EP2339075B1 - Method for making a floor slab element with drainage installation and the floor slab element - Google Patents

Method for making a floor slab element with drainage installation and the floor slab element Download PDF

Info

Publication number
EP2339075B1
EP2339075B1 EP10397526.4A EP10397526A EP2339075B1 EP 2339075 B1 EP2339075 B1 EP 2339075B1 EP 10397526 A EP10397526 A EP 10397526A EP 2339075 B1 EP2339075 B1 EP 2339075B1
Authority
EP
European Patent Office
Prior art keywords
cast
area
wet room
floor
provision area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP10397526.4A
Other languages
German (de)
French (fr)
Other versions
EP2339075A1 (en
Inventor
Heikki Kankkunen
Jussi Lehti
Ilkka Iivanainen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Consolis Technology Oy AB
Original Assignee
Consolis Technology Oy AB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Consolis Technology Oy AB filed Critical Consolis Technology Oy AB
Publication of EP2339075A1 publication Critical patent/EP2339075A1/en
Application granted granted Critical
Publication of EP2339075B1 publication Critical patent/EP2339075B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/39Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra
    • E04C1/397Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra serving for locating conduits
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • E04C2/521Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/141Tube mountings specially adapted therefor
    • F24D3/142Tube mountings specially adapted therefor integrated in prefab construction elements

Definitions

  • the invention relates to the field of prefabricated concrete building elements. Particularly, the invention relates to a method of making a floor element and to a floor element.
  • bathroom intermediate floor constructions have been made either casting in place on top of cast molds, as a composite slab or from load-bearing precast slabs.
  • the installation fittings are placed on site on top of the slab element and the final surface layer of the floor is cast leaving the installation fittings within the cast concrete.
  • the floor structure in the bathroom area is made thinner so as to be thinner than the other areas, so that the thickness of the final slab does not grow too much. This can be done at the factory, for example in casting phase, by breaking the hollow structure and compressing the concrete solid in the bathroom area, creating an appropriate sanitary cabin provision.
  • Patent publication DE 49863 discloses a drainage system including a floor element where pipes have been cast inside the floor element.
  • the floor element has a flat surface and a floor drain is placed onto the mold on the same level as the upper surface of the floor element. There are no floor inclinations on the element upper floor surface and they must be done later.
  • Patent publication FR 2503220 describes a sanitary floor module which comprises a concrete slab with embedded pipes and a floor drain.
  • the sanitary floor module is installed on top of the finished floor or on top of the floor slab on site. It does not disclose a floor element including a wet room provision area and a slab part.
  • a floor slab element which is completely factory-prefabricated and includes a wet area provision is used as a floor structure for wet rooms, which slab element is produced by essentially continuous mold casting. Onto the mold into the relevant areas are placed at least floor drain installation fittings, the floor is cast and pitch formatting required for floor draining is done in the wet room area.
  • a floor element cast is done at least in the floor drain pitch formatting area as a layered multi-phase cast using concrete having varying viscosity.
  • a wet room area is limited with a separating mold during at least one cast phase.
  • additional slab-specific installation fittings are placed into the mold before the cast.
  • At least the areas outside of the wet room provision are cast with self-compacting concrete.
  • the invention provides a floor element which comprises, in the wet room area, at least floor drain plumbing and floor drain pitch formatting and is, at least in the wet room area, made using essentially continuous mold casting.
  • the method according to the invention is characterized by what is stated in the characterizing part of claim 1, the floor element according to the invention is characterized by what is stated in the characterizing part of claim 7.
  • floor element 1 which consists of slab part 2 and wet room provision area 3.
  • Wet room provision area 3 is a space requiring inclination, e.g. bathroom with floor drain 5.
  • reinforcements are firstly placed into the mold, for example prestressed reinforcing strands.
  • the installation fittings required as selected are mounted into the wet room provision area 3, such as heating, water, plumbing, ventilation and electrical installation fittings and heating system plumbing or wires.
  • Plumbing like sewer pipes 4, must be exactly in the right place and must have the right slope.
  • location and height of floor drains 5 are strictly defined. Sewer pipes 4 and floor drains 5 must be supported so that they do not move or rise during casting.
  • FIG 2 a cross section of floor element 1, where sewer pipes 4 has been supported in the mold with the aid of adjustable prefabricated concrete supports 6.
  • Adjustable concrete supports 6 are preferably made of recycled waste concrete, in which case they are heavy and large enough to anchor the pipes during casting, and they do not require separate fastening to the mold.
  • Concrete support 6 consists of parts 6, 7 and 8, which are designed in such a way that when they are moved in various directions relative to each other, the overall height of the support changes.
  • Figure 3 shows that top concrete part 7 is so designed that it forms a parallel support surface with pipe 4, resulting in e.g. that drain 5 is positioned at the desired inclination, for example 1:50 or 1:60 - 1:100.
  • the undermost concrete part 8 has studs 9 in the bottom, so that the space between the bottom of concrete support 6 and the mold is filled with concrete during the element cast.
  • the first cast is carried out over the entire area of floor element 1 to a determined height, whereby the installation fittings located on the bottom of the mold become partly or totally embedded in concrete.
  • a stiff sheet-shaped separation mold 10 is installed at the border area between the wet room and the rest of the room space, forming a recess 11 at the wet room area.
  • Sheet-shaped separation mold 10 acts as a temporary mold stopper, preventing the concrete from moving into the recess area 11 as the cast in slab part 2 is raised to its final height.
  • a dam mold method can be used to generate recess area 11.
  • the height of recess area 11 is determined by the space required by pitch casting, plumbing, cabling and floor drain connections and can be 30 - 60 mm, typically 50 mm.
  • Floor drain 5 within recess area 11 is for example 10 - 50 mm above the bottom of recess area 11.
  • In the first cast is preferably used self-compacting concrete, the slump flow of which may be 450 - 800 mm.
  • underfloor heating cables or pipes are installed at the desired height position in recess area 11. Also other required installations can be done in recess area 11.
  • a second cast the so called pitch cast, is carried out in recess area 11, generating sufficient pitch in the wet room area.
  • the pitch cast is usually made using concrete different from that used in the first cast, for example by topping, in which the maximum grain size is below 8 mm, whereby an inclination is effected in the top surface of the recess area.
  • the pitch cast is usually carried out as soon as possible after the first cast phase, so the concrete does not have time to harden and the cast simultaneously acts as a part of the supporting structure of the element, forming a monolithic composite structure with the earlier cast.
  • the timing of the second cast depends on the speed of the concrete receipt and the concrete temperature, and it can be carried out for example 10-120 minutes after the first cast.
  • a floor element is cast in one phase whereby selected installation fittings are placed into the mold before the cast either at a wet room provision area and/or to a slab part.
  • the installation fittings can comprise heating system plumbing or cables.
  • a separation mold can be installed in the space requiring inclination in the wet room provision area, but the cast can be done also without a separation mold.
  • the slab part and the wet room provision area are cast with the same or different concrete.
  • a floor slab element is cast as a two-phase casting.
  • the first and the second cast are done over the entire floor element area, whereby in the second cast a wet room provision area is formed into a space needing inclinations.
  • selected installation fittings are mounted into the mold either in the wet room provision area and/or to the slab part.
  • Installation fittings may include heating system plumbing or cables.
  • a separation mold is placed in the space requiring inclinations. Heating system plumbing or cables will be installed either to the wet room provision area and/or to the slab part if they have not been added before the first cast.
  • the second cast is done over the slab part and in the wet room provision area, using either the same or different concrete.
  • the wet room provision area can be formed also without a separation mold, in which case the second cast is done on the slab part and in the wet room provision area, and the inclinations in the wet room provision area are formed in context of the cast by adjusting the amount of concrete and simultaneously applying floating until sufficient inclinations are achieved.
  • the slab part is cast to its final height in one phase and the area having a shaped surface in two phases.
  • selected installation fittings are mounted into the mold.
  • the installation fittings can include a heating system plumbing or cables.
  • a separation mold is mounted in the space requiring inclinations before the first cast to form a surface-shaping area. The separation mold and the heating system plumbing or cables are supported and fixed so that they do not move during the cast.
  • the slab part is cast to its final height and the first cast is carried out in the wet room provision area. After the first cast, heating system plumbing or cables are installed if needed in the space requiring inclinations and the second, pitch-forming cast is carried out.
  • the cast is done at least in a floor drain inclination area as a layered multi-phase cast with concrete having the same or different viscosity.
  • the cast can be done as multi-phase cast if e.g. different installation fittings require it.
  • the cast is done in one or in two phases.
  • the floor heating can be left out completely whereby heating system plumbing or cables are not installed before the first or the second cast, or if desired they can be mounted over the whole floor element area or only over the slab part or in the wet room provision area.
  • installation fittings mounted prior to the first cast include heating, water, sewer, ventilation and electrical installation fittings. After the first cast, heating system plumbing or cables are installed only in the wet room provision area.
  • installation fittings including heating, water, sewer, ventilation and electrical ducts as well as heating system plumbing or cables are mounted over the whole slab part prior to the first cast.
  • the concrete used in multi-phase casting can be the same throughout or it may vary between phases.
  • the concrete used in all casts is self-compacting concrete.
  • the surface-shaped area is formed by floating and it can be formed also without a separation mold.
  • a wet room area can also be coated ready at the factory, for example with moisture-proofing or waterproofing layer, in which case the element does not get wet in the storage or on site and the structure dries faster.
  • Moisture protector / waterproofing agent is sprayed onto the second cast, i.e. the pitch cast at the appropriate phase after casting before unloading the elements from the mold line.
  • the element height is reduced, for example from previously used 370 mm to 270 mm, because a massive slab is used as an element and installation fittings are mounted inside the floor element at the factory.
  • a thinner intermediate floor allows a lower overall storey height or allows for increasing the room height.
  • the width and the length of the element can be increased, leading to faster installation and the number of floor elements decreases even by three elements for each apartment. As a result, less filling and joint grouting is required on site, whereby the consumption of concrete and joint steel bars is reduced and the wet room floor dries faster.
  • the solution according to the invention leads to a greater preproduction rate, whereby the working stages on site and construction costs are reduced and time spent in planning is decreased.
  • plumbing and HVAC are installed inside the element at the factory, no subcontractors are required on site in the frame phase for these stages, and scheduling is easier.
  • construction quality is improved when curvature differences are reduced, leading to decreased use of filler.
  • a 270 mm massive slab according to the invention is 140 kg heavier per square meter than the commonly used 370 mm hollow-core slab. As a result of the weight difference, the air and impact sound isolation of the massive slab according to the invention is better than the above-mentioned hollow-core slab.
  • the floor element according to the invention can also be used outside of the bathroom, for example in the sauna, kitchen, toilet and other wet areas. None of the solutions disclosed above restrict the use of the invention in other appropriate locations.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Thermal Sciences (AREA)
  • Electromagnetism (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Floor Finish (AREA)

Description

    Field of the invention
  • The invention relates to the field of prefabricated concrete building elements. Particularly, the invention relates to a method of making a floor element and to a floor element.
  • Background of the invention
  • In residence buildings, especially in a bathroom area, space is needed in intermediate floor constructions for installation fittings, such as heating, plumbing, ventilation and electrical installation fittings. Conventionally, bathroom intermediate floor constructions have been made either casting in place on top of cast molds, as a composite slab or from load-bearing precast slabs.
  • When casting in place, all installation fittings are pre-mounted on top of the casting mold in the course of the reinforcement work, and after that the floor structure is cast, whereupon the installation fittings remain inside the cast concrete. In a composite slab solution, a thin composite slab is mounted undermost on site, acting as a mold for the final cast and later partly as a part of the supporting structure. Additional reinforcement and installation fittings are placed on the composite slab and a floor structure is cast on top of the installation fittings.
  • When using prefabricated elements, the installation fittings are placed on site on top of the slab element and the final surface layer of the floor is cast leaving the installation fittings within the cast concrete. In this solution, the floor structure in the bathroom area is made thinner so as to be thinner than the other areas, so that the thickness of the final slab does not grow too much. This can be done at the factory, for example in casting phase, by breaking the hollow structure and compressing the concrete solid in the bathroom area, creating an appropriate sanitary cabin provision.
  • Patent publication DE 49863 discloses a drainage system including a floor element where pipes have been cast inside the floor element. The floor element has a flat surface and a floor drain is placed onto the mold on the same level as the upper surface of the floor element. There are no floor inclinations on the element upper floor surface and they must be done later.
  • Patent publication FR 2503220 describes a sanitary floor module which comprises a concrete slab with embedded pipes and a floor drain. The sanitary floor module is installed on top of the finished floor or on top of the floor slab on site. It does not disclose a floor element including a wet room provision area and a slab part.
  • The problem in the above-described solutions is the large amount of casting in place on site. Casting in place involves numerous working steps and the concrete setting time is long, slowing down construction. At a frame stage, subcontractors are required on site simultaneously for different phases and scheduling of them is difficult, which often causes waiting and extends the total schedule. Also, raw materials transportation costs and carbon dioxide emissions are greater compared to totally industrially produced slabs. Consequently, there has been a demand to develop intermediate floor designs intended for wet room structures and speed up construction work in on-site conditions.
  • Disclosure of the invention
  • In the solution according to the invention, a floor slab element which is completely factory-prefabricated and includes a wet area provision is used as a floor structure for wet rooms, which slab element is produced by essentially continuous mold casting. Onto the mold into the relevant areas are placed at least floor drain installation fittings, the floor is cast and pitch formatting required for floor draining is done in the wet room area.
  • According to one embodiment, a floor element cast is done at least in the floor drain pitch formatting area as a layered multi-phase cast using concrete having varying viscosity.
  • According to another embodiment, a wet room area is limited with a separating mold during at least one cast phase.
  • According to a further embodiment, additional slab-specific installation fittings are placed into the mold before the cast.
  • According to a further embodiment, at least the areas outside of the wet room provision are cast with self-compacting concrete.
  • In addition, the invention provides a floor element which comprises, in the wet room area, at least floor drain plumbing and floor drain pitch formatting and is, at least in the wet room area, made using essentially continuous mold casting.
  • Floor elements which are completely prefabricated at the factory significantly accelerate construction work, since time-consuming casting-in-place is no longer needed. Also, construction quality is improved when curvature differences are reduced.
  • More specifically, the method according to the invention is characterized by what is stated in the characterizing part of claim 1, the floor element according to the invention is characterized by what is stated in the characterizing part of claim 7.
  • The invention will be described in more detail by way of example in the following, with reference to the enclosed drawings, wherein:
    • Fig. 1 shows a floor element according to the invention seen from above;
    • Fig. 2 shows a cross section of the floor element according to Fig. 1, and
    • Fig. 3 shows a cross section of a floor element according to the invention at the site of the floor drain.
  • In Figure 1 is shown floor element 1, which consists of slab part 2 and wet room provision area 3. Wet room provision area 3 is a space requiring inclination, e.g. bathroom with floor drain 5. In a process of manufacturing floor element 1 at a factory, reinforcements are firstly placed into the mold, for example prestressed reinforcing strands. Next, the installation fittings required as selected are mounted into the wet room provision area 3, such as heating, water, plumbing, ventilation and electrical installation fittings and heating system plumbing or wires. Plumbing, like sewer pipes 4, must be exactly in the right place and must have the right slope. Also, location and height of floor drains 5 are strictly defined. Sewer pipes 4 and floor drains 5 must be supported so that they do not move or rise during casting.
  • In Figure 2 is shown a cross section of floor element 1, where sewer pipes 4 has been supported in the mold with the aid of adjustable prefabricated concrete supports 6. Adjustable concrete supports 6 are preferably made of recycled waste concrete, in which case they are heavy and large enough to anchor the pipes during casting, and they do not require separate fastening to the mold. Concrete support 6 consists of parts 6, 7 and 8, which are designed in such a way that when they are moved in various directions relative to each other, the overall height of the support changes. Figure 3 shows that top concrete part 7 is so designed that it forms a parallel support surface with pipe 4, resulting in e.g. that drain 5 is positioned at the desired inclination, for example 1:50 or 1:60 - 1:100. The undermost concrete part 8 has studs 9 in the bottom, so that the space between the bottom of concrete support 6 and the mold is filled with concrete during the element cast.
  • When all the required installation fittings and reinforcement have been mounted onto the bottom of the mold, the first cast is carried out over the entire area of floor element 1 to a determined height, whereby the installation fittings located on the bottom of the mold become partly or totally embedded in concrete. In a suitable phase of the cast, a stiff sheet-shaped separation mold 10 is installed at the border area between the wet room and the rest of the room space, forming a recess 11 at the wet room area. Sheet-shaped separation mold 10 acts as a temporary mold stopper, preventing the concrete from moving into the recess area 11 as the cast in slab part 2 is raised to its final height. A dam mold method can be used to generate recess area 11. The height of recess area 11 is determined by the space required by pitch casting, plumbing, cabling and floor drain connections and can be 30 - 60 mm, typically 50 mm. Floor drain 5 within recess area 11 is for example 10 - 50 mm above the bottom of recess area 11. In the first cast is preferably used self-compacting concrete, the slump flow of which may be 450 - 800 mm.
  • When the concrete has stiffened sufficiently after the first cast, underfloor heating cables or pipes are installed at the desired height position in recess area 11. Also other required installations can be done in recess area 11. Subsequently, a second cast, the so called pitch cast, is carried out in recess area 11, generating sufficient pitch in the wet room area. The pitch cast is usually made using concrete different from that used in the first cast, for example by topping, in which the maximum grain size is below 8 mm, whereby an inclination is effected in the top surface of the recess area. The pitch cast is usually carried out as soon as possible after the first cast phase, so the concrete does not have time to harden and the cast simultaneously acts as a part of the supporting structure of the element, forming a monolithic composite structure with the earlier cast. The timing of the second cast depends on the speed of the concrete receipt and the concrete temperature, and it can be carried out for example 10-120 minutes after the first cast.
  • According to one example, a floor element is cast in one phase whereby selected installation fittings are placed into the mold before the cast either at a wet room provision area and/or to a slab part. The installation fittings can comprise heating system plumbing or cables. In addition, a separation mold can be installed in the space requiring inclination in the wet room provision area, but the cast can be done also without a separation mold. Next, the slab part and the wet room provision area are cast with the same or different concrete.
  • According to a further example, a floor slab element is cast as a two-phase casting. The first and the second cast are done over the entire floor element area, whereby in the second cast a wet room provision area is formed into a space needing inclinations. Before the first cast, selected installation fittings are mounted into the mold either in the wet room provision area and/or to the slab part. Installation fittings may include heating system plumbing or cables. After the first cast, a separation mold is placed in the space requiring inclinations. Heating system plumbing or cables will be installed either to the wet room provision area and/or to the slab part if they have not been added before the first cast. Next, the second cast is done over the slab part and in the wet room provision area, using either the same or different concrete. The wet room provision area can be formed also without a separation mold, in which case the second cast is done on the slab part and in the wet room provision area, and the inclinations in the wet room provision area are formed in context of the cast by adjusting the amount of concrete and simultaneously applying floating until sufficient inclinations are achieved.
  • According to a still further example, the slab part is cast to its final height in one phase and the area having a shaped surface in two phases. Before the first cast, selected installation fittings are mounted into the mold. The installation fittings can include a heating system plumbing or cables. In addition, a separation mold is mounted in the space requiring inclinations before the first cast to form a surface-shaping area. The separation mold and the heating system plumbing or cables are supported and fixed so that they do not move during the cast. Next, the slab part is cast to its final height and the first cast is carried out in the wet room provision area. After the first cast, heating system plumbing or cables are installed if needed in the space requiring inclinations and the second, pitch-forming cast is carried out.
  • According to a still further example, the cast is done at least in a floor drain inclination area as a layered multi-phase cast with concrete having the same or different viscosity. The cast can be done as multi-phase cast if e.g. different installation fittings require it. Preferably, the cast is done in one or in two phases.
  • In all the above mentioned examples, the floor heating can be left out completely whereby heating system plumbing or cables are not installed before the first or the second cast, or if desired they can be mounted over the whole floor element area or only over the slab part or in the wet room provision area. For example, installation fittings mounted prior to the first cast include heating, water, sewer, ventilation and electrical installation fittings. After the first cast, heating system plumbing or cables are installed only in the wet room provision area. According to the second example, installation fittings including heating, water, sewer, ventilation and electrical ducts as well as heating system plumbing or cables are mounted over the whole slab part prior to the first cast.
  • The concrete used in multi-phase casting can be the same throughout or it may vary between phases. Preferably, the concrete used in all casts is self-compacting concrete. The surface-shaped area is formed by floating and it can be formed also without a separation mold. A wet room area can also be coated ready at the factory, for example with moisture-proofing or waterproofing layer, in which case the element does not get wet in the storage or on site and the structure dries faster. Moisture protector / waterproofing agent is sprayed onto the second cast, i.e. the pitch cast at the appropriate phase after casting before unloading the elements from the mold line.
  • Using the solution according to the invention the element height is reduced, for example from previously used 370 mm to 270 mm, because a massive slab is used as an element and installation fittings are mounted inside the floor element at the factory. A thinner intermediate floor allows a lower overall storey height or allows for increasing the room height. Because of the massive structure, the width and the length of the element can be increased, leading to faster installation and the number of floor elements decreases even by three elements for each apartment. As a result, less filling and joint grouting is required on site, whereby the consumption of concrete and joint steel bars is reduced and the wet room floor dries faster.
  • The solution according to the invention leads to a greater preproduction rate, whereby the working stages on site and construction costs are reduced and time spent in planning is decreased. When plumbing and HVAC are installed inside the element at the factory, no subcontractors are required on site in the frame phase for these stages, and scheduling is easier. Also, construction quality is improved when curvature differences are reduced, leading to decreased use of filler.
  • A 270 mm massive slab according to the invention is 140 kg heavier per square meter than the commonly used 370 mm hollow-core slab. As a result of the weight difference, the air and impact sound isolation of the massive slab according to the invention is better than the above-mentioned hollow-core slab.
  • The floor element according to the invention can also be used outside of the bathroom, for example in the sauna, kitchen, toilet and other wet areas. None of the solutions disclosed above restrict the use of the invention in other appropriate locations.

Claims (12)

  1. A method for making a floor element (1) including a wet room provision area (3) having a floor drain and a slab part (2) by essentially continuous mold casting, characterized in that at least floor drain installation fittings are placed onto the mold, the floor element (1) is cast and wet room provision area (3) inclination formatting required by the floor drain (5) is done in the wet room provision area (3).
  2. A method according to claim 1, characterized in that floor inclination formatting is done by adjusting the amount of concrete and simultaneously applying floating until sufficient inclinations are achieved.
  3. A method according to claim 1 or 2, characterized in that the cast is carried out as a layered multi-phase cast at least in the floor drain (5) inclination formatting area.
  4. A method according to claim 3, characterized in that the first cast is carried out over the entire area of the floor element (1) and the second cast is done over the slab part (2) and the wet room provision area (3).
  5. A method according to any of the preceding claims, characterized in that the wet room provision area (3) is limited with a separating mold (10) at least during one casting phase.
  6. A method according to claim 3, characterized in that the first cast is carried out over the entire area of the floor element (1), the wet room provision area (3) is limited with a separating mold (10) to form a recess area (11) after which the slab part (2) is cast to its final height and the second cast is done over the wet room provision area (3).
  7. A method according to any of claims 3-6, characterized in that heating system plumbing or cables are installed to the slab part (2) or to the wet room provision area (3) after the first cast.
  8. A method according to any of claims 3-6, characterized in that heating system plumbing or cables are installed to the slab part (2) and to the wet room provision area (3) after the first cast.
  9. A method according to any of the preceding claims, characterized in that the cast is carried out in the wet room provision area (3) as a multi-phase cast using concrete having varying viscosity.
  10. A method according to any of the preceding claims, characterized in that additional slab-specific installation fittings are placed into the mold before the casting.
  11. A method according to any of the preceding claims, characterized in that at least the areas outside of the wet room provision area (3) are cast using self-compacting concrete.
  12. A floor element (1) including a wet room provision area (3) having a floor drain, and a slab part (2), characterized in that the floor element (1) comprises in the wet room area (3) at least floor drain plumbing and wet room provision area (3) inclination formatting required by the floor drain (5) and is, at least in the wet room area (3), made using essentially continuous mold casting.
EP10397526.4A 2009-12-22 2010-12-22 Method for making a floor slab element with drainage installation and the floor slab element Active EP2339075B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FI20096378A FI122394B (en) 2009-12-22 2009-12-22 Process for making floor elements as well as floor elements

Publications (2)

Publication Number Publication Date
EP2339075A1 EP2339075A1 (en) 2011-06-29
EP2339075B1 true EP2339075B1 (en) 2015-09-16

Family

ID=41462836

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10397526.4A Active EP2339075B1 (en) 2009-12-22 2010-12-22 Method for making a floor slab element with drainage installation and the floor slab element

Country Status (3)

Country Link
EP (1) EP2339075B1 (en)
DK (1) DK2339075T3 (en)
FI (1) FI122394B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE539386C2 (en) * 2015-02-10 2017-09-12 A drainage hole floor module and a method of production of such
FI129460B (en) * 2019-02-12 2022-02-28 Elematic Oyj Method for manufacturing prefabricated concrete products

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI49863C (en) * 1972-03-09 1975-10-10 Vaeaenaenen Olavi Sewer system for buildings.
CH577085A5 (en) * 1973-11-15 1976-06-30 Vogt Werner
FR2503220A1 (en) * 1981-04-03 1982-10-08 Charbonnages Sa Ste Indle Cale Prefabricated floor module for bathroom etc. - contains water inlet and outlet ducts cast in concrete slab
CH688722A5 (en) * 1996-10-28 1998-01-30 Theo Rellstab Mould component for producing recess in concrete structural part
FR2789711B1 (en) * 1999-02-12 2001-05-04 David Genevois RESERVATION BOX FOR THE INCORPORATION OF PIPES IN A CONCRETE SLAB AND ITS IMPLEMENTING METHOD
DE20102623U1 (en) * 2001-02-13 2001-05-03 Peuckert, Linus, Dipl.-Ing., 33098 Paderborn Ready-mixed concrete multi-function slab
FI20050906A (en) * 2005-09-12 2007-03-13 Elematic Oy Ab Method and apparatus for casting self-compacting concrete

Also Published As

Publication number Publication date
DK2339075T3 (en) 2016-01-04
FI20096378A0 (en) 2009-12-22
FI20096378A (en) 2011-06-23
EP2339075A1 (en) 2011-06-29
FI122394B (en) 2011-12-30

Similar Documents

Publication Publication Date Title
US20020059763A1 (en) Pre-fabricated bathroom
EP3670774B1 (en) Prefabricated bathroom and methods for constructing and installing the same
EP2739799A1 (en) Building structure of pre-cast monolithic walls and interfloor slabs
EP1214483B2 (en) Hollow-core slab for forming a floor field in which ducts can be incorporated, and method for forming a floor field with ducts using such hollow-core slabs
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
EP2339075B1 (en) Method for making a floor slab element with drainage installation and the floor slab element
CN102230338A (en) Prefabricated toilet and construction method and installation method thereof
KR100694586B1 (en) Wall Structure Using Precast Concrete Panel with Rib Rows
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN102230339A (en) Prefabricated kitchen and construction and installation method thereof
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
EP1982026B1 (en) Method for repairing sanitary facilities of a block of flats
EP2886733A1 (en) A method for assembling and the construction of a plane or inclined floor for residential and industrial use, with unidirectional or bidirectional reinforcement, and means for its implementation
CN212358790U (en) Floor plate member
CN102777032A (en) Installation method of prefabricated toilet
CN1963110A (en) Construction method for large-space rebuilding and double-girder replacement of bearing wall made of brick and concrete
EP3719229B1 (en) Concrete floor panel, method of production of such panel and floor made of this panel
EP4206419A1 (en) A method for realising an antiseismic system
CN107152114B (en) Assembled drop-free same-floor drainage floor system and construction method thereof
CN102777033A (en) Method for mounting prefabricated kitchen
JP7199439B2 (en) building construction method
EP1907179A1 (en) Method for the manufacture of a concrete floor
GB2540126A (en) Casting method and apparatus
GB2540127A (en) Building construction method and apparatus
CN114150806A (en) Floor plate member and method for manufacturing the same

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

17P Request for examination filed

Effective date: 20111219

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20150408

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 749959

Country of ref document: AT

Kind code of ref document: T

Effective date: 20151015

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602010027539

Country of ref document: DE

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

Effective date: 20160103

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151217

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

REG Reference to a national code

Ref country code: NO

Ref legal event code: T2

Effective date: 20150916

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 749959

Country of ref document: AT

Kind code of ref document: T

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160116

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151231

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160118

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602010027539

Country of ref document: DE

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602010027539

Country of ref document: DE

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151222

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

26N No opposition filed

Effective date: 20160617

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20151222

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20160831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151231

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151222

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151222

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20160701

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151231

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151231

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20101222

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150916

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20231218

Year of fee payment: 14

Ref country code: NO

Payment date: 20231218

Year of fee payment: 14

Ref country code: FI

Payment date: 20231214

Year of fee payment: 14

Ref country code: DK

Payment date: 20231219

Year of fee payment: 14