EP1583710B1 - Method and apparatus for installing an elevator during construction of a building - Google Patents

Method and apparatus for installing an elevator during construction of a building Download PDF

Info

Publication number
EP1583710B1
EP1583710B1 EP03775427A EP03775427A EP1583710B1 EP 1583710 B1 EP1583710 B1 EP 1583710B1 EP 03775427 A EP03775427 A EP 03775427A EP 03775427 A EP03775427 A EP 03775427A EP 1583710 B1 EP1583710 B1 EP 1583710B1
Authority
EP
European Patent Office
Prior art keywords
elevator
machine room
guide rails
floor
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP03775427A
Other languages
German (de)
French (fr)
Other versions
EP1583710A1 (en
Inventor
Gert Van Der Meijden
Jos Van Den Heuvel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kone Corp
Original Assignee
Kone Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kone Corp filed Critical Kone Corp
Publication of EP1583710A1 publication Critical patent/EP1583710A1/en
Application granted granted Critical
Publication of EP1583710B1 publication Critical patent/EP1583710B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation

Definitions

  • the present invention relates to a method as defined in the preamble of claim 1 and to an elevator as defined in the preamble of claim 6.
  • elevators are often needed during the construction stage before the building has been completed. Elevators are needed e.g. for construction-time use to allow the constructors to reach as high levels in the building as possible by elevator. Similarly, when the lower floors of a building are completed before the upper floors, the elevators must be available for use by the people already using the completed floors. As the construction work is progressing, the elevators have to be able to serve floors as high up as possible.
  • a prior-art solution for this type of construction-time use is the so-called jump-lift, wherein the hoisting height of the elevator is increased in steps of one or more floor levels each time when the construction work has reached a sufficient height relative to the previous jump.
  • the elevator machine room is removed upwards by the above-mentioned number of floors and all the components dependent on the hoisting height, such as car cables, overspeed governor ropes and other components mounted in the shaft, electric equipment in the shaft, shaft cables, compensation ropes etc. are extended to cover the height of the entire completed shaft.
  • the machine room has been lifted by using the building's own construction hoist, among other things.
  • the problem in this case is that the elevator installation is dependent on the use of the construction hoist.
  • the construction hoist may be needed elsewhere on the building site at the same time, in which case the hoist will not be available for use at the desired time or for a time long enough. Likewise, it may be very difficult to get an opportunity to utilize the construction hoist for temporary needs.
  • the US 2,298,462 discloses an elevator which is designed for the use in a scaffolding tower.
  • This elevator comprises a hoisting device which is securd via channel support members to the scaffold tower of the building under construction.
  • This solution necessitates a scaffolding tower to realise the elevator.
  • this solution can only be used for building sites in a very early construction stage. with this solution is that the thrust platform and the machine room are secured to the floors of the building already during construction time.
  • a group consisting of several elevators may have a total weight of several thousands of kilograms, which is a load too big and risky for floors still partly unfinished.
  • the ceiling between the elevators in a four-elevator group is relatively weak and can not withstand such loads.
  • the constructor may have to make extra openings in the structures to accommodate installation-time reinforcements.
  • a further problem with this solution is that the machine room can only be lifted one floor-to-floor distance at a time, which means that each lifting operation always involves the same additional preparatory arrangements and work, which together require plenty of extra construction time.
  • the object of the present invention is to overcome the above-mentioned drawbacks and to facilitate and accelerate construction-time elevator installation by providing an economical and reliable method for construction-time installation of an elevator that is easy and simple to implement.
  • An additional object is to achieve an apparatus for enabling construction-time installation of an elevator.
  • the method of the invention for construction-time installation of an elevator is characterized by what is disclosed in the characterization part of claim 1, and the elevator for construction-time installation of an elevator is characterized by what is disclosed in the characterization part of claim 6.
  • Other embodiments of the invention are characterized by what is disclosed in the other claims.
  • the main steps of the elevator installation process are as follows. After the constructor has first mounted in the shaft 1 a movable and waterproof supporting platform 7, which is secured to the floor slab of e.g. the fifth floor, the actual elevator installation work is started. First, a working platform 8 and an auxiliary hoist for the hoisting of elevator components are secured to the supporting platform 7. Furthermore, the working platform 8 is provided with slide shoes by means of which the working platform is guided by the elevator guide rails. After this, in the actual first stage of installation, the elevator guide rails 2 and the counterweight guide rails, the latter being omitted from the figures for the sake of clarity, are secured to the lower part of the shaft 1. During this stage, five guide bars are mounted one above the other, of which the bottommost and the topmost guide bars 10 are shorter than the other three bars, which are of equal length. With normal floor height, the guide rails now extend nearly to the height of the fifth floor.
  • the frame of the counterweight 11, the landing doors as well as the lighting and electrification of the shaft are installed up to a level as high as possible at this stage.
  • the equipment is installed up to the level of the fifth floor.
  • a temporary frame is built for the elevator machine room 4, and the machine room together with a hoisting machine 5 and a control panel is mounted in this frame and placed on the foundation floor of the elevator.
  • an overspeed governor is installed in the machine room and likewise a hoist 17 serving as a lifting means, by means of which the future jump lifts are to be performed.
  • the hoisting points for the hoisting rope 18 or equivalent of the hoist are secured to the upper ends of the elevator guide rails by means of a special, easily releasable securing structure 19 designed for this purpose.
  • the hoist 17 itself is well secured to the machine room and it is used to pull the machine room upwards in connection with a jump lift by means of the hoisting rope or equivalent supported by the upper ends of the elevator guide rails. If the working platform 8 is an obstruction to movement of the securing structure 19, it can be removed to a suitable place for the time it takes to perform the jump lift.
  • Fig. 1 illustrates a fourth stage of installation, wherein the machine room 4 has been lifted to the level of the second floor and the elevator car 3 is installed in the shaft on the foundation floor by building a car frame and securing the wall, ceiling and floor elements of the car to each other and to the car frame.
  • the electrification of the car can also be implemented.
  • the car is provided with a door and the finishing of the car is completed.
  • the elevator is also provided with a hoisting rope, which is as yet coiled on a rope drum.
  • the elevator car 3 is also connected to the machine room 4 e.g. by means of chains 6 to allow a jump lift.
  • a fifth stage as illustrated by Fig. 2 the combination of machine room and elevator car is hoisted upwards through one floor-to-floor distance by means of the hoist 17 and the combination is secured to the elevator guide rails 2 already installed.
  • the currently topmost tie plate of the elevator guide rails is fixed firmly in place.
  • the waterproof supporting platform 7 is raised five floors upwards for a future jump lift and secured to the floor slab.
  • the installation process is now continued by mounting in the next five-floor section the required piping and electrical equipment as well as the elevator guide rails 2, counterweight guide rails and landing doors.
  • a seventh stage as illustrated by Fig. 3 the actual jump lift is carried out.
  • the elevator machine room 4 together with the elevator car 3 is pulled upwards through five floor-to-floor distances, the elevator car being thus lifted from the first floor level to the sixth floor level.
  • the lifting is performed by means of the hoist 17, the lifting force being received by the supporting points at the upper ends of the elevator guide rails 2.
  • the load resulting from the lifting is evenly distributed on the elevator guide rails 2, so the lifting does not produce any stress on the building's own structures, such as walls, intermediate floor slabs or elevator shaft walls.
  • the combination of machine room and elevator car is secured uniformly to the elevator guide rails 2 already installed.
  • the currently topmost tie plate of the elevator guide rails is again secured firmly in place.
  • Fig. 4 illustrates an eighth stage of installation, wherein the required roping is installed.
  • the elevator ropes 13 are passed from the traction sheave of the machine 5 around the deflecting pulley 14 in the car frame to their fixing point, and similarly the counterweight ropes 15 are passed around a deflecting pulley 16 in the frame of the counterweight 11 to their fixing point.
  • the overspeed governor rope 12 is installed.
  • the elevator is also balanced by adding the required weights to the counterweight frame.
  • the required shaft components and switches are installed, whereupon the elevator is ready for inspection and operation within the six lowest floors.
  • the waterproof supporting platform 7 is again raised five floors upwards for a future jump lift and secured to the floor slab.
  • the installation process is now continued through the next five floors upwards in a manner corresponding to the above-described stages 6-8.
  • the installation work is carried on by this method in jumps of five floors at a time, making the elevator ready for operation at levels higher and higher up in the building as the construction work progresses.

Abstract

The invention also relates to a method for installing an elevator provided with a machine room and suspended by hoisting ropes (15) and moving along guide rails (2) during the construction stage of building. The elevator is provided with a hoisting device (17), by means of which the machine room (4), which is initially placed in the lower part of the elevator shaft (1), is lifted through one or more floor-to-floor distances at a time in the shaft in such manner that at least the vertical forces resulting from the lifting are transmitted to the bottom structures of the building substantially via the guide rails (2) already secured.

Description

  • The present invention relates to a method as defined in the preamble of claim 1 and to an elevator as defined in the preamble of claim 6.
  • In high-rise buildings, elevators are often needed during the construction stage before the building has been completed. Elevators are needed e.g. for construction-time use to allow the constructors to reach as high levels in the building as possible by elevator. Similarly, when the lower floors of a building are completed before the upper floors, the elevators must be available for use by the people already using the completed floors. As the construction work is progressing, the elevators have to be able to serve floors as high up as possible.
  • A prior-art solution for this type of construction-time use is the so-called jump-lift, wherein the hoisting height of the elevator is increased in steps of one or more floor levels each time when the construction work has reached a sufficient height relative to the previous jump. The elevator machine room is removed upwards by the above-mentioned number of floors and all the components dependent on the hoisting height, such as car cables, overspeed governor ropes and other components mounted in the shaft, electric equipment in the shaft, shaft cables, compensation ropes etc. are extended to cover the height of the entire completed shaft.
  • In prior art, the machine room has been lifted by using the building's own construction hoist, among other things. The problem in this case is that the elevator installation is dependent on the use of the construction hoist. The construction hoist may be needed elsewhere on the building site at the same time, in which case the hoist will not be available for use at the desired time or for a time long enough. Likewise, it may be very difficult to get an opportunity to utilize the construction hoist for temporary needs.
  • Another prior-art solution for the installation of an elevator is disclosed in PCT specification no. WO00/07923 , wherein, instead of utilizing the construction hoist, the elevator machine room is lifted one level at a time by utilizing a thrust platform and lifting cylinders or equivalent. A problem
  • The US 2,298,462 discloses an elevator which is designed for the use in a scaffolding tower. This elevator comprises a hoisting device which is securd via channel support members to the scaffold tower of the building under construction. This solution necessitates a scaffolding tower to realise the elevator. Anyway, already after finishing the basic elements of the buidling under construction alread in early stages of the construction, there is no scaffolding tower left, particularly if lower floors are already completed and are going to be put into use. Therefore this solution can only be used for building sites in a very early construction stage. with this solution is that the thrust platform and the machine room are secured to the floors of the building already during construction time. A group consisting of several elevators may have a total weight of several thousands of kilograms, which is a load too big and risky for floors still partly unfinished. For example, the ceiling between the elevators in a four-elevator group is relatively weak and can not withstand such loads. Another problem is that the constructor may have to make extra openings in the structures to accommodate installation-time reinforcements. A further problem with this solution is that the machine room can only be lifted one floor-to-floor distance at a time, which means that each lifting operation always involves the same additional preparatory arrangements and work, which together require plenty of extra construction time.
  • The object of the present invention is to overcome the above-mentioned drawbacks and to facilitate and accelerate construction-time elevator installation by providing an economical and reliable method for construction-time installation of an elevator that is easy and simple to implement. An additional object is to achieve an apparatus for enabling construction-time installation of an elevator.
  • The method of the invention for construction-time installation of an elevator is characterized by what is disclosed in the characterization part of claim 1, and the elevator for construction-time installation of an elevator is characterized by what is disclosed in the characterization part of claim 6. Other embodiments of the invention are characterized by what is disclosed in the other claims.
  • By applying the invention, one or more the following advantages can be achieved, among others:
    • installation of the elevator can be started at a very early stage of construction
    • the elevator machine room and all the equipment are lifted using a separate lifting arrangement developed for the elevator
    • the construction hoist of the building is not needed, and thus other construction work is not disturbed or retarded
    • elevator installation is independent of the use of the building crane
    • the machine room need not be supported on the walls of the elevator shaft or on the intermediate floor slabs
    • all or at least part of the weight of the machine room, elevator car and counterweight can be borne by the elevator guide rails during elevator installation
    • elevator installation produces no extra loads on the walls and intermediate floor slabs
    • no extra openings and reinforcements for elevator installation need to be made in the concrete structures of the building
    • the invention enables a transportation capacity and logistics utilization at least four times better than in prior-art construction-time elevators
    • allows savings in time by constructors and sub-contractors and leads to faster completion of the building project
    • less work needed for lifting the machine room
    • elevator installation times are shortened and the total installation costs reduced
    • safer installation environment
    • finished floors are ready for normal elevator operation very soon after their completion
    • the façade of the building can be finished earlier than normal
    • lower energy consumption than in prior-art techniques
    • less space is needed outside the building
    • easy to establish as a standard installation method.
  • In the following, the invention will be described in detail by the aid of an embodiment example with reference to the attached drawings, wherein
    • Fig. 1 presents a diagrammatic front view of an elevator installation situation according to the invention where the elevator car has already been installed on the foundation floor,
    • Fig. 2 presents a diagrammatic front view of an elevator installation situation according to the invention where the elevator car has been lifted to the first floor,
    • Fig. 3 presents a diagrammatic front view of an elevator installation situation according to the invention where a jump lift has been carried out and the elevator car has been lifted to the sixth floor, and
    • Fig. 4 presents a diagrammatic front view of an elevator installation according to the invention where a jump lift has been carried out and the elevator hoisting ropes as well as the overspeed governor rope have been installed at this height.
  • According to the method of the invention, the main steps of the elevator installation process are as follows. After the constructor has first mounted in the shaft 1 a movable and waterproof supporting platform 7, which is secured to the floor slab of e.g. the fifth floor, the actual elevator installation work is started. First, a working platform 8 and an auxiliary hoist for the hoisting of elevator components are secured to the supporting platform 7. Furthermore, the working platform 8 is provided with slide shoes by means of which the working platform is guided by the elevator guide rails. After this, in the actual first stage of installation, the elevator guide rails 2 and the counterweight guide rails, the latter being omitted from the figures for the sake of clarity, are secured to the lower part of the shaft 1. During this stage, five guide bars are mounted one above the other, of which the bottommost and the topmost guide bars 10 are shorter than the other three bars, which are of equal length. With normal floor height, the guide rails now extend nearly to the height of the fifth floor.
  • In a second stage of the installation process, the frame of the counterweight 11, the landing doors as well as the lighting and electrification of the shaft are installed up to a level as high as possible at this stage. In the example, the equipment is installed up to the level of the fifth floor.
  • In a third stage of installation, a temporary frame is built for the elevator machine room 4, and the machine room together with a hoisting machine 5 and a control panel is mounted in this frame and placed on the foundation floor of the elevator. At the same time, an overspeed governor is installed in the machine room and likewise a hoist 17 serving as a lifting means, by means of which the future jump lifts are to be performed. The hoisting points for the hoisting rope 18 or equivalent of the hoist are secured to the upper ends of the elevator guide rails by means of a special, easily releasable securing structure 19 designed for this purpose. The hoist 17 itself is well secured to the machine room and it is used to pull the machine room upwards in connection with a jump lift by means of the hoisting rope or equivalent supported by the upper ends of the elevator guide rails. If the working platform 8 is an obstruction to movement of the securing structure 19, it can be removed to a suitable place for the time it takes to perform the jump lift.
  • Fig. 1 illustrates a fourth stage of installation, wherein the machine room 4 has been lifted to the level of the second floor and the elevator car 3 is installed in the shaft on the foundation floor by building a car frame and securing the wall, ceiling and floor elements of the car to each other and to the car frame. At this stage, the electrification of the car can also be implemented. Moreover, the car is provided with a door and the finishing of the car is completed. At this stage the elevator is also provided with a hoisting rope, which is as yet coiled on a rope drum. In connection with the fourth stage, the elevator car 3 is also connected to the machine room 4 e.g. by means of chains 6 to allow a jump lift.
  • In a fifth stage as illustrated by Fig. 2, the combination of machine room and elevator car is hoisted upwards through one floor-to-floor distance by means of the hoist 17 and the combination is secured to the elevator guide rails 2 already installed. At this stage also the currently topmost tie plate of the elevator guide rails is fixed firmly in place.
  • In a sixth stage of installation, the waterproof supporting platform 7 is raised five floors upwards for a future jump lift and secured to the floor slab. The installation process is now continued by mounting in the next five-floor section the required piping and electrical equipment as well as the elevator guide rails 2, counterweight guide rails and landing doors.
  • In a seventh stage as illustrated by Fig. 3, the actual jump lift is carried out. The elevator machine room 4 together with the elevator car 3 is pulled upwards through five floor-to-floor distances, the elevator car being thus lifted from the first floor level to the sixth floor level. The lifting is performed by means of the hoist 17, the lifting force being received by the supporting points at the upper ends of the elevator guide rails 2. Thus, the load resulting from the lifting is evenly distributed on the elevator guide rails 2, so the lifting does not produce any stress on the building's own structures, such as walls, intermediate floor slabs or elevator shaft walls. After the jump lift has been carried out, the combination of machine room and elevator car is secured uniformly to the elevator guide rails 2 already installed. In addition, the currently topmost tie plate of the elevator guide rails is again secured firmly in place.
  • Fig. 4 illustrates an eighth stage of installation, wherein the required roping is installed. The elevator ropes 13 are passed from the traction sheave of the machine 5 around the deflecting pulley 14 in the car frame to their fixing point, and similarly the counterweight ropes 15 are passed around a deflecting pulley 16 in the frame of the counterweight 11 to their fixing point. In addition, the overspeed governor rope 12 is installed. During this stage, the elevator is also balanced by adding the required weights to the counterweight frame. In addition, the required shaft components and switches are installed, whereupon the elevator is ready for inspection and operation within the six lowest floors.
  • In the next stage, the waterproof supporting platform 7 is again raised five floors upwards for a future jump lift and secured to the floor slab. The installation process is now continued through the next five floors upwards in a manner corresponding to the above-described stages 6-8. The installation work is carried on by this method in jumps of five floors at a time, making the elevator ready for operation at levels higher and higher up in the building as the construction work progresses.
  • It is obvious to the person skilled in the art that different embodiments of the invention are not limited to the example described above, but that they may be varied within the scope of the claims presented below. In accordance with the examples described above, the skilled person may vary an embodiment of the invention e.g. by using a jump lift distance other than a five-floor distance as mentioned above. Depending on the circumstances, any distance equal to a floor height may be the most appropriate distance. Therefore, all floor-to-floor distances between 1...8 and suitably e.g. between 3...7 or between 4...6 may be mentioned.
  • It is also obvious to the skilled person that the order of different details of the installation method as well as the working method may vary. Likewise, the use and mode or operation of the hoist used for lifting the machine room may differ from the above description.

Claims (9)

  1. Method for installing an elevator provided with a machine room and hoisting ropes (15) and moving along guide rails (2) in a building during the construction stage, characterized in that the machine room (4), which is initially placed in the lower part of the elevator shaft (1), is lifted through one or more floor-to-floor distances at a time in the shaft in such manner that at least the vertical forces resulting from the lifting are transmitted to the bottom structures of the building substantially via the guide rails (2) already secured.
  2. Method according to claim 1, characterized in that, in connection with the lifting of the machine room (4), a hoisting device (17) mounted on the machine room (4) is connected via a hoisting rope (18) or equivalent to a securing structure (19) supported by the upper ends of the elevator guide rails (2).
  3. Method according to claim 1 or 2, characterized in that, in conjunction with the lifting of the machine room (4), an elevator car (3) temporarily connected to the machine room is lifted at the same time through a corresponding distance upwards.
  4. Method according to claim 1, 2 or 3, characterized in that the machine room (4) and the elevator car (3) are lifted through a distance corresponding to 1...8 floor-to-floor distances, suitably 3...7 floor-to-floor distances and preferably 5 floor-to-floor distances at a time.
  5. Method according to any one of the preceding claims, characterized in that, each time after the machine room (4) and elevator car (3) have been lifted, the machine room and elevator car are secured to the elevator guide rails (2), whereupon the securing structure (19) of the hoisting device (17) is released from the upper end of the guide rails (2).
  6. Elevator comprising a machine room (4) and hoisting ropes (15) and moving along guide rails (2) in a building, said elevator further comprises at least a hoisting device (17) designed for lifting the machine room (4) temporarily placed in the elevator shaft during the construction stage, characterized in that the hoisting device (17) is connected (19) to the already installed guide rails (2) so as to transmit at least the vertical forces resulting from the lifting substantially via the already secured guide rails (2) to the bottom structures of the building.
  7. Elevator according to claim 6, characterized in that the hoisting device (17) is a hoist secured to a structure of the machine room (4) and connected via a hoisting rope (18) or equivalent to the upper ends of the guide rails (2) already installed.
  8. Elevator according to claim 6 or 7, characterized in that the hoisting device (17) is connected to the upper ends of the guide rails (2) already installed by means of a releasable securing structure (19), which is designed to distribute the forces resulting from the lifting substantially evenly on the two guide rails (2).
  9. Elevator according to claim 6,7 or 8, characterized in that the length of the hoisting rope (18) or equivalent of the hoisting device (17) has been fitted to be such that the machine room (4) can be lifted through at least 1... 8 floor-to-floor distances at a time.
EP03775427A 2002-12-02 2003-11-26 Method and apparatus for installing an elevator during construction of a building Expired - Lifetime EP1583710B1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
FI20022122 2002-12-02
FI20022122A FI114458B (en) 2002-12-02 2002-12-02 Method and apparatus for installing a lift during the construction phase of a building
PCT/FI2003/000903 WO2004050526A1 (en) 2002-12-02 2003-11-26 Method and apparatus for installing an elevator during construction of a building

Publications (2)

Publication Number Publication Date
EP1583710A1 EP1583710A1 (en) 2005-10-12
EP1583710B1 true EP1583710B1 (en) 2008-02-13

Family

ID=8565016

Family Applications (1)

Application Number Title Priority Date Filing Date
EP03775427A Expired - Lifetime EP1583710B1 (en) 2002-12-02 2003-11-26 Method and apparatus for installing an elevator during construction of a building

Country Status (9)

Country Link
EP (1) EP1583710B1 (en)
CN (1) CN1313349C (en)
AT (1) ATE385987T1 (en)
AU (1) AU2003283459B2 (en)
DE (1) DE60319143T2 (en)
ES (1) ES2297237T3 (en)
FI (1) FI114458B (en)
HK (1) HK1080822A1 (en)
WO (1) WO2004050526A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010136636A1 (en) * 2009-05-28 2010-12-02 Kone Corporation Method for installing the hoisting roping of an elevator
US8616340B2 (en) 2009-03-06 2013-12-31 Kone Corporation Elevator arrangement and method

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI118335B (en) 2004-07-30 2007-10-15 Kone Corp Elevator
FI117335B (en) * 2004-07-30 2006-09-15 Kone Corp Method of lift installation and lift
FI20041044A (en) 2004-07-30 2006-02-08 Kone Corp Elevator
EP1785386A1 (en) * 2005-11-09 2007-05-16 Inventio Ag Method for installing an elevator system and elevator system therefor
SG132591A1 (en) 2005-11-09 2007-06-28 Inventio Ag Method of constructing a lift installation, and lift installation for that purpose
FI118644B (en) * 2006-11-17 2008-01-31 Kone Corp Elevator installing method for use during construction of tall building, involves dismounting machine room of elevator provided with room, and converting elevator into elevator without machine room by placing hoisting machine
FI20090134A (en) * 2009-04-06 2010-10-07 Kone Corp Elevator arrangement and procedure
FI20100223A0 (en) * 2010-05-28 2010-05-28 Kone Corp Procedure and lift arrangement
FI20106273A (en) * 2010-12-01 2012-06-02 Kone Corp Elevator system and procedure
CN102502378A (en) * 2011-11-15 2012-06-20 中建三局建设工程股份有限公司 Climbing elevator for building construction
FI20116190L (en) * 2011-11-28 2013-05-29 Kone Corp Lift arrangement and method
US9388020B2 (en) 2012-03-06 2016-07-12 Kone Corporation Method and an elevator arrangement
EP2636629B1 (en) 2012-03-06 2015-05-06 KONE Corporation A method and an elevator arrangement
CN104340813B (en) * 2014-10-30 2016-09-14 中国建筑股份有限公司 A kind of installation construction method for elevator
EP3127847B1 (en) * 2015-08-07 2017-12-20 KONE Corporation An arrangement and a method for measuring the position of an installation platform in an elevator shaft
CN105668472A (en) * 2016-04-25 2016-06-15 上海爱登堡电梯(宜昌)有限公司 Mounting device of super-high-rise building elevator
DE102018208588A1 (en) * 2018-05-30 2019-07-04 Thyssenkrupp Ag Installation of a lift system with linear motor
CN112566864B (en) * 2018-08-16 2022-04-15 三菱电机株式会社 Application method of lift extension technology of elevator
CN112867688B (en) * 2018-10-15 2023-05-23 通力股份公司 Method for installing guide rail of elevator in well and installation device of guide rail of elevator
CN109436985A (en) * 2018-11-15 2019-03-08 上海建工建集团有限公司 A kind of mould bases and its construction method for hoisting elevator
CN111302187B (en) * 2018-12-11 2022-09-27 奥的斯电梯公司 Lifting assembly, jump elevator and jump method
CN109592545A (en) * 2019-01-18 2019-04-09 通力电梯有限公司 Temporary machine room and duplex elevator for duplex elevator
WO2021038629A1 (en) * 2019-08-23 2021-03-04 株式会社日立製作所 Construction elevator device
CN110817661A (en) * 2019-10-22 2020-02-21 日立电梯(上海)有限公司 Elevator system used during construction
EP3865448A1 (en) * 2020-02-12 2021-08-18 KONE Corporation Method for constructing elevator
CN113620147A (en) 2020-05-09 2021-11-09 奥的斯电梯公司 Jump elevator system and jump method used in building construction
US11383959B1 (en) * 2021-02-03 2022-07-12 Otis Elevator Company Method for expanding a rise of an elevator hoistway

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3298462A (en) * 1966-01-17 1967-01-17 Beaver Advance Corp Traction lift for scaffolding towers
US3519101A (en) * 1968-01-10 1970-07-07 Otis Elevator Co Construction elevator system
US3759349A (en) * 1972-03-13 1973-09-18 Otis Elevator Co Elevator system with temporary hoistway structure and method for use thereof
JPH07237847A (en) * 1994-03-01 1995-09-12 Otis Elevator Co Installation method of elevator
CN2236477Y (en) * 1995-05-08 1996-10-02 大连第二建筑工程公司 High bulk material lifting apparatus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8616340B2 (en) 2009-03-06 2013-12-31 Kone Corporation Elevator arrangement and method
WO2010136636A1 (en) * 2009-05-28 2010-12-02 Kone Corporation Method for installing the hoisting roping of an elevator

Also Published As

Publication number Publication date
FI20022122A0 (en) 2002-12-02
AU2003283459B2 (en) 2009-11-05
ATE385987T1 (en) 2008-03-15
AU2003283459A1 (en) 2004-06-23
CN1703367A (en) 2005-11-30
DE60319143T2 (en) 2008-05-21
DE60319143D1 (en) 2008-03-27
HK1080822A1 (en) 2006-05-04
EP1583710A1 (en) 2005-10-12
FI114458B (en) 2004-10-29
WO2004050526A1 (en) 2004-06-17
ES2297237T3 (en) 2008-05-01
FI20022122A (en) 2004-06-03
CN1313349C (en) 2007-05-02

Similar Documents

Publication Publication Date Title
US7635049B2 (en) Method and apparatus for installing an elevator during the construction of a building
EP1583710B1 (en) Method and apparatus for installing an elevator during construction of a building
EP2490973B1 (en) Method in the manufacture of an elevator
AU2007321143B2 (en) Method and apparatus for installing an elevator without machine room during construction of a building, and use of a hoisting machine
US8291568B2 (en) Method of installing an elevator
EP2435350B1 (en) Method for installing the hoisting roping of an elevator
EP1789357B1 (en) Method for installing an elevator, and elevator
EP2247522B1 (en) Method for installing an elevator and method for installing the guide rails of an elevator
WO1998040305A1 (en) Procedure and apparatus for the installation of an elevator
CN209052240U (en) A kind of tool for super high-rise building duplex elevator vertical transport
AU2019409113B2 (en) Building site device having a climbing formwork and an elevator system
JP6813123B2 (en) How to apply elevator lift extension technology
JPH05201648A (en) Installation of elevator

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20050224

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL LT LV MK

RAX Requested extension states of the european patent have changed

Extension state: LV

Payment date: 20050224

Extension state: LT

Payment date: 20050224

17Q First examination report despatched

Effective date: 20061017

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RIC1 Information provided on ipc code assigned before grant

Ipc: B66B 7/00 20060101AFI20070515BHEP

Ipc: B66B 19/00 20060101ALN20070515BHEP

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: LT LV

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

Ref country code: CH

Ref legal event code: NV

Representative=s name: ABACUS PATENTANWAELTE KLOCKE SPAETH BARTH

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REF Corresponds to:

Ref document number: 60319143

Country of ref document: DE

Date of ref document: 20080327

Kind code of ref document: P

REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2297237

Country of ref document: ES

Kind code of ref document: T3

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

ET Fr: translation filed
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080714

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20081114

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080513

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081126

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081126

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080814

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080514

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 13

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 14

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 15

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20181120

Year of fee payment: 16

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IT

Payment date: 20181126

Year of fee payment: 16

REG Reference to a national code

Ref country code: SE

Ref legal event code: EUG

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20191130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191127

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191126

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191130

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20201125

Year of fee payment: 18

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20201118

Year of fee payment: 18

Ref country code: FR

Payment date: 20201120

Year of fee payment: 18

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: ES

Payment date: 20210122

Year of fee payment: 18

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: NL

Ref legal event code: MM

Effective date: 20211201

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211130

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211201

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211130

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20221125

Year of fee payment: 20

Ref country code: DE

Payment date: 20221123

Year of fee payment: 20

REG Reference to a national code

Ref country code: ES

Ref legal event code: FD2A

Effective date: 20230213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211127

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20230525

REG Reference to a national code

Ref country code: DE

Ref legal event code: R071

Ref document number: 60319143

Country of ref document: DE

REG Reference to a national code

Ref country code: GB

Ref legal event code: PE20

Expiry date: 20231125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20231125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20231125