CN112566864B - Application method of lift extension technology of elevator - Google Patents

Application method of lift extension technology of elevator Download PDF

Info

Publication number
CN112566864B
CN112566864B CN201880096384.8A CN201880096384A CN112566864B CN 112566864 B CN112566864 B CN 112566864B CN 201880096384 A CN201880096384 A CN 201880096384A CN 112566864 B CN112566864 B CN 112566864B
Authority
CN
China
Prior art keywords
unit
car
pit
counterweight
hoistway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201880096384.8A
Other languages
Chinese (zh)
Other versions
CN112566864A (en
Inventor
浅井贵行
古平大登
井村光芳
荻原诚
安藤英司
仓冈尚生
近藤力雄
古泽央至
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Publication of CN112566864A publication Critical patent/CN112566864A/en
Application granted granted Critical
Publication of CN112566864B publication Critical patent/CN112566864B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators
    • B66B5/28Buffer-stops for cars, cages, or skips
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • B66B9/16Mobile or transportable lifts specially adapted to be shifted from one part of a building or other structure to another part or to another building or structure
    • B66B9/187Mobile or transportable lifts specially adapted to be shifted from one part of a building or other structure to another part or to another building or structure with a liftway specially adapted for temporary connection to a building or other structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Transportation (AREA)
  • Automation & Control Theory (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

Provided is a method for applying lift extension technology of an elevator, which can eliminate the restriction of the maximum height capable of providing service through the elevator. The application method of the lift extension technology of the elevator comprises the following steps: a 1 st elevation stroke extension step of raising a relative position of the machine room unit (3) with respect to a pit unit (7), the pit unit (7) carrying at least one of a car buffer (8) and a counterweight buffer (9) and being capable of elevating in the hoistway below the machine room unit (3); a lifting stroke moving step of moving a lifting stroke according to the progress of building construction by lifting the pit unit (7) in a direction in which a machine room unit (3) on which the temporary setting hoisting machine (4) is mounted is lifted; and a 2 nd lifting stroke extension step of setting a tractor (14) for formal installation, and lowering the position of the pit unit (7) or setting a pit device for new installation.

Description

电梯的扬程延长技术的应用方法Application method of lift extension technology of elevator

技术领域technical field

本发明涉及电梯的扬程延长技术的应用方法。The invention relates to an application method of lift extension technology of elevators.

背景技术Background technique

扬程延长式电梯是轿厢的升降行程根据建筑施工的进展而依次被延长的电梯。在扬程延长式电梯中,通过使搭载有曳引机的机房单元在井道内上升来延长轿厢的升降行程。根据这样的电梯,能够高效地搬运建筑施工的作业人员及材料等。作为扬程延长式电梯,例如有专利文献1中公开的电梯。The lift-extended elevator is an elevator in which the lift of the car is sequentially extended according to the progress of the construction. In the lift-extended elevator, the lift stroke of the car is extended by raising the machine room unit on which the hoisting machine is mounted in the hoistway. According to such an elevator, it is possible to efficiently transport workers, materials, and the like for building construction. As an elevator of the extended lift type, there is an elevator disclosed in Patent Document 1, for example.

现有技术文献prior art literature

专利文献Patent Literature

专利文献1:欧洲专利第2804828号说明书Patent Document 1: Specification of European Patent No. 2804828

发明内容SUMMARY OF THE INVENTION

发明要解决的课题The problem to be solved by the invention

电梯的升降行程存在与曳引机的能力对应的极限值。由于在井道中能够配置机房单元的空间的制约,不可能在机房单元搭载大型曳引机。因此,在高层建筑物中,通过扬程延长式电梯能够提供服务的最大高度存在制约。The lift travel of the elevator has a limit value corresponding to the capacity of the hoisting machine. Due to the limitation of the space in which the machine room unit can be arranged in the hoistway, it is impossible to mount a large hoisting machine in the machine room unit. Therefore, in a high-rise building, there is a limit to the maximum height that can be served by an extended-lift elevator.

本发明是为了解决上述课题而完成的。其目的在于提供一种电梯的扬程延长技术的应用方法,能够消除通过电梯能够提供服务的最大高度的制约。The present invention has been made in order to solve the above-mentioned problems. The object of the invention is to provide an application method of the lift extension technology of an elevator, which can eliminate the restriction of the maximum height that can be served by the elevator.

用于解决课题的手段means of solving problems

本发明的电梯的扬程延长技术的应用方法包括如下的升降行程移动工序:在扬程延长式电梯中,通过使搭载有轿厢缓冲器以及对重缓冲器中的至少一个的底坑单元向搭载有曳引机的机房单元上升的方向上升,使升降行程根据建筑施工的进展而移动。The application method of the lift-extending technique of the elevator of the present invention includes the following step of moving the lift stroke: in the lift-extended elevator, the pit unit on which at least one of the car buffer and the counterweight buffer is mounted is moved to the elevator on which the lift is mounted. The machine room unit of the traction machine ascends in the ascending direction, so that the lifting stroke moves according to the progress of the building construction.

发明效果Invention effect

根据本发明,在升降行程移动工序中,使底坑单元向机房单元上升的方向上升。因此,能够消除电梯中能够提供服务的最大高度的制约。According to the present invention, in the lifting and lowering stroke moving step, the pit unit is raised in the direction in which the machine room unit is raised. Therefore, the restriction on the maximum height that can be serviced in the elevator can be eliminated.

附图说明Description of drawings

图1是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。1 : is a schematic diagram for demonstrating the application method of the lift extension technique of the elevator in Embodiment 1 (the case of the 2:1 roping ratio is shown).

图2是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。It is a schematic diagram for demonstrating the application method of the lift extension technique of the elevator in Embodiment 1 (it shows the case of 2:1 roping ratio).

图3是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。It is a schematic diagram for demonstrating the application method of the lift extension technique of the elevator in Embodiment 1 (it shows the case of 2:1 roping ratio).

图4是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。It is a schematic diagram for demonstrating the application method of the lift extension technique of the elevator in Embodiment 1 (it shows the case of 2:1 roping ratio).

图5是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。It is a schematic diagram for demonstrating the application method of the lift extension technique of the elevator in Embodiment 1 (it shows the case of 2:1 roping ratio).

图6是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图(示出2:1绕绳比的情况)。FIG. 6 is a schematic diagram for explaining a method of applying the lift extension technique of the elevator in Embodiment 1 (showing a case of a 2:1 roping ratio).

图7是示出实施方式1中的底坑单元的第1例的主视图。7 is a front view showing a first example of the pit unit in Embodiment 1. FIG.

图8是图7的A-A向视图。FIG. 8 is a view taken along the line A-A of FIG. 7 .

图9是图7的B-B向视图。FIG. 9 is a view taken along the line B-B of FIG. 7 .

图10是图7的C-C向视图。FIG. 10 is a view taken along the line C-C of FIG. 7 .

图11是示出实施方式1中的底坑单元的第2例的主视图。11 is a front view showing a second example of the pit unit in Embodiment 1. FIG.

图12是图11的A-A向视图。Fig. 12 is a view taken along the line A-A of Fig. 11 .

图13是图11的C-C向视图。FIG. 13 is a view taken along the line C-C of FIG. 11 .

图14是示出实施方式1中的底坑单元的第3例的主视图。14 is a front view showing a third example of the pit unit in Embodiment 1. FIG.

图15是图14的A-A向视图。FIG. 15 is a view taken along the line A-A of FIG. 14 .

图16是图14的B-B向视图。FIG. 16 is a view taken along the line B-B of FIG. 14 .

图17是图14的C-C向视图。FIG. 17 is a view taken along the line C-C of FIG. 14 .

图18是示出实施方式1中的底坑单元的第4例的主视图。18 is a front view showing a fourth example of the pit unit in Embodiment 1. FIG.

图19是图18的A-A向视图。Fig. 19 is a view taken along the line A-A of Fig. 18 .

图20是图18的C-C向视图。FIG. 20 is a view taken along the line C-C of FIG. 18 .

图21是用于说明实施方式1中的电梯的扬程延长技术的应用方法的步骤的流程图。21 is a flowchart for explaining the procedure of the application method of the lift extension technique of the elevator in Embodiment 1. FIG.

具体实施方式Detailed ways

以下,参照附图对实施方式进行说明。在各图中,对相同或相当的部分标注相同的标号。适当简化或省略重复的说明。Hereinafter, embodiments will be described with reference to the drawings. In each figure, the same reference numerals are attached to the same or corresponding parts. Duplicate descriptions are appropriately simplified or omitted.

实施方式1.Embodiment 1.

图1至图6是用于说明实施方式1中的电梯的扬程延长技术的应用方法的示意图。在图1至图6中虽然例示出绕绳方式为2:1绕绳比的情况,但是,电梯的扬程延长技术的应用方法还能够应用于绕绳方式为1:1绕绳比的情况。1 to 6 are schematic diagrams for explaining a method of applying the lift extension technique of the elevator in Embodiment 1. FIG. 1 to 6 illustrate the case where the roping method is a 2:1 roping ratio, the method of applying the lift extension technique of the elevator can also be applied to a case where the roping method is a 1:1 roping ratio.

图1至图6示出了建造中的建筑物的井道内的情况。例如,如图1所示,扬程延长式电梯具备轿厢1、对重2、机房单元3、临时设置用曳引机4、多个绳索5以及控制盘6。临时设置用曳引机4例如是不应对高行程的小型曳引机。Figures 1 to 6 show the situation in the hoistway of a building under construction. For example, as shown in FIG. 1 , the lift-extending elevator includes a car 1 , a counterweight 2 , a machine room unit 3 , a hoisting machine 4 for temporary installation, a plurality of ropes 5 , and a control panel 6 . The hoisting machine 4 for temporary installation is, for example, a small hoisting machine that cannot cope with a high stroke.

轿厢1能够由一对轿厢用导轨引导着在井道中升降。轿厢1例如能够相对于轿厢用导轨固定。对重2能够由一对对重用导轨引导着在井道中升降。对重2例如能够相对于对重用导轨固定。The car 1 can be raised and lowered in the hoistway while being guided by a pair of car guide rails. The cage|basket|car 1 can be fixed with respect to the guide rail for cage|basket|cars, for example. The counterweight 2 can be raised and lowered in the hoistway guided by a pair of counterweight guide rails. The counterweight 2 can be fixed relative to the counterweight guide rail, for example.

机房单元3例如能够由轿厢用导轨以及对重用导轨中的至少一方引导着在井道中升降。机房单元3例如能够相对于轿厢用导轨以及对重用导轨中的至少一方固定。机房单元3例如也可以固定于建造中的建筑物侧的结构体。该结构体也称为建筑结构体。The machine room unit 3 can be raised and lowered in the hoistway while being guided by, for example, at least one of the car guide rail and the counterweight guide rail. The machine room unit 3 can be fixed to, for example, at least one of the car guide rail and the counterweight guide rail. The machine room unit 3 may be fixed to, for example, a structure on the side of a building under construction. This structure is also called a building structure.

在机房单元3搭载有例如临时设置用曳引机4以及控制盘6。多个绳索5例如绕挂在临时设置用曳引机4的绳轮、轿厢1的悬吊轮以及对重2的悬吊轮上。绳索5的终端例如通过钩环(shackle)与机房单元3连接。绳索5的终端位于例如机房单元3的下端部。另外,在绕绳方式为1:1绕绳比的情况下,不设置轿厢1的悬吊轮以及对重2的悬吊轮,而将绳索5的终端例如通过钩环与轿厢1及对重2连接。For example, the hoisting machine 4 for temporary installation and the control panel 6 are mounted on the machine room unit 3 . The plurality of ropes 5 are wound around, for example, the sheave of the hoisting machine 4 for temporary installation, the suspension sheave of the car 1 , and the suspension sheave of the counterweight 2 . The ends of the ropes 5 are connected to the machine room unit 3, for example, by means of shackles. The end of the rope 5 is located, for example, at the lower end of the machine room unit 3 . In addition, when the roping method is a 1:1 roping ratio, the suspension sheave of the car 1 and the suspension sheave of the counterweight 2 are not provided, but the terminal end of the rope 5 is connected to the car 1 and the car 1 and the Counterweight 2 connections.

在机房单元3的下方设置有底坑单元7。在底坑单元7例如搭载有轿厢缓冲器8以及对重缓冲器9中的至少一方。轿厢缓冲器8位于轿厢1的正下方。对重缓冲器9位于对重2的正下方。A pit unit 7 is provided below the machine room unit 3 . For example, at least one of the car buffer 8 and the counterweight buffer 9 is mounted on the pit unit 7 . The car buffer 8 is located directly below the car 1 . The counterweight buffer 9 is located directly below the counterweight 2 .

在底坑单元7,例如也可以搭载未图示的补偿绳轮。在补偿绳轮上例如绕挂有补偿绳索,该补偿绳索连接轿厢1的下部和对重2的下部。在底坑单元7,例如也可以搭载未图示的轿厢张紧轮。在轿厢张紧轮上例如绕挂有轿厢限速器绳索。在底坑单元7,例如也可以搭载未图示的对重张紧轮。在对重张紧轮上例如绕挂有对重限速器绳索。For example, a compensation sheave not shown may be mounted on the pit unit 7 . For example, a compensating rope is wound around the compensating sheave, and the compensating rope connects the lower part of the car 1 and the lower part of the counterweight 2 . In the pit unit 7, for example, an unillustrated car tensioner may be mounted. For example, a car speed governor rope is wound around the car tensioning pulley. In the pit unit 7, for example, an unillustrated counterweight tensioner may be mounted. For example, a counterweight governor rope is wound around the counterweight tensioner.

底坑单元7例如能够由轿厢用导轨以及对重用导轨中的至少一方引导着在井道中升降。底坑单元7例如能够相对于轿厢用导轨以及对重用导轨中的至少一方固定。底坑单元7例如也可以固定于建造中的建筑物侧的结构体。该结构体也称为建筑结构体。The pit unit 7 can be raised and lowered in the hoistway while being guided by, for example, at least one of the car guide rail and the counterweight guide rail. The pit unit 7 can be fixed, for example, to at least one of the car guide rail and the counterweight guide rail. The pit unit 7 may be fixed to, for example, a structure on the side of a building under construction. This structure is also called a building structure.

当在轿厢1以及对重2的载荷被绳索5承受的状态下临时设置用曳引机4进行驱动时,轿厢1以及对重2在建造中的建筑物中的比机房单元3靠下方、并且比底坑单元7靠上方的范围内移动。该范围是轿厢1以及对重2在当前时刻的升降行程。临时设置用曳引机4例如由搭载于机房单元3的控制盘6控制。根据建筑施工的进展而延长轿厢1以及对重2的升降行程。When the hoisting machine 4 for temporary installation is driven in a state where the load of the car 1 and the counterweight 2 is received by the rope 5, the car 1 and the counterweight 2 are located below the machine room unit 3 in the building under construction. , and move within a range above the pit unit 7 . This range is the raising and lowering stroke of the car 1 and the counterweight 2 at the current time. The hoisting machine 4 for temporary installation is controlled by, for example, a control panel 6 mounted on the machine room unit 3 . The lifting and lowering strokes of the car 1 and the counterweight 2 are extended according to the progress of the building construction.

以下,使用图1至图6对电梯的扬程延长技术的应用方法进行说明。Hereinafter, the application method of the lift extension technique of an elevator is demonstrated using FIGS. 1-6.

电梯的扬程延长技术的应用方法包括第1升降行程延长工序。在第1升降行程延长工序中,将机房单元3相对于底坑单元7的相对位置拉起。在第1升降行程延长工序中,例如,使用提升装置10将机房单元3拉起到在当前时刻正在施工的上层楼层附近。图1例示出以底坑单元7设置在井道的底坑中的状态进行第1升降行程延长工序的情况。The application method of the lift extension technique of an elevator includes a 1st raising/lowering stroke extension process. In the 1st raising/lowering stroke extension process, the relative position of the machine room unit 3 with respect to the pit unit 7 is pulled up. In the 1st raising/lowering stroke extension process, for example, the machine room unit 3 is pulled up to the vicinity of the upper floor under construction at the present time using the hoisting device 10 . FIG. 1 illustrates a case where the first lifting stroke extension step is performed in a state where the pit unit 7 is installed in the pit of the hoistway.

用于机房单元3的拉起的提升装置10例如是塔式提升机或绞盘等。提升装置10例如通过安装于机房单元3的吊索11将机房单元3拉起。The hoisting device 10 for pulling up the machine room unit 3 is, for example, a tower hoist, a winch, or the like. The hoisting device 10 pulls up the machine room unit 3 by, for example, a sling 11 attached to the machine room unit 3 .

当在第1升降行程延长工序中机房单元3上升时,如图2所示,升降行程被延长。将到达目的高度的机房单元3被固定。图2例示出升降行程被延长到能够应用临时设置用曳引机4的最大升降行程后的情况。在图中,该最大升降行程被标记为“MAX.TR”。When the machine room unit 3 ascends in the first lifting and lowering stroke extension step, as shown in FIG. 2 , the lifting and lowering stroke is extended. The machine room unit 3 that will reach the target height is fixed. FIG. 2 illustrates a case where the lifting stroke is extended to the maximum lifting stroke to which the hoisting machine 4 for temporary installation can be applied. In the figure, this maximum lift travel is marked as "MAX.TR".

绳索5例如在每当升降行程被延长时被更换为更长的绳索。此外,例如,在绳索5从未图示的绕绳筒绕挂在临时设置用曳引机4等上的情况下,也可以根据延长后的升降行程从绕绳筒将绳索5送出。The rope 5 is replaced with a longer rope, for example, every time the lift stroke is extended. In addition, for example, when the rope 5 is wound around a hoisting machine 4 or the like for temporary installation from a not-shown rope reel, the rope 5 may be sent out from the rope reel according to an extended lifting and lowering stroke.

在图2的状态下,电梯例如能够在从最下层到当前时刻正在施工的上层楼层附近的范围内提供服务。In the state of FIG. 2 , for example, the elevator can provide service in the range from the lowest floor to the vicinity of the upper floor under construction at the present time.

电梯的扬程延长技术的应用方法包括升降行程移动工序。升降行程移动工序在机房单元3根据施工的进展而能够进一步上升的状态下进行。在升降行程移动工序中,机房单元3以及底坑单元7向上下方向上的相同的方向移动。The application method of the lift extension technology of the elevator includes the lifting stroke moving process. The raising and lowering stroke moving process is performed in a state in which the machine room unit 3 can be further raised in accordance with the progress of the construction. In the lift stroke movement process, the machine room unit 3 and the pit unit 7 are moved in the same direction in the up-down direction.

图3例示出在机房单元3与底坑单元7通过连结绳索12连结起来的状态下,使用提升装置10将机房单元3拉起的情况。即,图3例示出在升降行程移动工序中机房单元3以及底坑单元7同时被提升的情况。该情况下,即使在底坑单元7搭载有补偿绳轮,也不需要将补偿绳索从补偿绳轮卸下。FIG. 3 illustrates a state in which the machine room unit 3 and the pit unit 7 are connected by the connecting rope 12 , and the machine room unit 3 is pulled up using the hoisting device 10 . That is, FIG. 3 exemplifies the case where the machine room unit 3 and the pit unit 7 are lifted simultaneously in the lifting and lowering stroke moving process. In this case, even if the compensating sheave is mounted on the pit unit 7, it is not necessary to remove the compensating rope from the compensating sheave.

在升降行程移动工序中,例如,也可以不使用连结绳索12,而是分别提升机房单元3及底坑单元7。例如,在底坑单元7未搭载补偿绳轮的情况下,可以在拉起机房单元3以及底坑单元7中的一方之后,再拉起另一方。底坑单元7的拉起也可以使用提升装置10。底坑单元7的拉起还可以使用设置在机房单元3中的链滑车或绞盘等。In the lifting and lowering stroke moving process, for example, the machine room unit 3 and the pit unit 7 may be lifted separately without using the connecting rope 12 . For example, when the pit unit 7 is not equipped with a compensation sheave, one of the machine room unit 3 and the pit unit 7 may be pulled up, and then the other may be pulled up. The lifting device 10 can also be used for the lifting of the pit unit 7 . The pit unit 7 can also be pulled up by using a chain pulley or a winch or the like provided in the machine room unit 3 .

例如,在底坑单元7搭载有补偿绳轮的情况下,在升降行程移动工序中,也可以在从补偿绳轮卸下了补偿绳索的状态下,拉起机房单元3之后,再拉起底坑单元7。该情况下,能够通过一次的提升作业使机房单元3或者底坑单元7上升到目的高度。但是,该情况下,在拉起底坑单元7之后,需要在补偿绳轮上重新绕挂补偿绳索。For example, when the pit unit 7 is equipped with a compensating sheave, in the lifting and lowering stroke moving process, the machine room unit 3 may be pulled up after the compensating rope is removed from the compensating sheave, and then the bottom may be pulled up. Pit unit 7. In this case, the machine room unit 3 or the pit unit 7 can be raised to the target height by one lift operation. However, in this case, after the pit unit 7 is pulled up, it is necessary to rewind the compensation rope around the compensation sheave.

例如,在底坑单元7搭载有补偿绳轮的情况下,在升降行程移动工序中,也可以是,在补偿绳轮上绕挂有补偿绳索、并且轿厢1的下部和对重2的下部位于相同的高度的状态下,拉起底坑单元7之后,再拉起机房单元3。该情况下,虽然补偿绳索会暂时松弛,但不需要将补偿绳索从补偿绳轮卸下。但是,该情况下,由于能够通过一次的提升作业使机房单元3或底坑单元7上升的距离受到限制,因此可能需要多次的提升作业。For example, when the pit unit 7 is equipped with a compensating sheave, the compensating rope may be wound around the compensating sheave, and the lower part of the car 1 and the lower part of the counterweight 2 may be wound in the lifting and lowering stroke moving process. In a state of being at the same height, after the pit unit 7 is pulled up, the machine room unit 3 is pulled up. In this case, although the compensation rope is temporarily slack, it is not necessary to remove the compensation rope from the compensation sheave. However, in this case, since the distance over which the machine room unit 3 or the pit unit 7 can be lifted by one lift operation is limited, a plurality of lift operations may be required.

在升降行程移动工序中,当机房单元3以及底坑单元7上升时,如图4所示,升降行程本身上升。到达目的高度的机房单元3以及底坑单元7分别被固定。In the lifting stroke moving process, when the machine room unit 3 and the pit unit 7 rise, as shown in FIG. 4 , the lifting stroke itself rises. The machine room unit 3 and the pit unit 7 that have reached the target height are respectively fixed.

如图5所示,在升降行程移动工序之后,升降行程也能够维持在MAX.TR。在图5的状态下,电梯能够将上升后的底坑单元7作为临时设置底坑,为上层楼层提供服务。另外,在图5的状态下,电梯不能为比底坑单元7靠下方的楼层提供服务。但是,在图5所示的施工的进展阶段,由于其他低层用电梯已经开始运转,因此没有较大的障碍。As shown in FIG. 5 , even after the lifting and lowering stroke moving process, the lifting and lowering stroke can be maintained at MAX.TR. In the state of FIG. 5 , the elevator can use the raised pit unit 7 as a temporary pit to provide services for the upper floor. In addition, in the state of FIG. 5 , the elevator cannot serve the floor below the pit unit 7 . However, in the progress stage of the construction shown in FIG. 5, since other elevators for low-rise floors have already started to operate, there is no major obstacle.

通过反复进行使用图3至图5说明的升降行程移动工序,能够在维持能够应用临时设置用曳引机4的最大升降行程的状态下,使电梯的升降行程向上方移动。By repeating the hoisting stroke moving process described using FIGS. 3 to 5 , the hoisting stroke of the elevator can be moved upward while maintaining the maximum hoisting stroke that can be applied to the hoisting machine 4 for temporary installation.

电梯的扬程延长技术的应用方法包括第2升降行程延长工序。第2升降行程延长工序包括正式设置用曳引机设置工序以及底坑设备设置工序。正式设置用曳引机设置工序例如在施工工期结束后进行。在正式设置用曳引机设置工序中,如图6所示,将机房单元3以及临时设置用曳引机4撤除,在机房13中设置正式设置用曳引机14。在底坑设备设置工序中,例如,如图6所示,将底坑单元7降下至井道最下部。该情况下,底坑单元7被用作正式设置用的底坑设备。此外,在底坑设备设置工序中,也可以撤除在施工工期中作为临时设置用途而使用的底坑单元7,新设置与底坑单元7不同的正式设置用的底坑设备。当第2升降行程延长工序完成时,能够从建筑物的最下层到最上层提供电梯服务。The application method of the lift extension technique of an elevator includes a 2nd raising/lowering stroke extension process. The second elevating stroke extension process includes a main installation hoisting machine installation process and a pit equipment installation process. The hoisting machine installation process for formal installation is performed after, for example, the completion of the construction period. In the main installation hoisting machine installation step, as shown in FIG. 6 , the machine room unit 3 and the temporary installation hoisting machine 4 are removed, and the main installation hoisting machine 14 is installed in the machine room 13 . In the pit facility setting step, for example, as shown in FIG. 6 , the pit unit 7 is lowered to the lowest part of the hoistway. In this case, the pit unit 7 is used as a pit facility for formal installation. In addition, in the pit facility installation step, the pit unit 7 used for temporary installation during the construction period may be removed, and a pit facility for formal installation different from the pit unit 7 may be newly installed. When the second lifting and lowering stroke extension step is completed, the elevator service can be provided from the lowest floor to the uppermost floor of the building.

正式设置用曳引机14例如是与高行程对应的大型曳引机。在高层建筑物中,由于准备了比井道大的机房13,因此能够设置大型的正式设置用曳引机14。作为正式设置用曳引机14的控制盘,可以使用搭载于机房单元3的控制盘6,也可以使用其他控制盘。The hoisting machine 14 for formal installation is, for example, a large hoisting machine corresponding to a high stroke. In a high-rise building, since the machine room 13 larger than the hoistway is prepared, a large-scale hoisting machine 14 for formal installation can be installed. As the control panel of the hoisting machine 14 for formal installation, the control panel 6 mounted on the machine room unit 3 may be used, or another control panel may be used.

图7是示出实施方式1中的底坑单元的第1例的主视图。图8是图7的A-A向视图。图9是图7的B-B向视图。图10是图7的C-C向视图。7 is a front view showing a first example of the pit unit in Embodiment 1. FIG. FIG. 8 is a view taken along the line A-A of FIG. 7 . FIG. 9 is a view taken along the line B-B of FIG. 7 . FIG. 10 is a view taken along the line C-C of FIG. 7 .

以下,使用图7至图10对底坑单元7的第1例的结构进行说明。在该说明中,将图7中的近前侧作为前方、图7中的里侧作为后方而指定前后左右。Hereinafter, the configuration of the first example of the pit unit 7 will be described with reference to FIGS. 7 to 10 . In this description, front, rear, left and right are designated with the front side in FIG. 7 as the front and the back side in FIG. 7 as the rear.

在底坑单元7的第1例中,搭载有补偿绳轮15。补偿绳轮15设置在壳体16的内侧。在补偿绳轮15上绕挂有补偿绳索17。In the first example of the pit unit 7, the compensation sheave 15 is mounted. The compensation sheave 15 is provided inside the housing 16 . A compensation rope 17 is wound around the compensation sheave 15 .

底坑单元7的第1例具备轿厢侧缓冲器台18、对重侧缓冲器台19、轿厢侧缓冲器支承台20、对重侧缓冲器支承台21、轿厢侧缓冲器支承梁22、对重侧缓冲器支承梁23、缓冲器台连结梁24、补偿绳轮用轨道支承梁25、补偿绳轮用轨道26、轿厢侧第1引导部27、对重侧第1引导部28、轿厢侧第2引导部29以及对重侧第2引导部30。The first example of the pit unit 7 includes a car-side buffer table 18, a counterweight-side buffer table 19, a car-side buffer support table 20, a counterweight-side buffer support table 21, and a car-side buffer support beam 22. Counterweight side buffer support beam 23, buffer table connecting beam 24, compensating sheave rail support beam 25, compensating sheave rail 26, car side first guide portion 27, counterweight side first guide portion 28. The second guide portion 29 on the car side and the second guide portion 30 on the counterweight side.

轿厢侧缓冲器台18沿着前后方向配置在一对轿厢用导轨31之间。轿厢侧缓冲器台18支承轿厢侧缓冲器支承台20。轿厢侧缓冲器支承台20支承轿厢缓冲器8。根据底坑设备的布局性,在未配置轿厢侧缓冲器支承台20的情况下,轿厢侧缓冲器台18直接支承轿厢缓冲器8。The car-side buffer table 18 is arranged between the pair of car guide rails 31 along the front-rear direction. The car-side buffer table 18 supports the car-side buffer support table 20 . The car-side buffer support stand 20 supports the car buffer 8 . Depending on the layout of the pit facility, when the car-side buffer support table 20 is not arranged, the car-side buffer table 18 directly supports the car buffer 8 .

对重侧缓冲器台19沿着前后方向配置在一对对重用导轨32之间。对重侧缓冲器台19支承对重侧缓冲器支承台21。对重侧缓冲器支承台21支承对重缓冲器9。根据底坑设备的布局性,在未配置对重侧缓冲器支承台21的情况下,对重侧缓冲器台19直接支承对重缓冲器9。The counterweight-side buffer table 19 is arranged between the pair of counterweight guide rails 32 along the front-rear direction. The counterweight-side buffer table 19 supports the counterweight-side buffer support table 21 . The counterweight-side shock absorber support stand 21 supports the counterweight shock absorber 9 . Depending on the layout of the pit facility, when the counterweight-side buffer support table 21 is not disposed, the counterweight-side buffer table 19 directly supports the counterweight buffer 9 .

轿厢侧缓冲器支承梁22沿着前后方向配置在轿厢侧缓冲器台18的上方。轿厢侧缓冲器支承梁22从左侧支承轿厢缓冲器8。The car-side buffer support beam 22 is arranged above the car-side buffer table 18 in the front-rear direction. The car-side buffer support beam 22 supports the car buffer 8 from the left side.

对重侧缓冲器支承梁23沿着前后方向配置在对重侧缓冲器台19的上方。对重侧缓冲器支承梁23从右侧支承对重缓冲器9。The counterweight-side shock absorber support beam 23 is arranged above the counterweight-side shock absorber table 19 in the front-rear direction. The counterweight-side shock absorber support beam 23 supports the counterweight shock absorber 9 from the right side.

一对缓冲器台连结梁24沿着左右方向将轿厢侧缓冲器台18的上表面和对重侧缓冲器台19的上表面连结起来。一个缓冲器台连结梁24配置在比轿厢缓冲器8以及对重缓冲器9靠前方的位置。另一个缓冲器台连结梁24配置在比轿厢缓冲器8以及对重缓冲器9靠后方的位置。The pair of buffer table connecting beams 24 connects the upper surface of the car-side buffer table 18 and the upper surface of the counterweight-side buffer table 19 in the left-right direction. One buffer table connecting beam 24 is arranged in front of the car buffer 8 and the counterweight buffer 9 . The other buffer table connecting beam 24 is arranged behind the car buffer 8 and the counterweight buffer 9 .

一对补偿绳轮用轨道支承梁25沿着左右方向将轿厢侧缓冲器支承梁22和对重侧缓冲器支承梁23连结起来。一个补偿绳轮用轨道支承梁25配置在比轿厢缓冲器8以及对重缓冲器9靠前方的位置。另一个补偿绳轮用轨道支承梁25配置在比轿厢缓冲器8以及对重缓冲器9靠后方的位置。A pair of rail support beams 25 for compensating sheaves connect the car-side shock absorber support beam 22 and the counterweight-side shock absorber support beam 23 in the left-right direction. One compensating sheave rail support beam 25 is arranged in front of the car buffer 8 and the counterweight buffer 9 . The other rail support beam 25 for compensating sheaves is arrange|positioned in the position behind the cage|basket|car buffer 8 and the counterweight buffer 9. FIG.

一对补偿绳轮用轨道26沿着上下方向被一对缓冲器台连结梁24以及一对补偿绳轮用轨道支承梁25支承。补偿绳轮15的壳体16沿着补偿绳轮用轨道26被引导。The pair of compensating sheave rails 26 are supported by a pair of buffer table connecting beams 24 and a pair of compensating sheave rail support beams 25 along the vertical direction. The housing 16 of the compensating sheave 15 is guided along the compensating sheave rail 26 .

一对轿厢侧第1引导部27设置在轿厢侧缓冲器台18的两端。轿厢侧第1引导部27由轿厢用导轨31引导。A pair of car-side first guide portions 27 are provided at both ends of the car-side buffer table 18 . The car-side first guide portion 27 is guided by the car guide rail 31 .

一对对重侧第1引导部28设置在对重侧缓冲器台19的两端。对重侧第1引导部28由对重用导轨32引导。A pair of counterweight-side first guide portions 28 are provided at both ends of the counterweight-side buffer table 19 . The counterweight side first guide portion 28 is guided by the counterweight guide rail 32 .

一对轿厢侧第2引导部29设置在轿厢侧缓冲器支承梁22的两端。轿厢侧第2引导部29由轿厢用导轨31引导。A pair of car-side second guide portions 29 are provided at both ends of the car-side buffer support beam 22 . The car-side second guide portion 29 is guided by the car guide rail 31 .

一对对重侧第2引导部30设置在对重侧缓冲器支承梁23的两端。对重侧第2引导部30由对重用导轨32引导。A pair of counterweight-side second guide portions 30 are provided at both ends of the counterweight-side shock absorber support beam 23 . The counterweight side second guide portion 30 is guided by the counterweight guide rail 32 .

底坑单元7具备载荷支承装置33。载荷支承装置33用于将底坑单元7固定在井道内。The pit unit 7 includes a load support device 33 . The load bearing device 33 is used to fix the pit unit 7 in the hoistway.

底坑单元7的第1例中的载荷支承装置33例如具备筒状部件33a以及滑动部件33b。筒状部件33a沿着左右方向相对于轿厢侧缓冲器台18的下表面以及对重侧缓冲器台19的下表面固定。筒状部件33a例如配置在缓冲器台连结梁24的下方。滑动部件33b插入于筒状部件33a中。滑动部件33b例如能够完全收纳在筒状部件33a的内侧。滑动部件33b例如至少一部分能够从筒状部件33a突出。The load support device 33 in the first example of the pit unit 7 includes, for example, a cylindrical member 33a and a sliding member 33b. The cylindrical member 33 a is fixed to the lower surface of the car-side buffer table 18 and the lower surface of the counterweight-side buffer table 19 along the left-right direction. The cylindrical member 33a is arranged below the buffer table connecting beam 24, for example. The sliding member 33b is inserted into the cylindrical member 33a. The sliding member 33b can be completely accommodated inside the cylindrical member 33a, for example. For example, at least a part of the sliding member 33b can protrude from the cylindrical member 33a.

如图7所示,从筒状部件33a突出的滑动部件33b例如被支承于层站地板34或建造中的建筑物侧的结构体。底坑单元7通过由载荷支承装置33支承载荷而被固定在井道内。当底坑单元7被提升时,基于载荷支承装置33的支承被解除。载荷支承装置33例如也可以具备吊环螺栓等吊具,该吊环螺栓等吊具在底坑单元7被提升时与吊索11或连结绳索12连接。As shown in FIG. 7 , the sliding member 33b protruding from the cylindrical member 33a is supported by, for example, a hall floor 34 or a structure on the side of a building under construction. The pit unit 7 is fixed in the hoistway by supporting the load by the load supporting device 33 . When the pit unit 7 is lifted, the support by the load bearing device 33 is released. The load support device 33 may include, for example, a hanger such as an eyebolt that is connected to the sling 11 or the connecting rope 12 when the pit unit 7 is lifted.

图11是示出实施方式1中的底坑单元的第2例的主视图。图12是图11的A-A向视图。图13是图11的C-C向视图。11 is a front view showing a second example of the pit unit in Embodiment 1. FIG. Fig. 12 is a view taken along the line A-A of Fig. 11 . FIG. 13 is a view taken along the line C-C of FIG. 11 .

以下,使用图11至图13,以与图7至图10所示的第1例的不同点为中心,对底坑单元7的第2例的结构进行说明。Hereinafter, the configuration of the second example of the pit unit 7 will be described with reference to FIGS. 11 to 13 , focusing on the differences from the first example shown in FIGS. 7 to 10 .

在底坑单元7的第2例中,未搭载补偿绳轮15。底坑单元7的第2例不具备轿厢侧缓冲器支承台20、对重侧缓冲器支承台21、轿厢侧缓冲器支承梁22、对重侧缓冲器支承梁23、缓冲器台连结梁24、补偿绳轮用轨道支承梁25、补偿绳轮用轨道26、轿厢侧第2引导部29以及对重侧第2引导部30。In the second example of the pit unit 7, the compensation sheave 15 is not mounted. The second example of the pit unit 7 does not include the car-side buffer support platform 20, the counterweight-side buffer support platform 21, the car-side buffer support beam 22, the counterweight-side buffer support beam 23, and the buffer platform connection The beam 24 , the rail support beam 25 for compensating sheave, the rail 26 for compensating sheave, the second guide portion 29 on the car side, and the second guide portion 30 on the counterweight side.

在底坑单元7的第2例中,轿厢缓冲器8由轿厢侧缓冲器台18直接支承。在底坑单元7的第2例中,对重缓冲器9由对重侧缓冲器台19直接支承。在底坑单元7的第2例中,载荷支承装置33的结构与第1例相同。In the second example of the pit unit 7 , the car buffer 8 is directly supported by the car-side buffer table 18 . In the second example of the pit unit 7 , the counterweight buffer 9 is directly supported by the counterweight side buffer table 19 . In the second example of the pit unit 7, the structure of the load support device 33 is the same as that of the first example.

图14是示出实施方式1中的底坑单元的第3例的主视图。图15是图14的A-A向视图。图16是图14的B-B向视图。图17是图14的C-C向视图。14 is a front view showing a third example of the pit unit in Embodiment 1. FIG. FIG. 15 is a view taken along the line A-A of FIG. 14 . FIG. 16 is a view taken along the line B-B of FIG. 14 . FIG. 17 is a view taken along the line C-C of FIG. 14 .

以下,使用图14至图17,以与图7至图10所示的第1例的不同点为中心,对底坑单元7的第3例的结构进行说明。Hereinafter, the configuration of the third example of the pit unit 7 will be described with reference to FIGS. 14 to 17 , focusing on differences from the first example shown in FIGS. 7 to 10 .

在底坑单元7的第3例中,轿厢侧缓冲器台18以及对重侧缓冲器台19的结构与第1例不同。底坑单元7的第3例不具备轿厢侧第1引导部27以及对重侧第1引导部28。In the third example of the pit unit 7, the structures of the car-side buffer table 18 and the counterweight-side buffer table 19 are different from those of the first example. The third example of the pit unit 7 does not include the car-side first guide portion 27 and the counterweight-side first guide portion 28 .

底坑单元7的第3例中的载荷支承装置33设置在轿厢侧缓冲器台18以及对重侧缓冲器台19的两端。设置于轿厢侧缓冲器台18的一对载荷支承装置33由轿厢用导轨31引导。设置于对重侧缓冲器台19的一对载荷支承装置33由对重用导轨32引导。The load support device 33 in the third example of the pit unit 7 is provided at both ends of the car-side buffer table 18 and the counterweight-side buffer table 19 . The pair of load support devices 33 provided on the car-side buffer table 18 are guided by the car guide rails 31 . The pair of load support devices 33 provided on the counterweight side buffer table 19 are guided by the counterweight guide rails 32 .

底坑单元7的第3例中的载荷支承装置33具有能够相对于轿厢用导轨31以及对重用导轨32固定的功能。该功能例如通过与电梯的紧急停止装置相同的机构来实现。底坑单元7通过载荷支承装置33的驱动而被固定在井道内。当底坑单元7被提升时,由载荷支承装置33进行的固定被解除。轿厢侧缓冲器台18以及对重侧缓冲器台19例如也可以具备吊环螺栓等吊具,该吊环螺栓等吊具在底坑单元7被提升时与吊索11或连结绳索12连接。The load support device 33 in the third example of the pit unit 7 has a function of being able to be fixed to the guide rail 31 for cars and the guide rail 32 for re-use. This function is realized, for example, by the same mechanism as the emergency stop of the elevator. The pit unit 7 is fixed in the hoistway by the drive of the load bearing device 33 . When the pit unit 7 is lifted, the fixation by the load bearing device 33 is released. The car-side buffer table 18 and the counterweight-side buffer table 19 may be provided with, for example, a hanger such as an eye bolt that is connected to the sling 11 or the connecting rope 12 when the pit unit 7 is lifted.

图18是示出实施方式1中的底坑单元的第4例的主视图。图19是图18的A-A向视图。图20是图18的C-C向视图。18 is a front view showing a fourth example of the pit unit in Embodiment 1. FIG. Fig. 19 is a view taken along the line A-A of Fig. 18 . FIG. 20 is a view taken along the line C-C of FIG. 18 .

以下,使用图18至图20,以与图14至图17所示的第3例的不同点为中心,对底坑单元7的第4例的结构进行说明。Hereinafter, the configuration of the fourth example of the pit unit 7 will be described with reference to FIGS. 18 to 20 , focusing on differences from the third example shown in FIGS. 14 to 17 .

在底坑单元7的第4例中,未搭载补偿绳轮15。底坑单元7的第4例不具备轿厢侧缓冲器支承台20、对重侧缓冲器支承台21、轿厢侧缓冲器支承梁22、对重侧缓冲器支承梁23、缓冲器台连结梁24、补偿绳轮用轨道支承梁25、补偿绳轮用轨道26、轿厢侧第1引导部27、对重侧第1引导部28、轿厢侧第2引导部29以及对重侧第2引导部30。In the fourth example of the pit unit 7, the compensation sheave 15 is not mounted. The fourth example of the pit unit 7 does not include the car-side buffer support platform 20, the counterweight-side buffer support platform 21, the car-side buffer support beam 22, the counterweight-side buffer support beam 23, and the buffer platform connection Beam 24, track support beam 25 for compensation sheave, track 26 for compensation sheave, first car-side guide portion 27, counterweight-side first guide portion 28, car-side second guide portion 29, and counterweight-side first guide portion 29. 2. Guide part 30.

在底坑单元7的第4例中,轿厢缓冲器8由轿厢侧缓冲器台18直接支承。在底坑单元7的第4例中,对重缓冲器9由对重侧缓冲器台19直接支承。在底坑单元7的第4例中,轿厢侧缓冲器台18以及对重侧缓冲器台19的结构与第3例相同。在底坑单元7的第4例中,载荷支承装置33的功能与第3例相同。In the fourth example of the pit unit 7 , the car buffer 8 is directly supported by the car-side buffer table 18 . In the fourth example of the pit unit 7 , the counterweight buffer 9 is directly supported by the counterweight side buffer table 19 . In the fourth example of the pit unit 7, the structures of the car-side buffer table 18 and the counterweight-side buffer table 19 are the same as those of the third example. In the fourth example of the pit unit 7, the function of the load support device 33 is the same as that of the third example.

实施方式1中的底坑单元7的结构不限于图7至图20所示的结构。底坑单元7只要例如搭载轿厢缓冲器8以及对重缓冲器9中的至少一个即可。The structure of the pit unit 7 in Embodiment 1 is not limited to the structure shown in FIGS. 7 to 20 . The pit unit 7 only needs to mount at least one of the car buffer 8 and the counterweight buffer 9, for example.

图21是用于说明实施方式1中的电梯的扬程延长技术的应用方法的步骤的流程图。以下,使用图21对扬程延长技术的应用方法的步骤的一例进行说明。21 is a flowchart for explaining the procedure of the application method of the lift extension technique of the elevator in Embodiment 1. FIG. Hereinafter, an example of the procedure of the application method of the lift extension technique will be described with reference to FIG. 21 .

在步骤S101中,作业人员进行第1升降行程延长工序。第1升降行程延长工序也可以反复进行多次。然后,作业人员进行步骤S102的工序。在步骤S102中,作业人员进行升降行程移动工序。升降行程移动工序也可以反复进行多次。然后,作业人员进行步骤S103的工序。在步骤S103中,作业人员通过进行正式设置用曳引机设置工序、以及将固定在井道中间部的底坑单元7降下至井道最下部的工序或者设置正式设置用底坑设备的工序,来进行第2升降行程延长工序。其结果,能够与建筑物的高度无关地应用电梯的扬程延长技术。In step S101, an operator performs a 1st raising/lowering stroke extension process. The first elevating stroke extension process may be repeated a plurality of times. Then, the operator performs the process of step S102. In step S102, the operator performs the lifting stroke movement process. The lifting and lowering stroke moving process may be repeated several times. Then, the operator performs the process of step S103. In step S103, the operator performs the step of installing the hoisting machine for formal installation, the step of lowering the pit unit 7 fixed to the middle of the hoistway to the lowest part of the hoistway, or the step of installing pit equipment for formal installation. The second lifting stroke extension process. As a result, the lift extension technique of the elevator can be applied regardless of the height of the building.

根据在以上内容中进行了说明的实施方式1,电梯的扬程延长技术的应用方法包括第1升降行程延长工序、升降行程移动工序以及第2升降行程延长工序。第1升降行程延长工序是如下工序:使机房单元3相对于底坑单元7的相对位置上升,所述底坑单元7搭载轿厢缓冲器8以及对重缓冲器9中的至少一方且能够在机房单元3的下方在井道中升降。升降行程移动工序是使机房单元3以及底坑单元7向相同的方向移动的工序。因此,对于高层建筑物也能够应用使用了比正式设置用曳引机14小型且轻量的临时设置用曳引机4的电梯的扬程延长技术。第2升降行程延长工序是如下工序:设置正式设置用曳引机14,进而,使搭载轿厢缓冲器8以及对重缓冲器9中的至少一方且能够在井道中升降的底坑单元7的位置下降、或者设置新设置用底坑设备。其结果,能够消除通过电梯能够提供服务的最大高度的制约。According to Embodiment 1 described above, the method of applying the lift extension technique of the elevator includes the first lifting stroke extension step, the lifting stroke moving step, and the second lifting stroke extension step. The first lifting and lowering stroke extension step is a step of raising the relative position of the machine room unit 3 with respect to the pit unit 7 on which at least one of the car buffer 8 and the counterweight buffer 9 is mounted and can be The lower part of the machine room unit 3 is raised and lowered in the hoistway. The lifting stroke moving step is a step of moving the machine room unit 3 and the pit unit 7 in the same direction. Therefore, the lift extension technique of the elevator using the hoisting machine 4 for temporary installation which is smaller and lighter than the hoisting machine 14 for formal installation can also be applied to a high-rise building. The second raising and lowering stroke extension step is a step of installing the hoisting machine 14 for formal installation, and further, installing at least one of the car buffer 8 and the counterweight buffer 9 and enabling the pit unit 7 to be raised and lowered in the hoistway. Position drop, or set up pit equipment for new settings. As a result, the restriction on the maximum height that can be serviced by the elevator can be eliminated.

此外,在升降行程移动工序中,例如在底坑单元7与机房单元3被连结起来的状态下将机房单元3拉起。该情况下,由于提升作业一次完成,因此能够缩短作业时间。In addition, in the lift stroke moving process, for example, the machine room unit 3 is pulled up in a state where the pit unit 7 and the machine room unit 3 are connected. In this case, since the lifting work is completed at one time, the work time can be shortened.

此外,在升降行程移动工序中,例如也可以在从补偿绳轮15卸下了补偿绳索17的状态下将机房单元3拉起之后再拉起底坑单元7。该情况下,能够减轻提升作业中的负荷。此外,该情况下,能够通过一次提升作业使机房单元3或底坑单元7上升到目的高度。In addition, in the lifting and lowering stroke moving process, for example, the pit unit 7 may be pulled up after the machine room unit 3 is pulled up in a state in which the compensation rope 17 is removed from the compensation sheave 15 . In this case, the load in the lifting work can be reduced. Moreover, in this case, the machine room unit 3 or the pit unit 7 can be raised to the target height by one lift operation.

此外,在升降行程移动工序中,例如,也可以在补偿绳轮15上绕挂有补偿绳索17、并且轿厢1以及对重2被配置于能够在轿厢1下部与轿厢缓冲器8之间、以及对重2下部与对重缓冲器9之间形成空间的位置的状态下,拉起底坑单元7之后再拉起机房单元3。该情况下,能够减轻提升作业中的负荷。此外,该情况下,不需要对补偿绳轮15装卸补偿绳索17。In addition, in the lifting stroke moving process, for example, the compensation rope 17 may be wound around the compensation sheave 15, and the car 1 and the counterweight 2 may be arranged so as to be able to be located between the lower part of the car 1 and the car buffer 8. The machine room unit 3 is then pulled up after the pit unit 7 is pulled up in a state where the space between the counterweight 2 and the lower part of the counterweight 2 and the counterweight buffer 9 is formed. In this case, the load in the lifting work can be reduced. In addition, in this case, it is not necessary to attach and detach the compensation rope 17 to the compensation sheave 15 .

此外,在升降行程移动工序中,例如也可以在轿厢1被载置于轿厢缓冲器8之上的状态下使机房单元3或底坑单元7上升。在升降行程移动工序中,例如也可以在对重2被载置于对重缓冲器9之上的状态下使机房单元3或底坑单元7上升。在升降行程移动工序中,例如也可以在轿厢1被载置于轿厢缓冲器8之上、并且对重2被载置于对重缓冲器9之上的状态下,使机房单元3或底坑单元7上升。即,在升降行程移动工序中,也可以在轿厢1以及对重2中的至少一方的重量被底坑单元7支承的状态下使机房单元3或底坑单元7上升。该情况下,能够减轻提升作业中的负荷。In addition, in the raising and lowering stroke moving process, for example, the machine room unit 3 or the pit unit 7 may be raised in a state where the car 1 is placed on the car buffer 8 . In the lifting stroke moving step, for example, the machine room unit 3 or the pit unit 7 may be raised in a state where the counterweight 2 is placed on the counterweight buffer 9 . In the lifting stroke moving process, for example, in a state where the car 1 is placed on the car buffer 8 and the counterweight 2 is placed on the counterweight buffer 9, the machine room unit 3 or the machine room unit 3 or The pit unit 7 is raised. That is, in the raising and lowering stroke moving step, the machine room unit 3 or the pit unit 7 may be raised while the weight of at least one of the car 1 and the counterweight 2 is supported by the pit unit 7 . In this case, the load in the lifting work can be reduced.

此外,在第1升降行程延长工序中,例如将升降行程延长到能够应用临时设置用曳引机4的最大升降行程。该情况下,能够在最大限度地维持电梯的可移动范围的同时,消除能够提供服务的最大高度的制约。Moreover, in the 1st raising/lowering stroke extension process, for example, the raising/lowering stroke is extended to the maximum raising/lowering stroke which can apply the hoisting machine 4 for temporary installation. In this case, the restriction on the maximum height that can be serviced can be eliminated while maintaining the movable range of the elevator as much as possible.

此外,例如也可以预先在井道的外部组装底坑单元7。该情况下,能够实施如下工序:在实施升降行程移动工序之前,将预先组装好的底坑单元7从井道开口部一体搬入到井道内。此外,该情况下,能够实施如下工序:在实施升降行程移动工序之后,将作为临时设置用途而使用的底坑单元7从井道开口部取出而搬出至建筑物的外部。其结果,能够削减底坑单元7的安装以及撤除所需的时间。In addition, for example, the pit unit 7 may be assembled in advance outside the hoistway. In this case, it is possible to implement a process of carrying the pre-assembled pit unit 7 integrally into the hoistway from the hoistway opening before carrying out the lifting and lowering stroke moving process. In addition, in this case, it is possible to carry out a process of taking out the pit unit 7 used for temporary installation from the hoistway opening and carrying it out of the building after carrying out the lifting and lowering stroke moving process. As a result, the time required for installation and removal of the pit unit 7 can be reduced.

产业上的可利用性Industrial Availability

本发明能够用于高层建筑物中的扬程延长式电梯。The present invention can be used for lift-extending elevators in high-rise buildings.

标号说明Label description

1:轿厢;1: car;

2:对重;2: Counterweight;

3:机房单元;3: computer room unit;

4:临时设置用曳引机;4: Traction machine for temporary setting;

5:绳索;5: rope;

6:控制盘;6: Control panel;

7:底坑单元;7: pit unit;

8:轿厢缓冲器;8: car buffer;

9:对重缓冲器;9: Counterweight buffer;

10:提升装置;10: Lifting device;

11:吊索;11: sling;

12:连结绳索;12: Connect the rope;

13:机房;13: computer room;

14:正式设置用曳引机;14: Traction machine for formal setting;

15:补偿绳轮;15: Compensation sheave;

16:壳体;16: shell;

17:补偿绳索;17: Compensation rope;

18:轿厢侧缓冲器台;18: car side buffer table;

19:对重侧缓冲器台;19: Counterweight side buffer table;

20:轿厢侧缓冲器支承台;20: car side buffer support platform;

21:对重侧缓冲器支承台;21: Counterweight side buffer support table;

22:轿厢侧缓冲器支承梁;22: Support beam of car side buffer;

23:对重侧缓冲器支承梁;23: Counterweight side buffer support beam;

24:缓冲器台连结梁;24: Buffer table connecting beam;

25:补偿绳轮用轨道支承梁;25: Track support beam for compensation sheave;

26:补偿绳轮用轨道;26: Track for compensation sheave;

27:轿厢侧第1引导部;27: the first guide part on the car side;

28:对重侧第1引导部;28: The first guide part on the counterweight side;

29:轿厢侧第2引导部;29: the second guide part on the car side;

30:对重侧第2引导部;30: The second guide part on the counterweight side;

31:轿厢用导轨;31: Guide rail for car;

32:对重用导轨;32: For reusing guide rails;

33:载荷支承装置;33: Load bearing device;

33a:筒状部件;33a: cylindrical part;

33b:滑动部件;33b: sliding parts;

34:层站地板。34: The landing floor.

Claims (20)

1.一种电梯的扬程延长技术的应用方法,其包括:1. An application method of the lift extension technology of an elevator, comprising: 升降行程移动工序,在施工工期结束后设置正式设置用曳引机的电梯的井道中应用的扬程延长式电梯中,使底坑单元从井道最下部向搭载有曳引机的机房单元上升的方向上升,并固定于井道中间部,由此使升降行程根据建筑施工的进展而移动,其中,所述底坑单元搭载有轿厢缓冲器以及对重缓冲器中的至少一个,且具有被轿厢用导轨以及对重用导轨中的至少一方引导的结构;以及The lifting stroke movement process is used in the lift-extended elevator used in the hoistway of the elevator in which the hoisting machine for formal installation is installed after the completion of the construction period, and the pit unit is raised from the lowest part of the hoistway to the machine room unit equipped with the hoisting machine. It ascends and is fixed to the middle part of the hoistway, whereby the lifting and lowering stroke is moved according to the progress of the building construction, wherein the pit unit is equipped with at least one of a car buffer and a counterweight buffer, and has a covered car A guide rail and a structure for guiding at least one of the reused rails; and 如下工序,在实施所述升降行程移动工序之后,使固定在所述井道中间部的所述底坑单元被所述轿厢用导轨以及所述对重用导轨中的至少所述一方引导而下降到所述井道最下部,将所述底坑单元设置为正式设置用的底坑设备。A step of causing the pit unit fixed to the intermediate portion of the hoistway to be guided by at least one of the guide rail for the car and the guide rail for the counterweight to descend to the At the lowermost part of the hoistway, the pit unit is set as a pit equipment for formal installation. 2.根据权利要求1所述的电梯的扬程延长技术的应用方法,其中,2. The application method of the lift extension technology of the elevator according to claim 1, wherein, 所述底坑单元能够固定于所述轿厢用导轨、所述对重用导轨以及建筑结构体中的至少一个。The pit unit can be fixed to at least one of the car guide rail, the counterweight guide rail, and a building structure. 3.根据权利要求1所述的电梯的扬程延长技术的应用方法,其中,3. The application method of the lift extension technology of elevator according to claim 1, wherein, 在所述升降行程移动工序中,在使所述机房单元上升之后,使所述底坑单元上升。In the raising/lowering stroke moving step, after raising the machine room unit, the pit unit is raised. 4.根据权利要求2所述的电梯的扬程延长技术的应用方法,其中,4. The application method of the lift extension technology of the elevator according to claim 2, wherein, 在所述升降行程移动工序中,在使所述机房单元上升之后,使所述底坑单元上升。In the raising/lowering stroke moving step, after raising the machine room unit, the pit unit is raised. 5.根据权利要求1所述的电梯的扬程延长技术的应用方法,其中,5. The application method of the lift extension technology of the elevator according to claim 1, wherein, 在所述升降行程移动工序中,在轿厢以及对重被配置于能够在轿厢下部与所述轿厢缓冲器之间、以及对重下部与所述对重缓冲器之间形成空间的位置的状态下,在使所述机房单元上升之前,使所述底坑单元上升。In the lift stroke moving step, the car and the counterweight are arranged at positions where spaces can be formed between the lower part of the car and the car buffer and between the lower part of the counterweight and the counterweight buffer In the state, before the machine room unit is raised, the pit unit is raised. 6.根据权利要求2所述的电梯的扬程延长技术的应用方法,其中,6. The application method of the lift extension technology of the elevator according to claim 2, wherein, 在所述升降行程移动工序中,在轿厢以及对重被配置于能够在轿厢下部与所述轿厢缓冲器之间、以及对重下部与所述对重缓冲器之间形成空间的位置的状态下,在使所述机房单元上升之前,使所述底坑单元上升。In the lift stroke moving step, the car and the counterweight are arranged at positions where spaces can be formed between the lower part of the car and the car buffer and between the lower part of the counterweight and the counterweight buffer In the state, before the machine room unit is raised, the pit unit is raised. 7.根据权利要求1所述的电梯的扬程延长技术的应用方法,其中,7. The application method of the lift extension technology of the elevator according to claim 1, wherein, 在所述升降行程移动工序中,在所述机房单元和所述底坑单元被连结起来的状态下使双方同时上升。In the raising and lowering stroke moving step, both of the machine room unit and the pit unit are simultaneously raised in a state where the machine room unit and the pit unit are connected. 8.根据权利要求2所述的电梯的扬程延长技术的应用方法,其中,8. The application method of the lift extension technology of the elevator according to claim 2, wherein, 在所述升降行程移动工序中,在所述机房单元和所述底坑单元被连结起来的状态下使双方同时上升。In the raising and lowering stroke moving step, both of the machine room unit and the pit unit are simultaneously raised in a state where the machine room unit and the pit unit are connected. 9.根据权利要求1所述的电梯的扬程延长技术的应用方法,其中,9. The application method of the lift extension technology of the elevator according to claim 1, wherein, 在所述升降行程移动工序中,在轿厢以及对重中的至少一方的重量被所述底坑单元支承的状态下使所述机房单元或所述底坑单元上升。In the raising/lowering stroke moving step, the machine room unit or the pit unit is raised in a state where the weight of at least one of the car and the counterweight is supported by the pit unit. 10.根据权利要求2所述的电梯的扬程延长技术的应用方法,其中,10. The application method of the lift extension technology of the elevator according to claim 2, wherein, 在所述升降行程移动工序中,在轿厢以及对重中的至少一方的重量被所述底坑单元支承的状态下使所述机房单元或所述底坑单元上升。In the raising/lowering stroke moving step, the machine room unit or the pit unit is raised in a state where the weight of at least one of the car and the counterweight is supported by the pit unit. 11.根据权利要求1至10中的任一项所述的电梯的扬程延长技术的应用方法,其中,11. The method for applying the lift extension technology of an elevator according to any one of claims 1 to 10, wherein, 所述机房单元搭载有临时设置用曳引机。The machine room unit is equipped with a hoisting machine for temporary installation. 12.根据权利要求1至10中的任一项所述的电梯的扬程延长技术的应用方法,其中,12. The method for applying the lift extension technology of an elevator according to any one of claims 1 to 10, wherein, 还包括如下工序:在实施所述升降行程移动工序之前,将预先在所述井道的外部组装好的所述底坑单元从井道开口部一体搬入到井道内。The method further includes a step of carrying the pit unit assembled in advance outside the hoistway into the hoistway from the opening of the hoistway as a whole, before the lifting and lowering stroke movement process is performed. 13.根据权利要求11所述的电梯的扬程延长技术的应用方法,其中,13. The method for applying the lift extension technology of an elevator according to claim 11, wherein, 还包括如下工序:在实施所述升降行程移动工序之前,将预先在所述井道的外部组装好的所述底坑单元从井道开口部一体搬入到井道内。The method further includes a step of carrying the pit unit assembled in advance outside the hoistway into the hoistway from the opening of the hoistway as a whole, before the lifting and lowering stroke movement process is performed. 14.一种电梯的扬程延长技术的应用方法,其包括:14. An application method of lift extension technology of an elevator, comprising: 升降行程移动工序,在施工工期结束后设置正式设置用曳引机的电梯的井道中应用的扬程延长式电梯中,使底坑单元向搭载有曳引机的机房单元上升的方向上升,由此使升降行程根据建筑施工的进展而移动,其中,所述底坑单元搭载有轿厢缓冲器以及对重缓冲器中的至少一个,且搭载有供连接轿厢下部与对重下部的补偿绳索绕挂的补偿绳轮;以及In the lifting stroke moving process, in the lift-extended elevator used in the hoistway of the elevator in which the hoisting machine for formal installation is installed after the completion of the construction period, the pit unit is raised in the direction in which the machine room unit on which the hoisting machine is mounted rises. The lifting stroke is moved according to the progress of the construction, wherein the pit unit is equipped with at least one of a car buffer and a counterweight buffer, and is equipped with a compensation rope for connecting the lower part of the car and the lower part of the counterweight. hanging compensating sheaves; and 如下工序,在实施所述升降行程移动工序之后,将作为临时设置用途而使用的所述底坑单元从井道开口部取出,将与所述底坑单元不同的正式设置用的底坑设备设置在井道最下部,The step of taking out the pit unit used as a temporary installation purpose from the opening of the hoistway after the lifting and lowering stroke moving step is carried out, and installing the pit equipment for formal installation, which is different from the pit unit, on the the bottom of the shaft, 在所述升降行程移动工序中,在轿厢以及对重被配置于能够在所述轿厢下部与所述轿厢缓冲器之间、以及所述对重下部与所述对重缓冲器之间形成空间的位置、且所述补偿绳索绕挂于所述补偿绳轮的状态下,在使所述机房单元上升之前,使所述底坑单元上升。In the lifting stroke moving step, the car and the counterweight are arranged so as to be able to be located between the lower part of the car and the buffer for the car, and between the lower part of the counterweight and the buffer for the counterweight The pit unit is raised before raising the machine room unit at the position where the space is formed and the compensation rope is wound around the compensation sheave. 15.根据权利要求14所述的电梯的扬程延长技术的应用方法,其中,15. The application method of the lift extension technology of the elevator according to claim 14, wherein, 所述底坑单元具有被轿厢用导轨以及对重用导轨中的至少一方引导的结构。The pit unit has a structure guided by at least one of the car guide rail and the counter-reuse guide rail. 16.根据权利要求14所述的电梯的扬程延长技术的应用方法,其中,16. The method for applying the lift extension technology of an elevator according to claim 14, wherein, 所述底坑单元能够固定于轿厢用导轨、对重用导轨以及建筑结构体中的至少一个。The pit unit can be fixed to at least one of a guide rail for a car, a guide rail for a counterweight, and a building structure. 17.根据权利要求15所述的电梯的扬程延长技术的应用方法,其中,17. The method for applying the lift extension technology of an elevator according to claim 15, wherein, 所述底坑单元能够固定于轿厢用导轨、对重用导轨以及建筑结构体中的至少一个。The pit unit can be fixed to at least one of a guide rail for a car, a guide rail for a counterweight, and a building structure. 18.根据权利要求14至17中的任一项所述的电梯的扬程延长技术的应用方法,其中,18. The method for applying the lift extension technology of an elevator according to any one of claims 14 to 17, wherein, 所述机房单元搭载有临时设置用曳引机。The machine room unit is equipped with a hoisting machine for temporary installation. 19.根据权利要求14至17中的任一项所述的电梯的扬程延长技术的应用方法,其中,19. The application method of the lift extension technology of an elevator according to any one of claims 14 to 17, wherein, 还包括如下工序:在实施所述升降行程移动工序之前,将预先在所述井道的外部组装好的所述底坑单元从井道开口部一体搬入到井道内。The method further includes a step of carrying the pit unit assembled in advance outside the hoistway into the hoistway from the opening of the hoistway as a whole, before the lifting and lowering stroke movement process is performed. 20.根据权利要求18所述的电梯的扬程延长技术的应用方法,其中,20. The method for applying the lift extension technology of an elevator according to claim 18, wherein, 还包括如下工序:在实施所述升降行程移动工序之前,将预先在所述井道的外部组装好的所述底坑单元从井道开口部一体搬入到井道内。The method further includes a step of carrying the pit unit assembled in advance outside the hoistway into the hoistway from the opening of the hoistway as a whole, before the lifting and lowering stroke movement process is performed.
CN201880096384.8A 2018-08-16 2018-08-16 Application method of lift extension technology of elevator Active CN112566864B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2018/030449 WO2020035933A1 (en) 2018-08-16 2018-08-16 Method for applying construction elevator lifting height extension technology

Publications (2)

Publication Number Publication Date
CN112566864A CN112566864A (en) 2021-03-26
CN112566864B true CN112566864B (en) 2022-04-15

Family

ID=69525327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201880096384.8A Active CN112566864B (en) 2018-08-16 2018-08-16 Application method of lift extension technology of elevator

Country Status (3)

Country Link
JP (1) JP6813123B2 (en)
CN (1) CN112566864B (en)
WO (1) WO2020035933A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021186493A1 (en) * 2020-03-16 2021-09-23 株式会社日立製作所 Construction elevator device
CN113620147B (en) 2020-05-09 2024-07-30 奥的斯电梯公司 Jump elevator system and jump method for use in building construction
JP7167274B1 (en) 2021-09-03 2022-11-08 東芝エレベータ株式会社 Elevator system and its assembly method
JP7436126B1 (en) 2023-06-02 2024-02-21 三菱電機ビルソリューションズ株式会社 Elevator gondola installation method and gondola device

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3759349A (en) * 1972-03-13 1973-09-18 Otis Elevator Co Elevator system with temporary hoistway structure and method for use thereof
JPS5918309B2 (en) * 1979-07-07 1984-04-26 フジテツク株式会社 Installation method of mobile mechanical room elevator
JPS5935822B2 (en) * 1980-08-28 1984-08-30 フジテック株式会社 Construction elevator installation method
JP2783686B2 (en) * 1991-01-23 1998-08-06 株式会社東芝 Underground construction method by elevator
JP3214325B2 (en) * 1995-12-18 2001-10-02 三菱電機株式会社 Elevator installation method
JP2839872B2 (en) * 1996-07-29 1998-12-16 株式会社サノヤス・ヒシノ明昌 Rope elevator for shaft
FI114458B (en) * 2002-12-02 2004-10-29 Kone Corp Procedure and apparatus for mounting an elevator at the building stage
FI122066B (en) * 2009-12-31 2011-08-15 Kone Corp A method of making a lift
JP5799547B2 (en) * 2011-03-30 2015-10-28 株式会社大林組 Elevator installation method and elevator installation method
CN204958044U (en) * 2015-09-18 2016-01-13 西子西奥电梯有限公司 No pit car frame and no pit villa elevator

Also Published As

Publication number Publication date
JP6813123B2 (en) 2021-01-13
WO2020035933A1 (en) 2020-02-20
CN112566864A (en) 2021-03-26
JPWO2020035933A1 (en) 2020-08-27

Similar Documents

Publication Publication Date Title
CN104066670B (en) Method and elevator arrangement
CN112566864B (en) Application method of lift extension technology of elevator
CN102666347B (en) For the method and apparatus of mobile heavy lift
CN115038660A (en) Construction elevator device
CN110191855B (en) How to install elevator
JP6969686B2 (en) How to extend the lift of a construction elevator
WO2020142001A1 (en) A moveable platform
JP2004238151A (en) Elevator installation method
JP3807775B2 (en) How to lift the construction elevator
CN112739638B (en) Hoisting device and hoisting method for counterweight of elevator
JP2001114484A (en) Elevator main rope suspension method
JP2007210703A (en) Device and method for installing hoist machine in machine-room-less elevator
JP6336225B2 (en) Elevator equipment
JP5468029B2 (en) Elevator equipment
JP2013245033A (en) Method of installing hoisting machine
JP5930842B2 (en) Elevator installation method and installation jig
CN118076554A (en) Device and method for mounting guide rail of elevator
JP2001335255A (en) Elevator installation method and elevator installation unit
JPH0480188A (en) Double deck elevator
JP7436126B1 (en) Elevator gondola installation method and gondola device
JP6525328B2 (en) Elevator equipment loading and unloading method and elevator equipment loading and unloading apparatus
JP7559261B2 (en) Construction elevators and methods for extending the compensating ropes of construction elevators
JPH082850A (en) Elevator hoistway construction method
JP2016008131A (en) Elevator and remodeling method of existing elevator
JPH05201648A (en) Installation of elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant