EP2776644A1 - Procédé de production pour fabriquer des éléments de construction et élément de construction - Google Patents

Procédé de production pour fabriquer des éléments de construction et élément de construction

Info

Publication number
EP2776644A1
EP2776644A1 EP12826621.0A EP12826621A EP2776644A1 EP 2776644 A1 EP2776644 A1 EP 2776644A1 EP 12826621 A EP12826621 A EP 12826621A EP 2776644 A1 EP2776644 A1 EP 2776644A1
Authority
EP
European Patent Office
Prior art keywords
station
frame
plate
elements
frame elements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP12826621.0A
Other languages
German (de)
English (en)
Inventor
Finn Borg
Steffen B. PEDERSEN
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Borg Utviklingsselskab As
Original Assignee
Borg Utviklingsselskab As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Borg Utviklingsselskab As filed Critical Borg Utviklingsselskab As
Publication of EP2776644A1 publication Critical patent/EP2776644A1/fr
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B27WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
    • B27DWORKING VENEER OR PLYWOOD
    • B27D1/00Joining wood veneer with any material; Forming articles thereby; Preparatory processing of surfaces to be joined, e.g. scoring
    • B27D1/04Joining wood veneer with any material; Forming articles thereby; Preparatory processing of surfaces to be joined, e.g. scoring to produce plywood or articles made therefrom; Plywood sheets
    • B27D1/06Manufacture of central layers; Form of central layers
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/26Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups
    • E04C2/284Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups at least one of the materials being insulating
    • E04C2/296Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups at least one of the materials being insulating composed of insulating material and non-metallic or unspecified sheet-material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • E04C2/521Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0204Non-undercut connections, e.g. tongue and groove connections
    • E04B2002/0208Non-undercut connections, e.g. tongue and groove connections of trapezoidal shape
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0204Non-undercut connections, e.g. tongue and groove connections
    • E04B2002/0228Non-undercut connections, e.g. tongue and groove connections with tongues next to each other on one end surface and grooves next to each other on opposite end surface
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/30Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
    • E04C2/34Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure composed of two or more spaced sheet-like parts
    • E04C2002/3488Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure composed of two or more spaced sheet-like parts spaced apart by frame like structures

Definitions

  • the present invention concerns a process line for making finished building elements that are substantially made of wood or processed wood, e.g. in the form of plates and the like.
  • the case may be many uniform houses, e.g. as standard detached houses or in connection with terrace houses, low-rise apartment buildings and the like.
  • a large number of standard elements form part thereof, elements which according to traditional production methods all are made as special elements as carpenters and joiners typically will shape the elements on the construction site.
  • the invention thereby allows for a production procedure for making building elements, which building elements are made up of a front plate, a back plate and a structure there between and optionally insulation between front plate and back plate, wherein the procedure includes a series of process stations, wherein each station is automated and receives input from a central process control computer, and wherein the building elements move through the different stations:
  • a first station including one or more robots, which robots initially position top and bottom frame elements and subsequently position frame elements between top and bottom frame elements, wherein the frame elements are positioned according to input from the central process control computer, and wherein the robots fasten the frame elements in relation to each other such that a first frame is constructed;
  • a third robot places one or more plates upon the frame element layer such that the plate covers the frame element layer with the exception of areas in which disposition of doors, windows or other apertures are foreseen in the finished building component, and wherein the plate is fastened to the frame element layer.
  • a robot with an unrolling device positions a sealing strip on the outermost frame element all the way around the element and in window and door apertures and other cutouts which are not to be covered by the outer plate layer before the plates are laid on the framework.
  • the strip has the purpose of providing a wind seal towards an adjoining element or against windows or doors or other units which are placed in the framework.
  • a third station in which a turning device turns the building element 180° such that the plate/plates face downwards against the base.
  • a robot with insulation device fills the framework down against the underlying plate after which a new plate layer is placed over this insulation.
  • a fourth station wherein one or more robots position a second layer of top and bottom frame elements upon the uppermost plate layer and subsequently position frame elements between top and bottom frame elements, wherein the frame elements are positioned according to input from the central process control computer, and wherein the robots fasten the frame elements in relation to each other such that a second frame is constructed upon the first frame after which an insulation robot fills the cavities between top, bottom and remaining frame elements and the plate with insulating material;
  • - a fifth station wherein one or more robots position and fasten a third plate layer or web material as vapour barrier upon the second frame element layer;
  • a sixth station wherein one or more robots dispose a third layer of top and bottom frame elements upon the third plate layer or web material and subsequently position frame elements between top and bottom frame elements, wherein the frame elements are positioned according to input from the central process control computer, and wherein the robots fasten the frame elements in relation to each other;
  • the invention moreover comprises a building element made by the above mentioned production procedure where the building element includes a first outer plate to which is fastened a framework consisting of bottom and top frame elements and jointing elements that are interconnected in order to form a strong frame and where the frame elements are
  • Fig. 1 shows an example of a factory layout.
  • Fig. 2 shows assembling robots.
  • Fig. 3 shows an example of a turning device.
  • Fig. 4 shows an example of a turning device - element raiser.
  • Fig. 5 shows
  • Fig. 6 shows a transport car
  • Fig. 7 shows different frame types
  • Fig. 8 shows
  • the system is based on the fact that elements to be produced are recorded in a computer based drawing program and that all units in the machine line can communicate with a central computer that determines the sequence of the production of elements and determines the design of the elements based the drawings stored in the computer.
  • a reference line is defined along the machine line such that all operations, manual as well robotic, are controlled relative to the reference line.
  • the reference line will change side when the elements are turned such that typically the lower edge of the element will determine where the reference line is defined.
  • the computer can keep track of the reference line for each single element such that different elements on the machine line may have different reference lines.
  • the machine line is therefore designed such that all processes are performed rationally in the correct sequence and that materials etc are forwarded to the various stations with proper timing.
  • Plates and frame elements are convey ed/delivered in depots in the vicinity of shortening saw 10 and plate saw 1 1, respectively.
  • the saws are here fed at the rate that components (plates and frame elements) are to be used/built in farther down the line.
  • two conveyor belt are arranged for transporting the shaped components 14 to the predetermined stations.
  • the first frame elements are used in station 20 for making the first frame.
  • the first plate and strip layer are placed in the second station 30.
  • a plate layer which before positioning of frame elements inserts a first plate upon which bottom and top frame elements and strips and "stenders" are mounted subsequently as described.
  • Plate and strip are secured to the frame layer by e.g. nails or clamps. These are inserted by robots provided with nail guns mounted on transverse conveyors between or above the stations so that they can reach all points on the frames made at the first station. After fastening the plate and strip layer, the frame with fastened plate and strip is moved to a turning station 40 where the element is turned around such that the plate previously situated at the top is now at the bottom.
  • the turning device can e.g. be designed as indicated in Fig. 3.
  • a buffer station 50 is inserted subsequently.
  • the buffer station serves to provide that the production rate of the various stations is adapted such that the robots will be in time to perform the work to be done without appreciably impeding the flow through the production line.
  • the buffer station it is furthermore possible to perform quality control of the work performed in the first stations 20, 30.
  • the semi-finished element which now consists of frame plus the first plate layer, is then transferred to the next station 60.
  • the second frame layer is laid as well as insulation is filled in the recesses constituted by the plate, which is now the bottom, and the two frame layers upon each other.
  • a second plate layer is laid such that the element now has a lower plate fastened to the first frame layer in station 20 and two frame layers made in station 30 and station 60, and a cover plate applied in the last station 70.
  • the semifinished element then continues to an additional station 80 where a third frame layer is assembled and fastened upon the second plate layer.
  • a further station 90 electric and plumbing installations are mounted in the element, i.e. upon the second plate layer limited by the third frame layer.
  • the almost finished element is then conveyed to a further station 100 at which insulation is filled around the electric and plumbing installations provided at station 90, and finally the third and last plate layer is fastened upon the third frame layer.
  • a further station 100 at which insulation is filled around the electric and plumbing installations provided at station 90, and finally the third and last plate layer is fastened upon the third frame layer.
  • the element is raised to vertical position by turning 90°, after which the element is moved to a finishing line.
  • the finishing line includes a filling and drying station 120.
  • the filling of possible joints between plate elements and the drying is effected most expediently by an infrared heat source which rapidly and efficiently dries the filling material such that when the newly filled element is conveyed to the following station 130, the element is ready for grinding.
  • station 130 the newly filled areas are surface-ground such that when the element is moved on to the next station 140, which is a painting booth with associated drying, the element is ready for surface treatment.
  • the painting station is typically a paint booth with associated suction etc. Drying may again be effected by an infrared heat source but common air drying may be used as well, depending on the rate of production.
  • the element After painting and drying, the element is conveyed to the following station 150 where doors and windows are fitted to the extent defined in the computer program controlling the process. After mounting doors and windows the element is conveyed to the next station 160 where an external cladding is applied.
  • the external cladding may e.g. be a wooden covering which mounted on a list skeleton which has been mounted on the plates in connection with the production of the element at the stations 30 - 110.
  • glazing, mouldings etc. are mounted such that the element is completed and ready to be incorporated in the final building construction.
  • the element is conveyed to either a buffer station 180 or to an element depot 190.
  • the finished elements are taken out from the element depot in a given sequence to a module assembly station 200 where the elements are assembled into finished building modules, e.g. facades, roofing and the like.
  • the modules are transferred to a module storage 210 where the assembled and finished modules are ready to be fitted at the construction site.
  • Bottom and top frame elements 21 , 22 arrive at the station 20 guided standing or flat via conveyor belt 23.
  • Bottom and top frame elements 21, 22 can be in one or more pieces which are assembled into a length; this may be effected by glue, fish plates, sheet nails or other suitable means. This joint may occur before arrival at the position 20 or after arrival.
  • the item is identified and gripped by 1-2 separate robot/robots 24, 25 placing them in bottom and top positions, respectively, against a stop 26 which is variable on the assembly table 27. Then the robot/robots 24, 25 pick up a "stender" 28 appearing in continuous succession for disposition between bottom and top frame elements 21, 22. The first is disposed against a stop at the end of the assembly table 27 which together with the stop in longitudinal direction form a right angle.
  • the "stenders" 28 are then secured by clamps or other fastening means through bottom and top frame elements 21 , 22 by one or two separate robot(s) 24, 25 which is(are) equipped with clamping gun(s). This is repeated all the way across the element, and "spikerslag” and double or more "stenders” 28 are laid in where appropriate and these are fastened in the same way.
  • the individual items may also be entirely or partly manually disposed at the station 20 so that the robot 24, 25 fetches it from its individual position. Also, all or part of the individual operations may be manual functions.
  • the frames 29 are hereby constructed. Characteristics of frames are indicated below.
  • Width fixed or variable per subcomponent
  • Components/items to be assembled/machined may consist of wood, wood-based materials, composites, synthetic material, or combinations thereof.
  • the design of the frame 29 may vary from rectangular to mutually variable angles, see Fig. 7.
  • the spacing between fastening lines is variable, horizontally as well as vertically. There may be "stenders'Vcolumns, posts that abut on each other due to bearing or other purpose.
  • Nails/clamps/screws which are shot/screwed or pressed in by a piston. By all assemblies an unlimited number of nails/screws or clamps can be used.
  • Robot unrolls and fastens a strip along all outer edges and around door and window apertures.
  • Plates arrive as raw plates or completely cut at the station 30 in continuous sequence lying flatly and directionally guided via conveyor belts.
  • the plates are identified and gripped on the external surface by suction lifter or other device (not shown) mounted on a robot which places them over the frame 29, beginning from the angular line at the bottom or top position. Plates are fastened with clamps by gun mounted on robot while the other robot holds the plate in correct position. When the plate has been fastened so that it is positionally fixed, the holding robot releases it and fetches the next plate while the gun robot clamps the former plate, and so on until the outer side of the frame 29 is completely covered. If raw plates are used the entire adaptation or a part thereof occurs in the process at the station.
  • Diameter example on roll 200 - 300 mm or variable.
  • Example of spacing between the individual fastening lines from 0 to 1000 mm or variable, and in all window and door apertures or other cutouts, horizontal as well as vertical.
  • Fastening examples: clamps, glue, tape.
  • Length Variable, most used dim. 1200 mm to 3000 mm
  • Width Variable, most used dim. 600 mm to 1200 mm
  • Thickness Variable, most used dim. 4 mm to 24 mm
  • Edge design varies from rectangular edges to variable angles.
  • Edge design will be rectangular on plane, key and groove, overlay or other kind of edge profile. Spacing between fastening lines: variable, most used spacing 0 mm to 1.000 mm horizontal as well as vertical.
  • the outer frame can as a minimum, however, have one right angle.
  • the right angle can be an external corner or "stender” which is perpendicular to top or bottom frame element or a "spikerslag” emanating at right angles from a "stender” but which as a starting point will have variable angles on mutually abutting members as well.
  • Nails or clamps length variable. Most used lengths 35-70 mm. Spacing between points variable. Most used spacings 0 to 500 mm.
  • the plates are shot into by compressed air or are pressed in by a piston, see e.g. Fig. 13.
  • the element 1 which now consists of 1 st layer frame and 1 st layer plate is manually or automatically moved into the turning device 41.
  • the turning device 41 then closes around the element 1 which firstly is moved to vertical position (90°), see Fig. 3 c, then around to horizontal position again (180°). If desired, the process can be continued with vertical element in the succeeding stations.
  • the turning device opens and the element 1 is ready to continue to next position.
  • Figs. 3a-3d illustrate the various stages in the turning operation.
  • Fig. 4 is illustrated an alternative element turning device.
  • the turners in Figs. 3a-3d consist of large arches 42 arranged at each end such that the elements are controlled by means of grippers with wheels 43 and are moved around the arch during the turning operation.
  • the turning device can be incorporated in a transfer car, i.e. a mobile unit that may be displaced out of the machine line.
  • the transfer car with turning function can fetch elements for transport to other table and deliver it as well. If required for the process it is also possible to turn the element 180°. When the horizontal processes are finished, the transfer car with turning function can deliver the element in vertical position.
  • the transfer car By picking up an element on a work table, the transfer car rolls into position opposite the table after which a set of carriers are pushed in under the element. These carriers are lifted such that the element lies thereon. They are then withdrawn to the transfer car and the element is transferred to thereto.
  • the transfer car initiates a turning function which lifts two sets of carriers 90°, bringing the element to vertical position.
  • the element is then laid down on the opposite side by lowering the carriers and displace then laterally.
  • the transfer car again drives into position opposite a work table, and the carriers are pushed out to the side at which the element is desired to be delivered. Then they are lowered such that the element is laid down on the work table in question. The carriers are now drawn back to the transfer car.
  • a buffer station 50 can be inserted optionally.
  • the frames produced at the preceding positions can be stored temporarily here until vacancies occur at the subsequent stations.
  • the frame 1 arrives at this position from the turning device 41, and the reference line is moved to the opposing long side.
  • Robot/portal (not shown) with mounted insulation device starts filling insulation into the individual spaces between the "stenders" 28, see Fig. 1, down against the external plate.
  • the amount of supplied insulation through injection tubes is measured by a sensor immediately before the material leaves the tube.
  • the supplied amount determines the speed at which the robot moves the insulation device across the frame 1. The operation continues until each space has been filled satisfactorily based on a predefined density.
  • Raw material Wood fibres in small bags, large bags, container or other suitable delivery packing means.
  • the insulation may also consist of synthetic fibres of different kinds.
  • Installation method Injection by blowing under pressure. Cavity sizes and shapes:
  • Bottom and top frame elements for second frame layer - first layer was mounted in pos. 2(20), see Fig. 1 , arrive at the station while guided standing or flat via conveyor belt.
  • Bottom and top frame elements can be in one or more pieces which are assembled to a length; this may be effected by glue, lasers, sheet nails or other suitable means. This assembling may have occurred before arrival to the position or after arrival.
  • the item is identified and gripped by 1 - 2 separate robot(s) which position them in bottom and top position relative to the position of bottom/top frame elements and "stenders" in the underlying layer. Then the robots take “stenders" that arrive in continuous sequence for disposition between bottom and top members.
  • the "stenders” are fastened by clamps or other fastening means through bottom and top frame element and down through the plate layer to the underlying frame by 1 - 2 separate robot(s) which are equipped with clamp guns. This is repeated all the way across the element and "spikerslag” and double or more "stenders” are laid where relevant, and these are fastened in the same way.
  • the individual members may also be entirely or partly manually placed at the station so that the robot picks it up from their individual positions. Also, all or part of the individual operations may be manual functions.
  • Construction of the second layer is effected in an entirely corresponding way as described above for the first layer with reference to Fig. 2.
  • the format is variable.
  • Width Fixed or variable per subcomponent
  • Weight Variable per subcomponent Components/item to be assembled/machined may either consist of wood, wood-based materials, composites, synthetic material, or combinations thereof.
  • the design of the frame may vary from rectangular to mutually variable angles.
  • the spacing between fastening lines is variable, horizontally as well as vertically.
  • Nails/clamps/screws which are shot/screwed or pressed in by a piston.
  • the frame 1 arrives at this position on the rollerway.
  • Robot/portal with insulation device mounted thereon starts filing insulation in the individual spaces between the "stenders" down against the preceding insulation layer, an intermediate sheet material or web material.
  • This station is adapted corresponding to pos. 6 (60).
  • the insulation robots insulating the first beam layer can be brought into position such that the same robots can insulate the second frame layer as well.
  • the robots may be arranged on a beam structure running above the rollerway on which the elements are conveyed in the machine line.
  • the amount of supplied insulation through injection tubes is measured by sensor immediately before the material leaves the tube.
  • the amount supplied determines the speed at which the robot moves the insulation device across the frame. The operation continues until each space is filled satisfactorily based on a predefined density.
  • Raw materials Wooden fibres in small bags, large bags, container or other suitable delivery packing means.
  • the insulation may also consist of synthetic fibres of various kinds.
  • Installation method Injection by blowing under pressure.
  • a robot unrolls and fastens the vapour barrier along the outer edges with a few clamps.
  • the robot unrolls and fastens a vapour barrier along all outer edges and around door and window apertures.
  • a second layer of plates are forwarded.
  • the plates arrive as raw plates or completely cut to the station in continuous sequence lying flatly and directionally guided via conveyor belts.
  • the plates are identified and gripped on the external surface by suction lifter or other device mounted on a robot, disposing them over the vapour barrier, beginning from the angular line at the bottom or top position. Plates are fastened with clamps by gun mounted on separate robot while the other robot holds the plate in correct position. When the plate has been fastened so that it is positionally fixed, the holding robot releases it and fetches the next plate whereas the gun robot clamps the former plate, and so on until the frame is completely covered. If raw plates are used the entire adaptation or a part thereof occurs in the process at the station. These work routines correspond to those performed and explained with regard to Fig. 3.
  • Length Variable, most used dim. 1200 mm to 3000 mm
  • Width Variable, most used dim. 600 mm to 1200 mm
  • Thickness Variable, most used dim. 3 mm to 24 mm
  • Edge design will be at right angles to plane, key and groove, overlay or other kind of edge profile.
  • Spacing between fastening lines Variable, most used spacing 0 mm to 1.000 mm, horizontally as well as vertically.
  • the outer frame may have one right angle as a minimum.
  • the right angle can be an outer corner or a "stender” going perpendicularly on top or bottom frame element. Or a “spikerslag” extending perpendicularly from a "stender”. But basically also having variable angles on mutually abutting members.
  • Nails or clamps variable length. Most used lengths 35-70 mm
  • Shot in by compressed air or pressed in by a piston Shot in by compressed air or pressed in by a piston.
  • Bottom and top frame elements 21, 22 arrive at the station guided standing or flat via conveyor belt 12, 13.
  • Bottom and top frame elements may be in one or more pieces which are assembled to a length, this may be effected by glue, lasers, sheet nails or other suitable means. This assembling may have occurred before arrival to the position or after arrival.
  • the item is identified and gripped by 1 - 2 separate robot(s) which position them in bottom and top position relative to the position of bottom/top frame elements and "stenders" in underlying layer under the second plate layer. Then the robots take “stenders" that arrive in continuous sequence for disposition between bottom and top members.
  • the "stenders" are fastened by clamps or other fastening means through bottom and top frame elements and down through the plate layer or web material to the underlying frame by 1 - 2 separate robot(s) which are equipped with clamp guns. This is repeated all the way across the element and "spikerslag” and double or more "stenders" are laid where relevant, and these are fastened in the same way.
  • the individual items may also be entirely or partly manually placed at the station so that the robot picks it up from its individual position. Also, all or part of the individual operations may be manual functions.
  • Width Fixed or variable per subcomponent
  • Components/items to be assembled/machined may consist of wood, wood-based material, metal, composites, synthetic material, or combinations thereof.
  • the design of the frame may vary from perpendicular to mutually variable angles.
  • the spacing between fastening lines is variable horizontally as well as vertically.
  • Nails/clamps/screws of variable dimension and material Nails/clamps/screws that are shot/screwed or pressed in by piston.
  • rivets When using other materials welding, rivets, bolts, glue, tape or other kind of fastening means can be used as well.
  • the frame arrives at this position on the rollerway.
  • Robot/portal with mounted insulation device starts filling insulation into the individual spaces between the "stenders" down against the intermediate plate or web material.
  • the amount of supplied insulation through injection tubes is measured by a sensor immediately before the material leaves the tube.
  • the supplied amount determines the speed at which the robot moves the insulation device across the frame. The operation continues until each space has been filled satisfactorily, based on a predefined density.
  • the robot has been informed about the installation positions and dimensions thereof in beforehand.
  • Raw material Wood fibres in small bags, large bags, container or other suitable delivery packing means. Nature of raw material: Loose wood fibres or other natural fibres, compressed, moisture content 12 - 20%.
  • the insulation may also consist of synthetic fibres of different kinds.
  • Installation method Injection by blowing under pressure.
  • Plates arrive as raw plates or shaped plates at the station in continuous sequence lying flatly and guided directionally via conveyor belt 13. Plates are identified and gripped at the external face by suction lifter or other device mounted on robot which place them over the vapour barrier/frame, starting from the angular line at bottom or top positions. Plates are fastened by clamps with a gun mounted on separate robot while the other robot holds the plate in the right position. When the plate has been fastened such that it is positionally fixed, the holding robot releases and picks up the next plate while the gun robot finishes clamping the previously mentioned plate, and so on until the frame has been covered completely. If raw plates are used, all or some of the adaptation in the process takes place in the station. 3. Layer - Plate mounting internally
  • Length Variable, most used dim. 1200 mm to 3000 mm
  • Width Variable, most used dim. 600 mm to 1200 mm
  • Thickness Variable, most used dim. 3 mm to 24 mm
  • Edge design will be at right angles to plane, key and groove, overlay or other kind of edge profile.
  • Spacing between fastening lines Variable, most used spacing 0 mm to 1.000 mm, horizontally as well as vertically.
  • the outer frame may have one right angle as a minimum.
  • the right angle can be an outer corner or a "stender” going perpendicularly on top or bottom frame element. Or a “spikerslag” extending perpendicularly from a "stender”. But basically also having variable angles on mutually abutting members.
  • Nails or clamps variable length. Most used lengths 35-70 mm
  • rustic cladding is meant various forms of facade cladding.
  • Fastening Clamps or brads or other kind of fastening.
  • Raising elements to standing position for transfer to floor conveyor may here continue to element depot 190, directly to further transport to construction site 210 or they may continue in the further process 120-180 for surface treatment and/or assembly into modules.
  • the tilting table 110 can also function as transfer vehicle to a new station (machining, depot or other form of handling), or it may turn about its own axis for further transporting the element in another direction vertically standing, with variable inclination or in horizontal position.
  • Conveyor Conveyor handles the elements by guide rail, skates, rollers, active or passive conveyor belts at the bottom (floor) or other movable unit.
  • the position of the element is guided at the top by a guide stay fitted thereon, pin guided in a rail device suspended from the ceiling or frame system set up for the purpose.
  • Rail can be passive or active in connection with movement of the element.
  • the element arrives at the station via conveyor belt or other transport means. Internal filling of wall and ceiling elements is performed by automatic filling tools mounted on robots. At the same station external plaster work of various kinds may e.g. be applied. The application can be effected at both sides, in case of bilateral treatment it can be done simultaneously.
  • Drying is performed with IR drying zones at both sides of the conveyor line.
  • the IR drying zones are automatically moved in longitudinal direction together with the robots.
  • the element arrives at the station via conveyor belt or other transport means.
  • Automatic grinding of filled elements is performed by robots while the element is on the conveyor line, or it may be picked up and put in its own holder.
  • the process is performed at one or both sides of the element simultaneously.
  • the element is held at the top in order to avoid that the action of the grinding brush will cause oscillations in the element.
  • the element arrives at the station via conveyor belt or other transport means.
  • the facility can be established with or without automatic colour change.
  • the element arrives at the station via conveyor belt or other transport means. Drying is performed with IR drying zones at one or both sides of the element .
  • the IR drying zones can be moved automatically in longitudinal direction together with the robots, or they may be stationary.
  • Doors and windows may arrive at the station on their own transport means in the sequence in which they are to be used, or they may be taken from a fixed depot arranged at the station.
  • Windows and doors are mounted with the moving part mounted or dismounted, the fastening occurs in the rabbet or other placed intended for the purpose.
  • Fixed frames are supplied with fixed or loose glazing beads at sides/top/bottom so that mounting can be performed behind the glazing bead.
  • the mounting can also be performed at the external part of the frames with mounting means/system intended for the purpose. Mounting of mouldings inside and outside can be performed manually or automated.
  • the element arrives at the station via conveyor belt or other transport means.
  • the shape of the frame can vary from rectangular to mutually variable angles.
  • Example of distance between fastening lines 0 mm to 600 mm (variable), vertical as well as horizontal.
  • Nails/clamps are shot with compressed air or pressed in by piston
  • the element arrives at the station via conveyor belt or other transport means.
  • Edge design can be perpendicular to plane or inclined, key and groove, overlay or other edge design.
  • End joint can be sharp abutment, obliquely cut, key and groove, overlay or other joint form.
  • the shape of the frame can vary from rectangular to mutually variable angles.
  • Example of distance between fastening lines 0 mm to 600 mm, horizontally as well as vertically (variable).
  • Nails/clamps are shot with compressed air or pressed in by piston
  • the element arrives at the station via conveyor belt or other transport means.
  • An element depot is established where frames with the finished elements are placed before they are taken out for mounting on the finished module. Elements/frames can be taken arbitrarily from the depot.
  • the element arrives at the station via conveyor belt or other transport means from which they are lifted off by a portal crane or other lifting/moving device.
  • the assembly station is provided on a large turntable 200, see Fig. 1, which can be elevated and lowered for transferring the element to transport system in floor for finished modules. Assembly of modules is effected manually or entirely or partly automated.
  • Floor transport of modules is effected manually or entirely or partly automated.
  • the finished modules are placed on roller skates running in a rail system in the floor in order to ensure best freedom of movement in the area.
  • roller skates are provided without or with drive.
  • the rail system ensures transport from the assembly station for elements to and from the internal or external loading site/depot before further transport.
  • Conveyor transport may in some cases occur in the following way:
  • the elements are placed in adjustable frames/fixtures 210, see Fig. 6, for automatic transport in vertical position.
  • the frames 210 ensure support of elements 1 and unhindered access to automatic working of the surfaces.
  • the used frames 210 are reused when the elements 1 are removed at the module assembly station.
  • the frames 210 are driven and run on rails between the booths/work stations. Cars are made for transverse transport of the frames between the actual work stations.
  • the section frames (wall, ceiling, floor) are assembled on an assembly table by one or more robots or automatons that place and screw/nail the parts together into an element.
  • the assembly table can be horizontal, inclined or completely vertical. As a rule there is to be a rectangular corner on the element/item, but it can probably be solved in other ways.
  • Assembly tables see Fig. 8, used in one or more of the positions 2, 3, 6, 7, 8, 9, 10, 12, 15, 16 and 17 are made as a solid base 81, rollers or belt upon which the robots 82, 93 can position the individual parts correctly.
  • the table will be provided with some auxiliary units which can hold subelements, assisting the robots during the assembly process.
  • the robots are disposed on portals 84 across the table so that they can be moved around across the entire working area. If the table is made inclining or vertical, the robots are placed on guides along the table instead.
  • Assembly tables see Fig. 9, used in one or more of positions 2, 3, 6, 7, 8, 9, 10, 12, 15, 16 and 17 are med as a solid base, rollers 91 or belt upon which the robots may position the individual parts.
  • the table consists of a number of reference points which are used as reference for the robots when building up an element.
  • the reference points can either be fixed or made with elevating/lowering function. Besides the reference points variable stops 92 are distributed on the table to be called up according to need to a wanted position. The variable stops can retain items with a programmable pressure.
  • a turning device 41 is inserted, e.g. as illustrated in Figs. 3 or 4, for securely and carefully turning the elements without damaging the elements or twisting them out of format.
  • the turning device can be designed as a frame turning device with an upper and lower part or as one.
  • the turning device 41 see Figs. 3a-3d, may turn in a circular movement, part of a circular movement, with greater or lesser interruptions in the movement, example shown under.
  • the turning station may also function as work station for other entirely or partially automated functions.
  • the materials which the robots are to use for constructing the elements are placed within reach of the robots and positioned correctly by mechanical raisers. Materials can be conveyed to the robots via rollerways 23, see Fig. 1 , chain belts or transfer cars. Lift tables with mechanical raisers providing for supply of plates for the assembly process can be incorporated.
  • the insulation head/injection device 101 consists of a plate lying flatly down on the framework in which there are two slots. Injection tube/hose runs in the foremost through which the material is supplied to the underlying spaces in the element.
  • the tube can be moved in the slot from side to side and the tube can be turned 280° around so that the injection direction is variable.
  • the tube can furthermore be elevated and lowered relative to the bottom side of the plate such that it projects more or less down into the volume space across which the device is moved.
  • the tube mouth can be shaped according to the direction in which the supplied material is to be delivered. The tube mouth can be adjusted in relation to the size of the opening or it may be changed to a different size automatically or entirely or partially manually.
  • a variable "needle filter” consisting of rods that are lowered down to the bottom of the space. The ends of the rods are rounded in order not to adhere to irregularities in the bottom. Only the number of needles fitting the width of the volume space across which the device is moved are lowered. The redundant needles are held up by a catcher which can be elevated/lowered relative to the actual depth of the volume space. By asymmetric, curved or round spaces, the "needle width" is adapted during the movement. In both slots there is fitted a brush filter or other flexible sealing that seals around the injection tube and the "needle filter". A brush filter can be mounted on the needles at the sides towards the sides of adjacent needles. All filters are applied to prevent or limit material spillage.
  • a meter is provided on the hose for measuring the amount of material supplied under the plate. This measurement determines the speed at which the robot or other control device moves the plate across the element to be filled.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Mechanical Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Forests & Forestry (AREA)
  • Automatic Assembly (AREA)

Abstract

Cette invention concerne un procédé de production d'éléments de construction, lesdits éléments de construction étant constitués d'un panneau avant, d'un panneau arrière ainsi que d'une structure disposée entre ceux-ci, et comprenant optionnellement un matériau isolant entre le panneau avant et le panneau arrière. Ledit procédé comprend une série de postes de traitement agencés en une chaîne de production ou un îlot de production, chaque poste étant automatisé et recevant des entrées à partir d'un système central de commande de processus, et les éléments de construction se déplaçant à travers les différents postes. Lesdits postes comprennent : un premier poste comprenant un ou plusieurs robot(s), lesdits robots assurant le positionnement initial d'éléments de cadre supérieurs et inférieurs et disposant par la suite des éléments de cadre entre les éléments de cadre supérieurs et inférieurs, les éléments de cadre étant positionnés en fonction d'entrées provenant du système central de commande de processus et les robots fixant les éléments de cadre les uns aux autres de façon à former un premier cadre; un deuxième poste dans lequel un troisième robot dispose un ou plusieurs panneau(x) sur la couche d'éléments de cadre de telle façon que le panneau recouvre la couche d'éléments de cadre en exceptant les zones prévues pour disposition de portes, fenêtres et autres ouvertures dans l'élément de construction fini, ledit panneau étant fixé à la couche d'éléments de cadre; un troisième poste dans lequel un dispositif de pivotement fait pivoter l'élément de construction de 180° de telle façon que le ou les panneau(x) est/sont orientés vers le bas et disposés contre une base; un quatrième poste dans lequel un ou plusieurs robot(s) dispose(nt) une deuxième couche d'éléments de cadre supérieurs et inférieurs contre la première couche et disposent par la suite des éléments de cadre entre les éléments de cadre supérieurs et inférieurs, les éléments de cadre étant positionnés en fonction d'entrées provenant du système central de commande de processus et les robots fixant les éléments de cadre les uns aux autres de façon à former un second cadre au-dessus du premier cadre, suite à quoi un robot d'isolation remplit d'un matériau isolant les cavités entre le panneau et les éléments de cadre supérieurs, inférieurs et intermédiaires; un cinquième poste dans lequel un ou plusieurs robot(s) positionnent et fixent une deuxième couche de panneau sur la deuxième couche d'éléments de cadre; un sixième poste dans lequel un ou plusieurs robot(s) disposent une troisième couche d'éléments de cadre supérieurs et inférieurs sur la deuxième couche de panneau et disposent par la suite des éléments de cadre entre les éléments de cadre supérieurs et inférieurs, les éléments de cadre étant positionnés en fonction d'entrées provenant du système central de commande de processus et les robots fixant les éléments de cadre les uns aux autres; un huitième poste dans lequel une troisième couche de cadre est disposée sur le cadre supérieur; un neuvième poste dans lequel l'élément fini est retiré de la chaîne de production.
EP12826621.0A 2011-11-11 2012-11-12 Procédé de production pour fabriquer des éléments de construction et élément de construction Withdrawn EP2776644A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DKPA201100888 2011-11-11
PCT/IB2012/002400 WO2013076547A1 (fr) 2011-11-11 2012-11-12 Procédé de production pour fabriquer des éléments de construction et élément de construction

Publications (1)

Publication Number Publication Date
EP2776644A1 true EP2776644A1 (fr) 2014-09-17

Family

ID=47749888

Family Applications (1)

Application Number Title Priority Date Filing Date
EP12826621.0A Withdrawn EP2776644A1 (fr) 2011-11-11 2012-11-12 Procédé de production pour fabriquer des éléments de construction et élément de construction

Country Status (2)

Country Link
EP (1) EP2776644A1 (fr)
WO (1) WO2013076547A1 (fr)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2129226A1 (de) * 1971-05-14 1972-11-23 Monacelli, Joseph, La Chaux de Fonds (Schweiz) Bauelement
NL7804186A (nl) * 1977-04-19 1978-10-23 Sture Lennart Samuelsson Bouwblok en moduulsysteem voor huizenbouw.
FR2543994A1 (fr) * 1983-04-08 1984-10-12 Ferry Juhem Bureau Element de structure bois pour logement rez-de-chaussee ou a etage
DE102012011620A1 (de) * 2012-06-12 2013-12-12 Bruno Gruber Verbundteil und Verfahren zur Herstellung eines Verbundteils
WO2014187726A1 (fr) * 2013-05-21 2014-11-27 Rockwool International A/S Mur isolant, ensemble de colonne associé et procédé de construction d'un tel mur isolant

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE871829C (de) * 1950-09-27 1953-03-26 Bojsen Moller Paper & Trading Furnierhohlplatte mit Versteifungseinsatz und Verfahren zum Herstellen des Einsatzes
DE19707293C1 (de) * 1997-02-24 1998-01-15 Wild Maschinen Gmbh Verfahren zur Herstellung von mehrlagigen Türrohlingen oder ähnlich aufgebauten mehrlagigen Bauteilen
ES2845634T3 (es) * 2010-02-12 2021-07-27 Mac Invest B V Método, dispositivo y un programa informático para fabricar un segmento de armazón preaislado

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2129226A1 (de) * 1971-05-14 1972-11-23 Monacelli, Joseph, La Chaux de Fonds (Schweiz) Bauelement
NL7804186A (nl) * 1977-04-19 1978-10-23 Sture Lennart Samuelsson Bouwblok en moduulsysteem voor huizenbouw.
FR2543994A1 (fr) * 1983-04-08 1984-10-12 Ferry Juhem Bureau Element de structure bois pour logement rez-de-chaussee ou a etage
DE102012011620A1 (de) * 2012-06-12 2013-12-12 Bruno Gruber Verbundteil und Verfahren zur Herstellung eines Verbundteils
WO2014187726A1 (fr) * 2013-05-21 2014-11-27 Rockwool International A/S Mur isolant, ensemble de colonne associé et procédé de construction d'un tel mur isolant

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO2013076547A1 *

Also Published As

Publication number Publication date
WO2013076547A1 (fr) 2013-05-30

Similar Documents

Publication Publication Date Title
EP3802032B1 (fr) Systeme et methode pour l'assemblage d'une charpente pour un plancher ou un plafond dans une construction modulaire
US20120035758A1 (en) Device for coating an elongated workpiece
EP2031172A2 (fr) Appareil de fixation de cadre de porte décoratif
US9388566B2 (en) Method of erecting a building with wooden panels
WO2013076547A1 (fr) Procédé de production pour fabriquer des éléments de construction et élément de construction
ITBO990363A1 (it) Impianto per la lavorazione di corpi piani .
CN110436148B (zh) 一种建筑保温框材加工用移动式组合运装设备
CN116971622A (zh) 一种彩钢板材自动安装设备
CN113713983A (zh) 一种木门加工用高效喷漆设备及表面喷漆工艺
EP4134215A1 (fr) Ligne de production d'éléments de construction en bois
CN220080844U (zh) 一种彩钢板材自动安装设备
EP3992387A1 (fr) Installation et procédé de construction de façades préfabriquées en briques
EP4083349B1 (fr) Système de fabrication d'un segment de paroi robotique mobile
BE1027042B1 (nl) Bereidingsmethode prefabelementen
JPS5828738Y2 (ja) パネル枠組装置
JPH04261732A (ja) 長尺構造材のブラケット取付方法
JPH065913U (ja) タイルの枠体への自動切出装置
JPH04305262A (ja) Pc部材の外装仕上げ吹付け装置
IE20030155U1 (en) Method and apparatus for manufacturing pre-fabricated building construction elements
IES20030155A2 (en) Method and apparatus for manufacturing pre-fabricated building construction elements
JP2000141146A (ja) 壁パネル艤装装置
CZ244891A3 (en) APPARATUS FOR SETTING BUILDING ELEMENTS BY MEANS OF BRICk-LAYING MACHINE
IE20030154A1 (en) Method and apparatus for manufacturing pre-fabricated building construction elements

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20140611

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAX Request for extension of the european patent (deleted)
17Q First examination report despatched

Effective date: 20151214

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20190601