structure (1) and/or horizontal shear forces acting in the direction of the second level can be transferred from the at least one support structure (5) to the second framework structure (2) can be transferred, that no bending moments acting about axes running parallel to the first or second plane can be transferred from the at least one support structure (5) to the first (1) or the second frame structure (2), and that each of the girders (6) can transmit shear forces acting in the longitudinal direction of the girder at a first of its two ends to the framework structure (1; 2) connected to this end and no shearing forces acting in the longitudinal direction of the girder to the framework structure (1; 2) connected to this end at its second end. 2; 1) can transmit, and wherein the at least one carrier structure (5) is connected to the at least one further framework structure (3, 4) in such a way that horizontal shear forces acting in the direction of the vertical plane in which the at least one further scaffolding structure (3, 4) essentially extends can be transferred from the at least one support structure (5) to the at least one further scaffolding structure (3, 4), and that no bending moments acting about an axis running parallel to the vertical plane, in which the at least one further scaffolding structure (3, 4) essentially extends, from the at least one carrier structure (5) to the at least one further scaffolding structure (3, 4 ) can be transferred. 2. Tragstruktur für einen mehrfach auf- und abbaubaren Hallen-, Bühnen-, Tribünen- oder Brückenbau, insbesondere nach Anspruch 1, umfassend: a) eine wandartige erste Gerüststruktur (1), welche sich im Wesentlichen in einer vertikalen ersten Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; b) eine wandartige zweite Gerüststruktur (2), welche sich im Wesentlichen in einer vertikalen zweiten Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; c) mindestens eine wandartige weitere Gerüststruktur (3, 4), welche sich im Wesentlichen in einer vertikalen Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (10), dass sie schubsteif in dieser Ebene ist; d) mindestens eine Trägerstruktur (5), welche sich im Wesentlichen in einer horizontalen Ebene erstreckt, wobei sie derartig ausgebildet ist, insbesondere durch diagonale Verstrebungen (18), dass sie schubsteif in dieser Ebene ist; wobei sich die erste Gerüststruktur (1) und die zweite Gerüststruktur (2) mit einem Abstand gegenüberstehen und insbesondere die erste Ebene und die zweite Ebene im Wesentlichen parallel zueinander verlaufen, wobei die vertikale Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, quer, insbesondere senkrecht, zu der ersten und der zweiten Ebene verläuft, wobei die mindestens eine Trägerstruktur (5) von untereinander verbundenen und sich zwischen der ersten (1) und der zweiten Gerüststruktur (2) erstreckenden Trägern (6) gebildet ist und über die Enden dieser Träger (6) derartig mit diesen beiden Gerüststrukturen (1, 2) verbunden ist, dass die mindestens eine Trägerstruktur (5) von der ersten (1) und der zweiten Gerüststruktur (2) getragen wird, dass in Richtung der ersten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die erste Gerüststruktur (1) übertragen werden können und/oder in Richtung der zweiten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die zweite Gerüststruktur (2) übertragen werden können,dass keine um parallel zu der ersten bzw. zweiten Ebene verlaufende Achsen wirkende Biegemomente von der mindestens einen Trägerstruktur (5) auf die erste (1) bzw. die zweite Gerüststruktur (2) übertragen werden können, und dass jeder der Träger (6) an einem ersten seiner beiden Enden in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (1; 2) übertragen kann und an seinem zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (2; 1) übertragen kann, wobei die mindestens eine Trägerstruktur (5) derartig mit der ersten (1) und der zweiten Gerüststruktur (2) verbunden ist, dass in Richtung der vertikalen Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, wirkende horizontale Schubkräfte von der mindestens einen Trägerstruktur (5) auf die erste (1) und/oder die zweite Gerüststruktur (2) übertragen werden können, und wobei die erste (1) und/oder die zweite Gerüststruktur (2) derartig mit der mindestens einen weiteren Gerüststruktur (3, 4) verbunden ist bzw. sind, dass in Richtung der vertikalen Ebene, in welcher sich die mindestens eine weitere Gerüststruktur (3, 4) im Wesentlichen erstreckt, wirkende horizontale Schubkräfte von der ersten (1) und/oder der zweiten Gerüststruktur (2) auf die mindesten eine weitere Gerüststruktur (3, 4) übertragen werden können.2. Support structure for a hall, stage, tribune or bridge construction that can be assembled and disassembled multiple times, in particular according to claim 1, comprising: a) a wall-like first scaffolding structure (1) which essentially extends in a vertical first plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; b) a wall-like second scaffolding structure (2) which essentially extends in a vertical second plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; c) at least one wall-like additional scaffolding structure (3, 4) which essentially extends in a vertical plane, being designed in such a way, in particular by means of diagonal struts (10), that it is shear-resistant in this plane; d) at least one support structure (5) which extends essentially in a horizontal plane, being designed in such a way, in particular by diagonal struts (18), that it is shear-resistant in this plane; wherein the first framework structure (1) and the second framework structure (2) face one another at a distance and, in particular, the first plane and the second plane run essentially parallel to one another, wherein the vertical plane, in which the at least one further framework structure (3, 4) essentially extends, runs transversely, in particular perpendicularly, to the first and the second plane, the at least one support structure (5) being connected to one another and located between the first (1) and the second framework structure (2) extending beams (6) and over the ends of these beams (6) is connected to these two framework structures (1, 2) in such a way that that the at least one carrier structure (5) is carried by the first (1) and the second frame structure (2), that horizontal shearing forces acting in the direction of the first level can be transferred from the at least one support structure (5) to the first framework structure (1) and/or horizontal shearing forces acting in the direction of the second level can be transferred from the at least one support structure (5) to the second framework structure (2) can be transferred, that no bending moments acting about axes running parallel to the first or second plane can be transferred from the at least one support structure (5) to the first (1) or the second frame structure (2), and that each of the beams (6) can transmit shear forces acting in the longitudinal direction of the beam at a first of its two ends to the framework structure (1; 2) connected to this end and at its second end no shearing forces acting in the longitudinal direction of the beam to the framework structure ( connected to this end 2; 1) can transfer, wherein the at least one carrier structure (5) is connected to the first (1) and the second framework structure (2) in such a way that in the direction of the vertical plane in which the at least one further framework structure (3, 4) essentially extends horizontal shear forces can be transferred from the at least one support structure (5) to the first (1) and/or the second scaffolding structure (2), and wherein the first (1) and/or the second frame structure (2) is/are connected to the at least one further frame structure (3, 4) in such a way that in the direction of the vertical plane in which the at least one further frame structure ( 3, 4) essentially extended, acting horizontal shearing forces can be transferred from the first (1) and/or the second framework structure (2) to the at least one further framework structure (3, 4). 3. Tragstruktur nach einem der vorangehenden Ansprüche, wobei sämtliche Träger (6) der Trägerstruktur (5) mit ihren zweiten Enden mit der gleichen Gerüststruktur (1; 2) verbunden sind, nämlich nur mit der ersten Gerüststruktur (1) oder nur mit der zweiten Gerüststruktur (2).3. Support structure according to one of the preceding claims, wherein all the supports (6) of the support structure (5) are connected at their second ends to the same framework structure (1; 2), namely only to the first framework structure (1) or only to the second Framework structure (2). 4. Tragstruktur nach einem der Ansprüche 1 bis 2, wobei die Träger (6) der Trägerstruktur (5) mit ihren zweiten Enden mit unterschiedlichen Gerüststrukturen (1; 2) verbunden sind, nämlich mal mit der ersten Gerüststruktur (1) und mal mit der zweiten Gerüststruktur (2) .4. Support structure according to one of claims 1 to 2, wherein the supports (6) of the support structure (5) are connected at their second ends to different framework structures (1; 2), namely sometimes to the first framework structure (1) and sometimes to the second framework structure (2) . 5. Tragstruktur nach Anspruch 4, wobei die Träger (6) der Trägerstruktur (5) mit ihren zweiten Enden abwechselnd oder gruppenweise abwechselnd mal mit der ersten Gerüststruktur (1) und mal mit der zweiten Gerüststruktur (2) verbunden sind.5. Support structure according to claim 4, wherein the supports (6) of the support structure (5) are connected with their second ends alternately or in groups alternately to the first framework structure (1) and to the second framework structure (2). 6. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die Träger (6) der Trägerstruktur (5) mit ihren zweiten Enden jeweils mit einer Gleitfläche auf einer zugeordneten Gleitfläche an der dieses Ende tragenden Gerüststruktur (1; 2) aufliegen.6. Support structure according to one of the preceding claims, wherein the supports (6) of the support structure (5) rest with their second ends each with a sliding surface on an associated sliding surface on the frame structure (1; 2) supporting this end. 7. Tragstruktur nach einem der Ansprüche 1 bis 5, wobei die Träger (6) der Trägerstruktur (5) mit ihren zweiten Enden jeweils über eine Lasche an der dieses Ende tragenden Gerüststruktur (1; 2) angehängt sind.7. Support structure according to one of claims 1 to 5, wherein the supports (6) of the support structure (5) are attached with their second ends in each case via a strap to the framework structure (1; 2) supporting this end. 8. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die Längsachsen der Träger (6) der Trägerstruktur (5) nicht horizontal verlaufen.8. Support structure according to one of the preceding claims, wherein the longitudinal axes of the carrier (6) of the carrier structure (5) do not run horizontally. 9. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die mindestens eine weitere Gerüststruktur (3, 4) zwischen der ersten (1) und der zweiten Gerüststruktur (2) angeordnet ist, insbesondere mittig zwischen den Enden der ersten (1) und der zweiten Gerüststruktur (2).9. Support structure according to one of the preceding claims, wherein the at least one further framework structure (3, 4) is arranged between the first (1) and the second framework structure (2), in particular centrally between the ends of the first (1) and the second framework structure (2). 10. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die mindestens eine wandartige weitere Gerüststruktur (3, 4) eine dritte Gerüststruktur (3) umfasst, welche sich im Wesentlichen in einer vertikalen dritten Ebene erstreckt, und eine vierte Gerüststruktur (4) umfasst, welche sich im Wesentlichen in einer vertikalen vierten Ebene erstreckt, wobei sich die dritte Gerüststruktur (3) und die vierte Gerüststruktur (4) mit einem Abstand gegenüberstehen, und insbesondere, wobei die dritte Ebene und die vierte Ebene im Wesentlichen parallel zueinander verlaufen.10. Support structure according to one of the preceding claims, wherein the at least one wall-like further framework structure (3, 4) comprises a third framework structure (3) which extends substantially in a vertical third plane, and a fourth framework structure (4) which extends substantially in a vertical fourth plane, wherein the third skeleton structure (3) and the fourth skeleton structure (4) face each other at a distance, and in particular wherein the third plane and the fourth plane are substantially parallel to each other. 11. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die mindestens eine weitere Gerüststruktur (3, 4) bzw. die dritte (3) und die vierte Gerüststruktur (4) an einem Ende der ersten (1) und der zweiten Gerüststruktur (2) angeordnet ist bzw. sind, insbesondere derart, dass die Gerüststrukturen (1, 2, 3, 4) einen rechteckiger Raum begrenzen.11. Support structure according to one of the preceding claims, wherein the at least one further frame structure (3, 4) or the third (3) and the fourth frame structure (4) are arranged at one end of the first (1) and the second frame structure (2). is or are, in particular such that the framework structures (1, 2, 3, 4) delimit a rectangular space. 12. Tragstruktur nach einem der vorangehenden Ansprüche, dass die mindestens eine weitere Gerüststruktur (3, 4) bzw. die dritte (3) und die vierte Gerüststruktur (4) nicht mit der ersten (1) und der zweiten Gerüststruktur (2) verbunden ist bzw. sind.12. Support structure according to one of the preceding claims, that the at least one further frame structure (3, 4) or the third (3) and the fourth frame structure (4) is not connected to the first (1) and the second frame structure (2). or are. 13. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die mindestens eine Trägerstruktur (5) mehrere, insbesondere zwei, mit einem Abstand zueinander übereinander angeordnete Trägerstrukturen (5) umfasst, welche insbesondere im Wesentlichen parallel zueinander verlaufen.13. The support structure as claimed in claim 1, wherein the at least one support structure (5) comprises a plurality of, in particular two, support structures (5) which are arranged one above the other at a distance from one another and which in particular run essentially parallel to one another. 14. Tragstruktur nach einem der vorangehenden Ansprüche, wobei die Gerüststrukturen (1, 2, 3, 4) jeweils in horizontaler Richtung in der jeweiligen vertikalen Ebene, in welcher sie sich erstrecken, eine Erstreckung aufweisen, die einem Vielfachen ihrer Erstreckung senkrecht zu dieser Ebene beträgt14. Support structure according to one of the preceding claims, wherein the framework structures (1, 2, 3, 4) each have an extension in the horizontal direction in the respective vertical plane in which they extend, which is a multiple of their extension perpendicular to this plane amounts to 15. Tragstruktur nach einem der vorangehenden Ansprüchen, wobei die Trägerstruktur (5) mehrere quer, insbesondere senkrecht zu der ersten und der zweiten Ebene verlaufende, insbesondere gerade Träger (6) aufweist, insbesondere Fachwerkträger (6), welche sich mit einem Abstand zueinander und insbesondere parallel zueinander im Wesentlichen in horizontaler Richtung erstrecken und derartig miteinander verbunden sind, insbesondere durch quer zu diesen verlaufende Verstrebungen (18, 24), dass sie zusammen eine in horizontaler Richtung schubsteife Struktur bilden.15. Support structure according to one of the preceding claims, wherein the support structure (5) has a plurality of straight supports (6) running transversely, in particular perpendicularly, to the first and second planes, in particular truss girders (6), which are spaced apart from one another and in particular extend parallel to one another essentially in the horizontal direction and are connected to one another in such a way, in particular by struts (18, 24) running transversely thereto, that together they form a shear-resistant structure in the horizontal direction. 16. Tragstruktur nach Anspruch 15, wobei die erste (1) und die zweite Gerüststruktur (2) eine Vielzahl von vertikalen Gerüststandrohren (7) aufweisen und wobei die Träger (6) jeweils derartig mit der ersten (1) und der zweiten Gerüststruktur (2) verbunden sind, dass die von der Trägerstruktur (5) in vertikaler Richtung auf die erste (1) und die zweite Gerüststruktur (2) übertragenen Kräfte jeweils im Wesentlichen gleichmässig auf vier, in der Draufsicht gesehen einen insbesondere rechteckigen oder quadratischen Gerüststrukturteil bildende Gerüststandrohre (7) übertragen werden.16. Support structure according to claim 15, wherein the first (1) and the second scaffolding structure (2) have a plurality of vertical scaffolding standpipes (7) and wherein the girders (6) are each connected to the first (1) and the second scaffolding structure (2 ) are connected in that the forces transmitted from the carrier structure (5) in the vertical direction to the first (1) and the second scaffolding structure (2) are each transmitted essentially uniformly to four scaffolding upright tubes ( 7) are transferred. 17. Tragstruktur nach Anspruch 16, wobei zur Einleitung der vertikalen Kräfte in die vier Gerüststandrohre (7) jeweils diejenigen dieser Gerüststandrohre (7), welche sich in Richtung quer zu der ersten bzw. der zweiten Ebene gegenüberstehen, eine sich zwischen diesen Gerüststandrohren erstreckende erste Auflager-Tragstruktur (8) tragen, insbesondere ein Fachwerkträger (8), und dass diese ersten Auflager-Tragstrukturen (8) eine zweite Auflager-Tragstruktur (9) tragen, insbesondere einen T-Träger oder Doppel-T-Träger (9), welche sich zwischen diesen Gerüststandrohre (7) in einer Richtung parallel zu der ersten bzw. der zweiten Ebene erstreckt und welche ein Ende des jeweiligen Trägers (6) der Trägerstruktur (5) trägt.17. Supporting structure according to claim 16, wherein, in order to introduce the vertical forces into the four scaffolding uprights (7), those of these scaffolding uprights (7) which face each other in a direction transverse to the first or second plane have a first extending between these scaffolding uprights bearing support structure (8), in particular a truss girder (8), and that these first bearing support structures (8) carry a second bearing support structure (9), in particular a T-beam or double T-beam (9), which extends between these standpipes (7) in a direction parallel to the first or second level and which carries one end of the respective beam (6) of the support structure (5). 18. Tragstruktur nach Anspruch 17, wobei der Ort der Einleitung der vertikalen Kräfte von dem Träger (6) in die zweite Auflager-Tragstruktur (9) unterhalb von den Orten der Einleitung der vertikalen Kräfte von der zweiten Auflager-Tragstruktur (9) in die beiden ersten Auflager-Tragstrukturen (8) liegt, und insbesondere, dass der Träger (6) von unten an die zweite Auflager-Tragstruktur (9) angehängt ist.18. Support structure according to claim 17, wherein the location of the introduction of the vertical forces from the beam (6) in the second bearing structure (9) below the locations of the introduction of the vertical forces from the second bearing structure (9) in the the two first bearing structures (8), and in particular that the beam (6) is suspended from below on the second bearing structure (9). 19. Tragstruktur nach einem der Ansprüche 17 bis 18, wobei die erste (1) bzw. die zweite Gerüststruktur (2) ein bestimmtes Rastermass mit bestimmten Verbindungselementen (11, 12) aufweist und die ersten Auflager-Tragstrukturen (8) dieselben Verbindungselemente (11, 12) mit demselben Rastermass oder einem zu dem Rastermass der ersten (1) bzw. der zweiten Gerüststruktur (2) kompatiblen Rastermass aufweisen, so dass die ersten Auflager-Tragstrukturen (8) in ein Raumgerüst gemäss der ersten (1) bzw. der zweiten Gerüststruktur (2) integrierbar sind.19. Support structure according to one of claims 17 to 18, wherein the first (1) or the second framework structure (2) has a specific grid dimension with specific connecting elements (11, 12) and the first bearing support structures (8) have the same connecting elements (11 , 12) with the same grid size or a grid size that is compatible with the grid size of the first (1) or the second framework structure (2), so that the first support structures (8) can be placed in a three-dimensional framework according to the first (1) or the second framework structure (2) can be integrated. 20. Tragstruktur nach einem der Ansprüche 15 bis 19, wobei die Träger (6) jeweils im Bereich ihrer ersten Enden über jeweils genau eine Bolzenverbindung (13) lösbar mit der ersten (1) oder der zweiten Gerüststruktur (2) verbunden sind, und insbesondere, wobei das Zentrum der jeweiligen Bolzenverbindung (13) im Wesentlichen in der Neutralachse des jeweiligen Trägers (6) liegt.20. Support structure according to one of claims 15 to 19, wherein the carriers (6) are each in the region of their first ends releasably connected to the first (1) or the second frame structure (2) via exactly one bolt connection (13), and in particular , wherein the center of the respective bolt connection (13) lies essentially in the neutral axis of the respective carrier (6). 21. Tragstruktur nach einem der Ansprüche 15 bis 20, wobei die Träger (6) jeweils aus mehreren, insbesondere über Bolzenverbindungen (13) lösbar miteinander verbundenen Bauteilen (14, 15) aufgebaut sind.21. Support structure according to one of claims 15 to 20, wherein the carriers (6) are each constructed from a plurality of components (14, 15) which are detachably connected to one another, in particular via bolt connections (13). 22. Tragstruktur nach Anspruch 21, wobei die Träger (6) jeweils aus zwei Kopfteilen (14) und einem oder mehreren zwischen den Kopfteilen (14) angeordneten, insbesondere identischen Trägergrundelementen (15) aufgebaut sind.22. Support structure according to claim 21, wherein the supports (6) each consist of two head parts (14) and one or more, in particular identical, support base elements (15) arranged between the head parts (14). 23. Tragstruktur nach Anspruch 22, wobei die Trägergrundelemente (15) als zweidimensionale Fachwerke ausgebildet sind und untereinander und mit den Kopfteilen (14) jeweils über genau zwei Bolzenverbindungen (13) verbunden sind.23. Support structure according to claim 22, wherein the basic support elements (15) are designed as two-dimensional frameworks and are connected to each other and to the head parts (14) via exactly two bolt connections (13). 24. Tragstruktur nach einem der Ansprüche 22 bis 23, wobei die Trägergrundelemente (15) eine Länge von weniger als 5 m aufweisen, insbesondere eine Länge von 2 m oder 4 m.24. Support structure according to one of claims 22 to 23, wherein the basic support elements (15) have a length of less than 5 m, in particular a length of 2 m or 4 m. 25. Tragstruktur nach einem der Ansprüche 22 bis 24, wobei die Kopfteile (14) die vertikalen Kräfte jeweils über genau eine Bolzenverbindung (13), deren Bolzenlängsrichtung parallel zu der ersten bzw. zweiten Ebene verläuft, auf die erste (1) bzw. zweite Gerüststruktur (2) übertragen, und insbesondere, wobei die Kopfteile (14) jeweils als dreieckige Tragstruktur ausgebildet sind, an deren erster Ecke die Bolzenverbindung (13) zur Übertragung der vertikalen Kräfte auf die erste (1) bzw. zweite Gerüststruktur (2) angeordnet ist und an deren übrigen zwei Ecken die Bolzenverbindungen (13) zur Verbindung mit dem an dieses Kopfteil (14) anschliessenden Trägergrundelement (15) angeordnet sind.25. Supporting structure according to one of claims 22 to 24, wherein the head parts (14) transfer the vertical forces to the first (1) or second level via exactly one bolt connection (13), the longitudinal direction of which runs parallel to the first or second level Transfer scaffolding structure (2), and in particular, wherein the head parts (14) are each designed as a triangular supporting structure, at the first corner of which the bolt connection (13) for transmitting the vertical forces to the first (1) or second scaffolding structure (2) is arranged and at the other two corners of which the bolt connections (13) for connection to the base element (15) adjoining this head part (14) are arranged. 26. Tragstruktur nach einem der Ansprüche 22 bis 25, wobei die Kopfteile (14) insbesondere an ihrer Oberseite jeweils eine Körperlichkeit (16) zur Ankopplung einer Hebevorrichtung (17) aufweisen, insbesondere eine nach oben wegstehende Lasche (16) mit einer Befestigungsbohrung für eine Hebevorrichtung (17), und insbesondere, wobei diese Körperlichkeit (16) in einem Bereich angeordnet ist, welcher zwischen dem an dieses Kopfteil (14) angrenzenden Trägergrundelement (15) und dem Ort liegt, an welchem das Kopfteil (14) die vertikalen Kräfte auf die erste (1) bzw. zweite Gerüststruktur (2) überträgt.26. Support structure according to one of claims 22 to 25, wherein the head parts (14), in particular on their upper side, each have a body (16) for coupling a lifting device (17), in particular a lug (16) protruding upwards with a fastening bore for a Lifting device (17), and in particular, wherein said body (16) is arranged in a region which lies between the supporting base element (15) adjacent to said head part (14) and the place where said head part (14) bears the vertical forces the first (1) or second framework structure (2) transfers. 27. Tragstruktur nach einem der Ansprüche 15 bis 26, wobei die erste (1) und die zweite Gerüststruktur (2) ein bestimmtes Rastermass mit bestimmten Verbindungselementen (11, 12) aufweisen und die Träger (6) dieselben Verbindungselemente (11, 12) mit demselben Rastermass oder einem zu dem Rastermass der ersten (1) und zweiten Gerüststrukturen (2) kompatiblen Rastermass aufweisen, so dass die Träger (6) in ein Raumgerüst gemäss der ersten (1) oder der zweiten Gerüststruktur (2) integrierbar sind.27. Support structure according to one of claims 15 to 26, wherein the first (1) and the second framework structure (2) have a specific grid dimension with specific connecting elements (11, 12) and the carrier (6) with the same connecting elements (11, 12). have the same grid size or a grid size that is compatible with the grid size of the first (1) and second framework structures (2), so that the supports (6) can be integrated into a three-dimensional framework according to the first (1) or the second framework structure (2). 28. Tragstruktur nach einem der vorangehenden Ansprüche, wobei auf der Trägerstruktur (5) ein Raumgerüst angeordnet ist, insbesondere die Tragstruktur einer Tribüne, einer Brücke, einer Plattform oder eines insbesondere einseitig oder doppelseitig geneigten Daches.28. Supporting structure according to one of the preceding claims, wherein on the support structure (5) a space framework is arranged, in particular the support structure of a grandstand, a bridge, a platform or a roof, in particular inclined on one or both sides. 29. Verfahren zur Erstellung einer Tragstruktur insbesondere nach einem der Ansprüche 1 bis 28, umfassend die Schritte: a) Bereitstellen einer wandartigen ersten Gerüststruktur (1), welche sich im Wesentlichen in einer vertikalen ersten Ebene erstreckt und schubsteif in dieser Ebene ist; b) Bereitstellen einer wandartigen zweiten Gerüststruktur (2) welche sich im Wesentlichen in einer vertikalen, insbesondere parallel zur ersten Ebene verlaufenden zweiten Ebene erstreckt und schubsteif in dieser Ebene ist, wobei die erste (1) und die zweite Gerüststruktur (2) derartig bereitgestellt werden, dass sie sich mit einem Abstand gegenüberstehen; c) Bereitstellen einer Trägerstruktur (5) umfassend mindestens zwei Träger (6), welche sich im Wesentlichen in einer horizontalen Ebene, insbesondere in Bodennähe, zwischen der ersten Gerüststruktur (1) und der zweiten Gerüststruktur (2) erstreckt und schubsteif in dieser Ebene ist, wobei die Trägerstruktur (5) mit den Enden ihrer Träger (6) in die erste (1) und in die zweite Gerüststruktur (2) eindringt; d) Anordnen von Hebevorrichtungen (17), insbesondere von Seil- oder Kettenzügen (17), zwischen der ersten Gerüststruktur (1) und den Trägern (6) der Trägerstruktur (5) in dem Bereich oder nahe dem Bereich in welchem die Enden der Träger (6) in die erste Gerüststruktur (1) eindringen und zwischen der zweiten Gerüststruktur (2) und den Trägern (6) der Trägerstruktur (5) im dem Bereich oder nahe dem Bereich in welchem die Enden der Träger (6) in die zweite Gerüststruktur (2) eindringen; e) Anheben der Trägerstruktur (5) mittels der Hebevorrichtungen (17) unter einem vertikalen Verfahren der Enden der Träger (6) innerhalb der ersten (1) und der zweiten Gerüststruktur (2) in eine gewünschte Installationsposition zwischen der ersten (1) und der zweiten Gerüststruktur (2); und f) Verbinden der Enden der Träger (6) der Trägerstruktur (5) in der gewünschten Installationsposition derartig mit der ersten Gerüststruktur (1) und der zweiten Gerüststruktur (2), dass die Trägerstruktur (5) bei einem Entlasten bzw. Entfernen der Hebevorrichtungen (17) von der ersten (1) und der zweiten Gerüststruktur (2) getragen wird, dass in Richtung der ersten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die erste Gerüststruktur (1) übertragen werden können und/oder in Richtung der zweiten Ebene wirkende horizontale Schubkräfte von der mindesten einen Trägerstruktur (5) auf die zweite Gerüststruktur (2) übertragen werden können, dass keine um parallel zu der ersten bzw. zweite Ebene verlaufende Achsen wirkende Biegemomente von der Trägerstruktur (5) auf die erste (1) bzw. die zweite Gerüststruktur (2) übertragen werden können, und dass jeder der Träger (6) an einem ersten seiner beiden Enden in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (1; 2) übertragen kann und an seinem zweiten Ende keine in Trägerlängsrichtung wirkende Schubkräfte auf die mit diesem Ende verbundene Gerüststruktur (2; 1) übertragen kann.29. Method for creating a support structure, in particular according to one of claims 1 to 28, comprising the steps: a) providing a wall-like first framework structure (1) which essentially extends in a vertical first plane and is shear-resistant in this plane; b) providing a wall-like second scaffolding structure (2) which essentially extends in a vertical second plane, in particular running parallel to the first plane, and is shear-resistant in this plane, wherein the first (1) and second skeleton structures (2) are provided so as to face each other at a distance; c) providing a support structure (5) comprising at least two supports (6) which essentially extends in a horizontal plane, in particular near the ground, between the first scaffolding structure (1) and the second scaffolding structure (2) and is shear-resistant in this plane , the support structure (5) penetrating with the ends of its supports (6) into the first (1) and into the second frame structure (2); d) arranging lifting devices (17), in particular cable or chain hoists (17), between the first scaffolding structure (1) and the girders (6) of the girder structure (5) in the area or near the area in which the ends of the girders (6) penetrate into the first skeletal structure (1) and between the second skeletal structure (2) and the beams (6) of the skeletal structure (5) in the area or near the area in which the ends of the beams (6) enter the second skeletal structure (2) penetrate; e) lifting the support structure (5) by means of the lifting devices (17) while vertically moving the ends of the supports (6) within the first (1) and the second framework structure (2) to a desired installation position between the first (1) and the second framework structure (2); and f) connecting the ends of the girders (6) of the girder structure (5) in the desired installation position to the first skeletal structure (1) and the second skeletal structure (2), that the support structure (5) is carried by the first (1) and the second scaffolding structure (2) when the lifting devices (17) are relieved or removed, that horizontal shearing forces acting in the direction of the first level can be transferred from the at least one support structure (5) to the first framework structure (1) and/or horizontal shearing forces acting in the direction of the second level can be transferred from the at least one support structure (5) to the second framework structure (2) can be transferred, that no bending moments acting about axes running parallel to the first or second plane can be transferred from the support structure (5) to the first (1) or the second frame structure (2), and that each of the beams (6) can transmit shear forces acting in the longitudinal direction of the beam at a first of its two ends to the framework structure (1; 2) connected to this end and at its second end no shearing forces acting in the longitudinal direction of the beam to the framework structure ( connected to this end 2; 1) can be transmitted. 30. Verfahren nach Anspruch 29, wobei die Träger (6) der Trägerstruktur (5) mit einem oder mehreren Trägergrundelementen (15) gebildet werden, und wobei die Trägergrundelemente (15) bei der Montage der Träger (6) zwecks Bereitstellung der Trägerstruktur (5) mittels untergestellten Fahrwerken (20), insbesondere durch Muskelkraft, in die gewünschte Montageposition gefahren werden.30. The method according to claim 29, wherein the supports (6) of the support structure (5) are formed with one or more basic support elements (15), and wherein the basic support elements (15) during assembly of the support (6) for the purpose of providing the support structure (5 ) are moved into the desired assembly position by means of undercarriages (20), in particular by muscle power. 31. Verfahren nach Anspruch 30, wobei höheneinstellbare Fahrwerke (20) verwendet werden und wobei deren Höhe bei der Montage eingestellt wird.31. The method according to claim 30, wherein height-adjustable undercarriages (20) are used and the height of which is adjusted during assembly.
CH00028/21A 2021-01-14 2021-01-14 Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times. CH718252A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH00028/21A CH718252A2 (en) 2021-01-14 2021-01-14 Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH00028/21A CH718252A2 (en) 2021-01-14 2021-01-14 Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times.

Publications (1)

Publication Number Publication Date
CH718252A2 true CH718252A2 (en) 2022-07-15

Family

ID=82361145

Family Applications (1)

Application Number Title Priority Date Filing Date
CH00028/21A CH718252A2 (en) 2021-01-14 2021-01-14 Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times.

Country Status (1)

Country Link
CH (1) CH718252A2 (en)

Similar Documents

Publication Publication Date Title
EP3208405B1 (en) Device and method for assembling tower-like structures from pre-fabricated elements
DE7301816U (en) DEVICE FOR ERECTING PREFERABLY ENCLOSED CONCRETE BUILDINGS
DE2146701A1 (en) Multi-storey building construction from prefabricated building units and methods for erecting the same
DE2134069A1 (en) Method and apparatus for He set up multi-storey buildings
DE2109088A1 (en) Spatial building element for the formation of all kinds of support and support structures
DE102017114090B4 (en) Method of constructing a building
EP0350525A1 (en) Method for producing building-walls and a shuttering system
CH718252A2 (en) Supporting structure for a hall, stage, stand or bridge that can be assembled and dismantled several times.
EP3306010A1 (en) Protection and/or work scaffolding and method for erecting it
WO2017127947A1 (en) Supporting structure for a hall, stage, stand or bridge construction which can be assembled and disassembled multiple times
DE3029227A1 (en) CONSTRUCTION FOR MULTIPLE BUILDING AND METHOD FOR CONSTRUCTION
DE2352250A1 (en) STRUCTURE WITH VERTICAL STRUCTURAL WALLS AND HORIZONTAL CEILINGS
DE1684213C3 (en) Buildings with frames made from individual parts
DE2061544B2 (en) METHOD OF ERECTING MULTI-STORY BUILDINGS USING PRE-FABRICATED ROOM CELLS
EP1528173A2 (en) Prestressed floor with hollow floor slabs
DE19924466A1 (en) Modular structure for transportable building has outer walls forming framework and roof truss with fixing points for suspension for transport, with nodes to take weight of building during transport
DE2750931C2 (en)
DE69927833T2 (en) Lifting wall parts cast horizontally at the place
AT167332B (en) Connection for the links of building structures
DE2020381A1 (en) Cooling tower with prefabricated frame members
DE102021117834A1 (en) Elevating platform and method of installing or removing a dwelling unit in a main support structure of a building
WO2014023289A2 (en) Device and method for constructing a multistorey building from prefabricated concrete parts
DE1042871B (en) Building in which the supports are first erected and then the ceiling panels are made on the ground and pulled up into their final position
DE2212898A1 (en) CONSTRUCTION PRINCIPLE AND CONSTRUCTION METHOD FOR LARGE-AREA BRIDGE PLATFORMS CREATED IN IN-SITE CONCRETE
DE112009002323B3 (en) Steel core support