EP0541813A1 - Excavatrice a scie a fil, paroi d'isolation ou ouvrage de protection anti-eboulement realise a l'aide de cet appareil et procede de realisation - Google Patents

Excavatrice a scie a fil, paroi d'isolation ou ouvrage de protection anti-eboulement realise a l'aide de cet appareil et procede de realisation Download PDF

Info

Publication number
EP0541813A1
EP0541813A1 EP92903729A EP92903729A EP0541813A1 EP 0541813 A1 EP0541813 A1 EP 0541813A1 EP 92903729 A EP92903729 A EP 92903729A EP 92903729 A EP92903729 A EP 92903729A EP 0541813 A1 EP0541813 A1 EP 0541813A1
Authority
EP
European Patent Office
Prior art keywords
wire saw
ditch
guide
sheet
water barrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP92903729A
Other languages
German (de)
English (en)
Other versions
EP0541813A4 (en
Inventor
Toshio Shimizu Construction Co. Ltd. Watanabe
Yuuji Shimizu Construction Co. Ltd. Ohnishi
Shinichi Shimizu Construction Co. Ltd. Nishimura
Yasuo Shimizu Construction Co. Ltd. Kajioka
Yoshihiro Shimizu Construction Co. Ltd. Mukawa
Hitoshi Shimizu Construction Co. Ltd. Satoh
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP15509091A external-priority patent/JPH04353116A/ja
Priority claimed from JP6543991U external-priority patent/JP2539242Y2/ja
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Publication of EP0541813A1 publication Critical patent/EP0541813A1/fr
Publication of EP0541813A4 publication Critical patent/EP0541813A4/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/13Foundation slots or slits; Implements for making these slots or slits
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D1/00Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
    • B28D1/02Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by sawing
    • B28D1/08Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by sawing with saw-blades of endless cutter-type, e.g. chain saws, i.e. saw chains, strap saws
    • B28D1/088Sawing in situ, e.g. stones from rocks, grooves in walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/08Dredgers; Soil-shifting machines mechanically-driven with digging elements on an endless chain
    • E02F3/10Dredgers; Soil-shifting machines mechanically-driven with digging elements on an endless chain with tools that only loosen the material, i.e. with cutter-type chains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches

Definitions

  • the present invention relates to a wire saw excavator for excavating the ground, to a wall forming a water barrier and a method of construction of the wall forming a water barrier using the wire saw excavator, and to a landslide protection wall and a method of constructing the landslide protection wall using the wire saw excavator.
  • a wall forming a water barrier is disposed between two guide holes 2 and 2 in a ditch 3, which extends from the surface of the ground to a point just above the bottom of the ditch, and is comprised of a self-hardening impervious body 4.
  • the self-hardening body 4 is a hardening mixture of bentonite slurry and the self-hardening slurry comprising sodium silicate and cement as a primary component, in the ground.
  • the ditch 3 is formed by a wire saw excavator 10.
  • the wire saw excavator 10 is comprised of a main body and a guide apparatus for controlling the direction of movement of the main body.
  • the main body is comprised of: the wire saw 11; and driving apparatus 12 for driving the wire saw 11.
  • the wire saw 11 preferably consists of a material which is compatible with the material of the present invention, such as the diamond wire saw which is used in mining and the like and is adapted to the conditions of the ground (G).
  • the driving apparatus 12 is the same as in the wire saw 11.
  • the guide apparatus of the wire saw excavator 10 is comprised of: two upper guide pulleys 13 provided at the guide hole 2 in close proximity to the driving apparatus 12; electric driving apparatuses 14 provided, respectively, at close proximity to the guide holes 2 and 2; a bottom guide pulley 15 provided, respectively, in the bottom of the guide hole 2 and 2; two endless cables 16 held tightly between the electric driving apparatus 14 and the bottom guide pulley 15; pulley boxes 17 and 17' provided at the one point of the endless cable 16; and H-section steel 18 for guiding two pulley boxes 17 and 17' disposed, respectively, in the guide hole 2.
  • the electric driving apparatus 14 and the bottom guide pulley 15 are disposed so as to be parallel to each other and perpendicular to the vertical axis of the wall.
  • the pulley box 17 has two moving pulleys 17 (a) and 17 (a); two supporting axis 17 (b) and 17 (b) for supporting the moving pulleys 17 (a) and 17 (a), respectively; and four rollers 17 (c).
  • the pulleys 17 (a) and 17 (a) are rotatable and are located at the supporting axis 17 (b) and 17 (b), respectively, so that one pulley is disposed above the other in the plane view.
  • the supporting axis 17 (b) and 17 (b) are rotatable and located on the inside of the pulley box 17, so that one supporting axis is provided at the upper portion of the pulley box 17, and the other supporting axis is provided at the lower portion the pulley box 17.
  • the rollers 17 (c) are provided at both sides of the pulley box 17 (in the front view) so that each roller is rotatable at both ends of the supporting axis 17 (b) and 17 (b).
  • the construction of the other pulley box 17' is the same as the construction of the pulley box 17 except for the disposed position of the pulley 17 (a') is as shown Fig. 2.
  • the H-section steel guide 18 has guide channels 19 and 19, each of which is respectively disposed at the facing flanges of the H-section steel 18 so as to face the opening portion of the guide channel 19.
  • Each guide channel 19 is formed by two angle steel portions and is fixed at the flange by one edge of each angle steel being welded to the flange, so as to face the other edge.
  • the endless cables 16 and 16 are provided at the pulley boxes 17 and 17', respectively, in order to connect thereto.
  • the wire saw 11 is run by the driving apparatus 12.
  • the driving apparatus 12 moves in the direction indicated by the arrow (A) in Fig. 2; and the endless cables 16 rotate in the direction indicated by the arrow (C), by means of the electric driving apparatus 14; then the pulley boxes 17 and 17' are lowered, and the ditch 3 is formed as the wire saw 11 excavates the ground (G).
  • the driving apparatus 1 moves in the direction indicated by arrow (B); the endless cables 16 are rotated in the direction indicated by arrow (D); then the pulley boxes 17 and 17' move upward.
  • the two guide holes 2 and 2 are provided at the position corresponding to the two sides of the wall forming a water barrier 1 in the ground (G), in order to excavate by a machine specified by the present invention, such as the earth auger, while pouring bentonite slurry via a pipe inserted into the ditch.
  • a machine specified by the present invention such as the earth auger
  • the H-section steel guides 18 and 18 are provided in the guide holes 2 and 2 respectively; the wire saw excavator 10 is placed in close proximity to the guide hole 2; the ditch 3 is excavated by the wire saw excavator 10 in the ground (G); the pulley boxes 17 and 17' are moved up.
  • the sediment that is excavated is then transferred to the guide holes 2 and 2 by running the wire saw 11; part of the bentonite slurry is drained by a sludge withdrawal pipe, a drain pipe and the like, and the self-hardening slurry 4. such as mortar, is poured into pipe 2 and 2, and the like, which is inserted into the ditch.
  • the driving apparatus 12 is removed, the wire saw 11 descends to the bottom of the ditch 3 while it is running, and the wire saw 11 thereafter is moved up. Thereby, the bentonite slurry and the self-hardening slurry 4 are stirred and mixed, and the mixture is deposited throughout the entire length of the ditch 3.
  • the wall forming a water barrier 1 is constructed.
  • the moving pulleys 17(a) and 17(a') of the pulley boxes 17 and 17' are arranged at different positions in plane view, the upper portion and lower portion of the wire saw 11 between the moving pulleys 17(a) and 17(a') are not disposed so that one pulley is positioned above the other pulley in the plane view. Accordingly, it is possible to excavate a ditch 3 with a thickness that is two times greater than the diameter of the wire saw 11, in a single excavation.
  • the self-hardening slurry 4 comprising sodium silicate and the cement as the primary component, and a mixture of bentonite slurry and polyethylene, or bentonite slurry and asphalt is adopted. Furthermore, the property of self-hardening slurry is adopted for the impervious materials.
  • the self-hardening slurry 4 is mixed with the bentonite slurry in the above embodiment. However, only self-hardening slurry is adopted as the construction material for the wall forming a water barrier 1.
  • the H-section steel 18 is removed in the above embodiment; however, it may also be buried in the ground without being removed.
  • the shape of the wall forming a water barrier 1 is the shape as in Fig. 1(A) and Fig. 2(B). However, it is possible for the wall forming a water barrier 1 to be disposed in a slanted position in the ground. As shown in Fig. 4, the wall forming a water barrier is of a curved shape in the vertical section view. In particular, it is possible that the strength of the steel comprising the wall forming a water barrier corresponds to the pressure of the earth from outside (from the left in Fig. 5) of the curve of the wall forming a water barrier 1''. This strength is larger than the above strength of the wall forming a water barrier 1.
  • the numbers 1' indicate a wall forming a water barrier.
  • the wire saw excavator (A) is, as shown in Fig. 6, comprising: two H-section steel guides 20 provided, respectively, in the guide holes 2 and 2 excavated in the ground (G); two pulley boxes 21 and 21 which can be moved up and down, disposed on the H-section steel guides 20 and 20, respectively; auxiliary apparatuses 22 for moving two pulley boxes 21 and 21 in the upward and downward direction; pulleys 33 provided at the upper portion of the H-section steel guides 20 and 20, respectively; a wire saw 26 for excavating a ditch 3 between the guide holes 2 and 2, and is held tightly at the pulleys 33; an electric motor 32 for driving the wire saw 26; and graspers 35 and 35 for pulling the sheet, forming a water barrier 39, into the ditch 3 as the pulley boxes 21 and 21 descend into the ditch 3, and for grasping a sheet that is a construction element of the wall forming a water barrier 39.
  • the H-section steel guides 20 are provided in guide holes 2 and 2, respectively, which are located at the positions corresponding to the ends of the ditch 3 in the ground (G), and which extend from the surface of the ground (G) to the portion of the ground (G) which is deeper than the bottom of the wall forming a water barrier 1.
  • the guide holes 2 and 2 are formed by excavating with an earth auger and the like.
  • Each pulley box 21 is a box which opens at the upper and lower surfaces thereof and form a curved shape similar to the letter "C", and has a moving pulley 21(a) therein. Each moving pulley 21(a) is rotatable. As shown in Fig. 7, a stopper 21(b) is provided on the inside of the pulley box 21. Each stopper 21(b) is in the shape of an inverted letter "L”.
  • the auxiliary apparatus 22 is comprised of the following: four tackles 23 disposed, respectively, at each H-section steel 20; cable 24 held tightly between each of the four tackles 23 of each H-section steel 20; and a carriage motor 25 for driving the cables.
  • Two of the four tackles 23 are rotatable at the base 32 and are located at the upper portions of each H-section steel 20. Another pair of tackles 23 are rotatable at the lower portions of each H-section steel 2. Each tackle is rotatable in the vertical plane.
  • Each cable 24 is connected, respectively, at the pulley box 21 so that the end thereof is fixed at the upper portion of each pulley box 21, and the other end thereof is fixed at the lower portion of each pulley box 21.
  • Each carriage motor 25 is fixed on each base 32, and is an electrically-driven motor.
  • One tackle 23 of the pair of tackles 23 and 23 disposed at the base 32 is located at the output axis of the carriage motor 25.
  • the carriage motor 25 can also be disposed at another position so that the cable 24 is consequently extended.
  • One pulley 33 is disposed at the upper portion of the H-section steel 20 which is located on the left side (H-section steel 20 on left side in Fig. 6).
  • Two pulleys 33 are disposed at the upper portion of the H-section steel 20 located on the right side (H-section steel 20 on the right side in Fig. 6) .
  • Each pulley 33 is rotatable in the vertical plane. However, each pulley 33 is disposed so that the wire saw 26 does not make contact with the cables 24. Consequently, each pulley 33 does not overlap with the moving pulley 21(a).
  • the wire saw 26 is similar to the wire saw in accordance with the first embodiment. However, in the second embodiment, the wire saw 26 is held tightly and extends from the electric motor 32 to the pulleys 33 disposed on the H-section steel 20 located on the right side (H-section steel 20 on the right side in Fig. 6), therefrom to the moving pulley 21(a) on the pulley box 21 located on the right side [moving pulley 21(a) on the right side in Fig. 6], therefrom to the moving pulley 21(a) in pulley box 21 on the left side thereof [moving pulley 21(a) on the left side in Fig.
  • the expansion apparatus 33 is comprised of a support frame 28, a plurality of hanging pulleys 30 which are rotatable on the support frame 28, and a carriage 31 which is horizontally movable (right and left side in Fig. 6) on the surface of the ground (G).
  • the support frame 28 has two support bodies 29 and 29.
  • One support body 29 is disposed on the surface of the ground (G), in close proximity to the H-section steel 20 located on the right side (support body 29 on the right side in Fig. 6).
  • the other support body 29 is attached to the left end portion of the carriage 31 (support body 29 on the left side of carriage 31 in Fig.6).
  • the wire saw 26 from the H-section steel 20 located on the left side is held tightly from below and above by the hanging pulley 30.
  • the electric motor 32 is fixed on the right end portion of carriage 31.
  • Each grasper 35 is, as shown in Fig.
  • the clamp 36 is preferably a wire and the like.
  • the length of the sheet forming a water barrier 39 is a little longer than the ditch 3, and both sides of the sheet are disposed in the guide holes 2 and 2. Furthermore, in the second embodiment, as shown in Fig. 7, both ends of the sheet forming a water barrier 39 are attached, respectively, to two Spanseal (trademark) boards forming a water barrier 40 and 40.
  • the Spanseal board forming a water barrier 40 is made of a material which is an elastomer combined with a water-absorbing polymer.
  • the water-absorbing polymer is obtained by adding a low ratio of bridge structures to a water-soluble molecule such as polyacrylic acid. Accordingly, the Spanseal board forming a water barrier 40, which is made of material which is swollen by water, is swollen by water in the ground G or by water from the concrete.
  • the wire saw excavator (A) has a soil discharge apparatus 41 for discharging soil from the guide hole 2.
  • the soil discharge apparatus 41 is comprised of a soil discharge pipe 42 and a pump 43.
  • the soil discharge pipe 42 has one end thereof in the guide hole 2, and the other end connected to the pump 43.
  • the pump 43 is preferably an apparatus, such as a suction pump or an air compression type vacuum pump and the like.
  • the protection frame 44 is inserted at the opening of the guide hole 2 as shown in Fig. 6.
  • the protection frame 44 is a short pipe body which is made from steel, has a flange at the end thereof and has an opening for pulling the wire saw 26 and the sheet forming a water barrier 39 in the guide holes 2 and 2.
  • the H-section steel 20 guides the movement of the pulley box 21 upwards and downwards.
  • the pulley box 21 guides the movement of the wire saw 26 upwards and downwards, and prevents the wire saw 26 from deviating off course in a sideways direction.
  • the stopper 21 (b) supports the cable 38 when the pulley box 21 descends, and therefore prevents the cutting of the cable 38 by the wire saw 26.
  • the auxiliary apparatus 22 drives the pulley box 21 upwards and downwards, independent of the operation of the wire saw 26.
  • the support body 29 on the right side can move towards or away from the support body 29 on the left side (in Fig. 6) by moving the carriage 31, and thereby making it possible for the extension apparatus 27 to control the length of the wire saw 26 from the expansion apparatus 27. That is, the length of the wire saw 26 is longer when the right support body 29 moves in the direction of the arrow (E) shown in Fig. 6. The length of the wire saw 26 is shorter when the right support body 29 moves in the direction of the arrow (F) shown in Fig. 6. Therefore, it is possible to adjust the length of the wire saw 26, so that it is proportional to the depth of the ditch, during excavation, via the upward and downward movement of the pulley boxes 21.
  • the wire saw 26 runs in the direction of the arrow (W) (Fig. 6) and, by the driving force of the electric motor 32, excavates the ground (G), and forms the ditch 3.
  • the clamp 36 grasps the lower portion of the sheet forming a water barrier 39.
  • the cable 24 passes through the ring 37 in order to support the ring 37. Accordingly, the grasper 35 goes down when the pulley box 21 goes down, thereby pulling the sheet forming a water barrier 39 into the ditch 3.
  • the soil discharge apparatus 41 discharges the excavated soil and the supplied bentonite slurry from the bottom of the guide hole 2 to the surface of the ground (G) via the opening of guide hole 2 .
  • the protection frame 44 prevents collapse of the side walls at the opening of the guide holes 2 and 2.
  • the two Spanseal boards forming a water barrier 40 are swollen by water in the mud slurry.
  • the guide holes 2 and 2 are formed by excavating at positions corresponding to both sides of the ditch 3, and are constructed by the same method described in the first embodiment.
  • the wire saw excavator (A) is disposed in the ground (G) because the H-section steel guides 20 and 20 are, respectively, disposed in the guide holes 2 and 2.
  • the pulley boxes 21 are disposed at the upper portion of the H-section steel guides 20 and 20.
  • the sheet forming a water barrier 39 is rolled, as shown in Fig. 8(A), and is rotatable between two H-section steel guides 20 so as to be above the ditch 3 to be excavated.
  • the lower portion of the sheet forming a water barrier 39 is grasped by the clamps 36 and 36 of the graspers 35 and 35.
  • the cable 38 is supported at the stopper 21 (b) (not shown in Fig. 8(A)).
  • the ground (G) is excavated and the sheet forming a water barrier 39 is pulled into the excavated ditch as the wire saw 26 and carriage motor 25 are driven, and thereby forming the ditch 3.
  • the mud and slurry are poured into the guide holes 2 and 2 to prevent jamming of the wire saw.
  • the soil discharge apparatus 41 is moveable so that the mud and slurry will not fill up with the mud slurry and in order to discharge excavated soil.
  • the wire saw 26 is cut and is pulled up after the excavation of the ground (G), and the sheet forming a water barrier 39 is pulled into the ditch.
  • the pulley boxes 21 and 21 are disposed at the upper portion of the H-section steel 20 by auxiliary apparatuses 22 and 22.
  • the sheet forming a water barrier 39 remains in the ditch 3 even after the ditch 3 is formed because the sheet 39 is not connected to the pulley boxes 21 and 21. Because the lower portion of the stopper 21(b) (not shown in Fig. 8(C)) is open, the cable 38 does not go to the same depth as the pulley boxes 21 and 21.
  • the wall forming a water barrier 1 is constructed by repeating the above process.
  • the concrete is poured into the guide holes 2 and 2 after the sheets forming a water barrier 39 and 39, which are adjacent to each other, are disposed in parallel in the ditches 3 and 3.
  • the wire saw excavator (A) constructed as described above has the same advantages as in the first embodiment.
  • the wire saw excavator (A) has the graspers 35 and 35, the sheet forming a water barrier 39 is pulled into the ground (G) while excavating.
  • the movement of the electric motor 32 is less than that of the wire saw excavator in accordance with the first embodiment.
  • the grasper 35 is a separate body from the pulley box 21, and moreover, does not grasp the sheet forming a water barrier 39, it is possible to pull up the pulley box 21 and the wire saw 26 from the guide hole 2 and the ditch 3 during excavation, leaving only the sheet forming a water barrier 39 inside the ditch 3.
  • auxiliary apparatus 22 makes the wire saw 26 go up and down independent of the electric motor 32, it is possible to excavate equally between the guide holes 2 and 2, and to easily pull the sheet forming a water barrier 39 in the ditch 3, while controlling the height of the pulley box 21.
  • the grasper 35 is constructed as above; however, this is not intended to limit the scope of the invention; other apparatuses capable of grasping and being disposed in the ditch 3, such as the apparatus shown in Fig. 9 may also be adopted.
  • the apparatus shown in Fig. 9 comprises a clamp 51 for the lower portion of the sheet forming a water barrier (not numbered in Fig. 9); a ring 52 with a cable which is passed through the ring 52 and connected to a pulley box; a ball 53 which is fixed at the cable 24 for stopping the ring 52; a string 54 having one end thereof connected to the clamp 51, and having the other end thereof connected to the rings 52; and protection ring 55 which the wire saw passes through (not numbered in Fig. 9).
  • the sheet forming a water barrier 39 is pulled into the ditch 3 while the wire saw 26 is excavating the ditch.
  • the sheet forming a water barrier 39 it is also possible for the sheet forming a water barrier 39 to be pulled into the ditch 3 after the ditch 3 is formed, by operating the wire saw 26.
  • Fig. 11 is a side view of a wire saw excavator in accordance with the third embodiment.
  • numeral 111 indicates a guide hole which is excavated in the ground (G).
  • At least two guide holes 111 and 111 are disposed in an excavation area (S) of a ditch at the appropriate distance.
  • the guide holes 111 and 111 are formed so as to have sufficient depth for excavating the ditch.
  • each guide column 112 is made of channel steel and is provided so as to direct the opening portion of one channel steel to the opening portion of the other channel steel.
  • rails 113 are provided for sliding carriages (a driving carriage 115 and a control carriage 130) as described hereinafter, so as to extend in the upward and downward direction of the guide column 112.
  • the clearance 113 (a) is formed between the rails 113 and 113, which have plural pin racks 114 and 114 at regular intervals.
  • the pin rack 114 comprises a pin rack system of a travel mechanism 116.
  • a moveable driving carriage 113 is disposed on the rail 113, which is disposed on the guide column 112 in the other guide hole 111, to move in the upward and downward direction.
  • the driving carriage 113 is comprised primarily of the above-described travel mechanism 116 for moving the driving carriage up and down, an excavating portion 117 and a casing 118 of the travel mechanism 116, and the excavating portion 117 as shown in Figs. 12 and 13.
  • the casing 118 is comprised of a sliding back plate 118 (a) disposed so that it can move up and down while grasping the rail 113 of the guide column 112; and the cover plate 118(b) which is attached to the back plate 118(a), disposed so that it can open and close, and protrudes towards the front so as to ensure an internal space between the cover plate 118(b) and the back plate 118(a) .
  • the internal space of the casing 118 is divided into the upper space 119(a) and the lower space 119(b) by a diaphragm 118(c).
  • the travel mechanism is retracted into the upper space 119(a), and the excavated portion 117, which has the function of excavating the ground (G), is retracted into the lower space 119(b).
  • a slit 118(d) is formed for passing the wire saw 127 through to the casing 118 corresponding to the lower space 119(b).
  • a pin rack system is adopted in the travel mechanism 116 in the upper space 119(a), as shown in Fig. 15, which can move up and down by means of meshing between a pin rack 114 and 114 and a pinion 120. More specifically, the pinion 120 is formed so as to have five teeth 120(a) disposed in a star-shaped arrangement, and the pinion 120 is disposed so as to mesh with the travel mechanism 116.
  • a slit 118 (e) is provided at the position of the back plate 118(a), which corresponds to the pinion 120, so as to mesh with the pin rack 114.
  • An oil compression cable 126 is connected to a drive mechanism (not shown in Fig. 13) for rotating the pinion 120.
  • the excavating portion 117 provided at the lower space 119(b) of the casing 118 comprises three pulleys (the first pulley 121, the second pulley 122, and the third pulley 123); the wire saw 127 is held tightly from the first pulley 121, the second pulley 122, and the third pulley 123; and an oil compression motor 128 is connected to the first pulley 121 for driving the first pulley 121.
  • the first pulley 121, the second pulley 122, and the third pulley 123 are rotatable in the same vertical plane.
  • the second pulley 122 is disposed so that it is obliquely rotatable above the first pulley 121, so as to create friction therebetween and the wire saw 127.
  • the third pulley 123 is disposed so that it is directly rotatable above the first pulley 121.
  • the wire saw 127 is pulled out from the slit 118(d) to the outside of the casing 118, which is held tightly from the fourth pulley 124 and the fifth pulley 125 which are provided at the excavating portion 117 of the control carriage 130. That is, the wire saw 127 is held tightly from the first pulley 121, the second pulley 122, the third pulley 123, the fourth pulley 124 and the fifth pulley 125.
  • the wire saw 127 thereby, as a whole, forms an endless wire.
  • a wire saw length controller 129 is provided on the inside of the casing 118, and the third pulley 123 is provided at thereat.
  • the wire saw length controller 129 makes it possible to provide any length wire saw 127 from the pulleys 121, 122, 123, 124, and 125 by moving the mechanism up and down according to the required length of the wire saw 127.
  • the control carriage 130 is disposed so that it is moveable along the rail 113 which is provided at the guide column 112 in the other guide hole 112.
  • the control carriage 130 comprises a travel mechanism 116' for moving the driving carriage up and down on an excavating portion 117', a casing (not indicated in Fig. 11) of the travel mechanism 116', and the excavating portion 117, as in the driving carriage 115 described above.
  • the description of the travel mechanism 116' and the excavating portion 117 are omitted because the construction of the travel mechanism 116' is identical to the construction of the driving carriage 115 already described.
  • the excavating portion 117' is provided at the casing, as shown in Fig. 16, which is comprised of the fourth pulley 124 and the fifth pulley 125 which are rotatable in the vertical plane, and the wire saw 127.
  • the fourth pulley 124 is provided at the upper portion of the control carriage 130, and the fifth pulley 125 is provided at the lower portion of the control carriage 130.
  • the fourth pulley 124 is disposed so that it can be moved up and down, and the upper portion thereof is rotatable and connected to a spring tensioner 131 which is provided between the casing (similar to casing 118) and the diaphragm (similar to diaphragm 118(c)) .
  • the spring tensioner 131 is provided in order to maintain the constant tension of the wire saw 127, and so that it is possible for the fourth pulley 124 to move up and down by extension thereof.
  • the spring tensioner 131 is shortened when the driving carriage 115 and the control carriage 130 are in the same horizontal plane.
  • the spring tensioner 131 is extended when the position of the driving carriage 115 is lower than the position of the control carriage 130.
  • the plural guide holes 111 and 111 are formed by excavating along the circumference of the area where the wall forming a water barrier in the ground (G) is to be constructed, in order to attain a predetermined distance therebetween and an appropriate depth.
  • the wire saw excavator 110 is pulled into the ground (G). Specifically, the driving carriage 115 in one of the adjacent two guide holes 111 and 111 and the control carriage 130 in the other guide hole 111 are moved down along each guide column 112. The movement of the driving carriage 115 and the control carriage 130, for moving down, are operated by travel mechanisms 116 and 116, respectively.
  • the pinion 120 of the travel mechanism 116 is rotated by the motor (not shown in Figs. 16 and 17); then the pinion teeth 120(a) of the pinion 120 meshes with the pin rack 114; and thereby, the driving carriage 115 and the control carriage 130 are driven up and down.
  • the wire saw 127 is driven as the first pulley 121 is rotated by means of the oil compression motor 128.
  • the ditch is formed by excavating between the guide holes 111 and 111 in accordance with the excavation of the ground (S), because the wire saw 127 is running while it is moved by the downward movement of the driving carriage 115 and the control carriage 130.
  • the driving carriage 115 and the control carriage 130 are moved up by the travel mechanisms 116 and 116 after the ditch is formed between the guide holes 111 and 111 in the ground (G), and when the driving carriage 115 and the control carriage 130 arrive at the bottom of the guide holes 111 and 111.
  • the excavated soil is transferred thereby.
  • the driving carriage 115 and the control carriage 130 are not in the same horizontal plane because the driving carriage 115 and the control carriage 130 are made to go up and down independent of each other. If the driving carriage 115 and the control carriage 130 are not in the same horizontal plane, the tensioner 131 is extended and the vertical position is controlled by the driving carriage 115 and the control carriage 130. Therefore, it is possible for the driving carriage 115 and the control carriage 130 to be moved up and down.
  • the sheet 132 is pulled into the ditch, which is formed as described above, and thereby a sheet forming a water barrier 132 is constructed.
  • the method of pulling the sheet forming a water barrier 132 in the ditch, as shown in Fig. 20, is as follows. Both sides in the lower portion of the sheet forming a water barrier 132 are connected to each upper portion of the driving carriage 115 and the control carriage 130 by cable 133 and the like, respectively, and in this condition, the driving carriage 115 and the control carriage 130 are moved downward into the ditch.
  • a construction which is detachable therebetween in the ditch.
  • the components of this construction comprises: a vertical hole provided at the upper surface of the driving carriage 115 and the control carriage 130, respectively; a rope connected, respectively at both sides of the lower portion of the sheet forming a water barrier 132, with each end of the rope being ring-shaped; two pins which can be inserted and fixed in the hole and can be pulled, with the head of each pin being larger than the diameter of the ring formed by the rope so that it can suspend the ring.
  • the pin is first inserted into the hole, through the ring formed by the rope, before excavation.
  • the pin is then pulled out after the sheet forming a water barrier 132 arrives nearly to the bottom of the ditch.
  • Each pin is pulled from the hole and ring by a manually-operated pulley rope.
  • the sheet forming a water barrier 132 is thereby detached from the driving carriage 115 and the control carriage 130. Thereafter, only the driving carriage 115 and the control carriage 130 are moved up in the guide holes 111 and 111, and are retrieved thereby.
  • the wire saw excavator comprises, in general, the driving carriage 115 and the control carriage 130 which are moveable in the upward and downward direction along the guide columns 112 and 112 disposed in two adjacent guide holes 111 and 111; and the wire saw 127 which is held tightly between the driving carriage 115 and the control carriage 130; it is possible for the ground (G) to be excavated by the wire saw 127, and the ditch to be formed, as the driving carriage 115 and the control carriage 130 are moved downward along the guide columns 112 and 112.
  • the excavating portions 117 and 117' are provided at the driving carriage 115 and the control carriage, 130 respectively, and since the wire saw 127 is held tightly therebetween, the excavating portions 117 and 117' move up and down as the driving carriage 115 and the control carriage 130 move up and down along with the upward or downward movement of the wire saw 127. Accordingly, this part of the wire saw 127 is shorter than the wire saw 127 exhibited in the prior art. Therefore, it is not necessary to further extend the wire saw 127, and, consequently, the ditch is formed by the wire saw 127 of a relatively short and constant length. Therefore, it is possible for the wire saw excavator 110 to be smaller than in the prior art, and the performance of the wire saw excavator 110 to be improved. Therefore, the use of a wire saw excavator 110 is preferable in the case of excavating a ditch of great depth and construction of a wall forming a water barrier for such a ditch.
  • the travel mechanisms 116 and 116 are provided at the driving carriage 115 and the control carriage 130, it is possible to make the driving carriage 115 and the control carriage 130 move up and down. Furthermore, the tensioner 131, as a tension control apparatus, is provided at the travel portion 116 of the control carriage 130 and therefore the tension of the wire saw 127 is kept constant in spite of the horizontal position of the driving carriage 115 and the control carriage 130. It is therefore possible for the wire saw 127 to excavate the ground (G) under the best conditions.
  • the wire saw excavator 110 is not limited to the third embodiment. Accordingly, it is possible to modify specific parts thereof, such as the driving carriage 115, the control carriage 130, the travel mechanism 116, the excavating portion 117, and the wire saw 127.
  • the other mechanism of the tensioner 131 indicated in the third embodiment can be adopted as the mechanism for controlling the tension of the wire saw 127.
  • a running pulley 134' is disposed so that it is able to move up and down at the center of the line between the fourth pulley 124' and the fifth pulley 125';
  • a fixed but rotatable pulley 135' is disposed above the running pulley 134' and at the side of driving carriage 115.
  • a wire saw 127' is held tightly from the first pulley 121, the second pulley 122, the third pulley 123, the fourth pulley 124', the running pulley 134', the fixed pulley 135', the fifth pulley 125', and the first pulley 121.
  • the construction of the travel mechanism 116 and 116' provided on the driving carriage 115 and the control carriage 130 is not limited to a pin rack system as in the above third embodiment and other systems (for example, hoist gear mechanism) may be adopted.
  • the numbers and positions of the pulleys 121 through 125 provided at the excavating portion 117 and 117' are not limited to the above third embodiment, the construction is able to tightly hold and maintain the constant tension of the wire saw 126, which is adopted.
  • numeral 201 is a sheet forming a water barrier wall in accordance with the landslide protection wall.
  • the wall forming a water barrier 201 is comprised of guide holes 203 in the ground (G) which are disposed at a specified distance; a first soldier beam 202(a) and a second soldier beam 202(b) alternately disposed in the guide holes 203; a ditch 204 provided between the guide holes 203; a sheet forming a water barrier 205 disposed in the ditch 204; and a horizontal sheathing 206 provided at the first soldier beam 202(a) and the second soldier beam 202(b).
  • the first soldier beam 202(a) is made of H-section steel.
  • the lower portion of the second soldier beam 202(b) is H-section steel, tapering at the lower portion thereof.
  • the first soldier beam 202(a) is provided at the guide hole 203 so that a flange 202(c) thereof faces the excavated surface (Ga) of the ground(G).
  • the second soldier beam 202(b) is provided at the guide hole 203 so that a flange 202(c) of the tapered side faces the excavated surface (Ga) of the ground (G), the tapered side is provided so that it slants in proportion to the movement from one flange to the other flange on one edge.
  • each guide material 202(d) is C-shaped in transverse sectional view, and the open portion thereof faces outward because the portion corresponding to the middle portion of the C is fixed.
  • the guide material 202(d) is the same length as the soldier beam 202(a).
  • the portion of each guide material 202(d) corresponding to the open part of the C forms a guide channel 202(e) which passes through the longitudinal plane of the guide material 202(d).
  • the guide hole 203 is formed by excavating vertically for a specified distance in the horizontal plane, and has the shape of a circle in the transverse sectional view shown in Fig. 23.
  • the guide hole is then excavated along the longitudinal direction so that the capacity thereof is reduced by half when the construction is completed.
  • the ditch 204 is formed so that the width thereof is larger than the width of the sheet forming a water barrier 205, which is provided at the excavating surface (Ga) of the ground (G).
  • the guide hole 203 and the ditch 204 are then filled with the bentonite mortar 208.
  • the sheet forming a water barrier 205 is made from synthetic resin and the like, which has the flexibility and ability to prevent water seepage.
  • Connecting portions 207 which are connected to the guide channel 202(e), are provided at both sides thereof so that the sheet forming a water barrier 205 is tautly disposed in the ditch 204.
  • Each connecting portion 207 is formed so that both sides thereof are of greater thickness than any other part thereof, and in which a steel coil 207(a) is provided.
  • the sheet forming a water barrier 205 is held tightly between the guide holes 203 and 203 because both sides thereof are fixed by the hardened bentonite mortar in the guide holes 203 and 203.
  • the method of construction of the landslide protection wall is constructed as described above.
  • the guide holes 203 and 203 are first formed by a boring machine and the like.
  • a wire saw apparatus 209 and a sheet providing apparatus 210 are set in this space, and the guide pile 211 is disposed in the guide holes 211 and 211.
  • the wire saw apparatus 209 and the sheet providing apparatus 210 are disposed in close proximity to the guide holes 211 and 211.
  • guide piles 211 and 211 are provided in each guide hole 203.
  • the ditch 204 is formed between the guide holes 211 and 211, and the sheet forming a water barrier 205 is pulled therein by the sheet providing apparatus 210.
  • the guide hole 211 has thin steel members 211(a) and 211(a) which are respectively fixed on the side, running along the longitudinal axis of the flange, and are disposed face to face.
  • a guide portion 211(b) is disposed between the thin steel members members 211(a) and 211(a), wherein the guide portion 211(b) is provided.
  • the wire saw apparatus 209 comprises: guide holes 203 and 203 disposed in the ground; guide piles 211 and 211 disposed in the guide holes 203 and 203; travel carriages 209(a) and 209(a) attached to the guide piles 211 and 211 which are disposed in the adjacent two guide piles 211 and 211, respectively; a drive mortar 209(b) disposed on the ground; the first winches 209(c) and 209(c) disposed at the upper portion of the guide piles 211 and 211, and thereby the wire saw 209(d) is an endless saw.
  • the travel carriage 209(a) is shaped like a bucket with openings 209(g) at the surfaces facing each other and disposed at the guide portions 211(b) and 211(b).
  • the second winch 209(e) is rotatable and provided in each travel portion 209(a).
  • a wire saw hole 209 (f) is disposed at the upper portion of each travel carriage 209(a) so that it can pass in the vertical direction of the travel carriage 209(a).
  • the travel carriage 209(a) can go up and down because it is connected to the travel belt 209(h) which passes through the guide portion 211(b).
  • the travel belt 209(h) is rolled by the travel winch 209(g) which is held tightly between the upper and lower portions of the guide pile 211.
  • the upper portion and the lower portion of the sheet forming a water barrier 205 are connected to each other by a pulling wire 209(i) so that the sheet forming a water barrier 205, is thereby pulled into the ditch 204 as the travel carriage 209(a) moves downward.
  • the drive motor 209(b) supports the wire saw 209(d) at the end of an output axis 209(j) and therefore the wire saw 209(d) moves because the output axis rotates.
  • the first winch 209(c) is disposed so that an axis thereof is approximately horizontal.
  • the wire saw 209(d) is held tightly, in turn, by the first drive motor 209(b), one first winch 209(c) (the right side winch in Fig. 26), one second winch 209(e) (the right side winch in Fig. 26), another second winch 209(e) (the left side winch in Fig. 26), and another first winch 209(c) (the right side winch in Fig. 26).
  • the wire saw 209(d) is held tightly between the second winches 209(c) and 209(c) in a horizontal position, and the ground (G) therebetween is excavated.
  • the sheet providing apparatus 210 rolls the sheet forming a water barrier 205 around a rolling rod 210(a) and supports the sheet forming a water barrier 205. The sheet forming a water barrier 205 is then pulled into the ditch 204 as the rolling rod 210(a) rotates in reverse.
  • the ditch 204 is formed because the ground (G) is excavated between the guide holes 203 and 203 by the wire saw 209(d) which is driven simultaneously.
  • the sheet forming a water barrier 205 is pulled because the travel carriages 209(a) and 209(a) are moved downward to a specified depth by the travel winch 209(g) and 209(g).
  • the ditch 204 is thereby formed, and simultaneously, the sheet forming a water barrier 205 is pulled therein.
  • the ditch 204 is formed and the sheet is pulled therein between the guide holes 203 and 203 as described above.
  • One guide portion 211(b) and the other guide portion 211(b) of one guide pile 211 can, respectively, guide one side of one sheet forming a water barrier 205 and one side of the adjacent sheet forming a water barrier 205.
  • the sheet forming a water barrier 205 is pulled into the ditch 204 so that both sides (i.e. the vertical parts) thereof are in the guide holes 203 and 203.
  • the sheet forming a water barrier 205 pulled into the ditch 205 is cut from the sheet providing apparatus 210, as shown in Fig. 27, two suspension wires 207(b) and 207(b) are disposed, respectively, at both sides of the upper portion of the sheet forming a water barrier 205, and the sheet forming a water barrier 205 is supported by two suspension bars each of which is passed, respectively, through the suspension wires 207(b) and 207(b).
  • the guide pile 211 is pulled out of the guide hole 203.
  • the bentonite mortar 208 is placed between the excavating surface (Ga) and the outer surface of the flange of the guide pile 211 in the guide hole 203, and between the excavating surface (Ga) and the sheet 205.
  • the first soldier beams 202(a) are disposed in every other guide hole 203 before the bentonite mortar 208 hardens.
  • the sheet forming a water barrier 205 is pulled into the ditch 4 so that each connecting portion 207 is inserted into the guide channel 202(e) from the upper portion thereof. Thereby, each connecting portion 207 is connected to each guide material 202(d).
  • the bentonite mortar 208 is poured into the guide holes 203 which are between the first soldier beams 202(a) and 202(a).
  • the second soldier beams 202(b) are provided in the guide holes 203 where the first soldier beams 202(a) are not disposed.
  • the second soldier beams 202(b) are disposed between the sheet forming a water barrier 205 and the excavating surface (Ga) so that the slant thereof faces the excavating surface, and so that the flange thereof contacts the sheet forming a water barrier 205.
  • the ground (Gb) between the guide holes 203 and 203 is excavated.
  • the horizontal sheathings 206 are provided between the web of the first soldier beams 202(a) and the web of the second soldier beams 202(b), so as to form a wall-like structure.
  • the bentonite mortar 208 is placed between the sheet forming a water barrier 205 and the horizontal sheathing 206, so that the wall forming a water barrier 201, which has the ability to prevent water seepage, is constructed. Thereby, a landslide protection wall which has a higher ability to prevent water seepage, is constructed.
  • the landslide protection wall constructed as described above and because the bentonite mortar 208 is placed between the excavating surface (Ga) and the outer surface of the flange of the guide pile 211 and the guide hole 203, and between the excavating surface (Ga) and the sheet 205, it is therefore possible to improve the ability of the landslide protection wall to prevent water seepage, in comparison with the landslide protection wall constructed in accordance with the prior art. Since it is easy to adopt the sheet forming a water barrier 205 as the landslide protection wall using the horizontal sheathing 206, it is possible to execute the placement thereof in close proximity to a building that is adjacent to the excavation site. Therefore, the flexibility of the landslide protection wall is improved.
  • the efficiency of excavation is improved. Since the sheet forming a water barrier 205 is pulled into the ditch 204 easily and accurately, the precision of the execution is also improved.
  • a landslide protection wall and construction method thereof in accordance with the fifth embodiment will be described in detail with reference to Fig. 29.
  • the construction of the landslide protection wall is similar to the construction of the landslide protection wall constructed in accordance with the fourth embodiment, except that the position of the guide material 202(e) differs. Construction materials which are identical to those used in the fourth embodiment are numbered with the same numerals used in the description of the fourth embodiment.
  • each guide material 202(d) and 202(d) are fixed at the web 202(f) of each first soldier beam 202(a). Specifically, each guide material 202(d) is welded at approximately the center of the web 202(f), as shown in the transverse sectional view, so that the open portion thereof faces outward.
  • the sheet forming a water barrier 205 is provided in the ditch 204 on condition that the connecting portion 207 thereof is provided at the center of both surfaces of the web 202(f), as shown in the transverse sectional view, and the second soldier beam 202(b) is provided in the guide hole 203 between the first soldier beams 202(a) and 202(a), so that the part of the sheet forming a water barrier 205 is bowed with respect to the excavated surface (Ga).
  • the sheet forming a water barrier 205 is thereby held tightly in the ditch 204.
  • the sheet forming a water barrier 205 is held tightly in the ditch 204 and the slackening thereof is slight, and because the bentonite completely fills in the guide holes 203 and the ditch 204, there is no void area in the ditch 204. Therefore, the quality of the wall forming a water barrier 201 is improved.
  • the sheet forming a water barrier 205 is held tightly in the ditch 204 without slackening, the bentonite is poured smoothly into the ditch 204. Therefore, the efficiency of construction is improved.
  • a landslide protection wall and construction method thereof in accordance with the sixth embodiment will be described in detail with reference to Fig. 30.
  • the construction of the landslide protection wall is similar to the construction of the landslide protection wall constructed in the fourth embodiment except that the positioning of the guide material 202(e) differs. Construction materials which are identical to those used in accordance to the fourth embodiment are numbered with the same numerals used in the description of the fourth embodiment.
  • two guide materials 202(d) and 202(d) are fixed at the corner between the flange 202(c) on the side of the excavating surface (Ga) and the web 202(f) of each first soldier beam 202(a).
  • each guide material 202(d) is disposed at the flange 202(c) on the side of the excavating surface (Ga)
  • the distance between the sheet forming a water barrier 205 and the excavating surface (Ga) is shorter as compared with the distance according to the fifth embodiment. Accordingly, the quantity of the bentonite mortar between the excavating surface (Ga) and the sheet forming a water barrier 205 is smaller. Therefore, the stress in the sheet forming a water barrier 205 is smaller.
  • the construction of the landslide protection wall is similar to the construction of the landslide protection wall constructed in accordance with the fourth embodiment except that the position of the guide material 202(e) differs.
  • the construction materials which are identical to those in the fourth embodiment are numbered with the same numerals used in the description of the fourth embodiment.
  • two guide materials 202(d) and 202(d) are fixed on the two sides, located on the inside of the flange 202(c) of each first soldier beam 202(a). which face the side of the excavating surface (Ga).
  • the width of the sheet forming a water barrier 205 is smaller.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

On effectue dans le sol des forages (3) puis on excave un secteur entre deux forages adjacents (3) à l'aide d'un appareil à scie à fil (9), de manière à réaliser une tranchée (4) par laquelle on introduit un élément d'isolation (5). Un mortier de bentonite est coulé dans les forages (3) et dans la tranchée (4), de manière à réaliser par étanchéité une paroi d'isolation (1). Le sol (T) est excavé à l'aide d'un appareil à scie à fil (9) et d'un appareil de mise en place des éléments d'isolation (10) afin d'obtenir la tranchée (4), tandis que chaque élément d'isolation (5) est tiré dans la tranchée (4). On obtient ainsi une meilleure efficacité pour la réalisation d'une paroi d'isolation (1) et, par ailleurs, l'insertion de l'élément d'isolation (5) dans la tranchée s'effectue facilement et avec précision, améliorant ainsi la précision dans la réalisation de l'ouvrage.
EP19920903729 1991-05-31 1992-01-24 Wire saw excavator, cut-off wall or landslide protection construction constructed thereby and construction method thereof Withdrawn EP0541813A4 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
JP155090/91 1991-05-31
JP15509091A JPH04353116A (ja) 1991-05-31 1991-05-31 山留め構造及びその施工方法
JP65439/91U 1991-07-24
JP6543991U JP2539242Y2 (ja) 1991-07-24 1991-07-24 ワイヤソー掘削機

Publications (2)

Publication Number Publication Date
EP0541813A1 true EP0541813A1 (fr) 1993-05-19
EP0541813A4 EP0541813A4 (en) 1993-11-18

Family

ID=26406581

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19920903729 Withdrawn EP0541813A4 (en) 1991-05-31 1992-01-24 Wire saw excavator, cut-off wall or landslide protection construction constructed thereby and construction method thereof

Country Status (2)

Country Link
EP (1) EP0541813A4 (fr)
WO (1) WO1992021826A1 (fr)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168443A (zh) * 2010-11-15 2011-08-31 张永忠 双曲臂冲击成槽机
JP2014062364A (ja) * 2012-09-20 2014-04-10 Jtec Corp 地山防護プレートの滑材注出機構
EP2783823A1 (fr) * 2013-03-26 2014-10-01 Diamant Wire Teknikk AS Scie à fil améliorée destinée à conduire un fil de diamant sans fin
WO2022271034A1 (fr) * 2021-06-22 2022-12-29 Diamant Wire Teknikk As Installation de pisciculture basée sur terre

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736766B (zh) * 2009-12-03 2012-06-27 张永忠 液压锯槽机
CN111926862B (zh) * 2020-07-30 2021-05-14 济南城建集团有限公司 一种地下水引流生态保护系统及施工方法
CN114112854B (zh) * 2021-12-02 2024-08-23 安徽宏祥工程项目管理有限公司 一种建筑监理用建筑外墙渗水测试装置

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093090A (en) * 1981-01-29 1982-08-25 Nishimatsu Constr Co Ltd Method and apparatus for making a deep trench
DE3704885A1 (de) * 1987-02-17 1988-08-25 Schuetzeichel Wiedtal Geraete Verfahren und einrichtung zum herstellen von schlitzen im erdboden, insbesondere von entspannungsschlitzen im bodengestein usw.
DE3823784A1 (de) * 1988-07-14 1990-01-25 Hochtief Ag Hoch Tiefbauten Verfahren, abdichtungselemente und vorrichtung zur herstellung einer abdichtungsschlitzwand

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02171412A (ja) * 1988-12-23 1990-07-03 Toda Constr Co Ltd 遮水壁の構築工法
JPH02171423A (ja) * 1988-12-23 1990-07-03 Toda Constr Co Ltd 遮水壁用掘削溝の切削機
JPH02171415A (ja) * 1988-12-26 1990-07-03 Toda Constr Co Ltd 遮水壁の構築工法
JPH0621453B2 (ja) * 1988-12-29 1994-03-23 株式会社奥村組 連続地下壁の築造法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093090A (en) * 1981-01-29 1982-08-25 Nishimatsu Constr Co Ltd Method and apparatus for making a deep trench
DE3704885A1 (de) * 1987-02-17 1988-08-25 Schuetzeichel Wiedtal Geraete Verfahren und einrichtung zum herstellen von schlitzen im erdboden, insbesondere von entspannungsschlitzen im bodengestein usw.
DE3823784A1 (de) * 1988-07-14 1990-01-25 Hochtief Ag Hoch Tiefbauten Verfahren, abdichtungselemente und vorrichtung zur herstellung einer abdichtungsschlitzwand

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO9221826A1 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168443A (zh) * 2010-11-15 2011-08-31 张永忠 双曲臂冲击成槽机
JP2014062364A (ja) * 2012-09-20 2014-04-10 Jtec Corp 地山防護プレートの滑材注出機構
EP2783823A1 (fr) * 2013-03-26 2014-10-01 Diamant Wire Teknikk AS Scie à fil améliorée destinée à conduire un fil de diamant sans fin
WO2022271034A1 (fr) * 2021-06-22 2022-12-29 Diamant Wire Teknikk As Installation de pisciculture basée sur terre

Also Published As

Publication number Publication date
WO1992021826A1 (fr) 1992-12-10
EP0541813A4 (en) 1993-11-18

Similar Documents

Publication Publication Date Title
EP0810327B1 (fr) Procede et dispositif de construction de murs continus souterrains
US11560686B2 (en) Membrane-lined wall
CN105951711A (zh) 海边电站地下连续墙围护施工方法
CN107059877A (zh) 一种施工时底部带有链刀的基础及其施工法
CN112160324A (zh) 一种深基坑支护的施工方法
CN111455977A (zh) 一种地下连续墙施工方法
CN111734309A (zh) 用于smw工法桩施工的导向装置、smw工法桩施工设备及方法
CN109989392B (zh) 砂土地下连续墙施工成槽工艺
EP0541813A1 (fr) Excavatrice a scie a fil, paroi d'isolation ou ouvrage de protection anti-eboulement realise a l'aide de cet appareil et procede de realisation
JP6043006B1 (ja) 地中構造物の構築方法
EP0659943A1 (fr) Dispositif et procédé pour le creusement de tranchées
CN115478543B (zh) 一种人工挖孔桩基坑支护结构及施工方法
CN111851562A (zh) 一种移动式钻孔灌注桩施工平台及方法
CN111287194A (zh) 利用倾斜钢板桩的可回收基坑支护结构及其支护方法
CN212479071U (zh) 用于smw工法桩施工的导向装置以及smw工法桩施工设备
CN115584722A (zh) 一种富水含填石层软土区咬合桩施工方法
CN114232602A (zh) 地下连续桩施工工艺
JP2726621B2 (ja) ケーソンの沈設方法およびケーソン刃口構造
CN107012792A (zh) 一种桥梁下部结构的施工方法
CN111042049A (zh) 一种雨水管施工工艺
JP2879116B2 (ja) 止水壁の施工方法及び施工装置
CN113585237B (zh) 地连墙接头及地连墙施工方法
CN218969976U (zh) 一种适用于顶推法施工连续墙的顶推结构
CN115492161B (zh) 一种既有建筑地下室增层三面围合管幕施工方法
CN114875925B (zh) 一种填海地层临近地铁隧道的超大深基坑施工方法

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19930128

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): DE FR

A4 Supplementary search report drawn up and despatched

Effective date: 19931001

AK Designated contracting states

Kind code of ref document: A4

Designated state(s): DE FR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN WITHDRAWN

18W Application withdrawn

Withdrawal date: 19940708

R18W Application withdrawn (corrected)

Effective date: 19940708