EP2829661A1 - Ground and rock anchor - Google Patents
Ground and rock anchor Download PDFInfo
- Publication number
- EP2829661A1 EP2829661A1 EP13177343.4A EP13177343A EP2829661A1 EP 2829661 A1 EP2829661 A1 EP 2829661A1 EP 13177343 A EP13177343 A EP 13177343A EP 2829661 A1 EP2829661 A1 EP 2829661A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- tension element
- anchoring part
- soil
- rock anchor
- rock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011435 rock Substances 0.000 title claims abstract description 45
- 238000004873 anchoring Methods 0.000 claims abstract description 63
- 239000002689 soil Substances 0.000 claims description 14
- 229920002430 Fibre-reinforced plastic Polymers 0.000 claims description 3
- 239000011151 fibre-reinforced plastic Substances 0.000 claims description 3
- 238000005260 corrosion Methods 0.000 description 5
- 230000007797 corrosion Effects 0.000 description 5
- 239000000758 substrate Substances 0.000 description 5
- 239000004918 carbon fiber reinforced polymer Substances 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 239000004033 plastic Substances 0.000 description 2
- 229920003023 plastic Polymers 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000011152 fibreglass Substances 0.000 description 1
- 239000002657 fibrous material Substances 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 239000004519 grease Substances 0.000 description 1
- 230000005283 ground state Effects 0.000 description 1
- 230000000977 initiatory effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0026—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0026—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
- E21D21/0046—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts formed by a plurality of elements arranged longitudinally
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/808—Ground anchors anchored by using exclusively a bonding material
Definitions
- the present invention relates to an earth anchor and rock anchor, comprising a longitudinally stable flexible tension member, an anchoring part, in which the tension member is fixed to the one end portion, and an anchor head means, in which the tension member is held with the other end portion, which anchoring part thereto is intended to be introduced into an earth or rock hole and anchored there.
- Such earth and rock anchors are used in particular to stabilize slopes and rock walls by the forces to be absorbed by the anchoring part in the surface region of the earth and rock masses to be stabilized are introduced into deeper stable soil layers.
- a tension element which is usually formed of a rod or wire strands, which are anchored in the deeper soil layers.
- these rods or strands are fixed via a mortar mass initiated in the corresponding wellbore.
- the tensioning element can be tensioned via the anchor head device, and the surface soil or masses of rock can be stabilized by means of an anchoring plate on which a longarine is supported.
- the tension element can be used in a plastic sheath, the tension elements can also be accommodated in plastic pipes, which are filled with grease, for example.
- the object of the present invention is now to provide an earth anchor and rock anchor, which is easy to manufacture, and in which in particular the anchoring in the well and also on the anchoring part can be done in an optimal manner.
- the solution of this object is achieved in that the longitudinally stable flexible tension member at least at one end portion which is fixed in the anchoring part, at least one first loop, and that the anchoring part is a substantially prismatic or cylindrical longitudinal body, which is formed by a curable composition of which the at least one first loop of the longitudinally stable flexible tension element is enclosed.
- the anchoring part with at least one first loop of the longitudinally stable flexible tension element fixed therein is prefabricated, so that it is ensured that the fixation of this loop in the anchoring part is optimal.
- This longitudinal body formed of a hardenable mass with the fixed tension element is inserted into the borehole, by initiating a further hardenable mass in the borehole, the longitudinal body is anchored and held in an optimal manner in the borehole bottom.
- the longitudinally stable flexible tension element is formed of a fiber-reinforced plastic, preferably carbon fiber reinforced plastic, whereby corrosion can be excluded.
- a tension element also has the advantage that it is flexible, the flexible tension element can be rolled up, for example, for transporting the earth and rock anchors, which has a space saving the length expansion of such rock anchors result. Due to the possibility of rolling up or bending over the longitudinally stable flexible tension element, the space required in front of the borehole during insertion of the ground anchor and rock anchor is low.
- the longitudinally stable flexible tension element consists of several layers, wherein in one end region, which is fixed in the anchoring part, each layer or a bundle of layers each forms a separate first loop, which separate first loops each have different lengths. This results in a gradual fixation of this tension element in the anchoring part, whereby the anchoring and the power consumption is substantially improved.
- a further advantageous embodiment of the invention is that the hardenable mass, from which the anchoring part is formed, is a mortar-like mass.
- This mortar-like mass can be poured into a mold in which the one end portion of the flexible tension element is inserted, whereby a firm connection between mortar-like mass after curing and the first loops of the flexible tension element is ensured.
- the surface of the anchoring part is provided with structures which can be provided in the mold in which the anchoring part is made and in which the first loops are molded, whereby between the surface of the anchoring part and the hardenable mass initiated in the borehole an optimal connection is created.
- the structures consist of ribs projecting over the surface of the anchoring part, which are aligned substantially transversely to the direction of pull of the force acting on the tensioning element and on the anchoring part, which results in optimum fixation.
- a further advantageous embodiment of the invention is that the anchoring part is enclosed at least over portions of its length with clamping rings. By means of these clamping rings it is avoided that the longitudinal body hardened from a mortar-like mass can break out in these areas.
- a clamping ring is arranged in the entry region of the tension element in the anchoring part, since in this area the power consumption is very large.
- these clamping rings are each arranged in the region of the ends of the first loops of the tension element in the anchoring part, since in these areas the risk of breakout is greatest.
- a further advantageous embodiment of the invention is that the other end region of the tension element is designed as a second loop.
- the tension element can thus be produced as an endless loop, which has a positive effect on their strength.
- a bolt arranged transversely to the direction of pull is provided in the anchor head device, the second loop of the tension element can be laid in a simple manner via this bolt, the holding of the tension element in the anchor head device is optimal.
- the bolt is mounted in a tensioning device which is arranged in the anchor head device, whereby the tension element can be clamped more or less simply by displacing the bolt.
- FIG. 1 is a longitudinally stable flexible tension element 1 with the anchoring part 2 of a Erd- and rock anchor 3 can be seen.
- the one end region 4 of this tension element 1 is fixed in the anchoring part 2.
- the anchoring part 2 consists of a hardenable mass, in particular a mortar-like mass, the connection between anchoring part 2 and tension element 1 is achieved in that one end portion 4 of the tension element 1 is inserted into a mold or form, which form or formwork by the hardenable mass is poured out. After hardening of this mass, the mold or shell can be removed to obtain an anchoring part 2, in which the one end portion 4 of the tension element is optimally fixed and held.
- This anchoring part 2 is formed in the present embodiment by a longitudinal body 8, which has a cylindrical shape.
- this longitudinal body 8 a prismatic or another suitable shape.
- the one end portion 4 of the tension element 1 is formed as a first loop 5; as will be described later, the tension member 1 may have a plurality of first loops 5.
- the other end portion 6 of the tension member 1 is formed as a second loop 7, which can be secured in an anchor head device, not shown, as will be described later.
- FIG. 2 the longitudinal stable flexible tension element 1 is shown.
- This tension element 1 is formed from a fiber-reinforced plastic, preferably from a carbon fiber reinforced plastic, but also glass fiber reinforced plastics or other suitable reinforced Kunsscher are conceivable.
- a fiber-reinforced plastic preferably from a carbon fiber reinforced plastic, but also glass fiber reinforced plastics or other suitable reinforced Kunsscher are conceivable.
- several layers of carbon fiber reinforced plastic can be used, each of these layers or a bundle of layers forms an endless loop.
- the innermost layer or bundle of layers forms the first loop 5 '
- the second or middle layer or bundle of layers forms the first loop 5 "
- the outermost layer or bundle of layers forms the first loop 5"'
- this three first loops 5 ', 5 "and 5"' have different lengths.
- all these layers are formed on one another, so that a single second loop 7 is formed.
- the tension element 1 In the middle region of the tension element 1, all layers which form the loops are arranged one above the other, each of these layers forming a band, in the middle region 9 the tension element 1 thus consists of several superimposed bands. These bands can be laminated over the entire length, they can also be laminated only in areas alternately. Of course, a different number of layers and loops can be selected, depending on the type of use of earth and rock anchors. The layers can also be arranged one above the other and / or next to each other, so that juxtaposed loops of different lengths are conceivable. Large lengths of loops may additionally be provided with constrictions.
- FIG. 4 shows the first loops 5 ', 5 "and 5"', as they are incorporated in the cured mass forming the longitudinal body 8.
- an optimal fixation in the longitudinal body 8 is obtained, which is formed by the mortar-like mass.
- a known, high-strength mortar-like mass is used. This mortar-like mass can be added to their additional reinforcement in a known manner or fiber material.
- the surface 10 of the longitudinal body 8 forming the anchoring part 2 is provided with structures 11 projecting over the surface 10.
- these structures 11 are formed as ribs 12, which are aligned substantially transversely to the pulling direction of the force acting on the tension element 1, and for example, as a spirally encircling ribs 12 may be formed.
- These structures 11 or ribs 12 are incorporated into the surface of the casting mold, while the longitudinal body 8 is produced by the casting process, they are imaged on the surface 10 of the longitudinal body.
- the longitudinal body 8 is enclosed in each case with a clamping ring 13, as will be described in detail later.
- These clamping rings 13 are used to reinforce the longitudinal body 8 in particular in the inlet region of the tension element 1 in the anchoring part 2 and in the region of the first loops 5 ', 5 "and 5"'. In these areas, the risk of breaking out of the mortar-like mass is thereby minimized when loading the earth and rock anchors.
- FIG. 5 is a cross section through the longitudinal body 8, which forms the anchoring part 2, can be seen.
- longitudinal body 8 In this consisting of the mortar mass longitudinal body 8 is a first loop 5 'or 5 "or 5"' embedded.
- a clamping ring 13 To the longitudinal body 8 is in the region of the loop ends, as previously described, in each case a clamping ring 13 is inserted.
- This Clamping ring 13, which may also consist of a carbon fiber reinforced plastic surrounds the longitudinal body 8 in the region of the first loops 5 ', 5 "and 5"', in these areas the breaking of the mortar-like mass is suppressed, which serves to reinforce the anchoring part 2.
- Out FIG. 5 are also the ribs 12 can be seen, which are above the surface 10 of the longitudinal body 8 above.
- the earth anchor and rock anchor 3 according to the invention can be seen in the condition used in the substrate 14 to be stabilized.
- the one end portion 4 is introduced with the anchoring part 2 of the tension element 1 in a mounted in the ground 14 bore 15.
- insertion aids can be used in a known manner, such as rods for inserting the longitudinal body 8 in the bore 15.
- the other end portion 6 of the earth and rock anchor 3, which is designed as a second loop 7, is fastened in an anchor head device 16 which, as will be seen later, is designed as a tensioning device.
- an earth and rock anchor 3 used can have lengths of up to 70 meters or more. With such lengths, it may be appropriate to subdivide the tension element 1 into several sections and to connect them via coupling means, which simplifies handling.
- the longitudinal body 8 can easily have a length of 6 meters, whereby an optimal anchoring in the bore 15 of the substrate to be stabilized 14 can be achieved.
- FIG. 8 Out FIG. 8 is the anchor head device 16 can be seen, with which the other end portion 6 of the tension element 1 of the earth and rock anchor 3 is held.
- the anchor head device 16 consists of a mounting bracket 17 which is provided with two longitudinal slots 18. Inserted in these longitudinal slots 18 is a bolt 19. About this pin 19 is the second loop. 7 of the tension element 1 placed.
- the bolt 19 can be tensioned together with the second loop 7 of the tension element 1 in the direction of the longitudinal slots 18.
- clamping screws 20 are provided, which are screwed into the bolt 19, and which are supported on the support bracket 17. As a result, the tension element 1 can be clamped in a simple manner to the desired clamping force.
- the support bracket 17 is supported on a correspondingly shaped, inclinations receiving long arms 21, this support plate is placed on another plate 22, which may for example consist of concrete, and over which the substrate is stabilized in the surface region.
- the anchor head device 16 is protected in a known, not shown manner against corrosion.
- FIG. 9 again shows the one end 4 with the longitudinal body 8 of the Erd- and rock anchor 3 and anchored in the ground anchoring part 2.
- the guided through the bore 15 tension element 1 can be kept free, it is also conceivable, the bore with a corresponding hardenable mass up fill.
- Such earth and rock anchors can be produced in a simple manner, the introduction of force through the anchoring part in the substrate to be stabilized is optimal, the tension element is not subject to corrosion, thus can be dispensed with appropriate controls.
- Such earth and rock anchors can be used in a simple manner in the ground, they can also be easily transported because the tension element is flexible and can be wound up, whereby a large space savings is achieved.
- the tension element is characterized by a very low weight.
- the tension member can be dimensioned accordingly by the band may be wider and / or thicker, depending on which forces must be absorbed.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Ein Erd- und Felsanker (3) umfasst ein längsstabiles flexibles Zugelement (1), einen Verankerungsteil (2), in welchem das Zugelement (1) mit dem einen Endbereich (4) fixiert werden kann, und einer Ankerkopfeinrichtung, in welchem das Zugelement (1) mit dem anderen Endbereich (6) gehalten ist. Der Verankerungsteil (2) ist dazu bestimmt, in eine Erd- oder Felsbohrloch eingeführt und dort verankert zu werden. Das längsstabile flexible Zugelement (1) ist mindestens am einen Endbereich (4), der im Verankerungsteil (2) fixiert ist, mit mindestens einer ersten Schlaufe (5) versehen. Der Verankerungsteil (2) ist ein im Wesentlichen prismatischer oder zylindrischer Längskörper (8), der durch eine aushärtbare Masse gebildet ist, von welcher die mindestens eine erste Schlaufe (5) des längsstabilen flexiblen Zugelementes (1) umschlossen ist. Durch diese Ausgestaltung lassen sich die Kräfte in optimaler Weise übertragen. An earth and rock anchor (3) comprises a longitudinally stable flexible tension element (1), an anchoring part (2) in which the tension element (1) can be fixed to the one end region (4), and an anchor head device in which the tension element ( 1) is held with the other end portion (6). The anchoring part (2) is intended to be inserted and anchored in a hole in the earth or rock. The longitudinally stable flexible tension element (1) is provided with at least one first loop (5) at least at one end region (4) which is fixed in the anchoring part (2). The anchoring part (2) is a substantially prismatic or cylindrical longitudinal body (8), which is formed by a hardenable mass, of which the at least one first loop (5) of the longitudinally stable flexible tension element (1) is enclosed. By this configuration, the forces can be transmitted in an optimal manner.
Description
Die vorliegende Erfindung bezieht sich auf einen Erd- und Felsanker, umfassend ein längsstabiles flexibles Zugelement, einen Verankerungsteil, in welchem das Zugelement mit dem einen Endbereich fixiert ist, und einer Ankerkopfeinrichtung, in welchem das Zugelement mit dem anderen Endbereich gehalten ist, welcher Verankerungsteil dazu bestimmt ist, in ein Erd- oder Felsbohrloch eingeführt und dort verankert zu werden.The present invention relates to an earth anchor and rock anchor, comprising a longitudinally stable flexible tension member, an anchoring part, in which the tension member is fixed to the one end portion, and an anchor head means, in which the tension member is held with the other end portion, which anchoring part thereto is intended to be introduced into an earth or rock hole and anchored there.
Derartige Erd- und Felsanker dienen insbesondere dazu, Hänge und Felswände zu stabilisieren, indem die vom Verankerungsteil im Oberflächenbereich der zu stabilisierenden Erd- und Felsmassen aufzunehmenden Kräfte in tieferliegende stabile Bodenschichten eingeleitet werden. Zur Übertragung dieser Kräfte vom Verankerungsteil in die tieferliegenden Bodenschichten dient ein Zugelement, das üblicherweise aus einem Stab oder aus Drahtlitzen gebildet ist, die in den tieferen Bodenschichten verankert werden. Hierzu werden diese Stäbe bzw. Litzen über eine in das entsprechende Bohrloch initiierte Mörtelmasse fixiert. Über die Ankerkopfeinrichtung lässt sich das Zugelement spannen, über eine Verankerungsplatte, auf der sich eine Longarine abstützt, kann das oberflächige Erdreich oder die Felsmassen entsprechend stabilisiert werden.Such earth and rock anchors are used in particular to stabilize slopes and rock walls by the forces to be absorbed by the anchoring part in the surface region of the earth and rock masses to be stabilized are introduced into deeper stable soil layers. To transfer these forces from the anchoring part in the deeper soil layers is a tension element, which is usually formed of a rod or wire strands, which are anchored in the deeper soil layers. For this purpose, these rods or strands are fixed via a mortar mass initiated in the corresponding wellbore. The tensioning element can be tensioned via the anchor head device, and the surface soil or masses of rock can be stabilized by means of an anchoring plate on which a longarine is supported.
Derartige Erd- und Felsanker sollen dauerhaft eingesetzt werden, was bedeutet, dass die entsprechenden Bauteile der Erd- und Felsanker insbesondere gegen Korrosion geschützt sein müssen. Hierzu sind verschiedenste Methoden bekannt, beispielsweise kann das Zugelement in eine Kunststoffhülle eingesetzt sein, die Zugelemente können auch in Kunststoffrohren untergebracht werden, die beispielsweise mit Fett gefüllt sind.Such earth and rock anchors should be used permanently, which means that the corresponding components of the earth and rock anchors must be protected against corrosion in particular. For this purpose, a variety of methods are known, for example, the tension element can be used in a plastic sheath, the tension elements can also be accommodated in plastic pipes, which are filled with grease, for example.
Die Herstellung derartig korrosionsgeschützter Erd- und Felsanker ist relativ aufwändig, insbesondere ist es auch erforderlich, dass solche Erd- und Felsanker im eingebauten Zustand überprüft werden müssen, um feststellen zu können, ob eine Korrosion eingesetzt hat, was sich auf die Festigkeit von derartigen Erd- und Felsankern sehr negativ auswirken kann. Derartige Kontrollvorgänge werden beispielsweise in bekannter Weise durch Widerstandsmessungen ausgeführt, was ebenfalls aufwändig ist.The production of such corrosion-protected Erd- and rock anchors is relatively complex, in particular, it is also necessary that such Erd- and rock anchors must be checked when installed to determine whether a corrosion has begun, indicating the strength of such Erd - and rock anchors can have very negative effects. Such control operations are carried out for example in a known manner by resistance measurements, which is also expensive.
Die Aufgabe der vorliegenden Erfindung besteht nun darin, einen Erd- und Felsanker zu schaffen, der einfach in der Herstellung ist, und bei welchem insbesondere die Verankerung im Bohrloch und auch am Verankerungsteil in optimaler Weise erfolgen kann.The object of the present invention is now to provide an earth anchor and rock anchor, which is easy to manufacture, and in which in particular the anchoring in the well and also on the anchoring part can be done in an optimal manner.
Erfindungsgemäss erfolgt die Lösung dieser Aufgabe dadurch, dass das längsstabile flexible Zugelement mindestens am einen Endbereich, der im Verankerungsteil fixiert ist, mindestens eine erste Schlaufe aufweist, und dass der Verankerungsteil ein im Wesentlichen prismatischer oder zylindrischer Längskörper ist, der durch eine aushärtbare Masse gebildet ist, von welchem die mindestens eine erste Schlaufe des längsstabilen flexiblen Zugelementes umschlossen ist.According to the invention, the solution of this object is achieved in that the longitudinally stable flexible tension member at least at one end portion which is fixed in the anchoring part, at least one first loop, and that the anchoring part is a substantially prismatic or cylindrical longitudinal body, which is formed by a curable composition of which the at least one first loop of the longitudinally stable flexible tension element is enclosed.
Der Verankerungsteil mit der darin fixierten mindestens einen ersten Schlaufe des längsstabilen flexiblen Zugelementes wird vorfabriziert, sodass gewährleistet ist, dass die Fixierung dieser Schlaufe im Verankerungsteil optimal ist. Dieser aus einer aushärtbaren Masse gebildete Längskörper mit dem fixierten Zugelement wird in das Bohrloch eingesetzt, durch Initiieren einer weiteren aushärtbaren Masse in das Bohrloch wird der Längskörper in optimaler Weise im Bohrlochgrund verankert und gehalten.The anchoring part with at least one first loop of the longitudinally stable flexible tension element fixed therein is prefabricated, so that it is ensured that the fixation of this loop in the anchoring part is optimal. This longitudinal body formed of a hardenable mass with the fixed tension element is inserted into the borehole, by initiating a further hardenable mass in the borehole, the longitudinal body is anchored and held in an optimal manner in the borehole bottom.
In vorteilhafter Weise ist das längsstabile flexible Zugelement aus einem faserverstärkten Kunststoff gebildet, vorzugsweise kohlefaserverstärkten Kunststoff, wodurch eine Korrosion ausgeschlossen werden kann. Ein derartiges Zugelement hat zudem den Vorteil, dass es biegsam ist, das flexible Zugelement kann beispielsweise zum Transport des Erd- und Felsankers aufgerollt werden, was eine Platzeinsparung der Längenausdehnung derartiger Felsanker zur Folge hat. Durch die Möglichkeit des Aufrollens oder Umbiegens des längsstabilen flexiblen Zugelementes ist der Platzbedarf vor dem Bohrloch beim Einsetzen des Erd- und Felsankers gering.Advantageously, the longitudinally stable flexible tension element is formed of a fiber-reinforced plastic, preferably carbon fiber reinforced plastic, whereby corrosion can be excluded. Such a tension element also has the advantage that it is flexible, the flexible tension element can be rolled up, for example, for transporting the earth and rock anchors, which has a space saving the length expansion of such rock anchors result. Due to the possibility of rolling up or bending over the longitudinally stable flexible tension element, the space required in front of the borehole during insertion of the ground anchor and rock anchor is low.
In vorteilhafter Weise besteht das längsstabile flexible Zugelement aus mehreren Lagen, wobei im einen Endbereich, der im Verankerungsteil fixiert ist, jede Lage oder ein Bündel von Lagen jeweils eine separate erste Schlaufe bildet, welche separaten ersten Schlaufen jeweils unterschiedliche Längen aufweisen. Dadurch erfolgt eine stufenweise Fixierung dieses Zugelementes im Verankerungsteil, wodurch die Verankerung und die Kraftaufnahme wesentlich verbessert wird.Advantageously, the longitudinally stable flexible tension element consists of several layers, wherein in one end region, which is fixed in the anchoring part, each layer or a bundle of layers each forms a separate first loop, which separate first loops each have different lengths. This results in a gradual fixation of this tension element in the anchoring part, whereby the anchoring and the power consumption is substantially improved.
Eine weitere vorteilhafte Ausgestaltung der Erfindung besteht darin, dass die aushärtbare Masse, aus welcher der Verankerungsteil gebildet ist, eine mörtelartige Masse ist. Diese mörtelartige Masse lässt sich in eine Form giessen, in welcher der eine Endbereich des flexiblen Zugelementes eingelegt ist, wodurch eine feste Verbindung zwischen mörtelartiger Masse nach deren Aushärtung und den ersten Schlaufen des flexiblen Zugelementes gewährleistet ist.A further advantageous embodiment of the invention is that the hardenable mass, from which the anchoring part is formed, is a mortar-like mass. This mortar-like mass can be poured into a mold in which the one end portion of the flexible tension element is inserted, whereby a firm connection between mortar-like mass after curing and the first loops of the flexible tension element is ensured.
In vorteilhafter Weise ist die Oberfläche des Verankerungsteils mit Strukturen versehen, welche in der Form, in welcher der Verankerungsteil hergestellt wird und in welchem die ersten Schlaufen eingegossen sind, vorgesehen werden können, wodurch zwischen der Oberfläche des Verankerungsteils und der in das Bohrloch initiierten aushärtbaren Masse eine optimale Verbindung entsteht.Advantageously, the surface of the anchoring part is provided with structures which can be provided in the mold in which the anchoring part is made and in which the first loops are molded, whereby between the surface of the anchoring part and the hardenable mass initiated in the borehole an optimal connection is created.
In vorteilhafter Weise bestehen die Strukturen aus über die Oberfläche des Verankerungsteils vorstehenden Rippen, welche im Wesentlichen quer zur Zugrichtung der Kraft, die auf das Zugelement und auf den Verankerungsteil wirksam ist, ausgerichtet sind, was eine optimale Fixierung ergibt.Advantageously, the structures consist of ribs projecting over the surface of the anchoring part, which are aligned substantially transversely to the direction of pull of the force acting on the tensioning element and on the anchoring part, which results in optimum fixation.
Eine weitere vorteilhafte Ausgestaltung der Erfindung besteht darin, dass der Verankerungsteil mindestens über Teilbereiche seiner Länge mit Spannringen umschlossen ist. Durch diese Spannringe wird vermieden, dass der aus einer mörtelartigen Masse ausgehärtete Längskörper in diesen Bereichen ausbrechen kann.A further advantageous embodiment of the invention is that the anchoring part is enclosed at least over portions of its length with clamping rings. By means of these clamping rings it is avoided that the longitudinal body hardened from a mortar-like mass can break out in these areas.
In vorteilhafter Weise ist ein Spannring im Eintrittsbereich des Zugelementes in den Verankerungsteil angeordnet, da in diesem Bereich die Kraftaufnahme sehr gross ist.Advantageously, a clamping ring is arranged in the entry region of the tension element in the anchoring part, since in this area the power consumption is very large.
In vorteilhafter Weise sind diese Spannringe jeweils im Bereich der Enden der ersten Schlaufen des Zugelementes im Verankerungsteil angeordnet, da in diesen Bereichen die Ausbruchgefahr am grössten ist.Advantageously, these clamping rings are each arranged in the region of the ends of the first loops of the tension element in the anchoring part, since in these areas the risk of breakout is greatest.
Eine weitere vorteilhafte Ausgestaltung der Erfindung besteht darin, dass der andere Endbereich des Zugelementes als zweite Schlaufe ausgebildet ist. Das Zugelement lässt sich somit als Endlosschlaufe herstellen, was sich positiv auf deren Festigkeit auswirkt.A further advantageous embodiment of the invention is that the other end region of the tension element is designed as a second loop. The tension element can thus be produced as an endless loop, which has a positive effect on their strength.
In vorteilhafter Weise ist in der Ankerkopfeinrichtung ein quer zur Zugrichtung angeordneter Bolzen vorgesehen, über diesen Bolzen lässt sich die zweite Schlaufe des Zugelementes in einfacher Weise auflegen, die Halterung des Zugelementes in der Ankerkopfeinrichtung ist optimal.In an advantageous manner, a bolt arranged transversely to the direction of pull is provided in the anchor head device, the second loop of the tension element can be laid in a simple manner via this bolt, the holding of the tension element in the anchor head device is optimal.
Der Bolzen ist in einer Spanneinrichtung angebracht, die in der Ankerkopfeinrichtung angeordnet ist, wodurch sich das Zugelement in einfacher Weise durch Verschieben des Bolzens mehr oder weniger spannen lässt.The bolt is mounted in a tensioning device which is arranged in the anchor head device, whereby the tension element can be clamped more or less simply by displacing the bolt.
Eine Ausführungsform der Erfindung wird nachfolgend anhand der beiliegenden Zeichnung beispielhaft näher erläutert.An embodiment of the invention will be explained in more detail by way of example with reference to the accompanying drawings.
Es zeigt:
-
in räumlicher Darstellung ein Zugelement eines Erd- und Felsankers, eingesetzt in den Verankerungsteil;Figur 1 -
in räumlicher Darstellung das Zugelement mit mehreren ersten Schlaufen und der zweiten Schlaufe;Figur 2 -
Figur 3 eine Schnittdarstellung durch den Verankerungsteil mit eingesetztem Zugelement und Spannringen entlang Linie III-III gemäss Figur 5 ; -
eine Schnittdarstellung durch den Verankerungsteil mit eingesetztem Zugelement und Spannringen entlang Linie IV-Figur 4IV gemäss Figur 5 ; -
eine Schnittdarstellung durch den Verankerungsteil mit eingesetztem Zugelement entlang Linie V-V gemässFigur 5Figur 4 ; -
die Darstellung eines erfindungsgemässen Erd- und Felsankers im in den Untergrund eingesetzten Zustand;Figur 6 -
eine Schnittdarstellung des erfindungsgemässen Erd- und Felsankers, im in den Untergrund eingesetzten Zustand;Figur 7 -
eine Schnittdarstellung einer Ankerkopfeinrichtung im eingesetzten Zustand; undFigur 8 -
den Verankerungsteil mit eingesetzten Zugelement im in den Untergrund eingesetzten Zustand.Figur 9
-
FIG. 1 in a spatial representation of a tension element of a Erd- and rock anchor, inserted into the anchoring part; -
FIG. 2 in a spatial representation of the tension element with a plurality of first loops and the second loop; -
FIG. 3 a sectional view through the anchoring part with inserted tension element and clamping rings along line III-III according toFIG. 5 ; -
FIG. 4 a sectional view through the anchoring part with inserted tension element and clamping rings along line IV-IV according toFIG. 5 ; -
FIG. 5 a sectional view through the anchoring part with inserted tension element along line VV accordingFIG. 4 ; -
FIG. 6 the representation of an inventive earth and rock anchor in the state used in the underground state; -
FIG. 7 a sectional view of the inventive Erd- and rock anchor, in the state used in the underground state; -
FIG. 8 a sectional view of an anchor head device in the inserted state; and -
FIG. 9 the anchoring part with inserted tension element inserted in the ground state.
Aus
Der andere Endbereich 6 des Zugelementes 1 ist als zweite Schlaufe 7 ausgebildet, die in einer nicht dargestellten Ankerkopfeinrichtung befestigt werden kann, wie später noch beschrieben wird.The
In
Aus den
Wie ebenfalls aus den
Im Bereich der Enden der ersten Schlaufen 5', 5" und 5"' und im Eintrittsbereich des Zugelementes 1 in den Verankerungsteil 2 ist der Längskörper 8 jeweils mit einem Spannring 13 umschlossen, wie später noch im Detail beschrieben wird. Diese Spannringe 13 dienen der Verstärkung des Längskörpers 8 insbesondere im Eintrittsbereich des Zugelementes 1 in den Verankerungsteil 2 und im Bereich der ersten Schlaufen 5', 5" und 5"'. In diesen Bereichen wird dadurch bei Belastung des Erd- und Felsankers die Gefahr eines Ausbrechens der mörtelartigen Masse minimiert.In the region of the ends of the
Aus
Aus den
Der andere Endbereich 6 des Erd- und Felsankers 3, der als zweite Schlaufe 7 ausgebildet ist, wird in einer Ankerkopfeinrichtung 16 befestigt, die, wie später noch gesehen wird, als Spanneinrichtung ausgebildet ist. Ein derartig eingesetzter Erd- und Felsanker 3 kann Längen von bis zu 70 Meter oder mehr aufweisen. Bei derartigen Längen kann es zweckmässig sein, das Zugelement 1 in mehrere Teilstücke zu unterteilen und diese über Kupplungsmittel zu verbinden, was das Handling vereinfacht. Der Längskörper 8 kann ohne Weiteres eine Länge von 6 Metern haben, wodurch eine optimale Verankerung in der Bohrung 15 des zu stabilisierenden Untergrund 14 erreicht werden kann.The
Aus
Ein derartiger Erd- und Felsanker lässt sich auf einfache Weise herstellen, die Krafteinleitung über den Verankerungsteil in den zu stabilisierenden Untergrund ist optimal, das Zugelement ist keiner Korrosion unterworfen, somit kann auf entsprechende Kontrollen verzichtet werden. Derartige Erd- und Felsanker lassen sich auf einfache Weise in den Untergrund einsetzen, sie können auch einfach transportiert werden, da das Zugelement flexibel ist und aufgewickelt werden kann, wodurch auch eine grosse Platzersparnis erreicht wird. Zudem zeichnet sich das Zugelement auch durch ein sehr geringes Gewicht aus. Das Zugelement lässt sich entsprechend dimensionieren, indem das Band breiter und/oder dicker ausgebildet sein kann, je nachdem, welche Kräfte aufgenommen werden müssen.Such earth and rock anchors can be produced in a simple manner, the introduction of force through the anchoring part in the substrate to be stabilized is optimal, the tension element is not subject to corrosion, thus can be dispensed with appropriate controls. Such earth and rock anchors can be used in a simple manner in the ground, they can also be easily transported because the tension element is flexible and can be wound up, whereby a large space savings is achieved. In addition, the tension element is characterized by a very low weight. The tension member can be dimensioned accordingly by the band may be wider and / or thicker, depending on which forces must be absorbed.
Claims (13)
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP13177343.4A EP2829661B1 (en) | 2013-07-22 | 2013-07-22 | Ground and rock anchor |
US14/331,756 US9488048B2 (en) | 2013-07-22 | 2014-07-15 | Ground and rock anchor |
JP2014146840A JP2015021383A (en) | 2013-07-22 | 2014-07-17 | Ground and lock anchor |
CA2857324A CA2857324C (en) | 2013-07-22 | 2014-07-18 | Ground and rock anchor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP13177343.4A EP2829661B1 (en) | 2013-07-22 | 2013-07-22 | Ground and rock anchor |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2829661A1 true EP2829661A1 (en) | 2015-01-28 |
EP2829661B1 EP2829661B1 (en) | 2017-11-22 |
Family
ID=48803450
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP13177343.4A Active EP2829661B1 (en) | 2013-07-22 | 2013-07-22 | Ground and rock anchor |
Country Status (4)
Country | Link |
---|---|
US (1) | US9488048B2 (en) |
EP (1) | EP2829661B1 (en) |
JP (1) | JP2015021383A (en) |
CA (1) | CA2857324C (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102015220581A1 (en) * | 2015-10-21 | 2017-04-27 | Technische Universität Berlin | Tensile element made of fiber-reinforced plastic |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108687491A (en) * | 2017-04-11 | 2018-10-23 | 中国石化工程建设有限公司 | The bolted device to hole method of industrial furnace steel construction prefabricated component |
US10988906B2 (en) * | 2019-03-11 | 2021-04-27 | Horst K. Aschenbroich | Controlling backflow from drilling with hollow rebar and grouting |
AU2022244586A1 (en) * | 2021-03-23 | 2023-10-05 | Cmte Development Limited | A carbon fibre rock bolt |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3472120A (en) * | 1968-06-03 | 1969-10-14 | Raymond H Taylor | Looped cable wedge-type eyebolt |
EP1589146A1 (en) * | 2004-04-21 | 2005-10-26 | AVT Anker + Vorspanntechnik AG | Wire bundle anchor |
CH701928B1 (en) * | 2008-06-13 | 2011-04-15 | Stahlton Ag | Wire loop anchor for use as e.g. ground anchor in barrier structure for protection against e.g. falling rocks to anchor rope in building area, has loop connected with tube in form-fit manner, where ends of wire form tension member |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3999391A (en) * | 1975-06-12 | 1976-12-28 | Meredith Drilling Co., Inc. | Tie-back anchor components and method for a shoring system |
US5472296A (en) * | 1992-08-20 | 1995-12-05 | Dyckerhoff & Widmann Aktiengesellschaft | Corrosion protected support element for a soil anchor or a rock anchor, a pressure pile or the like |
GB2340144B (en) * | 1998-08-06 | 2000-06-28 | Keller Ltd | Ground anchorage |
EP2439359A1 (en) * | 2010-10-06 | 2012-04-11 | F.J. Aschwanden AG | Method for reinforcing concreted slabs for supporting elements |
-
2013
- 2013-07-22 EP EP13177343.4A patent/EP2829661B1/en active Active
-
2014
- 2014-07-15 US US14/331,756 patent/US9488048B2/en active Active
- 2014-07-17 JP JP2014146840A patent/JP2015021383A/en active Pending
- 2014-07-18 CA CA2857324A patent/CA2857324C/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3472120A (en) * | 1968-06-03 | 1969-10-14 | Raymond H Taylor | Looped cable wedge-type eyebolt |
EP1589146A1 (en) * | 2004-04-21 | 2005-10-26 | AVT Anker + Vorspanntechnik AG | Wire bundle anchor |
CH701928B1 (en) * | 2008-06-13 | 2011-04-15 | Stahlton Ag | Wire loop anchor for use as e.g. ground anchor in barrier structure for protection against e.g. falling rocks to anchor rope in building area, has loop connected with tube in form-fit manner, where ends of wire form tension member |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102015220581A1 (en) * | 2015-10-21 | 2017-04-27 | Technische Universität Berlin | Tensile element made of fiber-reinforced plastic |
US11396138B2 (en) | 2015-10-21 | 2022-07-26 | Technische Universitat Berlin | Traction element made of fiber reinforced plastic |
Also Published As
Publication number | Publication date |
---|---|
CA2857324A1 (en) | 2015-01-22 |
EP2829661B1 (en) | 2017-11-22 |
US9488048B2 (en) | 2016-11-08 |
CA2857324C (en) | 2021-01-26 |
US20150023740A1 (en) | 2015-01-22 |
JP2015021383A (en) | 2015-02-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2627524C3 (en) | Grouting anchor | |
DE69837524T2 (en) | Method for producing an anchoring, anchoring part and tensioning element for this purpose | |
DE69918444T2 (en) | ground anchor | |
EP1760208B1 (en) | System and method for making insulated cavity walls | |
EP0014426A1 (en) | Rock anchor | |
EP1591596A2 (en) | Embedded dowel | |
EP2829661B1 (en) | Ground and rock anchor | |
EP0976873B1 (en) | Injection- or prestressed ground anchor | |
DE3100730A1 (en) | Method of supporting and/or stabilising excavation walls in civil engineering, mining and tunnelling, apparatus for carrying out the method, and stabilising anchor sitting in a borehole in the excavation wall | |
CH640306A5 (en) | MOUNTAIN SUSPENSION AND METHOD FOR ANCHORING MOUNTAIN INFORMATION WITH THE SAME. | |
DE69314240T2 (en) | Removable ground anchor | |
EP2439359A1 (en) | Method for reinforcing concreted slabs for supporting elements | |
EP2108744B1 (en) | Method for reinforcing supporting walls | |
EP3336259B1 (en) | Anchor for anchoring in the ground and/or rock with reversible tension member | |
EP3690187B1 (en) | Pre-loadable ground anchor | |
EP0585537B1 (en) | Supporting element protected against corrosion for an earth or rock anchor, pressure pile or the like | |
DE3318050A1 (en) | METHOD FOR PRODUCING AN ARMED CONCRETE SUPPORT ELEMENT | |
EP2141287B1 (en) | Method of constructing a retaining wall | |
DE2201950C3 (en) | Injection anchor for anchoring components in earthy or rocky subsoil | |
AT380502B (en) | METHOD AND DEVICE FOR WIDING RUNWAY PANELS, BRIDGE ROADWAYS OR THE LIKE. | |
EP2276898B1 (en) | Prefabricated component with stabilization device | |
EP3336258B1 (en) | End anchorage for a soil and/or rock anchor | |
DE1634273C3 (en) | Grouting anchor | |
DE2518398A1 (en) | Device for lifting and transporting concrete slabs - has additional cast-in anchoring slab pierced by suspension device | |
DE3116619C2 (en) | Grouting anchors, especially permanent anchors |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
17P | Request for examination filed |
Effective date: 20130722 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
R17P | Request for examination filed (corrected) |
Effective date: 20150720 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E21D 21/00 20060101ALI20170517BHEP Ipc: E02D 5/80 20060101AFI20170517BHEP |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
INTG | Intention to grant announced |
Effective date: 20170714 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 948525 Country of ref document: AT Kind code of ref document: T Effective date: 20171215 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502013008863 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: BOVARD AG PATENT- UND MARKENANWAELTE, CH |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20171122 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20180222 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20180222 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20180223 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502013008863 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20180823 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180722 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20180731 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180722 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20130722 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171122 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171122 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20180322 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R081 Ref document number: 502013008863 Country of ref document: DE Owner name: LEVIAT AG, CH Free format text: FORMER OWNER: F.J. ASCHWANDEN AG, LYSS, CH |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: HC Ref document number: 948525 Country of ref document: AT Kind code of ref document: T Owner name: LEVIAT AG, CH Effective date: 20220119 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20220720 Year of fee payment: 10 Ref country code: DE Payment date: 20220720 Year of fee payment: 10 Ref country code: AT Payment date: 20220721 Year of fee payment: 10 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20220720 Year of fee payment: 10 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20220707 Year of fee payment: 10 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 502013008863 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 948525 Country of ref document: AT Kind code of ref document: T Effective date: 20230722 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20230722 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230722 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240201 Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230722 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230722 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |