EP0609953B1 - Installation for running out a ship's cable and ship equipped therewith - Google Patents
Installation for running out a ship's cable and ship equipped therewith Download PDFInfo
- Publication number
- EP0609953B1 EP0609953B1 EP19940200292 EP94200292A EP0609953B1 EP 0609953 B1 EP0609953 B1 EP 0609953B1 EP 19940200292 EP19940200292 EP 19940200292 EP 94200292 A EP94200292 A EP 94200292A EP 0609953 B1 EP0609953 B1 EP 0609953B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- ship
- cable
- auxiliary
- rope
- combination according
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B21/00—Tying-up; Shifting, towing, or pushing equipment; Anchoring
- B63B21/56—Towing or pushing equipment
Definitions
- the invention relates to the field of towing ships.
- the invention relates to the towing of ships which, as a consequence of calamities, such as the failure of the main propeller, collisions or the break-out of fire on board, are no longer able to reach a harbour under their own power.
- another vessel usually a tug, must be called for assistance to take the damaged ship under tow.
- a tow rope must be transferred between ship and tug, which in most cases is a routine matter.
- the aim of the invention is, to offer a solution to the above problems.
- This aim is achieved by a combination comprising a ship or freighter such as an oil tanker or a container ship, and an installation for running out a tow rope connected to said ship or freighter, which installation comprises a floating body, which is connected to the tow rope or an auxiliary cable and is provided with propelling means, and launching means fitted on board the ship for launching the floating body from the ship, such that, after the floating body has been launched, the rope or cable can be run out with respect to the ship by means of the tensile force delivered by the propelling means of the floating body.
- a cable can be run out to beyond the danger zone from the ship itself, without the intervention of crew present on said ship. Said cable can then be picked up by a tug at a safe distance.
- a command to set the installation according to the invention in operation can be given in various ways. For example, if the installation is equipped with a launching device which can be actuated by a receiver, use can be made of radio signals for this purpose. The installation is then set in operation from the tug.
- the floating body can be constructed in various ways. However, it is important that, even in heavy seas, said floating body must be able to travel in a specific line, in the direction away from the ship.
- the floating body is therefore constructed as an auxiliary vessel which also comprises steering means.
- the auxiliary vessel In connection with the pick-up, the auxiliary vessel carries fixing means to which a hoisting cable from a tug can be attached.
- the floating body comprises an energy source which can supply power to the propelling means at least for a few hours.
- the installation can keep the auxiliary cable or tow rope in the run-out position for a prolonged period. This period must be at least so long that a tug has sufficient time to sail, for example from a harbour where it is lying ready, to the stricken ship and to pick up the run-out auxiliary cable or tow rope.
- the propelling means can comprise either a combustion engine or an electric motor, or a combination of the two.
- the invention also relates to a ship provided with the installation described above, the launching means being installed close to the bow or the stern of the ship and pointing obliquely downwards, such that, on launching, the auxiliary vessel can be moved directly towards the water surface taking with it the auxiliary cable or the rope, which rope is attached to the ship on which the launching means are provided.
- the launching means can be located somewhat wide of the outermost point of the bow or stern. It is also possible to install two sets of launching means, directed towards different sides of the ship, at the bow or stern.
- the invention also relates to the use of an auxiliary vessel, which can be launched to sea and has an auxiliary cable or tow rope attached thereto, on board a ship or freighter for running out the auxiliary cable or tow rope, and keeping said cable or rope in the run-out position for a prolonged period, such that another ship, such as a tug, can take the run-out auxiliary cable or tow rope on board in order to tow the first ship.
- a floating body which is provided with propelling means and can be launched from a platform erected in the sea is disclosed in "Ship & Boat International", Part 41, No. 1, January 1988, Worchester Park, pages 19-20, “Getting Clear”.
- the purpose of the launched floating body is to pull a lifeboat lowered into the water from the platform away from the vicinity of said platform as quickly as possible.
- the energy source of the propelling means is exhausted after a few minutes. Within this period the lifeboat has been towed a sufficient distance away from the platform to enable it to sail further under its own power.
- This known installation is not suitable for running out a tow rope from a stricken ship, or for keeping the tow rope or auxiliary cable in the run-out position for a sufficiently long period such that a tug would be able to pick up the rope.
- Said installation 2 is installed on board the ship 1, only part of which is shown in the figure.
- Said installation 2 comprises mounting means 3, which are constructed as a tubular housing in which an auxiliary vessel 4 is housed.
- Said auxiliary vessel 4 is secured with respect to the mounting means 3 in a known manner.
- Said launching means comprise the rails 5, which are shown diagrammatically and extend to either side of the auxiliary vessel 4 in the mounting means 3. It is also possible to provide a drive charge, by means of which the auxiliary vessel 4 can be shot out of the mounting means 3 over the rails 5.
- the auxiliary vessel 4 is connected to a cable 6, which is wound on a reel 7.
- the auxiliary vessel 4 can be shot out, pulling the cable 6 with it.
- the auxiliary vessel makes a free fall, passing through the positions indicated by 8 and 9.
- the auxiliary vessel becomes submerged, comes up again and then floats on the surface of the water as shown at 10.
- steering means 12 which are known per se and are also indicated diagrammatically, are provided.
- the auxiliary vessel sails further and further away from the ship 1, until the entire cable 6 has been unwound from the reel 7.
- the propeller device 11 of the auxiliary vessel continues to operate, so that the cable 6 is continuously held in its position, pointing away from the ship 1.
- the auxiliary vessel is sufficiently large to carry a substantial energy source, so that such a position can be maintained over several hours. In the intervening period a tug is able to approach the auxiliary vessel 4 and pick it up by means of the fixing points 13.
- the cable 6 can be pulled in by the tug and, where necessary, a rope located on board ship 1 can be pulled to the tug.
- a lightweight cable is preferably used for cable 6, such that the auxiliary vessel 4 is well capable of dragging said cable 6 along over a fairly long distance from the ship. Nevertheless, cable 6 can also be made sufficiently heavy to enable it to be used itself as tow cable.
- cable 6 is a lightweight auxiliary cable
- a heavier tow rope can also be wound on reel 7.
- means can be provided on reel 7 which allow the auxiliary vessel 10 to unwind the relatively lightweight auxiliary cable 6 from the reel 7.
- Said means must then be constructed in such a way that they allow unwinding of the relatively heavy tow rope only if a traction force is exerted which is greater than the tensile force which can be exerted by the auxiliary vessel 4.
- a higher traction force of this type can easily be exerted by a tug, such that the tow rope is released by the reel 7 only under the influence of traction force exerted by the tug.
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Electric Cable Installation (AREA)
- Jib Cranes (AREA)
- Storing, Repeated Paying-Out, And Re-Storing Of Elongated Articles (AREA)
Description
- The invention relates to the field of towing ships. In particular, the invention relates to the towing of ships which, as a consequence of calamities, such as the failure of the main propeller, collisions or the break-out of fire on board, are no longer able to reach a harbour under their own power. In these cases another vessel, usually a tug, must be called for assistance to take the damaged ship under tow. To this end, a tow rope must be transferred between ship and tug, which in most cases is a routine matter.
- As long as the weather conditions are not too severe, and/or the nature of the defects is not too serious, no great difficulties are encountered in transfer of a tow rope. However, this changes when the ship concerned is in an area where weather is poor and there are high seas and, moreover, is on fire. Such a combination of factors makes transfer of a tow rope virtually impossible, the more so in view of the fact that the crew has by then already abandoned ship.
- Especially in the case of tankers, the consequences of such emergency conditions can be serious. Frequently the poor weather conditions and/or the heat of fires on board force such a long delay in the operations necessary for transferring the tow rope that the ship sinks with its cargo or founders on a nearby coast. This type of outcome in such emergency situations is disastrous for the environment and, if the area concerned is important for activities such as fishing or tourism, for the economy.
- From DE-A-3049235, it is known to bring out a tow rope from a ship by means of a helicopter. Here as well, bad weather conditions make the transfer of a tow rope very difficult having regard to the risks which are involved in the starting and landing operations on a stricken ship.
- The aim of the invention is, to offer a solution to the above problems. This aim is achieved by a combination comprising a ship or freighter such as an oil tanker or a container ship, and an installation for running out a tow rope connected to said ship or freighter, which installation comprises a floating body, which is connected to the tow rope or an auxiliary cable and is provided with propelling means, and launching means fitted on board the ship for launching the floating body from the ship, such that, after the floating body has been launched, the rope or cable can be run out with respect to the ship by means of the tensile force delivered by the propelling means of the floating body.
- According to the invention it is now no longer necessary to gain access from the tug to the stricken ship in order to transfer a tow rope. A cable can be run out to beyond the danger zone from the ship itself, without the intervention of crew present on said ship. Said cable can then be picked up by a tug at a safe distance.
- A command to set the installation according to the invention in operation can be given in various ways. For example, if the installation is equipped with a launching device which can be actuated by a receiver, use can be made of radio signals for this purpose. The installation is then set in operation from the tug.
- It is also conceivable to set the installation in operation automatically, by means of sensors on board the ship concerned itself.
- The floating body can be constructed in various ways. However, it is important that, even in heavy seas, said floating body must be able to travel in a specific line, in the direction away from the ship. The floating body is therefore constructed as an auxiliary vessel which also comprises steering means.
- In connection with the pick-up, the auxiliary vessel carries fixing means to which a hoisting cable from a tug can be attached.
- The floating body comprises an energy source which can supply power to the propelling means at least for a few hours. The installation can keep the auxiliary cable or tow rope in the run-out position for a prolonged period. This period must be at least so long that a tug has sufficient time to sail, for example from a harbour where it is lying ready, to the stricken ship and to pick up the run-out auxiliary cable or tow rope.
- The propelling means can comprise either a combustion engine or an electric motor, or a combination of the two.
- The invention also relates to a ship provided with the installation described above, the launching means being installed close to the bow or the stern of the ship and pointing obliquely downwards, such that, on launching, the auxiliary vessel can be moved directly towards the water surface taking with it the auxiliary cable or the rope, which rope is attached to the ship on which the launching means are provided. The launching means can be located somewhat wide of the outermost point of the bow or stern. It is also possible to install two sets of launching means, directed towards different sides of the ship, at the bow or stern.
- The invention also relates to the use of an auxiliary vessel, which can be launched to sea and has an auxiliary cable or tow rope attached thereto, on board a ship or freighter for running out the auxiliary cable or tow rope, and keeping said cable or rope in the run-out position for a prolonged period, such that another ship, such as a tug, can take the run-out auxiliary cable or tow rope on board in order to tow the first ship.
- A floating body which is provided with propelling means and can be launched from a platform erected in the sea is disclosed in "Ship & Boat International", Part 41, No. 1, January 1988, Worchester Park, pages 19-20, "Getting Clear". The purpose of the launched floating body is to pull a lifeboat lowered into the water from the platform away from the vicinity of said platform as quickly as possible. The energy source of the propelling means is exhausted after a few minutes. Within this period the lifeboat has been towed a sufficient distance away from the platform to enable it to sail further under its own power.
- This known installation is not suitable for running out a tow rope from a stricken ship, or for keeping the tow rope or auxiliary cable in the run-out position for a sufficiently long period such that a tug would be able to pick up the rope.
- The invention will be explained in more detail below with the aid of the illustrative embodiment shown in the figures.
- An installation according to the invention, which is indicated in its entirety by 2, is installed on board the ship 1, only part of which is shown in the figure. Said installation 2 comprises mounting means 3, which are constructed as a tubular housing in which an auxiliary vessel 4 is housed. Said auxiliary vessel 4 is secured with respect to the mounting means 3 in a known manner.
- Launching means, which are known per se, are also provided. Said launching means comprise the rails 5, which are shown diagrammatically and extend to either side of the auxiliary vessel 4 in the mounting means 3. It is also possible to provide a drive charge, by means of which the auxiliary vessel 4 can be shot out of the mounting means 3 over the rails 5.
- The auxiliary vessel 4 is connected to a cable 6, which is wound on a reel 7.
- If the ship gets into an emergency situation, the auxiliary vessel 4 can be shot out, pulling the cable 6 with it. When it is shot out, the auxiliary vessel makes a free fall, passing through the positions indicated by 8 and 9.
- The auxiliary vessel becomes submerged, comes up again and then floats on the surface of the water as shown at 10.
- In the meantime, the propeller installation of the auxiliary vessel 10, which installation is indicated diagrammatically by 11, has been set in operation, such that the auxiliary vessel sails away from the stricken ship 1, taking cable 6 with it.
- To ensure that the auxiliary vessel sails in the right direction, that is to say away from the ship 1, and also, in the event of the vessel foundering, away from the coast, steering means 12, which are known per se and are also indicated diagrammatically, are provided.
- The auxiliary vessel sails further and further away from the ship 1, until the entire cable 6 has been unwound from the reel 7. However, the propeller device 11 of the auxiliary vessel continues to operate, so that the cable 6 is continuously held in its position, pointing away from the ship 1.
- The auxiliary vessel is sufficiently large to carry a substantial energy source, so that such a position can be maintained over several hours. In the intervening period a tug is able to approach the auxiliary vessel 4 and pick it up by means of the fixing points 13.
- After the auxiliary vessel 4 has been taken on board a tug, the cable 6 can be pulled in by the tug and, where necessary, a rope located on board ship 1 can be pulled to the tug.
- A lightweight cable is preferably used for cable 6, such that the auxiliary vessel 4 is well capable of dragging said cable 6 along over a fairly long distance from the ship. Nevertheless, cable 6 can also be made sufficiently heavy to enable it to be used itself as tow cable.
- If cable 6 is a lightweight auxiliary cable, a heavier tow rope can also be wound on reel 7. In this case means can be provided on reel 7 which allow the auxiliary vessel 10 to unwind the relatively lightweight auxiliary cable 6 from the reel 7. Said means must then be constructed in such a way that they allow unwinding of the relatively heavy tow rope only if a traction force is exerted which is greater than the tensile force which can be exerted by the auxiliary vessel 4. A higher traction force of this type can easily be exerted by a tug, such that the tow rope is released by the reel 7 only under the influence of traction force exerted by the tug.
Claims (9)
- Combination comprising a ship or freighter such as an oil tanker or a container ship, and an installation (2) for running out a tow rope connected to said ship or freighter, which installation comprises a floating body (4), which is connected to the tow rope or an auxiliary cable (6) and is provided with propelling means, and launching means (5) fitted on board the ship for launching the floating body (4) from the ship, such that, after the floating body (4) has been launched, the rope or cable can be run out with respect to the ship by means of the tensile force delivered by the propelling means of the floating body (4),
characterized in that the floating body is an auxiliary vessel (4) which also comprises steering means, an engine for driving a propeller, as well as an energy source having a capacity suitable for supplying the engine for at least several hours. - Combination according to claim 1, wherein the auxiliary vessel (4) is provided with a combustion engine, as well as fuel containers having a capacity for supplying the combustion engine for at least a day.
- Combination according to Claim 1 or 2, wherein the rope or cable (6) can be unwound from a reel (7) on board the ship.
- Combination according to Claim 1, 2 or 3, wherein the floating body (4) is connected to one end of an auxiliary cable (6), which auxiliary cable (6) is connected at its other end to a tow rope.
- Combination according to Claim 1, 2, 3 or 4, wherein the auxiliary vessel (4) carries fixing means (13) to which a hoisting cable from a tug can be attached.
- Combination according to one of the preceding claims, wherein the launching means (5) are installed close to the bow or the stern of the ship and pointing obliquely downwards, such that, on launching, the auxiliary vessel (4) can be moved directly towards the water surface taking with it the auxiliary cable or the rope (6), which cable or rope (6) is attached to the ship on which the launching means (5) are provided.
- Combination according to Claim 6, wherein the rope or cable (6) is attached to the ship in the immediate vicinity of the location where the launching means (5) have been installed on board the ship.
- Combination according to Claim 6 or 7, wherein the cable (6) is a lightweight auxiliary cable which is connected to a tow rope located on board the vessel.
- Use of an auxiliary vessel on board a ship or freighter in the combination according to one of the preceding claims, comprising the steps of launching to sea said vessel together with an auxiliary cable or tow rope attached thereto, running out the auxiliary cable or tow rope, and keeping said cable or rope in the run-out position for at least several hours, such that another ship, such as a tug, can take the run-out auxiliary cable or tow rope on board in order to tow the first ship.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL9300217A NL9300217A (en) | 1993-02-03 | 1993-02-03 | Device for the distribution of a ship's cable and a vessel equipped with it. |
NL9300217 | 1993-02-03 |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0609953A1 EP0609953A1 (en) | 1994-08-10 |
EP0609953B1 true EP0609953B1 (en) | 1997-09-17 |
Family
ID=19862020
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19940200292 Expired - Lifetime EP0609953B1 (en) | 1993-02-03 | 1994-02-03 | Installation for running out a ship's cable and ship equipped therewith |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP0609953B1 (en) |
DE (1) | DE69405596D1 (en) |
NL (1) | NL9300217A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105416512A (en) * | 2015-12-16 | 2016-03-23 | 泰兴市依科攀船舶设备有限公司 | Emergency towing system for ship |
CN116495107B (en) * | 2023-05-22 | 2024-08-30 | 浙江海洋大学 | Marine aquaculture worker ship auxiliary ship |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3049235A1 (en) * | 1980-12-27 | 1982-07-29 | Hammer, Gero, 2330 Eckernförde | Ship mooring rope transfer unit - is controllable during transfer operation, is afterwards returned to ship |
FR2626546B1 (en) * | 1988-01-29 | 1990-06-29 | Garde Lebreton Maurice | ESTABLISHMENT OF SERVICE TRAILERS BY DRIVING BUOYS |
-
1993
- 1993-02-03 NL NL9300217A patent/NL9300217A/en not_active Application Discontinuation
-
1994
- 1994-02-03 EP EP19940200292 patent/EP0609953B1/en not_active Expired - Lifetime
- 1994-02-03 DE DE69405596T patent/DE69405596D1/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
DE69405596D1 (en) | 1997-10-23 |
EP0609953A1 (en) | 1994-08-10 |
NL9300217A (en) | 1994-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7350475B2 (en) | Launch and recovery system | |
US6178914B1 (en) | Method and an arrangement for launching and taking aboard a raft | |
US3525312A (en) | Storage or similar vessel | |
CN111727151B (en) | Life boat | |
WO2020058408A1 (en) | A marine structure comprising a launch and recovery system | |
EP0739290B1 (en) | A vessel for production and/or loading/unloading and transport of hydrocarbons from offshore fields, and/or for carrying out well operations | |
EP2497707B1 (en) | Marine craft deployment and recovery | |
US8757080B2 (en) | Marine craft depolyment and recovery | |
EP0609953B1 (en) | Installation for running out a ship's cable and ship equipped therewith | |
RU2201375C1 (en) | Ice-breaker (versions), method and system for single-support mooring and servicing of ships | |
WO2012041680A2 (en) | System and method for offshore rescue | |
US4711196A (en) | Marine survival system | |
GB2279045A (en) | Method and apparatus for recovery of survivors off-shore from ships lifeboats and the like | |
US7921793B2 (en) | Airborne tugboat for emergency aid for seagoing vessels | |
WO1995013958A1 (en) | Rescue system for mounting on a vessel | |
KR102552226B1 (en) | Ship assembly including seabed view electric boat car and electric seabed view tourism tugboat | |
RU2714014C1 (en) | Method of oil products unloading to unequipped shore from tankers | |
RU2809170C1 (en) | Method of supplying electrical cables, hoses, towing ropes and small cargo to the ship | |
RU2084372C1 (en) | System of sea facilities interacting in open sea | |
GB2199004A (en) | Marine survival system | |
RU2006420C1 (en) | Complex for delivery of liquid cargoes to beach | |
SU1245498A1 (en) | Arrangement for transferring cargo from ship to ship at open sea | |
NO20171607A1 (en) | Side pulling maneuverable tug | |
House | Ship Handling: Manoeuvring and Mooring Operations | |
RU2134211C1 (en) | Method of raising ship from bottom and transportation of raised ship |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): BE DE DK ES FR GB GR NL PT |
|
17P | Request for examination filed |
Effective date: 19950209 |
|
17Q | First examination report despatched |
Effective date: 19950927 |
|
GRAG | Despatch of communication of intention to grant |
Free format text: ORIGINAL CODE: EPIDOS AGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): BE DE DK ES FR GB GR NL PT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 19970917 Ref country code: FR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 19970917 Ref country code: ES Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19970917 Ref country code: DK Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19970917 |
|
REF | Corresponds to: |
Ref document number: 69405596 Country of ref document: DE Date of ref document: 19971023 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Effective date: 19971217 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 19971218 |
|
EN | Fr: translation not filed | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980228 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
BERE | Be: lapsed |
Owner name: VERHOEF ALUMINIUM SCHEEPSBOUW INDUSTRIE B.V. Effective date: 19980228 |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 19990823 Year of fee payment: 6 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20000801 Year of fee payment: 7 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20000901 |
|
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee |
Effective date: 20000901 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20010203 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20010203 |