EP0736665A2 - Construction of holes and tunnels having support walls - Google Patents

Construction of holes and tunnels having support walls Download PDF

Info

Publication number
EP0736665A2
EP0736665A2 EP96302315A EP96302315A EP0736665A2 EP 0736665 A2 EP0736665 A2 EP 0736665A2 EP 96302315 A EP96302315 A EP 96302315A EP 96302315 A EP96302315 A EP 96302315A EP 0736665 A2 EP0736665 A2 EP 0736665A2
Authority
EP
European Patent Office
Prior art keywords
hole
walls
wall
segment
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP96302315A
Other languages
German (de)
French (fr)
Other versions
EP0736665A3 (en
Inventor
Yitshaq Lipsker
Daniel Abramov
Oleg Figovsky
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lipsker & Partners Engineering Services (1975) Ltd
Original Assignee
Lipsker & Partners Engineering Services (1975) Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lipsker & Partners Engineering Services (1975) Ltd filed Critical Lipsker & Partners Engineering Services (1975) Ltd
Publication of EP0736665A2 publication Critical patent/EP0736665A2/en
Publication of EP0736665A3 publication Critical patent/EP0736665A3/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Earth Drilling (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A method for constructing an underground construction comprising a hole or tunnel having support walls, the method comprising the method comprising the steps of excavating an initial hole or tunnel segment, forming at least a portion of the initial segments so that its walls assume a final shape and size corresponding to the external shape and size of the support walls, inserting at least a leading support wall element into a the segment, excavating a further hole segment, forming the further hole segment so that its walls assume a final shape and size corresponding to the external shape and size of the support walls, allowing the at least first support wall element to translocate into the further segment and introducing one or more trailing support wall elements into the initial segment, repeating necessary steps until constructing the entire hole.

Description

    FIELD OF THE INVENTION
  • The present invention is generally in the field of excavations, e. g. construction of foundation elements, retaining walls and tunnels.
  • BACKGROUND OF THE INVENTION
  • Excavation of holes with support walls is required in several cases, particularly in loose soil or at excavations performed at watery environments, such as underwater excavations or excavations performed at high water tables. Holes with support walls may be useful also for obtaining higher strength of foundation elements or retaining walls.
  • One method for constructing a hole with support walls is by first excavating the hole, placing an insert into the hole and then casting concrete into the space between the insert and the walls of the hole. This method is not suitable for excavating in a watery environment unless, the excavation is constantly filled with a substance such as Bentonite or suitable polymeric substances, which must then be subsequently pumped out during the concrete casting procedure.
  • This is a time consuming procedure requiring special equipment and is relatively expensive. A further disadvantage of such a method lies in that the surface quality of the casted foundation elements or retaining walls (after removing the surrounding soil) is rough and for obtaining a smooth surface finish, treatment of the surface is necessary which again is a time and labor consuming procedure.
  • Another known method for excavating holes with support walls is by excavating an opening in the ground of a size substantially larger than the size of the actual required size of the hole, then inserting precast reinforcing wall elements into the excavation and then filling back the removed soil into the gap between the walls of the excavation and the external faces of the reinforcing elements and pressing it. This method is complicated and time consuming and is restricted to substantially short and vertical excavations.
  • It is an object of the present invention to provide a novel method for constructing holes or tunnels with reinforcing walls in which some of the above-noted disadvantages are substantially reduced or overcome.
  • SUMMARY OF THE INVENTION
  • According to the present invention there is provided a method for constructing an underground construction comprising a hole or tunnel having support walls, the method comprising:
    • (a) excavating an initial hole or tunnel segment;
    • (b) forming at least a portion of said initial segments so that its walls assume a final shape and size corresponding to the external shape and size of the support walls;
    • (c) inserting at least a leading support wall element into a said segment;
    • (d) excavating a further hole segment;
    • (e) forming said further hole segment so that its walls assume a final shape and size corresponding to the external shape and size of the support walls;
    • (f) allowing said at least first support wall element to translocate into said further segment and introducing one or more trailing support wall elements into said initial segment;
    • (g) repeating steps (d) - (f) until constructing the entire said hole.
  • According to one embodiment of the method according to the present invention, the excavation is substantially vertical and the construction, which comprises a hole having support walls, serves as a foundation element. According to another embodiment, the method comprises constructing a plurality of substantially vertical holes having support walls adjacent one another, these constructions serving as members in a retaining wall.
  • According to still another embodiment of the present invention, the excavation is horizontal or slanted, to construct a tunnel with support walls, useful as ducts, as pipes for protecting cables, e.g. telephone or electric cables, contained therein, etc.
  • At times, the method according to either of the above embodiments may comprise also filling the space confined within the walls of the holes with a filler substance, such as concrete, reinforced concrete, gravel, soil, etc. This is particularly the case where the construction is a vertical hole serving as a foundation element or a member in a retaining wall. Where the method involves filling the confined space with a filler substance, particularly concrete, the wall elements may comprise apertures for introducing concrete or the like into the interstice between the inner walls of the excavations and the external faces of the support walls. Alternatively, or in combination, contact grout or concrete may be applied into the interstice directly by injecting it through tubes inserted therein.
  • Where the constructions form part of a retaining wall, one side of all wall elements may have a shape or patents so that all such sides together form a uniform wall. The wall elements may consist of several elements which together form a tubular, e.g. cylindrical or prismatic, wall element. For example, each wall element may consist of two members with a substantially U-like cross-sectional shape, which together form a tubular wall element.
  • In accordance with one embodiment of the invention, at least one side of the wall elements is removable. In another embodiment, an inner surface of at least one side of the wall element is covered with a polymer substance.
  • The leading wall element may be identical or different to the other wall elements. According to a preferred embodiment of the invention, the leading wall element comprises a wedge-like leading edge on at least one side thereof.
  • According to a preferred embodiment of the invention, the excavation is performed by an excavating equipment comprising pressure members adapted for applying force in a radial direction. Where the excavation is a tunnel, the wall elements may be inserted and translocated within the hole by the use of such an excavation equipment.
  • Also provided by the present invention are prefabricated wall elements for use in conjunction with the method of the invention.
  • For better understanding, the invention will now be described, by way of example only, with reference to specific embodiments illustrated in the accompanying drawings.
  • DESCRIPTION OF THE DRAWINGS
    • Fig. 1 is an isometric view partially cut-out of a rectangular foundation element constructed according to the method of the present invention;
    • Figs. 2a - 2g illustrate the steps of constructing the foundation element of Fig. 1, each figure showing a front and a side cross-sectional view;
    • Fig. 3 is an isometric view partially cut-out of a cylindrical foundation element constructed according to the method of the present invention;
    • Figs. 4a - 4g illustrate the steps of constructing the foundation element of Fig. 3;
    • Figs. 5a - 5h illustrate the steps of constructing a tunnel according to the method of the present invention;
    • Fig. 6 is an isometric view partially cut-out of a retaining wall constructed according to the method of the present invention;
    • Fig. 7 is an isometric view illustrating a male-female connection of two consequent cylindrical wall elements of a foundation element according to the present invention;
    • Fig. 8 is a top cross-sectional view illustrating one way of locking two adjacent wall elements of a retaining wall constructed according to the method of the present invention;
    • Fig. 9 is an isometric view of a rectangular leading wall element according to the present invention;
    • Fig. 10 is a cross-sectional view along line X-X in Fig. 9;
    • Fig. 11 is an isometric view of a wall element comprising a removable side wall;
    • Fig. 12 is an isometric view of a wall element formed of two U-shaped wall elements;
    • Fig. 13 is an isometric view of a wall element according to the present invention comprising apertures; and
    • Fig. 14 is an isometric view partially cut-out of a foundation element illustrating how contact grout is injected into the interstice between the inner walls of the hole and the external walls of the reinforcing elements.
    DETAILED DESCRIPTION OF SPECIFIC EMBODIMENTS
  • Attention is first directed to Figs. 1 and 2a-2g showing how a rectangular foundation element 2 is constructed according to the present invention.
  • At a first step, an initial hole segment 4 is excavated, for example by an excavating equipment 6, such as that disclosed in PCT Patent Application WO 94/19272, comprising an excavating clamshell buckets 8 and surface clamping plates 10, adapted for lateral extraction and retraction, the excavating equipment being operated and displaced into and out of the excavation by cables 12 and 13. In addition, various other excavating equipment may also be used.
  • After the initial hole segment 4 is excavated, the surface clamping plates 10 apply lateral pressure on the inner wall of a portion 14 of the initial hole segment 4, as can be seen in Fig. 2B, whereby the walls of the portion 14 assume a final shape corresponding to the external shape and size of a rectangular leading reinforcing wall element 16. After hoisting the excavation equipment 6, from the hole, a leading wall element 16 is inserted into the formed portion 14, as shown in Fig. 2C. The wall elements are typically prefabricated elements, the nature of which will be explained in more detail below.
  • The next step in constructing the foundation element, as illustrated in Figs. 2D, is digging a further hole segment 18 and then the pressure plates 10 expand and form the walls of segment 18 so that they assume a shape and size corresponding to the external shape and size of the reinforcing wall elements.
  • Upon retraction of the pressure plates 10, after forming the further segment 18, the leading wall elements 16 drops into the further segment 18 and after withdrawing the excavating equipment 6, a trailing reinforcing wall element 20 is introduced into the initial hole segment 4 as shown in Fig. 2E.
  • The above procedure is repeated as illustrated in Figs. 2F and 2F until a foundation element 2 of a required depth is obtained, illustrated in Fig. 1.
  • Reference is now made to Figs. 3 and 4A-4G of the drawings, illustrating how a cylindrical hole 30 with a support wall is constructed according to the method of the present invention.
  • At a first step, an initial bore segment 32 is drilled, for example by using the drilling equipment 34 as disclosed in GB Patent No. 2176519, comprising a drilling tool such as an auger 36 connected to a drive (not shown) and further comprising clamping shells 38 having the shape of cylindrical segments, adapted for applying radial pressure on the walls of the bore and pressing the ground. As an alternative to auger 36, also a bucket or any other drilling tool adapted to the soil conditions may be used. The drilling equipment is introduced and removed from the bore by a hoisting cable 40.
  • After drilling the initial bore segment 32, at least a portion of its wall are pressed by clamping shells 38 and the walls of the hole then assume a shape and size corresponding to the external shape and size of an initial leading cylindrical wall element 42. Then, the drilling equipment is hoisted from the bore and the leading wall element 42 is inserted into the initial segment 32 as shown in Fig. 4c.
  • Thereafter, the drilling equipment 34 is again lowered into the bore through the confined space of leading wall element 42 and a further hole segment 44 is then excavated as shown in Fig. 4D. Then, the further hole segment 44 is formed by the clamping shells 38 to the shape and size corresponding to the external shape and size of the reinforcing wall elements 42 (Fig. 4D). Upon retraction of the clamping shells 38, the leading wall element 42 drops into the further hole segment 44 and after the drilling equipment 34 is withdrawn from the bore, a trailing wall element 46 is inserted into the initial bore and over the leading wall element 42, as shown in Fig. 4E.
  • The above steps are repeated (Figs. 4F and 4G) until constituting a complete hole with reinforcing walls 30 of the required depth, as seen in Fig. 3.
  • Referring now to Figs. 5A - 5H, it will be explained how a horizontal tunnel with support walls may be constructed according to the present invention. however, it should be obvious that tunnel construction in accordance with the invention is not restricted to horizontal and may obviously also be diagonal.
  • The principle difference between tunnelling and constructing foundation elements is that tunnels are substantially horizontal holes in which gravitation forces do not assist in excavating or in inserting the wall elements and thus, specialized equipment is required.
  • Drilling equipment 60 comprises a drilling end 62 (which may be for example a drilling bit, an auger or a bucket drill or any other drilling tool adapted to the specific ground conditions; in case of a drilling bit continuous drilling operations may be obtained by the aid of a flushing system) attached by a first shaft 64 to a drive (not shown) and further comprising a first set of clamping shells 66 linked by a second shaft 68 to a second set of clamping shells 70, both sets of clamping shells capable of radially expanding and retracting. The shafts 64 and 68 are axially retractable.
  • At a first step, an initial hole segment 74 is drilled (Figs. 5A,5B). Then the first set of clamping shells 66 are radially expanded whereby they clamp against the inner wall of the hole, followed by extraction of the first shaft 64, whereby the drilling end 62 is urged into the soil and further drilling is performed (Fig. 5C). Then clamp shells 66 contract and shaft 64 retracts. Subsequently, clamp shells 70 radially expand and clamp against the wall of the hole and the second shaft 68 extracts (Fig. 5D).
  • After forming the initial hole segment 74 by the clamp shells 66 and 70, the drilling equipment is removed from the hole and a leading wall element 78 is inserted into the initial hole segment 74.
  • The drilling equipment is then inserted through said leading element 78 and the above procedure is repeated (Figs. 5E-5G), whereby the tunnel is lengthened and trailing wall elements 80 are inserted following the leading wall element 78, until completing the tunnel (Fig. 5H).
  • The design of the clamp shells 66 and 70 is such that inserting the wall elements 78 and 80 may be performed by the aid of the clamp shells clampingly gripping the wall elements at their inner surfaces and advancing them into the hole (as illustrated in Fig. 5G).
  • Fig. 6 of the drawings illustrates a retaining wall 90 constructed of plurality of vertical reinforced holes 92, each consisting of a plurality of wall elements 94 and constructed as explained in connection with Figs. 1 and 2A-2G.
  • In order to assure aligning of the holes 92 and of wall elements 94 with one another, adjacent wall elements 94 above one another are fixed to one another by a male-female arrangement 96, whereas adjacent wall elements near one another are fixed by other male-female arrangement 98.
  • Turning now to Fig. 7, it is shown that a male-female arrangement 100 is also suitable for fixing two cylindrical wall elements 102 and 104 above one another, each such wall element comprising at a bottom edge thereof several cut-outs 106 whereas the opposed, top end of each of the elements comprises projections 108 of a shape and size adapted to blend with the cut-outs of a trailing wall element.
  • Fig. 8 of the drawing illustrates another method for fixing adjacent, neighboring wall elements of a retaining wall. According to this method, each of the wall elements 112 and 114 of holes 116 and 118, respectively, has U-like shaped sides 120, whereas when the two neighboring wall elements are constructed adjacent one another with the U-shaped edges facing one another, there is created a cavity 122. This cavity may be reinforced by cement cast or by soil, rocks, etc., whereby lateral movement between the adjacent reinforcement holes 116 and 118 is prevented.
  • Figs. 9 and 10 show a rectangular leading wall element 128 comprising a wedge-like edge 130 at two opposed edges thereof. This arrangement is useful in blazing the trail of the leading wall element by scraping the soil projecting into a hole segment which may obstruct the advancing of the wall elements. The wedge-like edge is also operating as a guide for the excavating tool while being extracted from the hole.
  • The confined space within the walls of the hole may be filled with a filler substance which may be, for example plain or reinforced concrete, soil which has been removed during excavating the hole, rocks, etc.
  • If a foundation element or a retaining wall is later to be exposed by removing the surrounding soil, it may at times be desired to have one or more sides of the construction with a decorative pattern or design, or simply obtain a good surface quality which will require no further operations thereon.
  • The rectangular wall element 138 of Fig.11 comprises a removable wall 140 secured to the element by locking nuts 142, the inner surface of the wall 140 comprising a molding pattern. The arrangement is such that after constructing the hole and casting concrete in it, the ground surrounding the foundation element or retaining wall is excavated and the removable walls 140 (all facing the same side) are removed, exposing a concrete wall having the negative design of the decorative pattern of the inner surface of the removed wall.
  • In order to obtain still a better surface quality, the inner surface of at least the removable wall 140 may be coated with a polymeric substance, which will ensure a smooth concrete surface.
  • Fig. 12 illustrates how a tubular wall element 146 may be constructed of several segments, in the present case of two substantially U-like shaped elements 148 and 150, with locking members 152 for attaching the elements to one another. Such elements are useful for example for constructing a retaining wall, where the partitioning walls between neighboring wall elements are removed, whereby a continuous wall is obtained.
  • Where it is required to improve contact between a foundation element or retaining wall and between the ground, e.g. in cases of extreme loads to be applied on the construction, or at watery environments, it is at times useful to introduce concrete or a contact grout in the interstice between the inner wall of the hole and between the external faces of the wall elements. For that purpose, for example, wall elements 160 as seen in Fig. 13 may be used, such elements comprise a plurality of side apertures 162. After inserting the wall elements into the hole, concrete is introduced into the space confined within the walls, which then penetrates into said interstice through the apertures 162.
  • In addition or in the alternative the contact between the construction and the surrounding ground may also be improved by applying contact grout directly into the interstice 166 as shown in Fig. 14, by a plurality of injecting tubes 168 introduced into the interstice 166, each tube comprising a plurality of nozzles 170. The tubes 168 are connected to a central tube 172 receiving pressurized contact grout from a pressure unit 174 whereby the contact grout is forcefully injected into to the interstice 166.
  • Excavations for constructing the holes according to the present invention may be performed by a variety of excavating means, however, it should be noted that an important feature of the excavating equipment is its ability to apply lateral pressure onto the walls of the hole for forming them into the shape and size corresponding to that of the external shape and size of the reinforcing walls, whereby the walls of the hole are pressed.
  • It should be obvious to a person versed in the art that the wall elements are prefabricated elements manufactured at a large variety of sizes and of various materials, e.g. plain or reinforced concrete, polymers, metal or various combinations thereof.
  • It would also be obvious to a person versed in the art that other locking means may be used for obtaining linkage between adjacent wall elements in order to ensure their alignment.

Claims (19)

  1. A method for constructing an underground construction comprising a hole or tunnel having support walls, the method comprising:
    (a) excavating an initial hole or tunnel segment;
    (b) forming at least a portion of said initial segments so that its walls assume a final shape and size corresponding to the external shape and size of the support walls;
    (c) inserting at least a leading support wall element into a said segment;
    (d) excavating a further hole segment;
    (e) forming said further hole segment so that its walls assume a final shape and size corresponding to the external shape and size of the support walls;
    (f) allowing said at least first support wall element to translocate into said further segment and introducing one or more trailing support wall elements into said initial segment;
    (g) repeating steps (d) - (f) until constructing the entire said hole.
  2. A method according to Claim 1, wherein the wall elements are made of concrete.
  3. A method according to Claim 1, comprising excavating a substantially vertical hole and inserting said wall elements into the hole.
  4. A method according to Claim 3, comprising filling the space confined within the walls of the hole by a filler substance.
  5. A method according to Claim 3, wherein the hole with reinforcing walls serves as a foundation element.
  6. A method according to Claim 3, comprising constructing a plurality of substantially vertical holes with reinforcing walls adjacent one another, the constructions serving as members in a retaining wall.
  7. A method according to claim 5, wherein one side of the retaining wall has a shape or pattern so that all such sides together form a uniform wall.
  8. A method according to claim 1, comprising excavating a substantially horizontal hole and inserting said wall elements into the hole, the construction serving as a tunnel.
  9. A method according to Claim to claim 1, wherein adjacent wall elements are fixed to one another by locking means.
  10. A method according to Claim 9, wherein said locking means comprise a male-female arrangement.
  11. A method according to Claim 1, wherein the wall elements comprise two members with a substantially U-like cross-sectional shape which together form a tubular wall element.
  12. A method according to Claim 1, wherein one or more wall elements comprise apertures.
  13. A method according to Claim 1, wherein said leading wall element comprises a wedge-like leading edge on at least one side thereof.
  14. A method according to Claim 1, wherein one side of the wall elements is removable.
  15. A method according to Claim 1, wherein an inner surface of at least one side of the wall element is covered with a polymeric substance.
  16. A method according to Claim 1, wherein the excavating is performed by excavating equipment comprising pressure members adapted for applying force in a radial direction.
  17. A method according to Claim 15, wherein the wall elements are inserted and translocated within the hole by said pressure members of said excavating equipment.
  18. A method according to any one of the preceding claims, wherein a contact grout is applied into an interstice between inner walls of the hole and between external sides of the reinforcing walls.
  19. For use in a method according to Claim 1, a prefabricated tubular wall element.
EP96302315A 1995-04-05 1996-04-01 Construction of holes and tunnels having support walls Withdrawn EP0736665A3 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
IL11326295 1995-04-05
IL11326295A IL113262A0 (en) 1995-04-05 1995-04-05 Construction of holes and tunnels having support walls

Publications (2)

Publication Number Publication Date
EP0736665A2 true EP0736665A2 (en) 1996-10-09
EP0736665A3 EP0736665A3 (en) 1997-11-19

Family

ID=11067320

Family Applications (1)

Application Number Title Priority Date Filing Date
EP96302315A Withdrawn EP0736665A3 (en) 1995-04-05 1996-04-01 Construction of holes and tunnels having support walls

Country Status (3)

Country Link
EP (1) EP0736665A3 (en)
JP (1) JPH08284581A (en)
IL (1) IL113262A0 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2447622A (en) * 2007-01-10 2008-09-24 Martello Piling Ltd Method of excavating a non-circular shaft

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE936561C (en) * 1954-01-27 1955-12-15 Holzmann Philipp Ag Procedure for sinking sheep
DE2352252A1 (en) * 1973-10-18 1975-04-24 Ruhrkohle Ag Drilling and extending of blind mine-shafts - involves initial drilling of hole from lower shaft and widening it with larger drill
DE2709114A1 (en) * 1977-03-02 1978-09-07 Zueblin Ag METHOD FOR MANUFACTURING UNDERGROUND TRANSPORT ROUTES OF LARGE DIAMETERS
US4227583A (en) * 1978-11-13 1980-10-14 Wirth Maschinen-Und Bohrgerate-Fabrik Method and apparatus for sinking shafts
GB2094860A (en) * 1981-03-14 1982-09-22 Dunlop Ltd Lining of tubular structures
GB2099479A (en) * 1981-05-13 1982-12-08 Charcon Tunnels Ltd Improvements in or relating to arcuate tunnel lining segments
DE3125274A1 (en) * 1981-06-24 1983-01-13 Philipp Holzmann Ag, 6000 Frankfurt Tubes for curved tunnels as well as a method of constructing curved tunnels
EP0132066A1 (en) * 1983-06-27 1985-01-23 Rees Construction Services Limited Tunnelling and tunnel relining equipment
DE3416287A1 (en) * 1984-05-03 1985-11-07 Ernst 7270 Nagold Wackenhut Method of producing a foundation
GB2176519A (en) * 1985-05-10 1986-12-31 Yitshaq Lipsker Drilling boreholes
EP0242497A1 (en) * 1986-04-25 1987-10-28 S.A. Entreprises Koeckelberg Tunnel construction process

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE936561C (en) * 1954-01-27 1955-12-15 Holzmann Philipp Ag Procedure for sinking sheep
DE2352252A1 (en) * 1973-10-18 1975-04-24 Ruhrkohle Ag Drilling and extending of blind mine-shafts - involves initial drilling of hole from lower shaft and widening it with larger drill
DE2709114A1 (en) * 1977-03-02 1978-09-07 Zueblin Ag METHOD FOR MANUFACTURING UNDERGROUND TRANSPORT ROUTES OF LARGE DIAMETERS
US4227583A (en) * 1978-11-13 1980-10-14 Wirth Maschinen-Und Bohrgerate-Fabrik Method and apparatus for sinking shafts
GB2094860A (en) * 1981-03-14 1982-09-22 Dunlop Ltd Lining of tubular structures
GB2099479A (en) * 1981-05-13 1982-12-08 Charcon Tunnels Ltd Improvements in or relating to arcuate tunnel lining segments
DE3125274A1 (en) * 1981-06-24 1983-01-13 Philipp Holzmann Ag, 6000 Frankfurt Tubes for curved tunnels as well as a method of constructing curved tunnels
EP0132066A1 (en) * 1983-06-27 1985-01-23 Rees Construction Services Limited Tunnelling and tunnel relining equipment
DE3416287A1 (en) * 1984-05-03 1985-11-07 Ernst 7270 Nagold Wackenhut Method of producing a foundation
GB2176519A (en) * 1985-05-10 1986-12-31 Yitshaq Lipsker Drilling boreholes
EP0242497A1 (en) * 1986-04-25 1987-10-28 S.A. Entreprises Koeckelberg Tunnel construction process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2447622A (en) * 2007-01-10 2008-09-24 Martello Piling Ltd Method of excavating a non-circular shaft

Also Published As

Publication number Publication date
IL113262A0 (en) 1995-07-31
JPH08284581A (en) 1996-10-29
EP0736665A3 (en) 1997-11-19

Similar Documents

Publication Publication Date Title
US4453861A (en) Trench walls and method for constructing same
US11692324B2 (en) Wall element system and method and apparatus for constructing shoring walls
US6749372B2 (en) Underground shell-pile continuous wall job practice and its special drill
EP0736665A2 (en) Construction of holes and tunnels having support walls
EP0580926A1 (en) Sealing joint in diaphragms formed by concrete panels cast in situ and a process for building said diaphragms
AU2022271401A1 (en) Improved caisson and wall element system and method and apparatus for constructing shoring walls
CN109653193B (en) Reverse construction method for underground continuous wall
JPH06306853A (en) Construction of underground structure
WO1988009849A1 (en) Reinforcement for continuously-cast concrete walls
CN115262533B (en) Joint-free underground diaphragm wall and construction method thereof
EP0337680A2 (en) Tunnel construction
KR100556976B1 (en) New Messer Shield engineering method
JP3766423B2 (en) Retaining wall construction method
EP1964981A1 (en) Reinforcement elements for in-situ cast walls and method to excavate in situ cast walls
JP3355282B2 (en) Construction method of perforated sheet pile and continuous underground wall having permeation section using this sheet pile
JP4146250B2 (en) Open caisson bottom plate construction method
CN110637126B (en) Water-proof wall
CN107059839A (en) A kind of construction method of armored concrete waveform sheet pile underground structure
DE3716750A1 (en) Method of constructing and sinking foundation structures
KR20200101637A (en) An auxiliary rack device for continuous construction of a pile
JPH05140940A (en) Sheathing method in large depth excavation
JPH0723084U (en) Concrete box for underground structure
CN110241850A (en) The construction method of open-cut station and large span Duplex Process bored tunnel interface
AU1803688A (en) Reinforcement for continuously-cast concrete walls
JP2000220158A (en) Construction method for water bottom tunnel

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): DE FR GB IT

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): DE FR GB IT

RHK1 Main classification (correction)

Ipc: E21D 1/08

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 19970410