EP2236677B1 - Method for creating a building under an architectural monument - Google Patents

Method for creating a building under an architectural monument Download PDF

Info

Publication number
EP2236677B1
EP2236677B1 EP10003429.7A EP10003429A EP2236677B1 EP 2236677 B1 EP2236677 B1 EP 2236677B1 EP 10003429 A EP10003429 A EP 10003429A EP 2236677 B1 EP2236677 B1 EP 2236677B1
Authority
EP
European Patent Office
Prior art keywords
loadbearing
building
piles
temporary
created
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Not-in-force
Application number
EP10003429.7A
Other languages
German (de)
French (fr)
Other versions
EP2236677A3 (en
EP2236677A2 (en
Inventor
Mägi Arvu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Amhold AS
Original Assignee
Amhold AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Amhold AS filed Critical Amhold AS
Publication of EP2236677A2 publication Critical patent/EP2236677A2/en
Publication of EP2236677A3 publication Critical patent/EP2236677A3/en
Application granted granted Critical
Publication of EP2236677B1 publication Critical patent/EP2236677B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block

Definitions

  • the invention belongs in the construction field, treating more specifically a method for creating a new building under and around an authentically preserved architectural monument, which is located on an infirm base.
  • a vertical dredging-type structural design is known ( JP4092020 , Obhayashi Corp, published on 25.03.1992), where the soil is excavated from beneath an existing building, using a method, where a steel-sheet cylinder is pressed down while using the existing building as the supporting points for the jack.
  • a cylinder-shaped shaft is dug into the soil and jacks are positioned between the upper edge of the shaft and the building. The shaft is pressed down with the compressive force of the jacks and with the inner concave. When the reaction force to the traction(repulsive) force of the jacks is removed, the shaft will sink in the bottom and a building can be created under the existing building without using temporary structures.
  • Another known method is that of producing an insulated foundation recess to an existing building ( JP 184144 , Taisei Corp, published on 15.07.1997).
  • the soil around the existing building is excavated, whereby a recess is formed.
  • the soil that is immediately under the framework casing of the existing building is also excavated, to achieve an underground space that joins the lower part of the recess, while the upper parts of the existing piles, where the piles have been installed in the soil in the lower part of the framework casing, remain exposed.
  • New piles are driven into the soil of the lower part of the recess. Then a pad footing together with new piles is created in the upper soil of the joined casing recess.
  • the support wall that surrounds the side walls of the casing is built into a joint casing together with the pad footing.
  • a pressure-resistant slab is formed, to increase the contact area with the underground soil.
  • the existing piles will penetrate the pressure-resistant slab without being in contact with it.
  • a method that is closest to this invention by the technical nature is the method for creating a new building under an existing building ( JP 58123925 , Tekken Constr Co, published on 23.07.1983).
  • the foundation of the existing building is joined with a new created support beam and is installed by means of a jack between the installed new support beam and support piles so that the new support beam will rise up, the weight of the existing building will be transferred to support piles.
  • the horizontal layer is formed by inserting a support material between the support beam and support piles, when the support material has expanded and hardened, the jack is removed, a recess is excavated and the new building is created under the existing building.
  • the applicant presents a method according to claim 1 for creating a building under an architectural monument, comprising the following stages:
  • the figure presents the conceptual solution for creating a building under and around an architectural monument.
  • a rigid loadbearing structure 2 is created vertically under the authentically preserved building 1.
  • the rigid loadbearing structure 2 is first executed at a half width of structure 2.
  • the rigid and loadbearing structure 2 is created with gaps and by sections as to the plan. After the completion of the executed section, the uncompleted parts of the rigid and loadbearing structure 2 are created. Then, after the first half of structure 2 has achieved its rigidity, the second half of structure 2 is executed similarly to the first half.
  • cross-beams 3 are installed in the structure, whereat the installation of a cross-beam is preceded by the installation of temporary piles 5, which reach down to and rest on the loadbearing soil layer 6.
  • Structure 2 is provided with openings for tensile fittings 4.
  • the rigid and load bearing structure 2 is pre-tensioned with tensile fittings 4 in the upper and lower half.
  • the cross-beam 3 is supported by means of temporary piles 5.
  • Jacks 7 are installed between the cross-beams 3 and temporary piles 5, providing the temporary piles 5 with pre-tension. Pre-tension is provided to temporary piles 5 in order to prevent possible subsiding of the authentically preserved building 1 as a result of a possible unevenness of loadbearing soil layer 6 and deformation.
  • a loadbearing and waterproof structure 9 is created around the sideways perimeter of the underground part 8 of the new building to be created under building 1, reaching down to the loadbearing surface 6.
  • the loadbearing and waterproof structure 9 is created under high pressure by pressing liquid binder into infirm soil 10, resulting in a slurry of the soil and the binder, which will turn into a hard and waterproof material, i.e. the loadbearing and waterproof structure 9, in the course of hardening.
  • a loadbearing and waterproof structure 9 will be created in vertical, similarly to the loadbearing structure of the preserved building 1.
  • a horizontal waterproof layer 11 is created under the underground part 8 of the new created building.
  • the waterproof horizontal layer 11 is created in a concave form between the loadbearing and waterproof structure 9 and temporary piles 5. Due to the concave form of the waterproof horizontal layer 11, an arch will form between the load bearing and waterproof structure and temporary piles 5, holding the buoyancy force of surface water.
  • the recess for the underground part 8 of the new building will be excavated by reach sections. This is followed by building piles 12, on-pile foundation 13 and loadbearing framework 14, after which the temporary piles 5 will be removed down to on-pile foundation 13. Jacks 7 and cross-beams 3 are also removed.
  • the temporary pulls 15 are installed to the load bearing and waterproof structure 9 to receive the side trust of soil. The temporary pulls 15 are released after the completion of the underground part 8 of the new building.
  • the new surface structures 16 are built, using transparent materials for the external borders 17, making it possible to display the authentically preserved building 1.
  • the level of surface water 18 next to the underground part 8 of the new building of the authentically preserved building 1 is not lowered and in order to prevent the local rise of surface water level, drainage 19 will be created around the underground part 8 of the new building. Drainage 19 will ensure that the surface water level 18 will remain unchanged in the vicinity of the underground part 8 of the new building.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Description

    Technical field
  • The invention belongs in the construction field, treating more specifically a method for creating a new building under and around an authentically preserved architectural monument, which is located on an infirm base.
  • Prior art
  • From the prior art there are solutions known, where a new building is created under an existing building.
  • A vertical dredging-type structural design is known ( JP4092020 , Obhayashi Corp, published on 25.03.1992), where the soil is excavated from beneath an existing building, using a method, where a steel-sheet cylinder is pressed down while using the existing building as the supporting points for the jack. A cylinder-shaped shaft is dug into the soil and jacks are positioned between the upper edge of the shaft and the building. The shaft is pressed down with the compressive force of the jacks and with the inner concave. When the reaction force to the traction(repulsive) force of the jacks is removed, the shaft will sink in the bottom and a building can be created under the existing building without using temporary structures.
  • Another known method is that of producing an insulated foundation recess to an existing building ( JP 184144 , Taisei Corp, published on 15.07.1997). The soil around the existing building is excavated, whereby a recess is formed. The soil that is immediately under the framework casing of the existing building is also excavated, to achieve an underground space that joins the lower part of the recess, while the upper parts of the existing piles, where the piles have been installed in the soil in the lower part of the framework casing, remain exposed. New piles are driven into the soil of the lower part of the recess. Then a pad footing together with new piles is created in the upper soil of the joined casing recess. The support wall that surrounds the side walls of the casing is built into a joint casing together with the pad footing. In the underground space a pressure-resistant slab is formed, to increase the contact area with the underground soil. In this case the existing piles will penetrate the pressure-resistant slab without being in contact with it.
  • A method that is closest to this invention by the technical nature, is the method for creating a new building under an existing building ( JP 58123925 , Tekken Constr Co, published on 23.07.1983). In that solution the foundation of the existing building is joined with a new created support beam and is installed by means of a jack between the installed new support beam and support piles so that the new support beam will rise up, the weight of the existing building will be transferred to support piles. The horizontal layer is formed by inserting a support material between the support beam and support piles, when the support material has expanded and hardened, the jack is removed, a recess is excavated and the new building is created under the existing building.
  • A drawback of the known solutions is that these do not allow creating a new building under architectural monuments, since special requirements apply to the preservation of architectural monuments.
  • Description of the invention
  • In built-up areas it is often necessary to create buildings near (beneath, next to and/or on top) an architectural monument due to natural factors, economic conditions or functional needs. At this, proceeding from historical principles, the existing architectural heritage should be preserved in its authentic form, while ensuring that it will be displayed. A majority of architectural monuments are not on a rigid soil (e.g. rock), and thereby complex problems will occur with the maintenance of the stability of the existing building and the new additional building.
  • The problem is made more complicated by the fact that architectural monuments are located on a relatively infirm soil and the level of surface water is at the height of the pad footing. The level of surface water may not be lowered, since it would cause subsiding in other buildings in the area. The National Heritage Board requests the preservation of existing architectural monuments in their authentic form, meaning that it is not permitted to disassemble and reassemble the monuments.
  • The applicant presents a method according to claim 1 for creating a building under an architectural monument, comprising the following stages:
    • a rigid loadbearing structure is created under the preserved building, whereas the structure is produced vertically in two parts;
    • the two parts of the structure are created with gaps and by sections as to the plan and after completing the executed sections, the structural parts that have not been executed will be created;
    • temporary piles will be created, which will rest on and reach to a loadbearing surface layer;
    • cross-beams are installed in the load bearing structure, leaving openings in the structure for tensile fittings, and the loadbearing structure is pre-tensioned by means of the tensile fittings in the upper and lower half of the structure;
    • jacks are mounted between the cross-beams and temporary piles;
    • under the preserved building, a loadbearing and waterproof structure is created around the underground part of the new building down to the loadbearing soil;
    • a horizontal waterproof layer is formed under the underground part of the new building, between the waterproof structure and the temporary piles;
    • the recess for the underground part of the new building is excavated, installing simultaneously temporary pullers to the load bearing waterproof structure;
    • piles, on-pile foundation and loadbearing framework are built;
    • temporary piles are removed down to the on-pile foundation, removing also the jacks and cross-beams, releasing temporary pullers;
    • new ground-level structures are built, using transparent materials for external borders;
    • drainage is created around the underground part of the new building.
    List of figures
  • The figure presents the conceptual solution for creating a building under and around an architectural monument.
  • Exemplary embodiment of the invention
  • A rigid loadbearing structure 2 is created vertically under the authentically preserved building 1. The rigid loadbearing structure 2 is first executed at a half width of structure 2. The rigid and loadbearing structure 2 is created with gaps and by sections as to the plan. After the completion of the executed section, the uncompleted parts of the rigid and loadbearing structure 2 are created. Then, after the first half of structure 2 has achieved its rigidity, the second half of structure 2 is executed similarly to the first half. During the construction of structure 2, cross-beams 3 are installed in the structure, whereat the installation of a cross-beam is preceded by the installation of temporary piles 5, which reach down to and rest on the loadbearing soil layer 6. Structure 2 is provided with openings for tensile fittings 4. The rigid and load bearing structure 2 is pre-tensioned with tensile fittings 4 in the upper and lower half. When the loadbearing structure 2 has been built, the cross-beam 3 is supported by means of temporary piles 5. Jacks 7 are installed between the cross-beams 3 and temporary piles 5, providing the temporary piles 5 with pre-tension. Pre-tension is provided to temporary piles 5 in order to prevent possible subsiding of the authentically preserved building 1 as a result of a possible unevenness of loadbearing soil layer 6 and deformation.
  • After resting the authentically preserved building 1 on the loadbearing soil layer 6, a loadbearing and waterproof structure 9 is created around the sideways perimeter of the underground part 8 of the new building to be created under building 1, reaching down to the loadbearing surface 6. The loadbearing and waterproof structure 9 is created under high pressure by pressing liquid binder into infirm soil 10, resulting in a slurry of the soil and the binder, which will turn into a hard and waterproof material, i.e. the loadbearing and waterproof structure 9, in the course of hardening. At the joint of the perimeters of the authentically preserved building 1 and the new underground part 8 of the new building, a loadbearing and waterproof structure 9 will be created in vertical, similarly to the loadbearing structure of the preserved building 1.
  • After the completion of the loadbearing and waterproof structure 9, a horizontal waterproof layer 11 is created under the underground part 8 of the new created building. The waterproof horizontal layer 11 is created in a concave form between the loadbearing and waterproof structure 9 and temporary piles 5. Due to the concave form of the waterproof horizontal layer 11, an arch will form between the load bearing and waterproof structure and temporary piles 5, holding the buoyancy force of surface water.
  • After the completion of the loadbearing and waterproof structure 9 and the waterproof horizontal layer 11, the recess for the underground part 8 of the new building will be excavated by reach sections. This is followed by building piles 12, on-pile foundation 13 and loadbearing framework 14, after which the temporary piles 5 will be removed down to on-pile foundation 13. Jacks 7 and cross-beams 3 are also removed. During the creation of the recess, the temporary pulls 15 are installed to the load bearing and waterproof structure 9 to receive the side trust of soil. The temporary pulls 15 are released after the completion of the underground part 8 of the new building.
  • After the creation of the underground part 8 of the new building under the authentically preserved building 1, the new surface structures 16 are built, using transparent materials for the external borders 17, making it possible to display the authentically preserved building 1.
  • The level of surface water 18 next to the underground part 8 of the new building of the authentically preserved building 1 is not lowered and in order to prevent the local rise of surface water level, drainage 19 will be created around the underground part 8 of the new building. Drainage 19 will ensure that the surface water level 18 will remain unchanged in the vicinity of the underground part 8 of the new building.

Claims (5)

  1. Method for creating a building under an architectural monument, comprising the stages of: supporting the foundation of the existing building by means of support beams and piles and with jacks; a horizontal layer is created, the jacks are removed, an underground recess is excavated, a new building is built under the existing building, characterized in that
    - a rigid loadbearing structure (2) is built under the building in order to support the foundation of the existing building (1), whereas the structure (2) is produced vertically in two parts;
    - two parts of the structure (2) are created with gaps and by sections as to the plan, and after the completed sections are ready, the structure (2) is further created in the uncompleted parts;
    - the structure (2) is pre-tensioned with tensile fittings (4) from the upper and lower part of the structure (2);
    - temporary piles are driven (5);
    - cross-beams (3) are installed in the structure (2) and the cross-beams are supported with the temporary piles (5);
    - jacks (7) are installed between the cross-beams (3) and the temporary piles (5);
    - under the existing building (1), around the underground part (8), a loadbearing and waterproof structure (9) is created down to the loadbearing surface;
    - under the underground part (8) of the new building a horizontal waterproof layer (11) is formed between the loadbearing and waterproof structure (9) and the temporary piles (5);
    - a recess is excavated for the new building and temporary pullers (15) are installed to the loadbearing and waterproof structure (9);
    - piles (12), on-pile foundation (13) and loadbearing framework (14) are built;
    - temporary piles (5), jacks (7), cross-beams (3) and temporary pullers (15) are removed;
    - new surface structures (16) are built, using a transparent material for external borders (17) and
    - drainage (19) is created around the underground part (8) of the new building.
  2. Method accordingly to claim 1, characterized in that structure (2) is produced by executing structure (2) first in a half width of structure (2) and when the first part has achieved its rigidity, the second part of structure (2) is executed, leaving openings for the tensile fittings (4) in the upper and lower part of structure (2).
  3. Method accordingly to claim 1, characterized in that the temporary piles (5) are driven so that they rest in a loadbearing layer of soil (6).
  4. Method accordingly to claim 1, characterized in that structure (9) is loadbearing and waterproof, executed by pressing liquid binder into infirm soil (10) under high pressure.
  5. Method accordingly to claim 1, characterized in that the temporary piles (5) are removed down to the on-pile foundation (13).
EP10003429.7A 2009-03-31 2010-03-30 Method for creating a building under an architectural monument Not-in-force EP2236677B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EEU200900032U EE00970U1 (en) 2009-03-31 2009-03-31 The method of constructing a building under the architectural “flattening

Publications (3)

Publication Number Publication Date
EP2236677A2 EP2236677A2 (en) 2010-10-06
EP2236677A3 EP2236677A3 (en) 2013-06-19
EP2236677B1 true EP2236677B1 (en) 2014-06-11

Family

ID=42307803

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10003429.7A Not-in-force EP2236677B1 (en) 2009-03-31 2010-03-30 Method for creating a building under an architectural monument

Country Status (2)

Country Link
EP (1) EP2236677B1 (en)
EE (1) EE00970U1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096109A (en) * 2020-08-27 2020-12-18 中国二十冶集团有限公司 Construction method for newly built building reserved beside building

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101026731B1 (en) 2010-12-16 2011-04-08 주식회사고려이엔시 Basement construction method of completed building
ES2396905B1 (en) * 2011-03-20 2014-05-06 Carlos LOPEZ DE CEBALLOS GARZON PROCEDURE FOR THE EXECUTION OF BASEMENTS BY DESCENDING Slabs IN EXISTING BUILDINGS
CN103437566B (en) * 2013-08-30 2015-06-17 山东建筑大学 Supporting steel pipe device of underground added layer of existing building and installing method of supporting steel pipe device
CN109024662A (en) * 2018-07-19 2018-12-18 深圳市工勘岩土集团有限公司 Method of the anchor pile underpinning without basement building underground space increasing layer
CN110616714B (en) * 2019-09-12 2021-07-23 上海建工集团股份有限公司 Novel enclosure construction method for existing underground structure deepening
ES3054008A1 (en) * 2024-07-09 2026-01-28 Bespi Construcciones S L MICROREC: RECOVERABLE (MICRO)PILES SYSTEM

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB325093A (en) * 1929-02-07 1930-02-13 Julian Anthony Formunt Improvements relating to the provision of substructures, particularly for subaqueous work
JPS6047413B2 (en) 1982-01-19 1985-10-22 鉄建建設株式会社 Construction method for constructing a new structure underground below an existing structure and filling material used therein
GB8720611D0 (en) 1987-09-02 1987-10-07 Philips Electronic Associated Gas chromatography apparatus
FR2647481B1 (en) * 1989-05-26 1991-07-26 Cofex METHOD FOR REALIZING A FREE VOLUME IN THE BASEMENT BETWEEN EXISTING BUILDINGS AND CONSTRUCTION OBTAINED
JP2566050B2 (en) 1990-08-03 1996-12-25 株式会社大林組 How to construct a vertical structure below an existing building
JP3534928B2 (en) * 1995-12-28 2004-06-07 大成建設株式会社 Construction method of seismic isolation pit for existing building
JP4703233B2 (en) * 2005-03-30 2011-06-15 報国エンジニアリング株式会社 Building foundation reinforcement method and structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096109A (en) * 2020-08-27 2020-12-18 中国二十冶集团有限公司 Construction method for newly built building reserved beside building
CN112096109B (en) * 2020-08-27 2022-02-25 中国二十冶集团有限公司 Construction method for newly built building reserved beside building

Also Published As

Publication number Publication date
EE00970U1 (en) 2010-10-15
EP2236677A3 (en) 2013-06-19
EP2236677A2 (en) 2010-10-06

Similar Documents

Publication Publication Date Title
EP2236677B1 (en) Method for creating a building under an architectural monument
CN106013241B (en) Guan Liang foundation trench uprightly performs and cap excavation method station integrated structure system and construction method
CN111456023A (en) A kind of construction method of underground prestressed support structure
EP2251503B1 (en) Method for replacing a loadbearing wall
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
US20200284026A1 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
KR101575858B1 (en) A recovering device and procedure for a differential settlement building
JP3761323B2 (en) How to rebuild a building
JP3850785B2 (en) Caisson laying method using main foundation pile
JP5038170B2 (en) How to rebuild a structure
JP5228862B2 (en) Underground structure, construction method of underground structure
JP2015036493A (en) Method for constructing underground storage tank
CN106400814A (en) Foundation pit supporting method
CN115822252B (en) Construction method and supporting structure for ultra-high inclined column in limited space
CN118223416A (en) Construction method for bridge pile foundation, pier stud and capping beam in filling and construction bench type river channel
CN105951863A (en) Construction device of active assembling type open caisson and construction method using same
CN117605492A (en) Double-side pilot tunnel steel frame rock wall combined support construction method for four-lane tunnel
CN205875210U (en) Hat liang ji upright executes in groove to do and digs method station integrated structure system with lid
JP5207086B2 (en) Construction method of underground tank
CN218933149U (en) SMW construction method pile structure
CN114875935A (en) Foundation pit enclosure structure with limited clearance and construction method thereof
CN113266038A (en) Construction method for excavating underground building in foundation pit
CN115262568B (en) Deepening support and excavation construction method based on zero-field deep foundation pit
CN111779312A (en) Device and construction method for jacking up existing buildings and renovating parking garages
CN119777407B (en) A method for constructing underground space in the surrounding area of an existing building by using a caisson

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: AL BA ME RS

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: AL BA ME RS

RIC1 Information provided on ipc code assigned before grant

Ipc: E02D 35/00 20060101ALI20130513BHEP

Ipc: E02D 27/48 20060101AFI20130513BHEP

Ipc: E04B 1/35 20060101ALI20130513BHEP

Ipc: E04G 23/02 20060101ALI20130513BHEP

Ipc: E04G 23/06 20060101ALI20130513BHEP

17P Request for examination filed

Effective date: 20131111

RBV Designated contracting states (corrected)

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20140127

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 672336

Country of ref document: AT

Kind code of ref document: T

Effective date: 20140715

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602010016572

Country of ref document: DE

Effective date: 20140724

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140912

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140911

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20140611

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 672336

Country of ref document: AT

Kind code of ref document: T

Effective date: 20140611

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141013

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141011

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602010016572

Country of ref document: DE

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

26N No opposition filed

Effective date: 20150312

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602010016572

Country of ref document: DE

Effective date: 20150312

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150330

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150331

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150331

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150330

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20160330

Year of fee payment: 7

Ref country code: FR

Payment date: 20160318

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20160429

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20100330

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602010016572

Country of ref document: DE

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20170330

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20171130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20171003

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170330

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140611