EP2247346B1 - Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor - Google Patents
Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor Download PDFInfo
- Publication number
- EP2247346B1 EP2247346B1 EP20090710950 EP09710950A EP2247346B1 EP 2247346 B1 EP2247346 B1 EP 2247346B1 EP 20090710950 EP20090710950 EP 20090710950 EP 09710950 A EP09710950 A EP 09710950A EP 2247346 B1 EP2247346 B1 EP 2247346B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- fitting
- sprinkler
- concrete
- adapter
- connection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
Images
Classifications
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62C—FIRE-FIGHTING
- A62C35/00—Permanently-installed equipment
- A62C35/58—Pipe-line systems
- A62C35/68—Details, e.g. of pipes or valve systems
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T137/00—Fluid handling
- Y10T137/0318—Processes
- Y10T137/0402—Cleaning, repairing, or assembling
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T137/00—Fluid handling
- Y10T137/598—With repair, tapping, assembly, or disassembly means
Definitions
- the invention relates to an arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor and a method for producing the connection possibility.
- DE 101 40 942 C1 a supply system for extinguishing agent, which consists of a feed pipe in a building material between a connection and a nozzle for spraying an extinguishing agent, wherein between the connection for the extinguishing agent and a connection for the nozzle in the building material, a flexible tube is arranged.
- a connection for a sprinkler on a concrete floor with a flexible pipe to which an extension piece is attached, which is passed through a shuttering to the boundary of the concrete ceiling.
- On the casing is a seal over which the attachment to the casing can be made and in which the end of the pipe and a part of the extension piece are added.
- connection cable is connected to a connection area of a fitting.
- a transition piece is arranged, which has a receptacle for a sprinkler on the side facing away from the fitting.
- a top of a sprinkler junction box is arranged to prevent the ingress of liquid concrete in the area of the inclusion of the sprinkler in the manufacture of concrete or reinforced concrete slab.
- a brass closure is placed in the receptacle for the sprinkler, so that the recording is protected from dirt.
- the compound thus prepared is connected to the lower part of the sprinkler connection box in such a way that the upper and lower part of the sprinkler connection box are connected to one another in a concrete-tight manner.
- a disadvantage is seen in the fact that after arranging a plurality of arrangements for the possibility of connecting sprinklers on a formwork also due to the large number of lines that are laid on the casing, it is difficult to detect the exact position and to check whether all connection options were laid. Furthermore, there is the problem that after curing of the concrete, the casing is removed and the lower parts of the sprinkler connection boxes are attached to this. Thus, these are removed with the casing from the tops of the sprinkler connection boxes, without special care must be taken at these locations in order to avoid damage to the tops that remain in the concrete floor.
- the fastener since the fastener partially encloses the box rests on the casing and is pressed over the fastener by means of the fastener against the casing, no concrete can penetrate into the can when pouring the concrete and thus the fastener and the second terminal portion of the fitting are kept free of Betonstromrungen , Thus, the fastener after curing of the concrete and the removal of the casing is removable and reusable.
- an extension element is provided which is connected to the adapter.
- the extension elements are therefore only necessary in the diameter dimension of the diameter of the connection areas of the sprinklers.
- the adapter is completely surrounded by the can.
- screw connections between the fitting and fastener or fitting and adapter and / or adapter and extension element allow easy assembly and disassembly.
- the fastening means is a female threaded nut. This can be screwed onto the threaded portion of the fastener and thus provides a simple and cost-effective way of attachment.
- a washer between the nut and the casing in order to prevent penetration into the usually made of wood casing and to ensure easy disassembly. Also, a too large opening in the casing can be covered with the washer, so that a secure tightening of the fastening means, in particular the mother can be ensured.
- the invention comprises a method for producing a connection possibility for a sprinkler on a limited by a formwork concrete or reinforced concrete ceiling.
- the method provides that first a fastener is connected to a first terminal portion of a fitting.
- the fitting can be a bow or branch, in particular a T-piece.
- a can is arranged via the fastening element, which is essentially cylindrical and has at one end a wall provided with an opening.
- the breakthrough is designed so that the can is tightly applied to a collar of the first connection area of the fitting.
- the cylindrical portion of the can surrounds a part of the fastening element, so that an annular cavity is enclosed.
- the fastener overhangs the can after it abuts the collar of the first port of the fitting.
- This projecting portion of the fastener is then passed through an opening in the formwork.
- this opening is introduced into the mostly made of wood casing.
- the fastener After the fastener has been passed through the opening, it is fastened on the side facing away from the fitting of the casing by means of a fastening means. Thereafter, the connection between at least one water pipe and a second connection region of the fitting is made. Now further laying work can be carried out on the shuttering. Also, reinforcement mats can be introduced, which achieve an increase in the stability of the ceiling. Thereafter, the concrete is placed on the formwork. This can not penetrate into the can, which is thereby pressed onto the casing by the attachment by means of a fastening means on the side facing away from the fitting, so that no concrete can reach the second connection region of the fitting and the fastener.
- the fastener After curing of the concrete, the fastener can be removed from the fitting.
- the shuttering can be removed from the ceiling without regard to the connection possibilities for the sprinklers.
- a sprinkler is connected to the first connection area of the fitting. Since the sprinkler body must be located below the ceiling, it may be necessary to insert an adapter between the sprinkler and the first connection area of the fitting.
- This adapter can be designed so that also diameter differences between the connection areas of the fitting and the sprinkler can be bridged. In this regard, it has been recognized that the adapter is connected either first to the sprinkler and then both together to the first port of the fitting, or first to connect the adapter to the first port of the fitting and then the sprinkler to the adapter.
- the fastening element is constructed from two parts.
- the fastening element consist of an adapter and an extension element. Since it is necessary in most applications to arrange an adapter between the first connection region of the fitting and the sprinkler, this can already be introduced as part of the fastening element.
- the adapter Since this adapter is completely surrounded by the box, it is not possible to pass through the formwork. To still ensure this, the adapter is connected to an extension element that bridges the missing length. It has been recognized that both the adapter with the first terminal portion of the fitting or first the adapter with the extension element can be connected.
- a releasable connection in particular a screw connection, is necessary between the adapter and the extension element.
- FIG. 1 is a section through a mounted on a formwork (7) inventive arrangement for producing a connection option shown.
- the arrangement has a fitting (3), which is T-shaped, with three connection areas (2a, 2b). But it is also possible that the fitting (3) has only two connection areas (2a, 2b), so that no forwarding of the fluid to further arrangements is possible.
- pipelines (1) are arranged, which in this example are fixed to the fitting (3) by means of sliding sleeves.
- a fastening element (4a, 4b) which consists of an adapter (4a) and an extension element (4b), releasably secured.
- Both fitting (3) and adapter (4a) and adapter (4a) and extension element (4b) are connected to each other via a screw connection.
- the adapter (4a) is designed in this example to be a kind of reducer, since the connection area (2a) of the fitting (3) has a larger dimension than the sprinkler to be attached later.
- the arrangement has a can (5) which surrounds the fastening element (4a, 4b) in regions.
- This can (5) is arranged on a collar (6) of the connection area (2a) of the fitting (3) which is not connected to a pipeline (1), so that its position relative to the fitting (3) is defined.
- the can (5) made of metal, but there are also other materials conceivable that meet the requirements in case of fire and cause no functional restrictions of the sprinkler in case of fire. It is also possible, as in this example, to place a seal (12) between the can (5) and the collar (6) of the fitting (3) to safely prevent the ingress of concrete at this point.
- the FIG. 1 also shows a formwork (7) through which the fastening element (4a, 4b), in particular the extension element (4b) protrudes.
- the formwork (7) has an opening (9) which is substantially identical in shape and surface area to the cross-section of the fastening element (4a, 4b), in particular of the extension element (4b).
- a fastening means (8) in the form of a nut is arranged on the fastening element (4a, 4b).
- the latter is connected to the fastening element (4a, 4b), in particular the extension element (4b), via the thread situated in the embodiment facing away from the fitting (3) at the end of the extension element (4b).
- fastening means (8) such as terminals or the like possible.
- FIG. 1 From the FIG. 1 can also be found that between the casing (7) and the nut as a fastening means (8) a washer (10)) is arranged with a larger diameter than the mother. This prevents that when tightening the nut this in the casing (7), which is usually made of wood, digs and thus complicates a later release.
- connection region (2a) of the fitting (3) is connected to the adapter (4a) via a screw connection. It can be introduced into the thread for sealing hemp, which expands by fluid intake and thus seals the connection. But there are also other sealants conceivable. In this connection, it is also possible to seal the connection between adapter (4a) and connection region (2a) of the fitting (3) by means of an additional or sole adhesive connection.
- connection portion (2a) of the fitting (3) and the fastener is necessary because the fastener must be removed after completion of the concrete or reinforced concrete ceiling.
- the extension element (4b) is detachably connected to the adapter (4a) via a screw connection.
- the connection region of the connecting element (4b) to the adapter (4a) is designed in the same diameter as the later to be used sprinkler. Due to the division of the fastening element (4a, 4b), it is possible to use only different adapters (4a) for different dimensions of the connection regions (2a) of the fitting (3), whereas in the number of variants the extension element (4b) only applies to the different sprinkler dimensions must be coordinated.
- the fastening element (4a, 4b), in particular the extension element (4b) is passed through an opening (9) introduced into the formwork (7).
- the opening (9) corresponds approximately to the cross section of the fastening element (4a, 4b), in particular of the extension element (4b).
- the fastening element (4a, 4b), in particular the extension element (4b) protrudes on one side of the casing (7) and on the other side of the casing (7) the can (5) is in contact with the formwork (7) ,
- the fitting (3) with the adapter (4a), the extension element (4b) and the box (5) would float, is on the side facing away from the fitting (3) of the shuttering ( 7) a fastening means (8) with the fastening element (4a, 4b), in particular connected to the extension element (4b).
- the connection is designed as a screw connection, wherein the fastening element (4a, 4b), in particular the extension element (4b) on its side facing away from the adapter (4a) has a thread and the fastening means (8) is designed as a nut.
- a washer (10) is arranged between the casing (7) and nut.
- pipelines (1) are connected to the still free connection area (s) (2b ) connected. This is generally done by widening the pipe end and sliding it onto the connection area (2b) of the fitting (3). Thereafter, a compression of the pipe end with the fitting (3) is performed. This can be done via a radially compressible compression sleeve, or by the use of a sliding sleeve (11).
- the pipes (1) are usually laid so that between the individual arrangements a closed ring with a one-sided or two-sided feed or individual strands, which are fed from one side, arise. These arrangements result in the fitting configurations to be used for the individual arrangements.
- a pressure test is carried out, in particular according to VdS CEA 4001. This makes it possible to detect and eliminate possible leaks before the concrete is introduced.
- the fastening element (4a, 4b) serves as a plug which seals against the environment the connection area, at which the sprinkler is later connected, and thus enables the pressure test. If no or a pressure drop in the tolerance range is detected, the concrete can be placed on the casing (7).
Landscapes
- Health & Medical Sciences (AREA)
- Public Health (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)
Abstract
Description
Die Erfindung betrifft eine Anordnung zum Herstellen einer Anschlussmöglichkeit, insbesondere für einen Sprinkler an einer Beton- oder Stahlbetondecke und ein Verfahren zur Herstellung der Anschlussmöglichkeit.The invention relates to an arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor and a method for producing the connection possibility.
Im Stand der Technik sind derartige Anordnungen bekannt. Beispielsweise beschreibt die
Weitere derartige Anordnungen bestehen z. B. aus einem Unterteil einer Sprinkleranschlussdose, die mithilfe von Schrauben oder Nägeln auf einer Verschalung befestigt wird. Die Anschlussleitung wird mit einem Anschlussbereich eines Fittings verbunden. An einen zweiten Anschlussbereich des Fittings wird ein Übergangsstück angeordnet, dass auf der dem Fitting abgewandten Seite eine Aufnahme für einen Sprinkler aufweist. Über diese Aufnahme wird ein Oberteil einer Sprinkleranschlussdose angeordnet, die beim Herstellen der Beton- oder Stahlbetondecke ein Eindringen von flüssigem Beton in den Bereich der Aufnahme des Sprinklers verhindern soll. Weiterhin wird ein Messingverschluss in der Aufnahme für den Sprinkler angeordnet, so dass die Aufnahme vor Schmutz geschützt ist. Die so vorbereitete Verbindung wird mit dem Unterteil der Sprinkleranschlussdose derart verbunden, dass Ober- und Unterteil der Sprinkleranschlussdose betondicht miteinander verbunden werden.Other such arrangements exist for. B. from a lower part of a sprinkler junction box, which is fastened by means of screws or nails on a formwork. The connection cable is connected to a connection area of a fitting. At a second connection region of the fitting, a transition piece is arranged, which has a receptacle for a sprinkler on the side facing away from the fitting. About this recording a top of a sprinkler junction box is arranged to prevent the ingress of liquid concrete in the area of the inclusion of the sprinkler in the manufacture of concrete or reinforced concrete slab. Furthermore, a brass closure is placed in the receptacle for the sprinkler, so that the recording is protected from dirt. The compound thus prepared is connected to the lower part of the sprinkler connection box in such a way that the upper and lower part of the sprinkler connection box are connected to one another in a concrete-tight manner.
Ein Nachteil wird darin gesehen, dass nach dem Anordnen mehrerer Anordnungen für die Anschlussmöglichkeit von Sprinklern auf einer Verschalung auch aufgrund der Vielzahl an Leitungen, die auf der Verschalung verlegt werden, es nur schwer möglich ist, die genaue Position zu erkennen und zu kontrollieren, ob alle Anschlussmöglichkeiten verlegt wurden. Weiterhin besteht das Problem, dass nach dem Aushärten des Betons die Verschalung entfernt wird und die Unterteile der Sprinkleranschlussdosen an dieser befestigt sind. Somit werden diese mit der Verschalung von den Oberteilen der Sprinkleranschlussdosen entfernt, ohne dass an diesen Stellen besonderes vorsichtig gearbeitet werden muss, um eine Beschädigung der Oberteile, die in der Betondecke verbleiben, zu vermeiden.A disadvantage is seen in the fact that after arranging a plurality of arrangements for the possibility of connecting sprinklers on a formwork also due to the large number of lines that are laid on the casing, it is difficult to detect the exact position and to check whether all connection options were laid. Furthermore, there is the problem that after curing of the concrete, the casing is removed and the lower parts of the sprinkler connection boxes are attached to this. Thus, these are removed with the casing from the tops of the sprinkler connection boxes, without special care must be taken at these locations in order to avoid damage to the tops that remain in the concrete floor.
Weiterhin ist es in den meisten Fällen nicht möglich die Unterteile der Sprinkleranschlussdosen bei einer anderen Decke wieder zu verwenden, da sie aufgrund der Krafteinwirkung zerstört oder beschädigt werden.Furthermore, it is in most cases not possible to reuse the lower parts of the sprinkler junction boxes in another ceiling, because they are destroyed or damaged due to the force.
Hier setzt die Erfindung ein, die es sich zur Aufgabe gestellt hat, die Nachteile des Standes der Technik zu vermeiden.This is where the invention, which has set itself the task of avoiding the disadvantages of the prior art.
Erfindungsgemäß wird diese Aufgabe durch die Kombination der Merkmale des Anspruches 1 gelöst.According to the invention this object is achieved by the combination of the features of
Bei der erfindungsgemäßen Anordnung sind die Nachteile des Standes der Technik dadurch vermieden, dass das Befestigungselement durch die Verschalung hindurchgeführt ist und somit eine Kontrolle der Position jeder Anschlussmöglichkeit von der Unterseite jederzeit möglich ist, ohne dass ein zeitaufwändiges Suchen in den auf der Verschalung verlegten Rohrleitungen und Armierungen notwendig ist.In the arrangement according to the invention, the disadvantages of the prior art are avoided in that the fastener is passed through the casing and thus controlling the position of each connection option from the bottom is possible at any time, without a time-consuming search in the laid on the casing piping and Reinforcements is necessary.
Da die das Befestigungselement bereichsweise umschließende Dose auf der Verschalung aufliegt und über das Befestigungselement mittels des Befestigungsmittels gegen die Verschalung gepresst wird, kann beim Vergießen des Betons kein Beton in die Dose eindringen und somit das Befestigungselement und der zweite Anschlussbereich des Fittings frei von Betonanlagerungen gehalten werden. Damit ist das Befestigungselement nach dem Aushärten des Betons und des entfernen der Verschalung demontierbar und wieder verwendbar.Since the fastener partially encloses the box rests on the casing and is pressed over the fastener by means of the fastener against the casing, no concrete can penetrate into the can when pouring the concrete and thus the fastener and the second terminal portion of the fitting are kept free of Betonanlagerungen , Thus, the fastener after curing of the concrete and the removal of the casing is removable and reusable.
Durch die Befestigung der Anordnung über ein an der dem Fitting abgewandten Seite der Verschalung angeordnetes Befestigungsmittel kann das Unterteil einer Sprinkleranschlussdose entfallen, da dieses von der Verschalung ersetzt wird. Somit ist zusätzlich eine Materialeinsparung möglich.By fastening the arrangement via a fastening means arranged on the side facing away from the fitting, the lower part of a sprinkler connection box can be dispensed with, since this is replaced by the shuttering. Thus, an additional material saving is possible.
Es hat sich gezeigt, dass die Verwendung eines aus zwei Teilen bestehenden Befestigungselementes günstig sein kann. Dies vor allem dann, wenn der zweite Anschlussbereich des Fittings in seinem Durchmesser größer ausgebildet ist als der Anschlussbereich des einzusetzenden Sprinklers. Um die Anzahl der verschiedenen Befestigungselemente zu reduzieren wurde erkannt, dass ein Adapter für die entsprechende Durchmesserreduzierung verwendet werden kann, der auf den Durchmesser des Sprinklers abgestimmt ist. Somit kann dieser Adapter auch gleich für das Verbinden mit dem Sprinkler verwendet werden. Da der Sprinkler aber an der Unterseite der Beton- oder Stahlbetondecke angeordnet ist, kann der Adapter in der Länge nicht so gestaltet sein, dass er eine Befestigung auf der dem Fitting abgewandten Seite der Verschalung ermöglicht.It has been found that the use of a two-part fastener can be beneficial. This is especially true if the diameter of the second connection region of the fitting is greater than the connection region of the sprinkler to be used. In order to reduce the number of different fasteners it has been recognized that an adapter can be used for the corresponding diameter reduction, which is matched to the diameter of the sprinkler. Thus, this adapter can also be used immediately for connecting to the sprinkler. However, since the sprinkler is located at the bottom of the concrete or reinforced concrete deck, the length of the adapter can not be designed to permit attachment to the side of the casing facing away from the fitting.
Um dies dennoch zu erreichen ist daher ein Verlängerungselement vorgesehen, das mit dem Adapter verbunden ist. Die Verlängerungselemente sind dadurch nur noch in den Durchmesserabmessung der Durchmesser der Anschlussbereiche der Sprinkler notwendig. Bei dieser Ausführungsvariante ist der Adapter vollständig von der Dose umgeben.To achieve this, however, therefore, an extension element is provided which is connected to the adapter. The extension elements are therefore only necessary in the diameter dimension of the diameter of the connection areas of the sprinklers. In this embodiment, the adapter is completely surrounded by the can.
In erwünschter Weise ermöglichen Schraubverbindungen zwischen Fitting und Befestigungselement oder Fitting und Adapter und/oder Adapter und Verlängerungselement eine einfache Montage und Demontage.Desirably, screw connections between the fitting and fastener or fitting and adapter and / or adapter and extension element allow easy assembly and disassembly.
Es hat sich gezeigt, dass wenn das Befestigungselement auf der dem Fitting abgewandten Seite ein Gewinde aufweist, eine kontinuierliche Befestigung mittels des Befestigungsmittels möglich ist. Somit kann die Dose gegen die Verschalung definiert gepresst werden.It has been shown that when the fastener on the side facing away from the fitting has a thread, a continuous attachment by means of the fastening means is possible. Thus, the box can be pressed defined against the shuttering.
In diesem Zusammenhang hat sich auch gezeigt, dass es günstig ist, wenn das Befestigungsmittel eine Mutter mit Innengewinde ist. Diese kann auf den Gewindeabschnitt des Befestigungsmittels aufgeschraubt werden und stellt so eine einfache und kostengünstige Möglichkeit der Befestigung dar.In this context, it has also been shown that it is favorable if the fastening means is a female threaded nut. This can be screwed onto the threaded portion of the fastener and thus provides a simple and cost-effective way of attachment.
Es kann vorteilhaft sein, zwischen der Mutter und der Verschalung eine Unterlegscheibe anzuordnen, um ein Eindringen in die meist aus Holz bestehende Verschalung zu verhindern und eine einfache Demontage zu gewährleisten. Auch kann mit der Unterlegscheibe eine zu große Öffnung in der Verschalung abgedeckt werden, so dass ein sicheres Anziehen des Befestigungsmittels, insbesondere der Mutter gewährleistet werden kann.It may be advantageous to arrange a washer between the nut and the casing in order to prevent penetration into the usually made of wood casing and to ensure easy disassembly. Also, a too large opening in the casing can be covered with the washer, so that a secure tightening of the fastening means, in particular the mother can be ensured.
Weiterhin umfasst die Erfindung ein Verfahren zum Herstellen einer Anschlussmöglichkeit für einen Sprinkler an einer durch eine Schalung begrenzten Beton- oder Stahlbetondecke.Furthermore, the invention comprises a method for producing a connection possibility for a sprinkler on a limited by a formwork concrete or reinforced concrete ceiling.
Das Verfahren sieht vor, dass zuerst ein Befestigungselement mit einem ersten Anschlussbereich eines Fittings verbunden wird. Der Fitting kann dabei ein Bogen oder Abzweig, insbesondere ein T-Stück sein. Danach wird über das Befestigungselement eine Dose angeordnet, welche im Wesentlichen zylinderförmig ausgebildet ist und an einem Ende eine mit einem Durchbruch versehene Wand aufweist. Der Durchbruch ist dabei so gestaltet, dass die Dose an einem Bund des ersten Anschlussbereichs des Fittings dicht anlegbar ist. Der zylindrische Bereich der Dose umgibt dabei einen Teil des Befestigungselements, so dass ein kreisringförmiger Hohlraum umschlossen wird.The method provides that first a fastener is connected to a first terminal portion of a fitting. The fitting can be a bow or branch, in particular a T-piece. Thereafter, a can is arranged via the fastening element, which is essentially cylindrical and has at one end a wall provided with an opening. The breakthrough is designed so that the can is tightly applied to a collar of the first connection area of the fitting. The cylindrical portion of the can surrounds a part of the fastening element, so that an annular cavity is enclosed.
Das Befestigungselement steht über die Dose nach deren Anlage am Bund des ersten Anschlussbereichs des Fittings über. Dieser überstehende Bereich des Befestigungselements wird anschließend durch eine Öffnung in der Schalung geführt. Dazu ist es vorher notwendig, dass diese Öffnung in die meist aus Holz hergestellte Verschalung eingebracht wird. Nachdem das Befestigungselement durch die Öffnung hindurchgeführt wurde, wird es auf der dem Fitting abgewandten Seite der Verschalung mittels eines Befestigungsmittels befestigt. Danach wird die Verbindung zwischen mindestens einer Wasserleitung und einem zweiten Anschlussbereich des Fittings hergestellt. Nun können weitere Verlegearbeiten auf der Verschalung durchgeführt werden. Auch können Bewehrungsmatten eingebracht werden, die eine Erhöhung der Stabilität der Decke erreichen. Danach wird der Beton auf die Schalung eingebracht. Dieser kann durch die Befestigung mittels eines Befestigungsmittels auf der dem Fitting abgewandten Seite der Verschalung nicht in die Dose, die dadurch auf die Verschalung gedrückt wird, eindringen, so dass kein Beton an den zweiten Anschlussbereich des Fittings und an das Befestigungselement gelangen kann.The fastener overhangs the can after it abuts the collar of the first port of the fitting. This projecting portion of the fastener is then passed through an opening in the formwork. For this it is necessary in advance that this opening is introduced into the mostly made of wood casing. After the fastener has been passed through the opening, it is fastened on the side facing away from the fitting of the casing by means of a fastening means. Thereafter, the connection between at least one water pipe and a second connection region of the fitting is made. Now further laying work can be carried out on the shuttering. Also, reinforcement mats can be introduced, which achieve an increase in the stability of the ceiling. Thereafter, the concrete is placed on the formwork. This can not penetrate into the can, which is thereby pressed onto the casing by the attachment by means of a fastening means on the side facing away from the fitting, so that no concrete can reach the second connection region of the fitting and the fastener.
Nach dem Aushärten des Betons kann das Befestigungselement vom Fitting demontiert werden. Somit kann die Verschalung von der Decke ohne Rücksicht auf die Anschlussmöglichkeiten für die Sprinkler entfernt werden.After curing of the concrete, the fastener can be removed from the fitting. Thus, the shuttering can be removed from the ceiling without regard to the connection possibilities for the sprinklers.
Im Anschluss daran, wird ein Sprinkler mit dem ersten Anschlussbereich des Fittings verbunden. Da der Sprinklerkörper unterhalb der Decke angeordnet sein muss, kann es notwendig sein, einen Adapter zwischen Sprinkler und erstem Anschlussbereich des Fittings einzusetzen. Dieser Adapter kann so ausgebildet sein, dass auch Durchmesserunterschiede zwischen den Anschlussbereichen des Fittings und des Sprinklers überbrückt werden können. In diesem Zusammenhang wurde erkannt, dass der Adapter entweder zuerst mit dem Sprinkler und dann beide gemeinsam mit dem ersten Anschlussbereich des Fittings verbunden werden oder aber, dass zuerst der Adapter mit dem ersten Anschlussbereich des Fitting und danach der Sprinkler mit dem Adapter verbunden wird.Subsequently, a sprinkler is connected to the first connection area of the fitting. Since the sprinkler body must be located below the ceiling, it may be necessary to insert an adapter between the sprinkler and the first connection area of the fitting. This adapter can be designed so that also diameter differences between the connection areas of the fitting and the sprinkler can be bridged. In this regard, it has been recognized that the adapter is connected either first to the sprinkler and then both together to the first port of the fitting, or first to connect the adapter to the first port of the fitting and then the sprinkler to the adapter.
Es hat sich weiterhin gezeigt, dass es vorteilhaft sein kann, wenn das Befestigungselement aus zwei Teilen aufgebaut ist. Dabei kann das Befestigungselement aus einem Adapter und einem Verlängerungselement bestehen. Da es in den meisten Anwendungsfällen notwendig ist einen Adapter zwischen dem ersten Anschlussbereich des Fittings und dem Sprinkler anzuordnen, kann dieser schon als ein Teil des Befestigungselements eingebracht werden.It has also been shown that it can be advantageous if the fastening element is constructed from two parts. In this case, the fastening element consist of an adapter and an extension element. Since it is necessary in most applications to arrange an adapter between the first connection region of the fitting and the sprinkler, this can already be introduced as part of the fastening element.
Da dieser Adapter von der Dose vollständig umgeben ist, ist ein Durchführen durch die Schalung nicht möglich. Um dies dennoch zu gewährleisten wird der Adapter mit einem Verlängerungselement verbunden, das die fehlende Länge überbrückt. Es wurde erkannt, dass sowohl zuerst der Adapter mit dem ersten Anschlussbereich des Fittings oder aber zuerst der Adapter mit dem Verlängerungselement verbunden werden kann.Since this adapter is completely surrounded by the box, it is not possible to pass through the formwork. To still ensure this, the adapter is connected to an extension element that bridges the missing length. It has been recognized that both the adapter with the first terminal portion of the fitting or first the adapter with the extension element can be connected.
Da das Verlängerungselement nach dem Aushärten des Betons wieder entfernt werden muss um einen Sprinkler anzubringen, ist zwischen dem Adapter und dem Verlängerungselement eine lösbare Verbindung, insbesondere eine Schraubverbindung, notwendig.Since the extension element has to be removed again after the concrete has hardened in order to attach a sprinkler, a releasable connection, in particular a screw connection, is necessary between the adapter and the extension element.
Somit ist es möglich nur das Verlängerungselement nach dem Aushärten des Betons zu entfernen und danach einen Sprinkler mit dem Adapter zu verbinden.Thus, it is possible to remove only the extension element after curing of the concrete and then connect a sprinkler with the adapter.
Um nach der Montage des Sprinklers nicht in die Dose schauen zu können, hat es sich als günstig erwiesen vor der Montage des Sprinklers eine Abdeckung auf der Dose an der Decke anzuordnen, die einen Durchgang für den Sprinkler aufweist. Diese Abdeckung kann auch mittels des Sprinklers an der Dose/Decke befestigt werden.In order not to look into the can after mounting the sprinkler, it has proven to be beneficial before installing the sprinkler to arrange a cover on the box on the ceiling, which has a passage for the sprinkler. This cover can also be attached to the can / ceiling by means of the sprinkler.
Die Erfindung soll nun an einem diese nicht einschränkenden Ausführungsbeispiel näher beschrieben werden. Es zeigt:
- Figur 1 -
- Schnitt durch eine an einer Schalung montierte erfindungsgemäße Anordnung zum Herstellen einer Anschlussmöglichkeit, insbesondere für einen Sprinkler an einer Beton- oder Stahlbetondecke
- FIG. 1 -
- Section through a mounted on a formwork arrangement according to the invention for producing a connection option, in particular for a sprinkler on a concrete or reinforced concrete ceiling
In
Sowohl Fitting (3) und Adapter (4a) als auch Adapter (4a) und Verlängerungselement (4b) sind hierbei über eine Schraubverbindung miteinander verbunden. Der Adapter (4a) ist in diesem Beispiel so gestaltet, dass er eine Art Reduzierstück darstellt, da der Anschlussbereich (2a) des Fittings (3) eine größere Abmessung aufweist, als der später zu befestigende Sprinkler.Both fitting (3) and adapter (4a) and adapter (4a) and extension element (4b) are connected to each other via a screw connection. The adapter (4a) is designed in this example to be a kind of reducer, since the connection area (2a) of the fitting (3) has a larger dimension than the sprinkler to be attached later.
Weiterhin weist die Anordnung eine Dose (5) auf, die das Befestigungselement (4a, 4b) bereichsweise umschließt, auf. Diese Dose (5) ist an einem Bund (6) des nicht mit einer Rohrleitung (1) verbundenen Anschlussbereichs (2a) des Fittings (3) angeordnet, so dass ihre Lage in Bezug auf den Fitting (3) definiert ist. In diesem Ausführungsbeispiel ist die Dose (5) aus Metall, es sind aber auch andere Materialien denkbar, die die Vorschriften im Brandfall erfüllen und keine Funktionseinschränkungen des Sprinklers im Brandfall hervorrufen. Es ist auch möglich, wie in diesem Beispiel eine Dichtung (12) zwischen der Dose (5) und dem Bund (6) des Fittings (3) anzuordnen, um sicher ein Eindringen von Beton an dieser Stelle zu vermeiden.Furthermore, the arrangement has a can (5) which surrounds the fastening element (4a, 4b) in regions. This can (5) is arranged on a collar (6) of the connection area (2a) of the fitting (3) which is not connected to a pipeline (1), so that its position relative to the fitting (3) is defined. In this embodiment, the can (5) made of metal, but there are also other materials conceivable that meet the requirements in case of fire and cause no functional restrictions of the sprinkler in case of fire. It is also possible, as in this example, to place a seal (12) between the can (5) and the collar (6) of the fitting (3) to safely prevent the ingress of concrete at this point.
Die
An der dem Fitting (3) abgewandten Seite der Verschalung (7) ist an dem Befestigungselement (4a, 4b) ein Befestigungsmittel (8) in Form einer Mutter angeordnet. Diese ist über das in diesem Ausführungsbeispiel an dem Fitting (3) abgewandten Ende des Verlängerungselements (4b) befindlichen Gewindes mit dem Befestigungselement (4a, 4b), insbesondere dem Verlängerungselement (4b) verbunden. Es sind aber auch andere Befestigungsmittel (8), wie Klemmen oder dergleichen möglich.On the side facing away from the fitting (3) of the casing (7), a fastening means (8) in the form of a nut is arranged on the fastening element (4a, 4b). The latter is connected to the fastening element (4a, 4b), in particular the extension element (4b), via the thread situated in the embodiment facing away from the fitting (3) at the end of the extension element (4b). But there are also other fastening means (8), such as terminals or the like possible.
Aus der
Um bei der Demontage des Verlängerungselements (4b) dieses leicht vom Adapter (4a) lösen zu können, hat es sich gezeigt, dass es vorteilhaft ist, wenn ein leicht lösbares Dichtmittel, insbesondere ein Teflonband in das Gewinde mit eingebracht wird. Im Gegensatz dazu soll der Adapter (4a) beim Demontieren des Verlängerungselements (4b) nicht herausgedreht werden. Auch soll der Adapter (4a) fluiddicht mit dem Fitting (3) verbunden sein. Hierzu hat sich die Verwendung eines schwer lösbaren Dichtmittels, insbesondere Hanf als günstig erwiesen.In order to be able to easily detach this from the adapter (4a) during disassembly of the extension element (4b), it has been shown that it is advantageous if an easily detachable sealing means, in particular a Teflon tape, is introduced into the thread. In contrast, the adapter (4a) when disassembling the extension element (4b) should not be unscrewed. Also, the adapter (4a) should be fluid-tightly connected to the fitting (3). For this purpose, the use of a hard-to-release sealant, especially hemp has proven to be beneficial.
Diese in
Bei der Verwendung eines einteiligen Befestigungselements, ist eine lösbare Verbindung zwischen dem Anschlussbereich (2a) des Fittings (3) und des Befestigungselements notwendig, da das Befestigungselement nach dem Fertigstellen der Beton- oder Stahlbetondecke wieder entfernt werden muss.When using a one-piece fastener, a detachable connection between the connection portion (2a) of the fitting (3) and the fastener is necessary because the fastener must be removed after completion of the concrete or reinforced concrete ceiling.
Nachdem der Adapter (4a) mit dem Anschlussbereich (2a) des Fittings (3) verbunden wurde, wird in diesem Beispiel das Verlängerungselement (4b) mit dem Adapter (4a) über eine Schraubverbindung lösbar verbunden. Der Anschlussbereich des Verbindungselements (4b) hin zum Adapter (4a) ist dabei im Durchmesser genauso gestaltet, wie der später einzusetzende Sprinkler. Aufgrund der Zweiteilung des Befestigungselements (4a, 4b), ist es möglich für verschiedene Abmessungen der Anschlussbereiche (2a) des Fittings (3) nur unterschiedliche Adapter (4a) zu verwenden, wohingegen das Verlängerungselement (4b) in der Variantenanzahl nur auf die verschiedenen Sprinklerabmessungen abgestimmt sein muss.After the adapter (4a) has been connected to the connection region (2a) of the fitting (3), in this example the extension element (4b) is detachably connected to the adapter (4a) via a screw connection. The connection region of the connecting element (4b) to the adapter (4a) is designed in the same diameter as the later to be used sprinkler. Due to the division of the fastening element (4a, 4b), it is possible to use only different adapters (4a) for different dimensions of the connection regions (2a) of the fitting (3), whereas in the number of variants the extension element (4b) only applies to the different sprinkler dimensions must be coordinated.
Nun wird die Dose (5) mit einer Dichtung (12) über das Befestigungselement (4a, 4b) aufgeschoben, bis die Dose (5) mit der Dichtung (12) an dem Bund (6) des Anschlussbereichs (2a) des Fittings (3) anliegt. Es ist jedoch nicht zwingend erforderlich eine Dichtung (12) einzusetzten. Dies ist besonders dann von Vorteil, wenn die Beschaffenheit des Betons eine zusätzliche Abdichtung erfordert. Danach wird das Befestigungselement (4a, 4b), insbesondere das Verlängerungselement (4b) durch eine in die Schalung (7) eingebrachte Öffnung (9) hindurchgeführt. Die Öffnung (9) entspricht dabei in etwa dem Querschnitt des Befestigungselements (4a, 4b), insbesondere des Verlängerungselements (4b). Nun ragt das Befestigungselement (4a, 4b), insbesondere das Verlängerungselement (4b) auf der einen Seite der Verschalung (7) heraus und auf der anderen Seite der Verschalung (7) ist die Dose (5) mit der Schalung (7) in Berührung.Now the can (5) with a seal (12) on the fastening element (4a, 4b) pushed until the can (5) with the seal (12) on the collar (6) of the connection portion (2a) of the fitting (3 ) is present. However, it is not mandatory to use a seal (12). This is particularly advantageous if the nature of the concrete requires additional sealing. Thereafter, the fastening element (4a, 4b), in particular the extension element (4b) is passed through an opening (9) introduced into the formwork (7). The opening (9) corresponds approximately to the cross section of the fastening element (4a, 4b), in particular of the extension element (4b). Now the fastening element (4a, 4b), in particular the extension element (4b) protrudes on one side of the casing (7) and on the other side of the casing (7) the can (5) is in contact with the formwork (7) ,
Da beim Einbringen des Betons für eine Beton- oder Stahlbetondecke der Fitting (3) mit dem Adapter (4a), dem Verlängerungselement (4b) und der Dose (5) aufschwimmen würde, wird auf der dem Fitting (3) abgewandten Seite der Verschalung (7) ein Befestigungsmittel (8) mit dem Befestigungselement (4a, 4b), insbesondere mit dem Verlängerungselement (4b) verbunden. In diesem Beispiel ist die Verbindung als Schraubverbindung ausgeführt, wobei das Befestigungselement (4a, 4b), insbesondere das Verlängerungselement (4b) an seiner dem Adapter (4a) abgewandten Seite ein Gewinde aufweist und das Befestigungsmittel (8) als Mutter ausgebildet ist. Um das spätere Lösen der Mutter zu vereinfachen, ist zwischen Verschalung (7) und Mutter eine Unterlegscheibe (10) angeordnet.Since during the introduction of the concrete for a concrete or reinforced concrete ceiling the fitting (3) with the adapter (4a), the extension element (4b) and the box (5) would float, is on the side facing away from the fitting (3) of the shuttering ( 7) a fastening means (8) with the fastening element (4a, 4b), in particular connected to the extension element (4b). In this example, the connection is designed as a screw connection, wherein the fastening element (4a, 4b), in particular the extension element (4b) on its side facing away from the adapter (4a) has a thread and the fastening means (8) is designed as a nut. To simplify the subsequent release of the nut, a washer (10) is arranged between the casing (7) and nut.
Nun wird über das Befestigungsmittel (8) die Dose (5) auf der Verschalung (7) fixiert, so dass beim Einbringen des Betons diese nicht aufschwimmen kann und auch kein Beton zwischen Verschalung (7) und Dose (5) eindringen kann.Now the box (5) on the casing (7) is fixed on the fastening means (8), so that during the introduction of the concrete, these can not float and no concrete between the shuttering (7) and can (5) can penetrate.
Dieser Vorgang wird für alle Anordnungen zum Herstellen einer Anschlussmöglichkeit für die zu bestückende Beton- oder Stahlbetondecke wiederholt. Nachdem alle Anordnungen angebracht wurden, kann von der Unterseite der Verschalung (7) aus kontrolliert werden, ob alle Positionen mit dem Plan übereinstimmen. Dies ist besonders leicht möglich, da die Befestigungselemente (4a, 4b), insbesondere die Verlängerungselemente (4b) und die Befestigungsmittel (8) auf der den Fittingen (3) abgewandten Seite der Verschalung (7) sichtbar sind und die Position somit leicht erkennbar ist.This process is repeated for all arrangements for establishing a connection possibility for the concrete or reinforced concrete floor to be equipped. After all arrangements have been made, it is possible to check from the bottom of the casing (7) whether all positions correspond to the plan. This is particularly easy because the fastening elements (4a, 4b), in particular the extension elements (4b) and the fastening means (8) on the side facing away from the fittings (3) of the casing (7) are visible and the position is thus easily recognizable ,
im Anschluss an die Positionierung und Befestigung des Fittings (3) mit dem Befestigungselement (4a, 4b), der Dose (5) und dem Befestigungsmittel (8), werden Rohrleitungen (1) mit dem/den noch freien Anschlussbereich/-en (2b) verbunden. Dies geschieht im Allgemeinen durch Aufweiten des Rohrendes und Aufschieben auf den Anschlussbereich (2b) des Fittings (3). Danach wird eine Verpressung des Rohrendes mit dem Fitting (3) durchgeführt. Dies kann über eine radial verpressbare Presshülse, oder durch den Einsatz einer Schiebehülse (11) geschehen.following the positioning and fastening of the fitting (3) with the fastening element (4a, 4b), the box (5) and the fastening means (8), pipelines (1) are connected to the still free connection area (s) (2b ) connected. This is generally done by widening the pipe end and sliding it onto the connection area (2b) of the fitting (3). Thereafter, a compression of the pipe end with the fitting (3) is performed. This can be done via a radially compressible compression sleeve, or by the use of a sliding sleeve (11).
Die Rohrleitungen (1) werden meist so verlegt, dass zwischen den einzelnen Anordnungen ein geschlossener Ring mit einer einseitigen oder zweiseitigen Speisung oder aber einzelne Stränge, die nur von einer Seite gespeist werden, entstehen. Aus diesen Anordnungen ergeben sich die für die einzelnen Anordnungen zu verwendenden Fittingausgestaltungen.The pipes (1) are usually laid so that between the individual arrangements a closed ring with a one-sided or two-sided feed or individual strands, which are fed from one side, arise. These arrangements result in the fitting configurations to be used for the individual arrangements.
Nachdem alle Rohrleitungen (1) angeschlossen wurden, wird eine Druckprüfung, insbesondere nach VdS CEA 4001, durchgeführt. Diese ermöglicht es, mögliche undichte Stellen vor dem Einbringen des Betons zu erkennen und zu beheben. Dabei dient das Befestigungselement (4a, 4b) als Stopfen, der den Anschlussbereich, an dem später der Sprinkler angeschlossen wird, gegenüber der Umwelt abdichtet und so die Druckprüfung erst ermöglicht. Wird kein bzw. ein im Toleranzbereich liegender Druckabfall festgestellt, kann der Beton auf die Verschalung (7) eingebracht werden.After all pipes (1) have been connected, a pressure test is carried out, in particular according to VdS CEA 4001. This makes it possible to detect and eliminate possible leaks before the concrete is introduced. In this case, the fastening element (4a, 4b) serves as a plug which seals against the environment the connection area, at which the sprinkler is later connected, and thus enables the pressure test. If no or a pressure drop in the tolerance range is detected, the concrete can be placed on the casing (7).
Es ist auch möglich vor dem Einbringen des Betons noch weitere nicht für eine Sprinkleranlage notwendige Rohrleitungen, sowie Kabel und Verstärkungselemente, insbesondere Bewehrungsmatten oder dergleichen einzubringen.It is also possible before the introduction of the concrete even more not necessary for a sprinkler system piping, as well as cables and reinforcing elements, in particular reinforcing mats or the like to bring.
Nachdem der Beton eingebracht wurde, wird nochmals eine Druckprüfung, insbesondere nach VdS CEA 4001, durchgeführt. Diese dient zur Kontrolle der Dichtheit. Danach muss der Beton austrocknen und aushärten. Ist dies erfolgt, können die Befestigungsmittel (8), insbesondere die Muttern entfernt werden. Nun können die Verschalung (7) und die Befestigungselemente (4a, 4b), insbesondere die Verlängerungselemente (4b) demontiert werden. Im Anschluss daran wird ein Sprinkler mit dem freien Anschlussbereich (2a) des Fittings (3) oder dem Adapter (4a) verbunden. In den Fällen, wo aus optischen Gesichtspunkten die Dose (5) nicht offen in der Beton- oder Stahlbetondecke erkennbar sein soll kann eine Abdeckung vor dem Anbringen des Sprinklers angeordnet werden.After the concrete has been introduced, another pressure test is carried out, in particular according to VdS CEA 4001. This serves to control the tightness. Thereafter, the concrete must dry out and harden. Once this is done, the fastening means (8), in particular the nuts can be removed. Now the shuttering (7) and the fastening elements (4a, 4b), in particular the extension elements (4b) can be dismantled. Following this, a sprinkler is connected to the free connection area (2a) of the fitting (3) or the adapter (4a). In cases where, from an optical point of view, the can (5) should not be visible in the concrete or reinforced concrete ceiling, a cover can be arranged before attaching the sprinkler.
Claims (13)
- Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, comprising- at least one pipeline (1) which is connected to a first connection region (2a) of a fitting (3),- a fastening element (4a, 4b) which is detachably connected to a second connection region (2b) of the fitting (3),- a box (5) which surrounds the fastening element (4a, 4b) in certain regions and which is arranged on a collar (6) of the second connection region (2b) of the fitting (3), and- a shuttering (7), wherein- the fastening element (4a, 4b) is led through the shuttering (7) for delimiting the concrete or reinforced concrete floor and, on its side facing away from the fitting (3), is fixed to the shuttering (7) of the concrete or reinforced concrete floor using a fastening means (8).
- Arrangement according to Claim 1, characterized in that the fastening element (4a, 4b) consists of two parts, in particular an adapter (4a) and an extension element (4b), which are detachably connected to one another.
- Arrangement according to Claim 1 or 2, characterized in that the fitting (3) and the fastening element (4a, 4b) or the fitting (3) and the adapter (4a) and/or the adapter (4a) and the extension element (4b) are connected by a screwed connection.
- Arrangement according to at least one of the preceding claims, characterized in that the fastening element (4a, 4b) has a thread on the side facing away from the fitting (3).
- Arrangement according to Claim 4, characterized in that in that the fastening means (8) takes the form of a nut.
- Method for producing a connection possibility for a sprinkler on a concrete or reinforced concrete floor delimited by a shuttering (7), comprising the following method steps:- connecting a fastening element (4a, 4b) to a first connection region (2a) of a fitting (3),- arranging a box (5), which encloses the fastening element (4a, 4b) in certain regions, on a collar (6) of the first connection region (2a) of the fitting (3),- leading the fastening element (4a, 4b) through an opening (9) in the shuttering (7),- fastening the fastening element (4a, 4b) to the shuttering (7) using a fastening means (8) which is arranged on the side of the shuttering (7) facing away from the fitting (3),- producing a connection between at least one water line (1) and a second connection region (2b) of the fitting (3), and- pouring the concrete onto the shuttering (7).
- Method according to Claim 6, characterized in that, after the concrete has cured, the fastening element (4a, 4b) is removed from the fitting (3).
- Method according to Claim 7, characterized in that a sprinkler is then connected to the first connection region (2a) of the fitting (3).
- Method according to Claim 8, characterized in that, prior to connecting the sprinkler, the latter is connected to an adapter (4a) and the adapter (4a) is connected to the first connection region (2a) of the fitting (3).
- Method according to Claim 6, characterized in that the fastening element (4a, 4b) consists of two parts, in particular an adapter (4a) for connecting to the first connection region (2a) of the fitting (3), and an extension element (4b), which are detachably connected to one another before connecting to the first connection region (2a) of the fitting (3).
- Method according to Claim 10, characterized in that, after the concrete has cured, only the extension element (4b) is removed from the adapter (4a) and the adapter (4a) remains connected to the fitting (3).
- Method according to Claim 11, characterized in that a sprinkler is then connected to the adapter (4a).
- Method according to at least one of Claims 8, 9 and 12, characterized in that, prior to mounting the sprinkler, a cover which has an opening for the sprinkler is arranged on the box (5).
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102008008570A DE102008008570A1 (en) | 2008-02-11 | 2008-02-11 | Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor |
PCT/EP2009/000840 WO2009100860A1 (en) | 2008-02-11 | 2009-02-06 | Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2247346A1 EP2247346A1 (en) | 2010-11-10 |
EP2247346B1 true EP2247346B1 (en) | 2011-11-02 |
Family
ID=40577928
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP20090710950 Not-in-force EP2247346B1 (en) | 2008-02-11 | 2009-02-06 | Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor |
Country Status (6)
Country | Link |
---|---|
US (1) | US20110017314A1 (en) |
EP (1) | EP2247346B1 (en) |
AT (1) | ATE531429T1 (en) |
AU (1) | AU2009214387B2 (en) |
DE (1) | DE102008008570A1 (en) |
WO (1) | WO2009100860A1 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102009041415A1 (en) | 2009-09-16 | 2011-03-24 | Minimax Gmbh & Co. Kg | Method and device for producing a connection possibility |
DE102010012209A1 (en) * | 2010-03-19 | 2011-09-22 | Rehau Ag + Co. | Arrangement for manufacturing connection facility for connecting sprinkler at e.g. reinforced concrete ceiling, has shell designed as solid component and arranged in space between box and adaptor, where shell partly rests inside box |
DE102010015022A1 (en) * | 2010-04-14 | 2011-10-20 | Rehau Ag + Co. | House installation pipe system and its use |
EP2586934B1 (en) * | 2011-10-27 | 2017-12-06 | Georg Fischer JRG AG | Sprinkler connection box |
US9303419B2 (en) * | 2012-09-28 | 2016-04-05 | Tyco Fire Products Lp | Concrete mold for sprinkler installation and installation method |
AU2013202548B2 (en) * | 2012-09-28 | 2016-07-28 | Tyco Fire Products Lp | Concrete mold for sprinkler installation and installation method |
CN112975744B (en) * | 2021-02-04 | 2022-12-16 | 哈密豪建钢结构工程施工有限责任公司 | Workpiece fastening equipment for building |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US545928A (en) * | 1895-09-10 | Lead-pipe coupling | ||
US2012091A (en) * | 1933-05-24 | 1935-08-20 | John G Zollcis | Valve |
US2537678A (en) * | 1948-01-24 | 1951-01-09 | Koetting Fritz | Pipe joint for water heaters |
US2788380A (en) * | 1954-07-28 | 1957-04-09 | American Instr Co Inc | Thermocouple assembly for fluid lines |
ES347326A1 (en) * | 1966-11-24 | 1969-02-01 | Lanzoni | Two-fluid heat exchanger |
FR1518229A (en) * | 1967-04-07 | 1968-03-22 | Svenska Flaektfabriken Ab | Mussel improvement |
GB1221706A (en) * | 1968-10-22 | 1971-02-10 | Selbsttatige Feuerloschanlagen | Improvements in overhead sprinklers for dry-conduit automatic fire-extinguishing installations |
US3782704A (en) * | 1973-01-15 | 1974-01-01 | Schramm Inc | Apparatus and method for producing air bubbles in a body of liquid |
DE4215731A1 (en) * | 1992-05-13 | 1993-11-18 | Rene P Schmid | Process for erecting concrete walls using formwork, and device and means for carrying out this process |
US5794853A (en) * | 1996-08-06 | 1998-08-18 | Perkins; Lloyd | Institutional sprinkler head nipple |
DE10140942C1 (en) * | 2001-08-21 | 2003-08-14 | Preussag Ag Minimax | Feed system for an extinguishing agent comprises a flexible feed pipe arranged in a building material between a connection for the extinguishing agent and a connection for a nozzle |
DE102006011094A1 (en) * | 2006-03-08 | 2007-09-13 | Rsl Rodust & Sohn Lichttechnik Gmbh | Cover installation ring for sealing jar, has edge that is provided with bevel and is aligned towards cover, where ring is arranged in cover and has groove arranged at circumference of ring |
-
2008
- 2008-02-11 DE DE102008008570A patent/DE102008008570A1/en not_active Withdrawn
-
2009
- 2009-02-06 US US12/866,241 patent/US20110017314A1/en not_active Abandoned
- 2009-02-06 WO PCT/EP2009/000840 patent/WO2009100860A1/en active Application Filing
- 2009-02-06 AU AU2009214387A patent/AU2009214387B2/en not_active Ceased
- 2009-02-06 AT AT09710950T patent/ATE531429T1/en active
- 2009-02-06 EP EP20090710950 patent/EP2247346B1/en not_active Not-in-force
Also Published As
Publication number | Publication date |
---|---|
AU2009214387A1 (en) | 2009-08-20 |
WO2009100860A1 (en) | 2009-08-20 |
ATE531429T1 (en) | 2011-11-15 |
EP2247346A1 (en) | 2010-11-10 |
US20110017314A1 (en) | 2011-01-27 |
DE102008008570A1 (en) | 2009-08-13 |
AU2009214387B2 (en) | 2013-01-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2247346B1 (en) | Arrangement for producing a connection possibility, in particular for a sprinkler on a concrete or reinforced concrete floor, and method therefor | |
EP2955426B1 (en) | Construction kit for a pipe conduit connection | |
DE102008021920A1 (en) | Eccentric spiral pump has stator of flexible material and rotor supported in stator, where stator is area wise surrounded by stator core having two stator fitting lines | |
EP2663435B1 (en) | Admixture piece and housing element for a mixing device | |
EP1312848B1 (en) | Pipe coupling and method to achieve a pipe coupling | |
EP2586934B1 (en) | Sprinkler connection box | |
DE102010012209A1 (en) | Arrangement for manufacturing connection facility for connecting sprinkler at e.g. reinforced concrete ceiling, has shell designed as solid component and arranged in space between box and adaptor, where shell partly rests inside box | |
DE60128347T2 (en) | ATTACHING SHELL COMPONENTS TO PIPES | |
EP3154757B1 (en) | Method and apparatus for producing a sewer pipe element | |
EP1541781A1 (en) | Shuttering system with tensioning anchor, anchor and setup method for the shuttering system | |
EP2312088B1 (en) | Method and device for producing a point of connection in a concrete or reinforced concrete ceiling | |
EP0246219A1 (en) | Throughpass for a pipe | |
EP3449163B1 (en) | Pressure-tight flange connection and method for quick connection | |
DE2726672C3 (en) | Wall bushing for earth conductors, in particular earth straps | |
DE102014111691B4 (en) | Sealing arrangement on a building wall | |
EP2597344A1 (en) | Adapter ring to be inserted into a pipe element of a lead-through for conduits | |
DE202016102251U1 (en) | Pressure-tight flange connection | |
DE102020134023B4 (en) | Sleeve connection device, manufacturing method and method for integrating or renovating connections | |
EP2558762B1 (en) | Connection between a pipe and a pipe component | |
DE4108894A1 (en) | Loose flange connection for plastics pipe system - rests on support centring ring preventing curvature | |
DE102005030470A1 (en) | Process to produce assembly frame for sealing packing for wall repair whereby pipe containing sealing material around one end is guided into mold cavity which is then filled with thermosetting material | |
DE9414082U1 (en) | Wall duct with centering and sealing insert | |
DE8204255U1 (en) | CORROSION-RESISTANT TUBE | |
DE9415532U1 (en) | Self-sealing connecting element, especially for liquid media | |
DE102021103195A1 (en) | Sealing sleeve with clamping element for sealing an anchor clamping point on a concrete formwork |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20100826 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA RS |
|
RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: WEGESIN, JOHANNES Inventor name: REUTER, STEFAN |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502009001796 Country of ref document: DE Effective date: 20120112 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: T3 |
|
LTIE | Lt: invalidation of european patent or patent extension |
Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120202 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120302 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120203 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120302 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FD4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120202 Ref country code: IE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20120229 |
|
26N | No opposition filed |
Effective date: 20120803 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502009001796 Country of ref document: DE Effective date: 20120803 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20120213 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20130214 Year of fee payment: 5 Ref country code: FR Payment date: 20130222 Year of fee payment: 5 Ref country code: DE Payment date: 20130228 Year of fee payment: 5 Ref country code: CH Payment date: 20130208 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20130207 Year of fee payment: 5 Ref country code: BE Payment date: 20130207 Year of fee payment: 5 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20111102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20120206 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20090206 |
|
BERE | Be: lapsed |
Owner name: REHAU A.G. + CO Effective date: 20140228 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 502009001796 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: V1 Effective date: 20140901 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20140206 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140901 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140228 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140228 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20141031 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 502009001796 Country of ref document: DE Effective date: 20140902 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140228 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140228 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140902 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140206 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 531429 Country of ref document: AT Kind code of ref document: T Effective date: 20140206 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140206 |