EP2236677B1 - Method for creating a building under an architectural monument - Google Patents
Method for creating a building under an architectural monument Download PDFInfo
- Publication number
- EP2236677B1 EP2236677B1 EP10003429.7A EP10003429A EP2236677B1 EP 2236677 B1 EP2236677 B1 EP 2236677B1 EP 10003429 A EP10003429 A EP 10003429A EP 2236677 B1 EP2236677 B1 EP 2236677B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- loadbearing
- building
- piles
- temporary
- created
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
- 238000000034 method Methods 0.000 title claims description 12
- 239000002689 soil Substances 0.000 claims description 19
- 239000011230 binding agent Substances 0.000 claims description 3
- 239000012780 transparent material Substances 0.000 claims description 3
- 239000007788 liquid Substances 0.000 claims description 2
- 239000010410 layer Substances 0.000 description 9
- 239000002352 surface water Substances 0.000 description 6
- 239000000463 material Substances 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000004321 preservation Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/48—Foundations inserted underneath existing buildings or constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0266—Enlarging
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/06—Separating, lifting, removing of buildings; Making a new sub-structure
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
Definitions
- the invention belongs in the construction field, treating more specifically a method for creating a new building under and around an authentically preserved architectural monument, which is located on an infirm base.
- a vertical dredging-type structural design is known ( JP4092020 , Obhayashi Corp, published on 25.03.1992), where the soil is excavated from beneath an existing building, using a method, where a steel-sheet cylinder is pressed down while using the existing building as the supporting points for the jack.
- a cylinder-shaped shaft is dug into the soil and jacks are positioned between the upper edge of the shaft and the building. The shaft is pressed down with the compressive force of the jacks and with the inner concave. When the reaction force to the traction(repulsive) force of the jacks is removed, the shaft will sink in the bottom and a building can be created under the existing building without using temporary structures.
- Another known method is that of producing an insulated foundation recess to an existing building ( JP 184144 , Taisei Corp, published on 15.07.1997).
- the soil around the existing building is excavated, whereby a recess is formed.
- the soil that is immediately under the framework casing of the existing building is also excavated, to achieve an underground space that joins the lower part of the recess, while the upper parts of the existing piles, where the piles have been installed in the soil in the lower part of the framework casing, remain exposed.
- New piles are driven into the soil of the lower part of the recess. Then a pad footing together with new piles is created in the upper soil of the joined casing recess.
- the support wall that surrounds the side walls of the casing is built into a joint casing together with the pad footing.
- a pressure-resistant slab is formed, to increase the contact area with the underground soil.
- the existing piles will penetrate the pressure-resistant slab without being in contact with it.
- a method that is closest to this invention by the technical nature is the method for creating a new building under an existing building ( JP 58123925 , Tekken Constr Co, published on 23.07.1983).
- the foundation of the existing building is joined with a new created support beam and is installed by means of a jack between the installed new support beam and support piles so that the new support beam will rise up, the weight of the existing building will be transferred to support piles.
- the horizontal layer is formed by inserting a support material between the support beam and support piles, when the support material has expanded and hardened, the jack is removed, a recess is excavated and the new building is created under the existing building.
- the applicant presents a method according to claim 1 for creating a building under an architectural monument, comprising the following stages:
- the figure presents the conceptual solution for creating a building under and around an architectural monument.
- a rigid loadbearing structure 2 is created vertically under the authentically preserved building 1.
- the rigid loadbearing structure 2 is first executed at a half width of structure 2.
- the rigid and loadbearing structure 2 is created with gaps and by sections as to the plan. After the completion of the executed section, the uncompleted parts of the rigid and loadbearing structure 2 are created. Then, after the first half of structure 2 has achieved its rigidity, the second half of structure 2 is executed similarly to the first half.
- cross-beams 3 are installed in the structure, whereat the installation of a cross-beam is preceded by the installation of temporary piles 5, which reach down to and rest on the loadbearing soil layer 6.
- Structure 2 is provided with openings for tensile fittings 4.
- the rigid and load bearing structure 2 is pre-tensioned with tensile fittings 4 in the upper and lower half.
- the cross-beam 3 is supported by means of temporary piles 5.
- Jacks 7 are installed between the cross-beams 3 and temporary piles 5, providing the temporary piles 5 with pre-tension. Pre-tension is provided to temporary piles 5 in order to prevent possible subsiding of the authentically preserved building 1 as a result of a possible unevenness of loadbearing soil layer 6 and deformation.
- a loadbearing and waterproof structure 9 is created around the sideways perimeter of the underground part 8 of the new building to be created under building 1, reaching down to the loadbearing surface 6.
- the loadbearing and waterproof structure 9 is created under high pressure by pressing liquid binder into infirm soil 10, resulting in a slurry of the soil and the binder, which will turn into a hard and waterproof material, i.e. the loadbearing and waterproof structure 9, in the course of hardening.
- a loadbearing and waterproof structure 9 will be created in vertical, similarly to the loadbearing structure of the preserved building 1.
- a horizontal waterproof layer 11 is created under the underground part 8 of the new created building.
- the waterproof horizontal layer 11 is created in a concave form between the loadbearing and waterproof structure 9 and temporary piles 5. Due to the concave form of the waterproof horizontal layer 11, an arch will form between the load bearing and waterproof structure and temporary piles 5, holding the buoyancy force of surface water.
- the recess for the underground part 8 of the new building will be excavated by reach sections. This is followed by building piles 12, on-pile foundation 13 and loadbearing framework 14, after which the temporary piles 5 will be removed down to on-pile foundation 13. Jacks 7 and cross-beams 3 are also removed.
- the temporary pulls 15 are installed to the load bearing and waterproof structure 9 to receive the side trust of soil. The temporary pulls 15 are released after the completion of the underground part 8 of the new building.
- the new surface structures 16 are built, using transparent materials for the external borders 17, making it possible to display the authentically preserved building 1.
- the level of surface water 18 next to the underground part 8 of the new building of the authentically preserved building 1 is not lowered and in order to prevent the local rise of surface water level, drainage 19 will be created around the underground part 8 of the new building. Drainage 19 will ensure that the surface water level 18 will remain unchanged in the vicinity of the underground part 8 of the new building.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Mechanical Engineering (AREA)
- Electrochemistry (AREA)
- Chemical & Material Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Description
- The invention belongs in the construction field, treating more specifically a method for creating a new building under and around an authentically preserved architectural monument, which is located on an infirm base.
- From the prior art there are solutions known, where a new building is created under an existing building.
- A vertical dredging-type structural design is known (
, Obhayashi Corp, published on 25.03.1992), where the soil is excavated from beneath an existing building, using a method, where a steel-sheet cylinder is pressed down while using the existing building as the supporting points for the jack. A cylinder-shaped shaft is dug into the soil and jacks are positioned between the upper edge of the shaft and the building. The shaft is pressed down with the compressive force of the jacks and with the inner concave. When the reaction force to the traction(repulsive) force of the jacks is removed, the shaft will sink in the bottom and a building can be created under the existing building without using temporary structures.JP4092020 - Another known method is that of producing an insulated foundation recess to an existing building (
, Taisei Corp, published on 15.07.1997). The soil around the existing building is excavated, whereby a recess is formed. The soil that is immediately under the framework casing of the existing building is also excavated, to achieve an underground space that joins the lower part of the recess, while the upper parts of the existing piles, where the piles have been installed in the soil in the lower part of the framework casing, remain exposed. New piles are driven into the soil of the lower part of the recess. Then a pad footing together with new piles is created in the upper soil of the joined casing recess. The support wall that surrounds the side walls of the casing is built into a joint casing together with the pad footing. In the underground space a pressure-resistant slab is formed, to increase the contact area with the underground soil. In this case the existing piles will penetrate the pressure-resistant slab without being in contact with it.JP 184144 - A method that is closest to this invention by the technical nature, is the method for creating a new building under an existing building (
, Tekken Constr Co, published on 23.07.1983). In that solution the foundation of the existing building is joined with a new created support beam and is installed by means of a jack between the installed new support beam and support piles so that the new support beam will rise up, the weight of the existing building will be transferred to support piles. The horizontal layer is formed by inserting a support material between the support beam and support piles, when the support material has expanded and hardened, the jack is removed, a recess is excavated and the new building is created under the existing building.JP 58123925 - A drawback of the known solutions is that these do not allow creating a new building under architectural monuments, since special requirements apply to the preservation of architectural monuments.
- In built-up areas it is often necessary to create buildings near (beneath, next to and/or on top) an architectural monument due to natural factors, economic conditions or functional needs. At this, proceeding from historical principles, the existing architectural heritage should be preserved in its authentic form, while ensuring that it will be displayed. A majority of architectural monuments are not on a rigid soil (e.g. rock), and thereby complex problems will occur with the maintenance of the stability of the existing building and the new additional building.
- The problem is made more complicated by the fact that architectural monuments are located on a relatively infirm soil and the level of surface water is at the height of the pad footing. The level of surface water may not be lowered, since it would cause subsiding in other buildings in the area. The National Heritage Board requests the preservation of existing architectural monuments in their authentic form, meaning that it is not permitted to disassemble and reassemble the monuments.
- The applicant presents a method according to claim 1 for creating a building under an architectural monument, comprising the following stages:
- a rigid loadbearing structure is created under the preserved building, whereas the structure is produced vertically in two parts;
- the two parts of the structure are created with gaps and by sections as to the plan and after completing the executed sections, the structural parts that have not been executed will be created;
- temporary piles will be created, which will rest on and reach to a loadbearing surface layer;
- cross-beams are installed in the load bearing structure, leaving openings in the structure for tensile fittings, and the loadbearing structure is pre-tensioned by means of the tensile fittings in the upper and lower half of the structure;
- jacks are mounted between the cross-beams and temporary piles;
- under the preserved building, a loadbearing and waterproof structure is created around the underground part of the new building down to the loadbearing soil;
- a horizontal waterproof layer is formed under the underground part of the new building, between the waterproof structure and the temporary piles;
- the recess for the underground part of the new building is excavated, installing simultaneously temporary pullers to the load bearing waterproof structure;
- piles, on-pile foundation and loadbearing framework are built;
- temporary piles are removed down to the on-pile foundation, removing also the jacks and cross-beams, releasing temporary pullers;
- new ground-level structures are built, using transparent materials for external borders;
- drainage is created around the underground part of the new building.
- The figure presents the conceptual solution for creating a building under and around an architectural monument.
- A rigid loadbearing structure 2 is created vertically under the authentically preserved building 1. The rigid loadbearing structure 2 is first executed at a half width of structure 2. The rigid and loadbearing structure 2 is created with gaps and by sections as to the plan. After the completion of the executed section, the uncompleted parts of the rigid and loadbearing structure 2 are created. Then, after the first half of structure 2 has achieved its rigidity, the second half of structure 2 is executed similarly to the first half. During the construction of structure 2,
cross-beams 3 are installed in the structure, whereat the installation of a cross-beam is preceded by the installation oftemporary piles 5, which reach down to and rest on theloadbearing soil layer 6. Structure 2 is provided with openings fortensile fittings 4. The rigid and load bearing structure 2 is pre-tensioned withtensile fittings 4 in the upper and lower half. When the loadbearing structure 2 has been built, thecross-beam 3 is supported by means oftemporary piles 5. Jacks 7 are installed between thecross-beams 3 andtemporary piles 5, providing thetemporary piles 5 with pre-tension. Pre-tension is provided totemporary piles 5 in order to prevent possible subsiding of the authentically preserved building 1 as a result of a possible unevenness ofloadbearing soil layer 6 and deformation. - After resting the authentically preserved building 1 on the
loadbearing soil layer 6, a loadbearing and waterproof structure 9 is created around the sideways perimeter of theunderground part 8 of the new building to be created under building 1, reaching down to theloadbearing surface 6. The loadbearing and waterproof structure 9 is created under high pressure by pressing liquid binder intoinfirm soil 10, resulting in a slurry of the soil and the binder, which will turn into a hard and waterproof material, i.e. the loadbearing and waterproof structure 9, in the course of hardening. At the joint of the perimeters of the authentically preserved building 1 and the newunderground part 8 of the new building, a loadbearing and waterproof structure 9 will be created in vertical, similarly to the loadbearing structure of the preserved building 1. - After the completion of the loadbearing and waterproof structure 9, a horizontal waterproof layer 11 is created under the
underground part 8 of the new created building. The waterproof horizontal layer 11 is created in a concave form between the loadbearing and waterproof structure 9 andtemporary piles 5. Due to the concave form of the waterproof horizontal layer 11, an arch will form between the load bearing and waterproof structure andtemporary piles 5, holding the buoyancy force of surface water. - After the completion of the loadbearing and waterproof structure 9 and the waterproof horizontal layer 11, the recess for the
underground part 8 of the new building will be excavated by reach sections. This is followed bybuilding piles 12, on-pile foundation 13 andloadbearing framework 14, after which thetemporary piles 5 will be removed down to on-pile foundation 13.Jacks 7 andcross-beams 3 are also removed. During the creation of the recess, thetemporary pulls 15 are installed to the load bearing and waterproof structure 9 to receive the side trust of soil. Thetemporary pulls 15 are released after the completion of theunderground part 8 of the new building. - After the creation of the
underground part 8 of the new building under the authentically preserved building 1, thenew surface structures 16 are built, using transparent materials for theexternal borders 17, making it possible to display the authentically preserved building 1. - The level of
surface water 18 next to theunderground part 8 of the new building of the authentically preserved building 1 is not lowered and in order to prevent the local rise of surface water level,drainage 19 will be created around theunderground part 8 of the new building.Drainage 19 will ensure that thesurface water level 18 will remain unchanged in the vicinity of theunderground part 8 of the new building.
Claims (5)
- Method for creating a building under an architectural monument, comprising the stages of: supporting the foundation of the existing building by means of support beams and piles and with jacks; a horizontal layer is created, the jacks are removed, an underground recess is excavated, a new building is built under the existing building, characterized in that- a rigid loadbearing structure (2) is built under the building in order to support the foundation of the existing building (1), whereas the structure (2) is produced vertically in two parts;- two parts of the structure (2) are created with gaps and by sections as to the plan, and after the completed sections are ready, the structure (2) is further created in the uncompleted parts;- the structure (2) is pre-tensioned with tensile fittings (4) from the upper and lower part of the structure (2);- temporary piles are driven (5);- cross-beams (3) are installed in the structure (2) and the cross-beams are supported with the temporary piles (5);- jacks (7) are installed between the cross-beams (3) and the temporary piles (5);- under the existing building (1), around the underground part (8), a loadbearing and waterproof structure (9) is created down to the loadbearing surface;- under the underground part (8) of the new building a horizontal waterproof layer (11) is formed between the loadbearing and waterproof structure (9) and the temporary piles (5);- a recess is excavated for the new building and temporary pullers (15) are installed to the loadbearing and waterproof structure (9);- piles (12), on-pile foundation (13) and loadbearing framework (14) are built;- temporary piles (5), jacks (7), cross-beams (3) and temporary pullers (15) are removed;- new surface structures (16) are built, using a transparent material for external borders (17) and- drainage (19) is created around the underground part (8) of the new building.
- Method accordingly to claim 1, characterized in that structure (2) is produced by executing structure (2) first in a half width of structure (2) and when the first part has achieved its rigidity, the second part of structure (2) is executed, leaving openings for the tensile fittings (4) in the upper and lower part of structure (2).
- Method accordingly to claim 1, characterized in that the temporary piles (5) are driven so that they rest in a loadbearing layer of soil (6).
- Method accordingly to claim 1, characterized in that structure (9) is loadbearing and waterproof, executed by pressing liquid binder into infirm soil (10) under high pressure.
- Method accordingly to claim 1, characterized in that the temporary piles (5) are removed down to the on-pile foundation (13).
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| EEU200900032U EE00970U1 (en) | 2009-03-31 | 2009-03-31 | The method of constructing a building under the architectural “flattening |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| EP2236677A2 EP2236677A2 (en) | 2010-10-06 |
| EP2236677A3 EP2236677A3 (en) | 2013-06-19 |
| EP2236677B1 true EP2236677B1 (en) | 2014-06-11 |
Family
ID=42307803
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP10003429.7A Not-in-force EP2236677B1 (en) | 2009-03-31 | 2010-03-30 | Method for creating a building under an architectural monument |
Country Status (2)
| Country | Link |
|---|---|
| EP (1) | EP2236677B1 (en) |
| EE (1) | EE00970U1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112096109A (en) * | 2020-08-27 | 2020-12-18 | 中国二十冶集团有限公司 | Construction method for newly built building reserved beside building |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101026731B1 (en) | 2010-12-16 | 2011-04-08 | 주식회사고려이엔시 | Basement construction method of completed building |
| ES2396905B1 (en) * | 2011-03-20 | 2014-05-06 | Carlos LOPEZ DE CEBALLOS GARZON | PROCEDURE FOR THE EXECUTION OF BASEMENTS BY DESCENDING Slabs IN EXISTING BUILDINGS |
| CN103437566B (en) * | 2013-08-30 | 2015-06-17 | 山东建筑大学 | Supporting steel pipe device of underground added layer of existing building and installing method of supporting steel pipe device |
| CN109024662A (en) * | 2018-07-19 | 2018-12-18 | 深圳市工勘岩土集团有限公司 | Method of the anchor pile underpinning without basement building underground space increasing layer |
| CN110616714B (en) * | 2019-09-12 | 2021-07-23 | 上海建工集团股份有限公司 | Novel enclosure construction method for existing underground structure deepening |
| ES3054008A1 (en) * | 2024-07-09 | 2026-01-28 | Bespi Construcciones S L | MICROREC: RECOVERABLE (MICRO)PILES SYSTEM |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB325093A (en) * | 1929-02-07 | 1930-02-13 | Julian Anthony Formunt | Improvements relating to the provision of substructures, particularly for subaqueous work |
| JPS6047413B2 (en) | 1982-01-19 | 1985-10-22 | 鉄建建設株式会社 | Construction method for constructing a new structure underground below an existing structure and filling material used therein |
| GB8720611D0 (en) | 1987-09-02 | 1987-10-07 | Philips Electronic Associated | Gas chromatography apparatus |
| FR2647481B1 (en) * | 1989-05-26 | 1991-07-26 | Cofex | METHOD FOR REALIZING A FREE VOLUME IN THE BASEMENT BETWEEN EXISTING BUILDINGS AND CONSTRUCTION OBTAINED |
| JP2566050B2 (en) | 1990-08-03 | 1996-12-25 | 株式会社大林組 | How to construct a vertical structure below an existing building |
| JP3534928B2 (en) * | 1995-12-28 | 2004-06-07 | 大成建設株式会社 | Construction method of seismic isolation pit for existing building |
| JP4703233B2 (en) * | 2005-03-30 | 2011-06-15 | 報国エンジニアリング株式会社 | Building foundation reinforcement method and structure |
-
2009
- 2009-03-31 EE EEU200900032U patent/EE00970U1/en active Protection Beyond IP Right Term
-
2010
- 2010-03-30 EP EP10003429.7A patent/EP2236677B1/en not_active Not-in-force
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112096109A (en) * | 2020-08-27 | 2020-12-18 | 中国二十冶集团有限公司 | Construction method for newly built building reserved beside building |
| CN112096109B (en) * | 2020-08-27 | 2022-02-25 | 中国二十冶集团有限公司 | Construction method for newly built building reserved beside building |
Also Published As
| Publication number | Publication date |
|---|---|
| EE00970U1 (en) | 2010-10-15 |
| EP2236677A3 (en) | 2013-06-19 |
| EP2236677A2 (en) | 2010-10-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2236677B1 (en) | Method for creating a building under an architectural monument | |
| CN106013241B (en) | Guan Liang foundation trench uprightly performs and cap excavation method station integrated structure system and construction method | |
| CN111456023A (en) | A kind of construction method of underground prestressed support structure | |
| EP2251503B1 (en) | Method for replacing a loadbearing wall | |
| CN102071698B (en) | Construction method of beddings of foundation downward overturn beam and pile cap | |
| US20200284026A1 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
| KR101575858B1 (en) | A recovering device and procedure for a differential settlement building | |
| JP3761323B2 (en) | How to rebuild a building | |
| JP3850785B2 (en) | Caisson laying method using main foundation pile | |
| JP5038170B2 (en) | How to rebuild a structure | |
| JP5228862B2 (en) | Underground structure, construction method of underground structure | |
| JP2015036493A (en) | Method for constructing underground storage tank | |
| CN106400814A (en) | Foundation pit supporting method | |
| CN115822252B (en) | Construction method and supporting structure for ultra-high inclined column in limited space | |
| CN118223416A (en) | Construction method for bridge pile foundation, pier stud and capping beam in filling and construction bench type river channel | |
| CN105951863A (en) | Construction device of active assembling type open caisson and construction method using same | |
| CN117605492A (en) | Double-side pilot tunnel steel frame rock wall combined support construction method for four-lane tunnel | |
| CN205875210U (en) | Hat liang ji upright executes in groove to do and digs method station integrated structure system with lid | |
| JP5207086B2 (en) | Construction method of underground tank | |
| CN218933149U (en) | SMW construction method pile structure | |
| CN114875935A (en) | Foundation pit enclosure structure with limited clearance and construction method thereof | |
| CN113266038A (en) | Construction method for excavating underground building in foundation pit | |
| CN115262568B (en) | Deepening support and excavation construction method based on zero-field deep foundation pit | |
| CN111779312A (en) | Device and construction method for jacking up existing buildings and renovating parking garages | |
| CN119777407B (en) | A method for constructing underground space in the surrounding area of an existing building by using a caisson |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
| AX | Request for extension of the european patent |
Extension state: AL BA ME RS |
|
| PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
| AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
| AX | Request for extension of the european patent |
Extension state: AL BA ME RS |
|
| RIC1 | Information provided on ipc code assigned before grant |
Ipc: E02D 35/00 20060101ALI20130513BHEP Ipc: E02D 27/48 20060101AFI20130513BHEP Ipc: E04B 1/35 20060101ALI20130513BHEP Ipc: E04G 23/02 20060101ALI20130513BHEP Ipc: E04G 23/06 20060101ALI20130513BHEP |
|
| 17P | Request for examination filed |
Effective date: 20131111 |
|
| RBV | Designated contracting states (corrected) |
Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
| GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
| INTG | Intention to grant announced |
Effective date: 20140127 |
|
| GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
| REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
| REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 672336 Country of ref document: AT Kind code of ref document: T Effective date: 20140715 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602010016572 Country of ref document: DE Effective date: 20140724 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140912 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140911 |
|
| REG | Reference to a national code |
Ref country code: NL Ref legal event code: VDEP Effective date: 20140611 |
|
| REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 672336 Country of ref document: AT Kind code of ref document: T Effective date: 20140611 |
|
| REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20141013 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20141011 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602010016572 Country of ref document: DE |
|
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| 26N | No opposition filed |
Effective date: 20150312 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602010016572 Country of ref document: DE Effective date: 20150312 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150330 Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150331 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150331 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150330 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 7 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20160330 Year of fee payment: 7 Ref country code: FR Payment date: 20160318 Year of fee payment: 7 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20160429 Year of fee payment: 7 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20100330 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602010016572 Country of ref document: DE |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20170330 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20171130 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171003 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20170331 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20170330 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140611 |