EP1162325A2 - Saddle roof structure - Google Patents

Saddle roof structure Download PDF

Info

Publication number
EP1162325A2
EP1162325A2 EP01113328A EP01113328A EP1162325A2 EP 1162325 A2 EP1162325 A2 EP 1162325A2 EP 01113328 A EP01113328 A EP 01113328A EP 01113328 A EP01113328 A EP 01113328A EP 1162325 A2 EP1162325 A2 EP 1162325A2
Authority
EP
European Patent Office
Prior art keywords
tarpaulin
profile unit
construction according
roof construction
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP01113328A
Other languages
German (de)
French (fr)
Other versions
EP1162325A3 (en
EP1162325B1 (en
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wilhelm Layher Verwaltungs GmbH
Original Assignee
Wilhelm Layher Vermoegensverwaltungs GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wilhelm Layher Vermoegensverwaltungs GmbH filed Critical Wilhelm Layher Vermoegensverwaltungs GmbH
Publication of EP1162325A2 publication Critical patent/EP1162325A2/en
Publication of EP1162325A3 publication Critical patent/EP1162325A3/en
Application granted granted Critical
Publication of EP1162325B1 publication Critical patent/EP1162325B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H15/00Tents or canopies, in general
    • E04H15/18Tents having plural sectional covers, e.g. pavilions, vaulted tents, marquees, circus tents; Plural tents, e.g. modular
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/02Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
    • E04B7/022Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs consisting of a plurality of parallel similar trusses or portal frames
    • E04B7/024Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs consisting of a plurality of parallel similar trusses or portal frames the trusses or frames supporting load-bearing purlins, e.g. braced purlins
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D5/00Roof covering by making use of flexible material, e.g. supplied in roll form
    • E04D5/14Fastening means therefor
    • E04D5/141Fastening means therefor characterised by the location of the fastening means
    • E04D5/142Fastening means therefor characterised by the location of the fastening means along the edge of the flexible material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D5/00Roof covering by making use of flexible material, e.g. supplied in roll form
    • E04D5/14Fastening means therefor
    • E04D5/144Mechanical fastening means
    • E04D5/146Linear fastening means, e.g. strips
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/242Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/28Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence

Definitions

  • the present is a tarpaulin roof construction with several spaced parallel to each other on / on one Supported roof trusses, in particular Lattice girders with top flange, diagonals and bottom flange, lateral support units for the roof trusses and one Roof skin.
  • the present invention the technical problem respectively based on the task of constructing a tarpaulin roof specify the type mentioned at the outset, which is achieved by using Series parts known in scaffolding are economical Production ensures sufficient structural safety implements and enables a permanently reliable function.
  • the tarpaulin roof construction according to the invention of the type mentioned above is accordingly characterized in that the roof skin is designed as a tarpaulin, a connection profile unit is detachably saddled on the upper belt of the binder, on or in the connection profile unit one Driving in / screwing in fasteners allowing a full profile unit is arranged, the tarpaulin is connected to the connection profile unit by means of fasteners screwed in / screwed into the full profile unit and connection elements are present on the connection profile unit for detachable connection of the lateral support units.
  • the top chord of the tie can alternatively be used as Connection profile unit to be formed.
  • connection profile unit has an upwardly open U-profile cross section and the Full profile unit than in the connection profile unit arranged squared timber is formed.
  • connection elements as hanging pockets are formed with a wedge, one in the end regions the existing protrusion unit introduced is and the projection unit by means of the wedge each is detachably locked in the hanging pockets.
  • lateral Support units are used to advantage characterized in that the lateral support units known as a frame-like double bar railing Standard scaffolding, especially the company's flash scaffolding Layher, are trained.
  • double railings are from the assemblers can be handled manually without any problems since they have a relatively low weight and simple and way to the described wedge clamp technology Connection profile unit can be connected.
  • the distance between the lateral support units is preferred with each other in the range between 40 cm (centimeters) and 60 cm (centimeters) selected, which is a water bag formation Counteracts tarpaulin.
  • a particularly preferred embodiment of the tarpaulin roof construction according to the invention stands out characterized in that on the connection profile unit and / or the full profile unit a hat-shaped, open at the bottom Cover profile unit is connected with their Legs press the connected tarp down, which creates a certain pre-tension within the tarpaulin becomes.
  • the cover profile unit is preferably screwed to trained the full profile unit and serves on the one hand Sealing purposes and on the other hand for tensioning the Roof tarpaulin, which also forms a water bag counteracts.
  • connection elements for the lateral support units connected on the underside to the connection profile unit are. This measure makes it more compact Achieve roof structure, while supporting the Planning through the final unit ensures what counteracts water bag formation.
  • a particularly economical variant to manufacture is characterized in that the lattice girders as mass-produced scaffolding components of a known Standard scaffolding, especially the company's flash scaffolding Layher, are trained.
  • the lattice girders are preferably made of aluminum and Connection profile units can preferably be made of steel be trained.
  • the proposed design represents an inexpensive one Roof solution, being particularly economical that is largely due to scaffolding known series parts can be used. So that's the Scaffolders able to use existing series scaffolding parts using the connection profile unit and the full profile unit a permanently and reliably functioning To create hall construction.
  • the substructure for the roof structure can be made from standard scaffolding components exist or special support structures for the Have roof structure.
  • spans are up to 15 m can be easily implemented.
  • standard scaffolding parts becomes a not inconsiderable economic Advantage when creating hall roofs.
  • the main advantages of the tarpaulin roof construction according to the invention consist of using normal Series parts known from scaffolding Roof construction with high stiffening economical can be created.
  • through the top connected cover profile unit in addition to a reliable Sealing in the overlap area of the tarpaulin achieved simultaneous pretensioning of the tarpaulins, so that a Water bag formation can be reliably avoided.
  • the measures / features mentioned can usually be at Flap movements and tarpaulin roof structures Noise can be avoided as much as possible as tarpaulins, the cheap tarpaulins common in scaffolding be used.
  • the use of relatively expensive tarpaulins with Piping and corresponding piping rails is available from Construction according to the invention is not required.
  • the scaffolding plans are set up in a simple manner the connection profile unit and the cover profile unit then ensures a reliable and rainproof cover while pretensioning the To plan.
  • Tarpaulin roof construction 10 has two in this cross section each outwardly inclined roof trusses 12 in Ridge area with one another via connecting elements 48 are connected so that a gable roof contour is created.
  • the Roof trusses 12 are made of aluminum with a lattice girder 12 a tubular upper chord 14, a tubular lower chord 16 and rising and falling pipe diagonals 15 educated.
  • each lattice girder 12 is connected to an in 1 schematically shown substructure 22 connected.
  • This substructure 22 can for example an articulated connection of the lattice girders 12 represent. It is also possible that the upper chord 14 and the lower flange 16 in this area on scaffolding stems known way are connected.
  • the lattice girders 12 in turn come from a known in the art Scaffolding support system, for example from the so-called Layher-Blitz scaffolding system.
  • connection profile unit 24 is a U-profile unit open at the top formed, the interior of which is a full profile unit 26, which is designed as square timber, fills such that the upward-facing ends of the webs of the U-profile unit 24 finish flush with the top of the square timber 26.
  • connection elements on the underside of the connection profile unit 28 connected are 24 connection elements on the underside of the connection profile unit 28 connected, the at a closer distance A less than the distance B of the protrusion units 30 in Longitudinal direction of the connection profile unit 24 connected are.
  • connection profile unit 24 is by lateral Support units 20 (see Fig. 3 and Fig. 4) secured against lateral evasion. Through the connection the lateral support 20 acts with the lattice girder 12 also on the lattice girder 12.
  • the lateral support units 20 are as frame-like Double railing 20 formed, each two in one Distance A in the longitudinal direction to the connection profile unit 24 spaced existing individual rods 21 which in End area through a cross strut 23 to form a frame are connected.
  • Each in the front end area Single rod 21 is a bent at right angles to this, flattened projection unit 38 present in the Connection elements 28 of the connection profile unit 24 can be introduced, the connecting elements 28 as Hang-in pockets 34 with wedge 36 (FIG. 5) are formed.
  • the double railings 20 are also standardized Scaffolding system components from the well-known Layher-Blitz scaffolding system.
  • the clamping detachable connection by means of the Wedge 36 of the hanging bag 34 from both sides in the Suspension bag 34 inserted projection units 38 of the Double railing 20 by means of a hammer blow provides one extremely simple and effective quick assembly connection the double railing 20 to the U-profile 24.
  • Lattice beam pairs 12 is on the connection profile unit 24 a tarpaulin 18 attached.
  • the tarpaulin attachment 18 or on both sides of the connection profile unit 24 arriving tarpaulin 18 is schematic in Fig. 5 shown in cross section.
  • Each tarpaulin 18 is over the Connection profile unit 24 pulled so that it is easier Way, for example by means of metal clips 42 the full profile unit 26 (Kantholz 26) are stapled can. Then the tarpaulin 18 on the opposite side pulled over the connection profile unit 24 and also with Stapled metal clips 42.
  • the distance C of the lattice girders 12 is a concrete one Embodiment at 257 cm (centimeters).
  • simple tarpaulins are 270 cm wide (Centimeters), so that with these tarpaulins a sufficient Given overlap in the area of the connection profile unit 24 is.
  • the standardized structure of a quick-assembly hall roof can be done for example as follows become. After the substructure 22, for example Layher Blitz or Layher all-round scaffolding system components is created, at least two in the longitudinal direction spaced-apart saddle straps, consisting of two lattice girders 12, on the substructure 22 attached. Then the connection profile units 24 with inserted timber 26 on the pipe couplings 32 on Upper chord 14 of the lattice girder 12 attached.
  • the trusses are braced respectively Lattice girder 12 on the top chord 14 or on the Connection profile unit 24 through the side Support units 20 (double railings) as series components in simple way by inserting the projection units 38 in the hanging pockets 34 and then Hammer blow on the wedge 36.
  • the small distances of the Double railing 20, preferably in the range between 40 cm (Centimeters) to 60 cm (centimeters) prevent that Formation of water bags.
  • the roof tarpaulin 18 are then on Squared timber 26 stapled, the then at the tarpaulin joint Cover surfaces are screwed on for sealing and serve to tension the roof tarpaulin 18. By tightening the Roof tarpaulin 18 continues to form a water bag counteracted.
  • the tarpaulin 18 by the Preload insensitive to flutter movements as a result Influence of wind.
  • the lattice girders 12 are preferably made of aluminum and have in one embodiment, a system height of 45 cm (Centimeters). With such a construction Spans of up to 15 m (meters) without snow load easy to remove. With an additional drawstring, stretched from tie end to tie end per saddle tie is a removal of an increased roof load to Example of additional snow load.
  • the roof structure 10 shown enables an extreme quick assembly or disassembly and sets in Connection with the use of many standard scaffolding parts an economical solution.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Tents Or Canopies (AREA)
  • Bridges Or Land Bridges (AREA)
  • Building Awnings And Sunshades (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The tarpaulin roof cover has a tarpaulin attached to a profiled connection unit (24) through fixings which can be screwed or hammered into the solid profile unit. The profiled connection unit is fitted detachably on the upper tie (16) of the roof binders which are mounted parallel spaced from each other on a support structure (22) and are supported by side support units. The side support units are detachably connected to the profiled connector unit through further connectors (28).

Description

TECHNISCHES GEBIETTECHNICAL AREA

Die vorliegende eine Planendachkonstruktion mit mehreren parallel beabstandet zueinander angeordneten an/auf einer Unterkonstruktion gelagerten Dachbindern, insbesondere Gitterträgern mit Obergurt, Diagonalen und Untergurt, seitlichen Abstützeinheiten für die Dachbinder und einer Dachhaut.The present is a tarpaulin roof construction with several spaced parallel to each other on / on one Supported roof trusses, in particular Lattice girders with top flange, diagonals and bottom flange, lateral support units for the roof trusses and one Roof skin.

STAND DER TECHNIKSTATE OF THE ART

Aus dem deutschen Patent 35 42 610 ist ein Schnell-Montage-Hallendach bekannt, bei dem die Dachbinder-Obergurte als nach oben offene Profile mit im Wesentlichen vertikal verlaufenden Schenkeln ausgebildet sind. Die Dachhautelemente weisen einen Rahmen auf, wobei in Neigungsrichtung des Daches verlaufende Randleisten einen nach unten gerichteten Schenkel aufweisen, der in das nach oben offene Profil des Dachbinderobergurtes eingreift. Die Dachhautelemente selbst sind als im Querschnitt trapez- oder wellenförmige Stahlbleche ausgebildet. Eine derartige Konstruktion hat sich in der Praxis bewährt, ermöglicht eine schnelle Montage beziehungsweise Demontage und ist geeignet, große Spannweiten abzudecken. Die Dachhautelemente mit ihrem Rahmen können aufgrund ihres Gewichtes nur mit einem Hebezeug montiert werden. Für die Montage wird in jedem Fall ein Kran benötigt. From the German patent 35 42 610 is a quick assembly hall roof known, in which the Dachbinder top chords as profiles open to the top with essentially vertical extending legs are formed. The roof skin elements have a frame, being in the direction of inclination of the roof edge strips one down have directed leg, which in the open to the top Profile of the roof truss engages. The roof skin elements themselves are trapezoidal or in cross section corrugated steel sheets. Such Construction has proven itself in practice, enables a quick assembly or disassembly and is suitable to cover large spans. The roof skin elements with their Due to their weight, frames can only be used with one Hoist. In any case, for assembly a crane is needed.

DARSTELLUNG DER ERFINDUNGPRESENTATION OF THE INVENTION

Ausgehend von dem genannten Stand der Technik liegt der vorliegenden Erfindung das technische Problem beziehungsweise die Aufgabe zugrunde, eine Planendachkonstruktion der eingangs genannten Art anzugeben, die durch Verwendung von im Gerüstbau bekannten Serienteilen eine wirtschaftliche Herstellung gewährleistet, eine ausreichende Tragsicherheit umsetzt und eine dauerhaft zuverlässige Funktion ermöglicht.Based on the prior art mentioned, the present invention the technical problem respectively based on the task of constructing a tarpaulin roof specify the type mentioned at the outset, which is achieved by using Series parts known in scaffolding are economical Production ensures sufficient structural safety implements and enables a permanently reliable function.

Die erfindungsgemäße Planendachkonstruktion ist durch die Merkmale des unabhängigen Anspruchs 1 gegeben. Vorteilhafte Ausgestaltungen und Weiterbildungen sind Gegenstand der abhängigen Ansprüche.The tarpaulin roof construction according to the invention is by the Features of independent claim 1 given. Beneficial Refinements and developments are the subject of dependent claims.

Die erfindungsgemäße Planendachkonstruktion der eingangs genannten Art zeichnet sich demgemäß dadurch aus, dass die Dachhaut als Plane ausgebildet ist, auf dem Obergurt des Binders eine Anschlussprofileinheit lösbar aufgesattelt ist, an oder in der Anschlussprofileinheit eine das
Einschlagen/Einschrauben von Befestigungsmitteln erlaubende Vollprofileinheit angeordnet ist, die Plane über in die Vollprofileinheit eingeschlagene/eingeschraubte Befestigungsmittel an die Anschlussprofileinheit angeschlossen ist und an der Anschlussprofileinheit Anschlusselemente zum lösbaren Anschluss der seitlichen Abstützeinheiten vorhanden sind.
The tarpaulin roof construction according to the invention of the type mentioned above is accordingly characterized in that the roof skin is designed as a tarpaulin, a connection profile unit is detachably saddled on the upper belt of the binder, on or in the connection profile unit one
Driving in / screwing in fasteners allowing a full profile unit is arranged, the tarpaulin is connected to the connection profile unit by means of fasteners screwed in / screwed into the full profile unit and connection elements are present on the connection profile unit for detachable connection of the lateral support units.

Der Obergurt des Binders kann alternativ selbst als Anschlussprofileinheit ausgebildet sein.The top chord of the tie can alternatively be used as Connection profile unit to be formed.

Eine konstruktiv besonders einfach umzusetzende und eine wirtschaftliche Herstellung ermöglichende Ausführungsform zeichnet sich dadurch aus, dass die Anschlussprofileinheit einen nach oben offenen U-Profilquerschnitt aufweist und die Vollprofileinheit als in der Anschlussprofileinheit angeordnetes Kantholz ausgebildet ist.A particularly easy to implement constructively and one embodiment enabling economical production is characterized by the fact that the connection profile unit has an upwardly open U-profile cross section and the Full profile unit than in the connection profile unit arranged squared timber is formed.

Eine bevorzugte Ausführungsform zeichnet sich dadurch aus, dass die Anschlussprofileinheit über Vorsprungeinheiten mit Rohrkupplungen an dem Obergurt des Gitterträgers angeschlossen ist.A preferred embodiment is characterized in that that the connection profile unit with protrusion units with Pipe couplings on the top chord of the lattice girder connected.

Eine besonders vorteilhafte Weiterbildung, die die Montage beziehungsweise Demontage stark vereinfacht, zeichnet sich dadurch aus, dass die Anschlusselemente als Einhängetaschen mit Keil ausgebildet sind, in die eine in den Endbereichen der Abstützeinheiten vorhandene Vorsprungeinheit eingeführt ist und die Vorsprungeinheit mittels des Keiles jeweils lösbar in den Einhängetaschen arretiert ist.A particularly advantageous further training, the assembly or disassembly greatly simplified characterized in that the connection elements as hanging pockets are formed with a wedge, one in the end regions the existing protrusion unit introduced is and the projection unit by means of the wedge each is detachably locked in the hanging pockets.

Im Hinblick auf eine wirtschaftliche Herstellung der Gesamtkonstruktion zeichnet sich eine besonders vorteilhafte Ausgestaltung dadurch aus, dass die seitlichen Abstützeinheiten als Geländerstäbe eines bekannten Standard-Gerüstsystem, insbesondere des Blitz-Gerüstsystems der Firma Layher, ausgebildet sind.With a view to the economic production of Overall construction is particularly advantageous Design characterized in that the lateral Support units as handrails of a known standard scaffolding system, especially the company's flash scaffolding system Layher, are trained.

Dabei kann eine Ausführungsvariante der seitlichen Abstützeinheiten vorteilhaft eingesetzt werden, die sich dadurch auszeichnet, dass die seitlichen Abstützeinheiten als rahmenartiges Doppelstabgeländer eines bekannten Standard-Gerüsts, insbesondere des Blitz-Gerüsts der Firma Layher, ausgebildet sind. Derartige Doppelgeländer sind von den Montagepersonen problemlos manuell handhabbar, da sie ein relativ geringes Gewicht aufweisen und in einfacher Art und Weise mit der beschriebenen Keilklemmtechnik an die Anschlussprofileinheit angeschlossen werden können. An embodiment variant of the lateral Support units are used to advantage characterized in that the lateral support units known as a frame-like double bar railing Standard scaffolding, especially the company's flash scaffolding Layher, are trained. Such double railings are from the assemblers can be handled manually without any problems since they have a relatively low weight and simple and way to the described wedge clamp technology Connection profile unit can be connected.

In der Praxis gelangt man zu einer genügend steifen Konstruktion, wenn zwischen den Dachbindern abwechselnd Doppelgeländer und im benachbarten Feld zwischen den Dachbindern einfache Geländerstäbe eingesetzt werden.In practice you get a sufficiently stiff one Construction if alternating between the roof trusses Double railing and in the adjacent field between the Simple balusters can be used for roof trusses.

Um die Handhabbarkeit der Plane montagetechnisch gesehen einfach zu gestalten, weist eine Planeneinheit im Wesentlichen den Abstand zweier Dachbinder auf, die insbesondere überlappend an der Vollprofileinheit befestigt werden können.To see the manageability of the tarpaulin assembly technology A tarpaulin unit in the Essentially the distance between two roof trusses that in particular overlapping attached to the full profile unit can be.

Bevorzugt ist der Abstand der seitlichen Abstützeinheiten untereinander im Bereich zwischen 40 cm (Zentimeter) und 60 cm (Zentimeter) gewählt, was einer Wassersackbildung der Plane entgegenwirkt.The distance between the lateral support units is preferred with each other in the range between 40 cm (centimeters) and 60 cm (centimeters) selected, which is a water bag formation Counteracts tarpaulin.

Eine besonders bevorzugte Ausgestaltung der erfindungsgemäßen Planendachkonstruktion zeichnet sich dadurch aus, dass auf der Anschlussprofileinheit und/oder der Vollprofileinheit eine hutförmige, nach unten offene Abdeckprofileinheit angeschlossen ist, die mit ihren Schenkeln die angeschlossene Plane nach unten drückt, wodurch innerhalb der Plane eine gewisse Vorspannung erzeugt wird. Die Abdeckprofileinheit ist bevorzugt verschraubt mit der Vollprofileinheit ausgebildet und dient einerseits zu Abdichtungszwecken und andererseits zum Spannen der Dachplanen, was ebenfalls einer Wassersackbildung entgegenwirkt.A particularly preferred embodiment of the tarpaulin roof construction according to the invention stands out characterized in that on the connection profile unit and / or the full profile unit a hat-shaped, open at the bottom Cover profile unit is connected with their Legs press the connected tarp down, which creates a certain pre-tension within the tarpaulin becomes. The cover profile unit is preferably screwed to trained the full profile unit and serves on the one hand Sealing purposes and on the other hand for tensioning the Roof tarpaulin, which also forms a water bag counteracts.

Eine hinsichtlich der konstruktiven Ausgestaltung besonders bevorzugte Weiterbildung zeichnet sich dadurch aus, dass die Anschlusselemente für die seitlichen Abstützeinheiten unterseitig an der Anschlussprofileinheit angeschlossen sind. Durch diese Maßnahme lässt sich ein kompakter Dachaufbau erzielen, wobei gleichzeitig eine Stützung der Planen durch die Abschlusseinheit gewährleistet wird, was einer Wassersackbildung entgegenwirkt.One particularly with regard to the structural design preferred further training is characterized in that the Connection elements for the lateral support units connected on the underside to the connection profile unit are. This measure makes it more compact Achieve roof structure, while supporting the Planning through the final unit ensures what counteracts water bag formation.

Eine besonders wirtschaftlich herzustellende Ausführungsvariante zeichnet sich dadurch aus, dass die Gitterträger als serienmäßig hergestellte Gerüstbauteile eines bekannten Standard-Gerüsts, insbesondere des Blitz-Gerüsts der Firma Layher, ausgebildet sind.A particularly economical variant to manufacture is characterized in that the lattice girders as mass-produced scaffolding components of a known Standard scaffolding, especially the company's flash scaffolding Layher, are trained.

Die Gitterträger sind bevorzugt aus Aluminium und die Anschlussprofileinheiten können bevorzugt aus Stahl ausgebildet sein.The lattice girders are preferably made of aluminum and Connection profile units can preferably be made of steel be trained.

Hinsichtlich einer besonders wirtschaftlichen Montageweise ist es besonders vorteilhaft, die Plane mit eingeschlagenen, insbesondere getackerten, Metallklammern an der Vollprofileinheit zu befestigen.With regard to a particularly economical assembly method it is particularly advantageous to cover the tarpaulin with especially stapled metal clips on the full profile unit to fix.

Die vorgeschlagene Konstruktion stellt eine kostengünstige Dachlösung dar, wobei in wirtschaftlicher Hinsicht besonders zu Buche schlägt, dass größtenteils aus dem Gerüstbau bekannte Serienteile eingesetzt werden können. Damit ist der Gerüstbauer in der Lage, mit vorhandenen Serien-Gerüstteilen unter Einsatz der Anschlussprofileinheit und der Vollprofileinheit eine dauerhaft und zuverlässig funktionierende Hallenkonstruktion zu erstellen. Die Unterkonstruktion für die Dachkonstruktion kann aus Standard-Gerüstbauteilen bestehen oder spezielle Auflagerkonstruktionen für die Dachkonstruktion aufweisen. The proposed design represents an inexpensive one Roof solution, being particularly economical that is largely due to scaffolding known series parts can be used. So that's the Scaffolders able to use existing series scaffolding parts using the connection profile unit and the full profile unit a permanently and reliably functioning To create hall construction. The substructure for the roof structure can be made from standard scaffolding components exist or special support structures for the Have roof structure.

Insbesondere ist hervorzuheben, dass die Binderaussteiffung am Obergurt durch die standardisierten Doppelgeländer-elemente aufgrund der geringen Abstände der Doppelgeländer verhindern, dass sich Wassersäcke bilden. Die Befestigung der Dachplanen mit getackerten Metallklammern auf dem Kantholz der Abschlussprofileinheit beschleunigt die Montage erheblich. Das Vorsehen einer Abdeckprofileinheit erhöht einerseits die Dichtigkeit und sorgt andererseits für eine gewisse Vorspannung der Dachplanen, was wiederum einer Wassersackbildung entgegenwirkt.In particular, it should be emphasized that the gusset bracing on the top chord through the standardized double railing elements due to the small distances between the double railings prevent water bags from forming. The attachment the roof tarpaulin with stapled metal clips on the Squared timber of the end profile unit speeds up assembly considerably. The provision of a cover profile unit increases on the one hand the tightness and on the other hand ensures a certain pre-tensioning of the roof tarpaulin, which in turn is one Counteracts water bag formation.

Mit der vorgeschlagenen Konstruktion sind Spannweiten bis zu 15 m problemlos umsetzbar. Durch den Einsatz von Serien-Gerüstteilen wird ein nicht unerheblicher wirtschaftlicher Vorteil bei der Erstellung von Hallendächern ermöglicht.With the proposed construction, spans are up to 15 m can be easily implemented. Through the use of standard scaffolding parts becomes a not inconsiderable economic Advantage when creating hall roofs.

Die wesentlichen Vorteile der erfindungsgemäßen Planendachkonstruktion bestehen darin, dass unter Einsatz von normalen aus dem Gerüstbau bekannten Serienteilen eine Dachkonstruktion mit hoher Aussteifung wirtschaftlich erstellt werden kann. Durch den Einsatz von Geländer-bauteilen zur seitlichen Stützung der Binder in relativ engem Abstand wird einer Wassersackbildung zuverlässig entgegengewirkt. Gleichzeitig wird durch die oberseitig angeschlossene Abdeckprofileinheit neben einer zuverlässigen Abdichtung im Überlappungsbereich der Planen eine gleichzeitige Vorspannung der Planen erzielt, sodass eine Wassersackbildung zuverlässig vermieden kann. Durch die genannten Maßnahmen/Merkmale können die üblicherweise bei Planendachkonstruktionen auftretenden Flatterbewegungen und Geräusche weitestgehend vermieden werden.Gleichzeitig können als Planen die im Gerüstbau üblichen, billigen Abdeckplanen verwendet werden. Der Einsatz von relativ teuren Planen mit Kedern und entsprechenden Kederschienen ist bei der erfindungsgemäßen Konstruktion nicht erforderlich. The main advantages of the tarpaulin roof construction according to the invention consist of using normal Series parts known from scaffolding Roof construction with high stiffening economical can be created. Through the use of railing components for lateral support of the trusses in relative A water bag formation becomes reliable at a close distance counteracted. At the same time, through the top connected cover profile unit in addition to a reliable Sealing in the overlap area of the tarpaulin achieved simultaneous pretensioning of the tarpaulins, so that a Water bag formation can be reliably avoided. Through the The measures / features mentioned can usually be at Flap movements and tarpaulin roof structures Noise can be avoided as much as possible as tarpaulins, the cheap tarpaulins common in scaffolding be used. The use of relatively expensive tarpaulins with Piping and corresponding piping rails is available from Construction according to the invention is not required.

Die Gerüstbauplanen werden in einfacher Art und Weise auf der Anschlussprofileinheit festgetackert und die Abdeckprofileinheit sorgt anschließend für eine zuverlässige und regendichte Abdeckung bei gleichzeitiger Vorspannung der Planen.The scaffolding plans are set up in a simple manner the connection profile unit and the cover profile unit then ensures a reliable and rainproof cover while pretensioning the To plan.

Weitere Ausführungsformen und Vorteile der Erfindung ergeben sich durch die in den Ansprüchen ferner aufgeführten Merkmale sowie durch das nachstehend angegebene Ausführungsbeispiel. Die Merkmale der Ansprüche können in beliebiger Weise miteinander kombiniert werden, insoweit sie sich nicht offensichtlich gegenseitig ausschließen.Further embodiments and advantages of the invention result themselves by the features listed in the claims as well as by the exemplary embodiment specified below. The features of the claims can be in any Ways can be combined with each other insofar as they are not obviously mutually exclusive.

KURZE BESCHREIBUNG DER ZEICHNUNGBRIEF DESCRIPTION OF THE DRAWING

Die Erfindung sowie vorteilhafte Ausführungsformen und Weiterbildungen derselben werden im folgenden anhand des in der Zeichnung dargestellten Beispiels näher beschrieben und erläutert. Die der Beschreibung und der Zeichnung zu entnehmenden Merkmale können einzeln für sich oder zu mehreren in beliebiger Kombination erfindungsgemäß angewandt werden. Es zeigen:

Fig. 1
Ansicht einer Planendachkonstruktion, ausgebildet als Satteldach mit zwei Gitterträgern und aufgesattelten Anschlussprofileinheiten,
Fig. 2
schematischer Schnitt durch die Dachkonstruktion gemäß Fig. 1 entlang Schnittführung I-I mit zusätzlich dargestellter Plane und Abdeckprofileinheit im noch nicht befestigten Zustand,
Fig. 3
schematische Detailperspektivuntersicht unter eine Planendachkonstruktion gemäß Fig. 1 ohne Darstellung der Planen und der Unterkonstruktion für die Binder,
Fig. 4
schematische Untersichtsperspektivdarstellung des Details A gemäß Fig. 3 in Explosionsdarstellung und
Fig. 5
schematischer Schnitt durch eine Anschlussprofileinheit mit Vollprofileinheit unter Darstellung des Anschlusses der seitlichen Abstützeinheiten und der angeschlossenen Abdeckprofileinheit.
The invention and advantageous embodiments and developments thereof are described and explained in more detail below with reference to the example shown in the drawing. The features to be gathered from the description and the drawing can be used according to the invention individually or in groups in any combination. Show it:
Fig. 1
View of a tarpaulin roof construction, designed as a gable roof with two lattice girders and saddled connection profile units,
Fig. 2
1 shows a schematic section through the roof construction according to FIG. 1 along section II with additionally shown tarpaulin and cover profile unit in the not yet fastened state,
Fig. 3
schematic detailed perspective underside under a tarpaulin roof construction according to FIG. 1 without representation of the tarpaulins and the substructure for the trusses,
Fig. 4
schematic perspective view of detail A according to FIG. 3 in an exploded view and
Fig. 5
schematic section through a connection profile unit with a full profile unit, showing the connection of the lateral support units and the connected cover profile unit.

WEGE ZUM AUSFÜHREN DER ERFINDUNGWAYS OF CARRYING OUT THE INVENTION

Die in Fig. 1 im Querschnitt schematisch dargestellte Planendachkonstruktion 10 weist in diesem Querschnitt zwei jeweils nach außen geneigte Dachbinder 12 auf, die im Firstbereich über Verbindungselemente 48 miteinander verbunden sind, sodass eine Satteldachkontur ensteht. Die Dachbinder 12 sind als Gitterträger 12 aus Aluminium mit einem rohrförmigen Obergurt 14, einem rohrförmigen Untergurt 16 und steigenden und fallenden Rohrdiagonalen 15 ausgebildet.The schematically shown in Fig. 1 in cross section Tarpaulin roof construction 10 has two in this cross section each outwardly inclined roof trusses 12 in Ridge area with one another via connecting elements 48 are connected so that a gable roof contour is created. The Roof trusses 12 are made of aluminum with a lattice girder 12 a tubular upper chord 14, a tubular lower chord 16 and rising and falling pipe diagonals 15 educated.

Im unteren Endbereich ist jeder Gitterträger 12 an eine in Fig. 1 schematisch dargestellte Unterkonstruktion 22 angeschlossen. Diese Unterkonstruktion 22 kann beispielsweise einen gelenkigen Anschluss der Gitterträger 12 darstellen. Es ist auch möglich, dass der Obergurt 14 und der Untergurt 16 in diesem Bereich an Gerüststiele in bekannter Art und Weise angeschlossen sind. Die Gitterträger 12 stammen wiederum aus einem im Stand der Technik bekannten Gerüsttragsystem, beispielsweise aus dem sogenannten Layher-Blitz-Gerüstsystem. In the lower end region, each lattice girder 12 is connected to an in 1 schematically shown substructure 22 connected. This substructure 22 can for example an articulated connection of the lattice girders 12 represent. It is also possible that the upper chord 14 and the lower flange 16 in this area on scaffolding stems known way are connected. The lattice girders 12 in turn come from a known in the art Scaffolding support system, for example from the so-called Layher-Blitz scaffolding system.

Auf die Obergurte 14 der Gitterträger 12 ist jeweils eine über die gesamte Länge des Gitterträgers 12 verlaufende Anschlussprofileinheit 24 aufgesattelt, wobei unterseitig an der Anschlussprofileinheit 24 Vorsprungeinheiten 30 angeschlossen sind, deren Endbereich wiederum eine Rohrkupplung 32 zum lösbar klemmenden Anschluss an den Obergurt 14 des Dachbinders 12 aufweist. Die Anschlussprofileinheit 24 ist als nach oben offene U-Profileinheit ausgebildet, wobei deren Innenraum eine Vollprofileinheit 26, die als Kantholz ausgebildet ist, derart ausfüllt, dass die nach oben weisenden Enden der Stege der U-Profileinheit 24 bündig mit der Oberseite des Kantholzes 26 abschließen.There is one on each of the upper chords 14 of the lattice girders 12 extending over the entire length of the lattice girder 12 Saddled connection profile unit 24, on the underside the connection profile unit 24, projection units 30 are connected, the end region of which is a Pipe coupling 32 for releasably clamping connection to the Upper chord 14 of the roof truss 12 has. The connection profile unit 24 is a U-profile unit open at the top formed, the interior of which is a full profile unit 26, which is designed as square timber, fills such that the upward-facing ends of the webs of the U-profile unit 24 finish flush with the top of the square timber 26.

In dem Zwischenbereich zwischen dem Obergurt 14 und dem Gitterträger 12 und der Anschlussprofileinheit 24 sind unterseitig an der Anschlussprofileinheit 24 Anschlusselemente 28 angeschlossen, die in einem geringeren Abstand A unterienander als der Abstand B der Vorsprungeinheiten 30 in Längsrichtung der Anschlussprofileinheit 24 angeschlossen sind.In the intermediate area between the top chord 14 and the Lattice girder 12 and the connection profile unit 24 are 24 connection elements on the underside of the connection profile unit 28 connected, the at a closer distance A less than the distance B of the protrusion units 30 in Longitudinal direction of the connection profile unit 24 connected are.

Die Anschlussprofileinheit 24 ist durch seitliche Abstützeinheiten 20 (siehe Fig. 3 beziehungsweise Fig. 4) gegen seitliches Ausweichen gesichert. Durch die Verbindung mit dem Gitterträger 12 wirkt die seitliche Abstützung 20 auch auf den Gitterträger 12.The connection profile unit 24 is by lateral Support units 20 (see Fig. 3 and Fig. 4) secured against lateral evasion. Through the connection the lateral support 20 acts with the lattice girder 12 also on the lattice girder 12.

Die seitlichen Abstützeinheiten 20 sind als rahmenartige Doppelgeländer 20 ausgebildet, die jeweils zwei in einem Abstand A in Längsrichtung zur Anschlussprofileinheit 24 beabstandet vorhandene Einzelstäbe 21 aufweist, die im Endbereich durch eine Querstrebe 23 zu einem Rahmen verbunden sind. Im stirnseitigen Endbereich jedes Einzelstabes 21 ist eine rechtwinklig zu diesem gebogene, abgeflachte Vorsprungeinheit 38 vorhanden, die in die Anschlusselemente 28 der Anschlussprofileinheit 24 eingeführt werden können, wobei die Anschlusselemente 28 als Einhängetaschen 34 mit Keil 36 (Fig. 5) ausgebildet sind.The lateral support units 20 are as frame-like Double railing 20 formed, each two in one Distance A in the longitudinal direction to the connection profile unit 24 spaced existing individual rods 21 which in End area through a cross strut 23 to form a frame are connected. Each in the front end area Single rod 21 is a bent at right angles to this, flattened projection unit 38 present in the Connection elements 28 of the connection profile unit 24 can be introduced, the connecting elements 28 as Hang-in pockets 34 with wedge 36 (FIG. 5) are formed.

Die Doppelgeländer 20 sind ebenfalls standardisierte Gerüstsystem-Bauteile aus dem bekannten Layher-Blitz-Gerüstsystem. Der klemmende lösbare Anschluss mittels des Keiles 36 der Einhängetasche 34 der von beiden Seiten in die Einhängetasche 34 eingeführten Vorsprungeinheiten 38 der Doppelgeländer 20 mittels eines Hammerschlages stellt einen äußerst einfachen und effektiven Schnell-Montage-Anschluss der Doppelgeländer 20 an das U-Profil 24 dar.The double railings 20 are also standardized Scaffolding system components from the well-known Layher-Blitz scaffolding system. The clamping detachable connection by means of the Wedge 36 of the hanging bag 34 from both sides in the Suspension bag 34 inserted projection units 38 of the Double railing 20 by means of a hammer blow provides one extremely simple and effective quick assembly connection the double railing 20 to the U-profile 24.

Zwischen zwei in Längsrichtung mit dem Abstand C vorhandenen Gitterträgerpaaren 12 ist auf der Anschlussprofileinheit 24 eine Plane 18 befestigt. Die Befestigung der Plane 18 beziehungsweise der auf beiden Seiten der Anschlussprofileinheit 24 ankommenden Planen 18 ist in Fig. 5 schematisch im Querschnitt dargestellt. Jede Plane 18 wird über die Anschlussprofileinheit 24 gezogen, sodass sie in einfacher Art und Weise beispielsweise mittels Metallklammern 42 an der Vollprofileinheit 26 (Kantholz 26) angetackert werden kann. Sodann wird die Plane 18 der gegenüberliegenden Seite über die Anschlussprofileinheit 24 gezogen und ebenfalls mit Metallklammern 42 angetackert. Schließlich ist noch eine nach unten hutförmig offene Abdeckprofileinheit 40 mit nach unten weisenden Schenkeln 46 vorhanden, deren lichter Innenabstand größer ist als der Außenabstand der Schenkel 46 der Anschlussprofileinheit 24. Durch die Schenkel 46 der Abdeckprofileinheit 40 wird die Plane 18 nach unten gedrückt, wodurch eine gewisse Vorspannung erzeugt wird und die Plane 18 auf den seitlichen Abstützeinheiten 20 nahezu aufliegt. Die Abdeckprofileinheit 40 ist über Schrauben 44 mit der Vollprofileinheit 26 verbunden. Between two existing in the longitudinal direction with the distance C. Lattice beam pairs 12 is on the connection profile unit 24 a tarpaulin 18 attached. The tarpaulin attachment 18 or on both sides of the connection profile unit 24 arriving tarpaulin 18 is schematic in Fig. 5 shown in cross section. Each tarpaulin 18 is over the Connection profile unit 24 pulled so that it is easier Way, for example by means of metal clips 42 the full profile unit 26 (Kantholz 26) are stapled can. Then the tarpaulin 18 on the opposite side pulled over the connection profile unit 24 and also with Stapled metal clips 42. Finally, there is one downward hat-shaped cover profile unit 40 with after legs 46 pointing below, their lights Inner distance is greater than the outer distance of the legs 46 the connection profile unit 24. Through the legs 46 of the Cover profile unit 40, the tarpaulin 18 is down pressed, which creates a certain bias and the tarpaulin 18 on the side support units 20 almost lies on. The cover profile unit 40 is via screws 44 connected to the full profile unit 26.

Der Abstand C der Gitterträger 12 liegt bei einem konkreten Ausführungsbeispiel bei 257 cm (Zentimeter). Im Gerüstbau übliche, einfache Planen weisen eine Breite von 270 cm (Zentimeter) auf, sodass mit diesen Planen eine ausreichende Überlappung im Bereich der Anschlussprofileinheit 24 gegeben ist.The distance C of the lattice girders 12 is a concrete one Embodiment at 257 cm (centimeters). In scaffolding Common, simple tarpaulins are 270 cm wide (Centimeters), so that with these tarpaulins a sufficient Given overlap in the area of the connection profile unit 24 is.

Mit der dargestellten Konstruktion ist eine äußerst kostengünstige Dachlösung möglich, da größtenteils Serienteile aus dem Gerüstbau eingesetzt werden können.With the construction shown is an extreme Inexpensive roof solution possible, for the most part Series parts from scaffolding can be used.

Der standardisierte Aufbau eines Schnell-Montage-Hallendaches kann beispielsweise wie folgt durchgeführt werden. Nachdem die Unterkonstruktion 22 beispielsweise aus Layher-Blitz- oder Layher-Allround-Gerüstsystem-Bauteilen erstellt ist, werden zumindest zwei in Längsrichtung beabstandet zueinander angeordnete Sattelbinder, bestehend aus zwei Gitterträgern 12, an der Unterkonstruktion 22 befestigt. Danach werden die Anschlussprofileinheiten 24 mit eingelegtem Kantholz 26 über die Rohrkupplungen 32 am Obergurt 14 der Gitterträger 12 befestigt. Anschließend erfolgt die Aussteifung der Binder beziehungsweise Gitterträger 12 am Obergurt 14 beziehungsweise an der Anschlussprofileinheit 24 durch die seitlichen Abstützeinheiten 20 (Doppelgeländer) als Serien-Bauteile in einfacher Art und Weise durch Einfügen der Vorsprungeinheiten 38 in die Einhängetaschen 34 und anschließendem Hammerschlag auf den Keil 36. Die geringen Abstände der Doppelgeländer 20, die bevorzugt im Bereich zwischen 40 cm (Zentimeter) bis 60 cm (Zentimeter) liegen, verhindern das Entstehen von Wassersäcken. Anschließend werden weitere Sattelbinder aufgestellt und mit dem Doppelgeländer 20 seitlich ausgesteift. Die Dachplanen 18 werden dann auf das Kantholz 26 getackert, wobei dann am Planenstoß die Abdeckflächen aufgeschraubt werden, die zum Abdichten und zum Spannen der Dachplanen 18 dienen. Durch das Spannen der Dachplanen 18 wird einer Wassersackbildung weiter entgegengewirkt. Zudem wird die Plane 18 durch die Vorspannung unempfindlich gegen Flatterbewegungen infolge Windeinfluss.The standardized structure of a quick-assembly hall roof can be done for example as follows become. After the substructure 22, for example Layher Blitz or Layher all-round scaffolding system components is created, at least two in the longitudinal direction spaced-apart saddle straps, consisting of two lattice girders 12, on the substructure 22 attached. Then the connection profile units 24 with inserted timber 26 on the pipe couplings 32 on Upper chord 14 of the lattice girder 12 attached. Subsequently the trusses are braced respectively Lattice girder 12 on the top chord 14 or on the Connection profile unit 24 through the side Support units 20 (double railings) as series components in simple way by inserting the projection units 38 in the hanging pockets 34 and then Hammer blow on the wedge 36. The small distances of the Double railing 20, preferably in the range between 40 cm (Centimeters) to 60 cm (centimeters) prevent that Formation of water bags. Then more Saddle girder set up and with the double railing 20 laterally braced. The roof tarpaulin 18 are then on Squared timber 26 stapled, the then at the tarpaulin joint Cover surfaces are screwed on for sealing and serve to tension the roof tarpaulin 18. By tightening the Roof tarpaulin 18 continues to form a water bag counteracted. In addition, the tarpaulin 18 by the Preload insensitive to flutter movements as a result Influence of wind.

Bevorzugt sind die Gitterträger 12 aus Aluminium und weisen in einem Ausführungsbeispiel eine Systemhöhe von 45 cm (Zentimeter) auf. Mit einer derartigen Konstruktion sind Spannweiten von bis zu 15 m (Meter) ohne Schneelast problemlos abtragbar. Mittels eines zusätzlichen Zugbandes, das von Binderende zu Binderende je Sattelbinder gespannt wird, wird eine Abtragung einer erhöhten Dachlast, zum Beispiel zusätzliche Schneelast, ermöglicht.The lattice girders 12 are preferably made of aluminum and have in one embodiment, a system height of 45 cm (Centimeters). With such a construction Spans of up to 15 m (meters) without snow load easy to remove. With an additional drawstring, stretched from tie end to tie end per saddle tie is a removal of an increased roof load to Example of additional snow load.

Die dargestellte Dachkonstruktion 10 ermöglicht eine äußerst schnelle Montage beziehungsweise Demontage und setzt in Verbindung mit der Verwendung von vielen Serien-Gerüstteilen eine wirtschaftliche Lösung um.The roof structure 10 shown enables an extreme quick assembly or disassembly and sets in Connection with the use of many standard scaffolding parts an economical solution.

Claims (15)

Planendachkonstruktion (10) mit mehreren parallel beabstandet zueinander angeordneten an/auf einer Unterkonstruktion (22) gelagerten Dachbindern, insbesondere Gitterträgern (12) mit Obergurt (14), Diagonalen (15) und Untergurt (16), seitlichen Abstützeinheiten (20) für die Dachbinder und einer Dachhaut,
dadurch gekennzeichnet, dass
die Dachhaut als Plane (18) ausgebildet ist, auf dem Obergurt (16) des Binders eine Anschlussprofileinheit (24) lösbar aufgesattelt ist oder der Obergurt eine Anschlussprofileinheit darstellt, an oder in der Anschlussprofileinheit (24) eine das Einschlagen/Einschrauben von Befestigungsmitteln erlaubende Vollprofileinheit (26) angeordnet ist, die Plane (18) über in die Vollprofileinheit (26) eingeschlagene/eingeschraubte Befestigungsmittel an die Anschlussprofileinheit (24) angeschlossen ist und an der Anschlussprofileinheit (24) Anschlusselemente (28) zum lösbaren Anschluss der seitlichen Abstützeinheiten (20) vorhanden sind.
Tarpaulin roof construction (10) with a plurality of roof trusses, spaced parallel to one another and supported on / on a substructure (22), in particular lattice girders (12) with top flange (14), diagonals (15) and bottom flange (16), lateral support units (20) for the roof trusses and a roof skin,
characterized in that
the roof skin is designed as a tarpaulin (18), a connection profile unit (24) is detachably saddled on the upper belt (16) of the binder or the upper belt represents a connection profile unit, a full profile unit (26) allowing the fastening / screwing in of fastening means is arranged on or in the connecting profile unit (24), the tarpaulin (18) is connected to the connection profile unit (24) by means of fastening means screwed in / screwed into the full profile unit (26) and there are connection elements (28) on the connection profile unit (24) for the detachable connection of the lateral support units (20).
Planendachkonstruktion nach Anspruch 1,
dadurch gekennzeichnet, dass
die Anschlussprofileinheit (24) einen nach oben offenen U-Profilquerschnitt aufweist und die Vollprofileinheit (26) als in der Anschlussprofileinheit (24) angeordnetes Kantholz ausgebildet ist.
Tarpaulin roof construction according to claim 1,
characterized in that
the connection profile unit (24) has a U-profile cross section that is open at the top, and the full profile unit (26) is designed as a square timber arranged in the connection profile unit (24).
Planendachkonstruktion nach Anspruch 1 oder 2,
dadurch gekennzeichnet, dass
die Anschlussprofileinheit (24) über Vorsprungeinheiten (30) mit Rohrkupplungen (32) an dem Obergurt (14) des Gitterträgers (12) angeschlossen ist.
Tarpaulin roof construction according to claim 1 or 2,
characterized in that
the connection profile unit (24) is connected to the upper flange (14) of the lattice girder (12) by means of projection units (30) with pipe couplings (32).
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Anschlusselemente (28) als Einhängetaschen (34) mit Keil (36) ausgebildet sind, in die eine in den Endbereichen der Abstützeinheiten (20) jeweils vorhandene Vorsprungeinheit (38) eingeführt ist und die Vorsprungeinheit (38) mittels des Keiles (36) jeweils lösbar in den Einhängetaschen (34) arretiert ist.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the connection elements (28) are designed as suspension pockets (34) with wedges (36) into which a projection unit (38) present in the end regions of the support units (20) is inserted and the projection unit (38) by means of the wedge (36) is detachably locked in the hanging pockets (34).
Planendachkonstruktion nach Anspruch 4,
dadurch gekennzeichnet, dass
die seitlichen Abstützeinheiten (20) als serienmäßig hergestellte Geländerstäbe eines bekannten Standard-Gerüstsystem, insbesondere des Blitz-Gerüstsystems der Firma Layher, ausgebildet sind.
Tarpaulin roof construction according to claim 4,
characterized in that
the lateral support units (20) are designed as mass-produced railing rods of a known standard scaffolding system, in particular the flash scaffolding system from Layher.
Planendachkonstruktion nach Anspruch 4,
dadurch gekennzeichnet, dass
die seitlichen Abstützeinheiten (20) als rahmenartiges serienmäßig hergestelltes Doppelstabgeländer eines bekannten Standard-Gerüsts, insbesondere des Blitz-Gerüsts der Firma Layher, ausgebildet sind.
Tarpaulin roof construction according to claim 4,
characterized in that
the lateral support units (20) are designed as a frame-like, double-rod railing of a known standard scaffold, in particular the lightning scaffold from Layher.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
der Abstand der seitlichen Abstützeinheiten (20) untereinander im Bereich zwischen 40 cm (Zentimeter) und 60 cm (Zentimeter) liegt.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the distance between the lateral support units (20) is between 40 cm (centimeters) and 60 cm (centimeters).
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Breite der Plane im Wesentlichen dem Abstand zweier Dachbinder entspricht.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the width of the tarpaulin corresponds essentially to the distance between two roof trusses.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
auf der Anschlussprofileinheit (24) und/oder der Vollprofileinheit (26) eine hutförmige, nach unten offene Abdeckprofileinheit (40) angeschlossen ist, die mit ihren Schenkeln die angeschlossene Plane (18) nach unten drückt, wodurch innerhalb der Plane (18) eine Vorspannung erzeugt wird.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
on the connection profile unit (24) and / or the full profile unit (26) a hat-shaped cover profile unit (40) which is open at the bottom is connected and which presses the connected tarpaulin (18) down with its legs, as a result of which a prestress is created within the tarpaulin (18) is produced.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Anschlusselemente (28) für die seitlichen Abstützeinheiten (20) unterseitig an der Anschlussprofileinheit (24) angeschlossen sind.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the connection elements (28) for the lateral support units (20) are connected on the underside to the connection profile unit (24).
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Gitterträger als serienmäßig hergestelltes Gerüstbauteil eines bekannten Standard-Gerüsts, insbesondere des Blitz-Gerüsts der Firma Layher, ausgebildet sind.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the lattice girders are designed as a series-produced scaffolding component of a known standard scaffolding, in particular the flash scaffolding from Layher.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Gitterträger aus Aluminium bestehen.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the lattice girders are made of aluminum.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Anschlussprofileinheit aus Stahl besteht.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the connection profile unit is made of steel.
Planendachkonstruktion nach einem oder mehreren der vorstehenden Ansprüche,
dadurch gekennzeichnet, dass
die Plane (18) mit eingeschlagenen, insbesondere getackerten Metallklammern (42) an der Vollprofileinheit (26) befestigt ist.
Tarpaulin roof construction according to one or more of the preceding claims,
characterized in that
the tarpaulin (18) is fastened to the full profile unit (26) by means of hammered, in particular stapled, metal clips (42).
Planendachkonstruktion nach Anspruch 9,
dadurch gekennzeichnet, dass
die Abdeckprofileinheit (40) mittels Schrauben (44) mit der Vollprofileinheit (26) verbunden ist.
Tarpaulin roof construction according to claim 9,
characterized in that
the cover profile unit (40) is connected to the full profile unit (26) by means of screws (44).
EP01113328A 2000-06-09 2001-05-31 Saddle roof structure Expired - Lifetime EP1162325B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE10028262 2000-06-09
DE10028262A DE10028262A1 (en) 2000-06-09 2000-06-09 Tarpaulin roof construction

Publications (3)

Publication Number Publication Date
EP1162325A2 true EP1162325A2 (en) 2001-12-12
EP1162325A3 EP1162325A3 (en) 2003-06-04
EP1162325B1 EP1162325B1 (en) 2007-04-04

Family

ID=7645041

Family Applications (1)

Application Number Title Priority Date Filing Date
EP01113328A Expired - Lifetime EP1162325B1 (en) 2000-06-09 2001-05-31 Saddle roof structure

Country Status (4)

Country Link
EP (1) EP1162325B1 (en)
AT (1) ATE358754T1 (en)
DE (2) DE10028262A1 (en)
PL (1) PL347964A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004072410A1 (en) * 2003-02-17 2004-08-26 Baker, Diane, Margaret Structures
CN107013051A (en) * 2017-04-24 2017-08-04 苏州新区德力精密机械有限公司 A kind of prefabricated house
CN110145028A (en) * 2019-05-07 2019-08-20 天津大学 The centripetal double rustling sounds in top for beam-string structure support joint system
WO2023227685A1 (en) * 2022-05-25 2023-11-30 Pluseight Technology Ab A temporary protective roof system
CN118461820A (en) * 2024-07-15 2024-08-09 辽宁永壮铝业集团有限公司 Assembled aluminum alloy section bar ceiling frame

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE502006002431D1 (en) 2006-04-15 2009-02-05 Layher W Verwaltungs Gmbh U-profile beams of a canopy, hall, grandstand, stairs, a scaffold or podium
CN104100113B (en) * 2014-08-05 2016-06-22 广汉久创石油机械有限责任公司 Rain-proof shelter and using method thereof for oil drilling solid controlling system
DE202014106083U1 (en) 2014-12-16 2015-01-14 B+P Gerüstbau Gmbh Rapid installation canopy
DE202022002594U1 (en) 2022-07-09 2023-04-25 Hakos Gmbh angle lattice girder

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3542610A1 (en) 1985-12-03 1987-06-04 Ulrich Layher Rapid-assembly hall roof

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US824502A (en) * 1903-06-05 1906-06-26 Edmond Molloy Frame structure.
US2828756A (en) * 1955-10-21 1958-04-01 Harold Smith J Sectional tent
US2986150A (en) * 1958-03-17 1961-05-30 Torian William Harold Means for mounting thin, flexible membranes
US2996160A (en) * 1958-07-30 1961-08-15 Acrow Eng Ltd Builder's appliances
GB985913A (en) * 1960-06-14 1965-03-10 Kwikform Ltd Improvements in or relating to builders scaffolding
LU62093A1 (en) * 1970-11-19 1972-07-26
DE3107416A1 (en) * 1981-02-27 1982-09-16 Eberhard 7129 Güglingen Layher "STRUCTURAL CONSTRUCTION FOR ASSEMBLY AND DEGRADABLE ROOFS OR HALLS"
DE8230404U1 (en) * 1982-10-29 1982-12-30 Karl Höcker Stahlbau GmbH & Co KG, 4902 Bad Salzuflen ROOF TIES FOR A TENT STRUCTURE
US4586301A (en) * 1984-08-06 1986-05-06 W. P. Hickman Company Retainer clamp membrane fastening system
US4624721A (en) * 1985-06-18 1986-11-25 Sadler David E Method of using a roll of perforated plastic roofing tabs
DE9110828U1 (en) * 1991-08-22 1992-01-09 Günter Rux GmbH, 5800 Hagen framework
US5269106A (en) * 1991-11-20 1993-12-14 Fast Truss, Inc. Modular building structure
US5333425A (en) * 1993-01-07 1994-08-02 Rubb, Inc. Tension membrane structure wrinkle elimination

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3542610A1 (en) 1985-12-03 1987-06-04 Ulrich Layher Rapid-assembly hall roof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004072410A1 (en) * 2003-02-17 2004-08-26 Baker, Diane, Margaret Structures
GB2417517A (en) * 2003-02-17 2006-03-01 Diane Margaret Baker Structures
CN107013051A (en) * 2017-04-24 2017-08-04 苏州新区德力精密机械有限公司 A kind of prefabricated house
CN110145028A (en) * 2019-05-07 2019-08-20 天津大学 The centripetal double rustling sounds in top for beam-string structure support joint system
WO2023227685A1 (en) * 2022-05-25 2023-11-30 Pluseight Technology Ab A temporary protective roof system
CN118461820A (en) * 2024-07-15 2024-08-09 辽宁永壮铝业集团有限公司 Assembled aluminum alloy section bar ceiling frame

Also Published As

Publication number Publication date
EP1162325A3 (en) 2003-06-04
DE10028262A1 (en) 2001-12-13
PL347964A1 (en) 2001-12-17
EP1162325B1 (en) 2007-04-04
DE50112279D1 (en) 2007-05-16
ATE358754T1 (en) 2007-04-15

Similar Documents

Publication Publication Date Title
DE1559410A1 (en) Prefabricated building construction
EP2984255B1 (en) Lattice girder for a weather protection roof, and weather protection roof having multiple lattice girders
EP1162325B1 (en) Saddle roof structure
EP1035271B1 (en) Quick erecting shed roof
DE202014106083U1 (en) Rapid installation canopy
DE3108020A1 (en) "PROTECTIVE DEVICE FOR METAL FRAME"
DE8336223U1 (en) SOUND INSULATING WALL
DE938874C (en) Building consisting of a metal skeleton and panel cladding
EP3650616A1 (en) Weather protection roof made of spanneed roof tarpaulin with scaffold boards mounted over the tarpaulin
EP1808550B1 (en) Roof with gable scaffolding and method of erection and use
EP1961886B1 (en) U-shaped beam of a canopy, hall, grandstand, staircase, scaffolding or platform
DE3716552A1 (en) Metal trussed girder
DE20105534U1 (en) Quick assembly hall
DE102016004074A1 (en) Rigid corner construction for the supporting structure of a Keder roof
DE1271363B (en) Outer wall cladding made of panel-shaped cladding elements lined up on tension elements
DE202005009660U1 (en) Temporary fall prevention device for use on a sloping roof has parallel profiled roof posts, a net and a mounting arrangement that is supported on the roof tile transverse supports or battens
DE202016107006U1 (en) scaffold tower
DE3421742A1 (en) Roofing structure for building sites
EP0943753B1 (en) Covering device for scaffold structures
DE1509056A1 (en) Components for roof structures
DE3417068A1 (en) Transportable collapsible hall
DE202022002594U1 (en) angle lattice girder
DE9318732U1 (en) Structure for a construction such as a hall, inner tent, tent or the like.
DE2748242A1 (en) Hut roof with foil membrane covering - has extensible rafters hinged to girders and thrust into arched setting (IL 29.4.77)
DE20203066U1 (en) Shelter with sloping roof, especially for horses kept in fields, comprises tubular frame and flexible material wall panelling

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Free format text: AL;LT;LV;MK;RO;SI

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Extension state: AL LT LV MK RO SI

RIC1 Information provided on ipc code assigned before grant

Ipc: 7E 04G 1/26 B

Ipc: 7E 04D 5/14 B

Ipc: 7E 04B 7/02 A

Ipc: 7E 04H 15/44 B

Ipc: 7E 04B 1/342 B

17P Request for examination filed

Effective date: 20031007

AKX Designation fees paid

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: WILHELM LAYHER VERWALTUNGS-GMBH

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RIC1 Information provided on ipc code assigned before grant

Ipc: E04B 1/342 20060101ALI20061102BHEP

Ipc: E04D 5/14 20060101ALI20061102BHEP

Ipc: E04H 15/44 20060101ALI20061102BHEP

Ipc: E04B 7/02 20060101AFI20061102BHEP

Ipc: E04G 5/00 20060101ALI20061102BHEP

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REF Corresponds to:

Ref document number: 50112279

Country of ref document: DE

Date of ref document: 20070516

Kind code of ref document: P

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070704

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070715

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070904

NLV1 Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act
GBV Gb: ep patent (uk) treated as always having been void in accordance with gb section 77(7)/1977 [no translation filed]

Effective date: 20070404

REG Reference to a national code

Ref country code: IE

Ref legal event code: FD4D

EN Fr: translation not filed
BERE Be: lapsed

Owner name: WILHELM LAYHER VERWALTUNGS-GMBH

Effective date: 20070531

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

Ref country code: IE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

26N No opposition filed

Effective date: 20080107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20071130

Ref country code: GB

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20080515

Year of fee payment: 8

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20070404

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20091201

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070531