EP0461743B2 - Hot roughing mill installation - Google Patents

Hot roughing mill installation Download PDF

Info

Publication number
EP0461743B2
EP0461743B2 EP19910301592 EP91301592A EP0461743B2 EP 0461743 B2 EP0461743 B2 EP 0461743B2 EP 19910301592 EP19910301592 EP 19910301592 EP 91301592 A EP91301592 A EP 91301592A EP 0461743 B2 EP0461743 B2 EP 0461743B2
Authority
EP
European Patent Office
Prior art keywords
roughing mill
installation
slab
mill
roughing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP19910301592
Other languages
German (de)
French (fr)
Other versions
EP0461743A2 (en
EP0461743B1 (en
EP0461743A3 (en
Inventor
Nobuhiro Tazoe
Seizo Baba
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=15535999&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP0461743(B2) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by IHI Corp filed Critical IHI Corp
Publication of EP0461743A2 publication Critical patent/EP0461743A2/en
Publication of EP0461743A3 publication Critical patent/EP0461743A3/en
Publication of EP0461743B1 publication Critical patent/EP0461743B1/en
Application granted granted Critical
Publication of EP0461743B2 publication Critical patent/EP0461743B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/22Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling plates, strips, bands or sheets of indefinite length
    • B21B1/30Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling plates, strips, bands or sheets of indefinite length in a non-continuous process
    • B21B1/32Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling plates, strips, bands or sheets of indefinite length in a non-continuous process in reversing single stand mills, e.g. with intermediate storage reels for accumulating work
    • B21B1/34Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling plates, strips, bands or sheets of indefinite length in a non-continuous process in reversing single stand mills, e.g. with intermediate storage reels for accumulating work by hot-rolling
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/02Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling heavy work, e.g. ingots, slabs, blooms, or billets, in which the cross-sectional form is unimportant ; Rolling combined with forging or pressing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/02Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling heavy work, e.g. ingots, slabs, blooms, or billets, in which the cross-sectional form is unimportant ; Rolling combined with forging or pressing
    • B21B1/024Forging or pressing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B15/00Arrangements for performing additional metal-working operations specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills
    • B21B2015/0057Coiling the rolled product

Definitions

  • the present invention relates to a hot roughing mill installation.
  • Known hot roughing mill installations are described for example in the JP-A-53-26759 or the JP-B-61-3561.
  • the former is directed to a large-scale production facility according to the pre-characterising part of Claim 1 having a sizing press for achieving higher production efficiency and the latter to a medium-scale production facility having a coil box, i.e. a coiling device, for winding up the roughed metal strip to reduce the length of the roughing mill line.
  • a coil box i.e. a coiling device
  • the installation described in the former publication has a very long roughing mill line, whilst the latter installation does not achieve good production efficiency.
  • the object of the present invention is therefore, amongst other things, to provide an installation with a short roughing mill line and which operates at a high production efficiency.
  • a hot roughing mill installation which, in use, receives from a furnace a slab of hot metal which passes through the installation in a working direction, comprises a first roughing mill and a sizing press upstream of the roughing mill and is characterised in that the first roughing mill is a reversing roughing mill, that a coil box is provided downstream of the roughing mill which, in use, receives and coils a metal strip from the roughing mill, that edgers are provided upstream and downstream of the first roughing mill, which edgers, in use, form a thickened portion on each side of the slab and that a two-high rolling mill is located between the sizing press and the roughing mill.
  • the sizing press drafts the slab to a desired width before it passes through the roughing mill.
  • the thickened portion or "dog bone” on each side of the slab ensures that portions of reduced thickness, or "edge drops” are not created during roughing in the roughing mill.
  • the two-high rolling mill is included in the installation in order to flatten the thickened portions produced by the sizing press or edgers, should these portions be too pronounced.
  • a second reversing roughing mill may be included in the installation, downstream of the first.
  • further edgers may be incorporated immediately upstream and/or immediately downstream of the second roughing mill.
  • the drawing shows a first embodiment of the present invention in which reference numeral 1 represents a furnace for heating a slab S; and 2, a sizing press for drafting, or reducing the width of, the slab S when it has been taken out from the furnace 1.
  • Numeral 3 represents edgers upstream and downstream of the roughing mill 4 for forming a "dog bone", or thickened portion, on each side of the slab S. Because edgers are situated upstream and downstream of the roughing mill, the sides of the metal strip P can be drafted by the edger 3 immediately prior to entering the roughing mill 4, regardless of the actual direction of travel of the strip P at that time.
  • a two-high rolling mill 6 is arranged between the sizing press 2 and the upstream edger 3 so that, even if the thickened portions generated on each side of the slab S or metal strip P when it is drafted by the sizing press 2 or by the edger 3 are too big, they can be crushed by the two-high rolling mill 6.
  • Downstream of the roughing mill 4 is a coiling device, 5, specifically a coil box for winding up the roughed strip P.
  • the two-high rolling mill 6, sizing press 2, upstream edger 3, roughing mill 4, downstream edger 3 and coil box 5 are arranged on the exit side of the furnace 1 in that order in the direction D of travel of the slab.
  • the direction D is the working direction in which the slab moves; that is to say it is the direction in which the slab progresses through the installation, although it may in fact also have a reciprocating motion, and the direction of travel at any instant may not be the same as the working direction D.
  • a mill (not shown) for finishing the metal strip P is arranged downstream of the coil box 5 with respect to the direction of travel D.
  • the slab S is heated in the furnace 1 to a predetermined temperature and is then taken out of the furnace 1 and drafted to a predetermined width in the sizing press 2. Then, the slab S is reverse rolled several times in the reversing roughing mill 4 and is thereby formed into a metal strip P with the desired thickness.
  • the strip P is then wound up into a coil in the coil box 5.
  • the metal strip P is thereafter uncoiled to be sent to the finishing mill (not shown) for finishing.
  • edge drops, or portions of reduced thickness, on each side of the slab S can be created during the reverse rolling process in the roughing mill 4. This is prevented, in an installation according to the invention, by initially drafting the slab S in the edger 3 to generate dog bones, or portions of increased thickness, on the sides of the slab. Accordingly, no edge drops may be observed on the metal strip P after roughing in an installation according to the present invention.
  • the sizing press 2 is used to width-draft the slab S so that the amount of width drafting of the slab S which may be carried out can be increased in comparison with an installation not including a sizing press. Therefore, the range of widths of slab which may be cast by a continuous casting machine upstream of the installation and fed to the furnace 1 may be large. The number of different types of slab which the casting machine must produce is accordingly lowered, and as a result, the frequency with which the moulds on the casting machine must be changed is also reduced, resulting in an enhancement of the production efficiency.
  • the length of the production line from the roughing mill 4 to the finishing mill can be shortened, which leads to the installation being smaller than if the coil box were not included.

Description

  • The present invention relates to a hot roughing mill installation. Known hot roughing mill installations are described for example in the JP-A-53-26759 or the JP-B-61-3561. The former is directed to a large-scale production facility according to the pre-characterising part of Claim 1 having a sizing press for achieving higher production efficiency and the latter to a medium-scale production facility having a coil box, i.e. a coiling device, for winding up the roughed metal strip to reduce the length of the roughing mill line.
  • The installation described in the former publication has a very long roughing mill line, whilst the latter installation does not achieve good production efficiency. There is at present no hot roughing mill installation which has both high production efficiency and a relatively short roughing mill line. The object of the present invention is therefore, amongst other things, to provide an installation with a short roughing mill line and which operates at a high production efficiency.
  • According to the present invention, a hot roughing mill installation, which, in use, receives from a furnace a slab of hot metal which passes through the installation in a working direction, comprises a first roughing mill and a sizing press upstream of the roughing mill and is characterised in that the first roughing mill is a reversing roughing mill, that a coil box is provided downstream of the roughing mill which, in use, receives and coils a metal strip from the roughing mill, that edgers are provided upstream and downstream of the first roughing mill, which edgers, in use, form a thickened portion on each side of the slab and that a two-high rolling mill is located between the sizing press and the roughing mill.
  • The sizing press drafts the slab to a desired width before it passes through the roughing mill.
  • The thickened portion or "dog bone" on each side of the slab ensures that portions of reduced thickness, or "edge drops" are not created during roughing in the roughing mill.
  • The two-high rolling mill is included in the installation in order to flatten the thickened portions produced by the sizing press or edgers, should these portions be too pronounced.
  • It is possible for a second reversing roughing mill to be included in the installation, downstream of the first. In this case, further edgers may be incorporated immediately upstream and/or immediately downstream of the second roughing mill.
  • The following description of a specific embodiment of the present invention is given by way of example only, with reference to the single accompanying drawing which is a highly schematic side view of a hot roughing mill installation in accordance with the invention.
  • The drawing shows a first embodiment of the present invention in which reference numeral 1 represents a furnace for heating a slab S; and 2, a sizing press for drafting, or reducing the width of, the slab S when it has been taken out from the furnace 1. Numeral 3 represents edgers upstream and downstream of the roughing mill 4 for forming a "dog bone", or thickened portion, on each side of the slab S. Because edgers are situated upstream and downstream of the roughing mill, the sides of the metal strip P can be drafted by the edger 3 immediately prior to entering the roughing mill 4, regardless of the actual direction of travel of the strip P at that time. A two-high rolling mill 6 is arranged between the sizing press 2 and the upstream edger 3 so that, even if the thickened portions generated on each side of the slab S or metal strip P when it is drafted by the sizing press 2 or by the edger 3 are too big, they can be crushed by the two-high rolling mill 6. Downstream of the roughing mill 4 is a coiling device, 5, specifically a coil box for winding up the roughed strip P. The two-high rolling mill 6, sizing press 2, upstream edger 3, roughing mill 4, downstream edger 3 and coil box 5 are arranged on the exit side of the furnace 1 in that order in the direction D of travel of the slab. The direction D is the working direction in which the slab moves; that is to say it is the direction in which the slab progresses through the installation, although it may in fact also have a reciprocating motion, and the direction of travel at any instant may not be the same as the working direction D. A mill (not shown) for finishing the metal strip P is arranged downstream of the coil box 5 with respect to the direction of travel D.
  • The slab S is heated in the furnace 1 to a predetermined temperature and is then taken out of the furnace 1 and drafted to a predetermined width in the sizing press 2. Then, the slab S is reverse rolled several times in the reversing roughing mill 4 and is thereby formed into a metal strip P with the desired thickness.
  • The strip P is then wound up into a coil in the coil box 5. The metal strip P is thereafter uncoiled to be sent to the finishing mill (not shown) for finishing.
  • It is possible that edge drops, or portions of reduced thickness, on each side of the slab S can be created during the reverse rolling process in the roughing mill 4. This is prevented, in an installation according to the invention, by initially drafting the slab S in the edger 3 to generate dog bones, or portions of increased thickness, on the sides of the slab. Accordingly, no edge drops may be observed on the metal strip P after roughing in an installation according to the present invention.
  • As described above, the sizing press 2 is used to width-draft the slab S so that the amount of width drafting of the slab S which may be carried out can be increased in comparison with an installation not including a sizing press. Therefore, the range of widths of slab which may be cast by a continuous casting machine upstream of the installation and fed to the furnace 1 may be large. The number of different types of slab which the casting machine must produce is accordingly lowered, and as a result, the frequency with which the moulds on the casting machine must be changed is also reduced, resulting in an enhancement of the production efficiency.
  • Since the metal strip P, after roughing, is wound up in the coil box 5, the length of the production line from the roughing mill 4 to the finishing mill can be shortened, which leads to the installation being smaller than if the coil box were not included.
  • It is to be understood that the present invention is not limited to the above-described embodiment and that various modifications may be made within the scope of the invention as defined in the appended claims.

Claims (4)

  1. A hot roughing mill installation which, in use, receives from a furnace (1) a slab (S) of hot metal which passes through the installation in a working direction (D), the installation comprising a first roughing mill (4) and a sizing press (2) upstream of the roughing mill (4), characterised in that the first roughing mill is a reversing roughing mill, that a coil box (5) is provided downstream of the roughing mill (4) which, in use, receives and coils a metal strip (P) from the roughing mill (4), that edgers (3) are provided upstream and downstream of the first roughing mill (4), which edgers, in use, form a thickened portion on each side of the slab, and that a two-high rolling mill (6) is located between the sizing press (2) and the roughing mill (4).
  2. An installation as claimed in Claim 1 characterised by a second roughing mill (4) located downstream of the first roughing mill (4).
  3. An installation as claimed in Claim 2 characterised by an edger (3) immediately upstream of the second roughing mill (4).
  4. An installation as claimed in Claim 3 characterised by a further edger (3) immediately downstream of the second roughing mill (4).
EP19910301592 1990-06-11 1991-02-27 Hot roughing mill installation Expired - Lifetime EP0461743B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP152233/90 1990-06-11
JP15223390 1990-06-11
JP15223390A JPH0446602A (en) 1990-06-11 1990-06-11 Hot rough rolling equipment

Publications (4)

Publication Number Publication Date
EP0461743A2 EP0461743A2 (en) 1991-12-18
EP0461743A3 EP0461743A3 (en) 1992-03-11
EP0461743B1 EP0461743B1 (en) 1995-01-11
EP0461743B2 true EP0461743B2 (en) 1999-08-04

Family

ID=15535999

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19910301592 Expired - Lifetime EP0461743B2 (en) 1990-06-11 1991-02-27 Hot roughing mill installation

Country Status (3)

Country Link
EP (1) EP0461743B2 (en)
JP (1) JPH0446602A (en)
DE (1) DE69106596T3 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW340067B (en) * 1996-11-13 1998-09-11 Ishikawajima Harima Heavy Ind Rolled strip joining device and a hot strip mill having such a device
KR100490347B1 (en) * 1996-11-13 2005-10-19 수미도모 메탈 인더스트리즈, 리미티드 Rolled plate joining apparatuss and continuous hot rolling apparatus equipped with the same
GB9803409D0 (en) * 1998-02-19 1998-04-15 Kvaerner Metals Davy Ltd Method and apparatus for the manufacture of light gauge steel strip

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3358358A (en) * 1964-12-31 1967-12-19 United States Steel Corp Method of reducing width of metal slabs
GB1373375A (en) * 1971-11-15 1974-11-13 Canada Steel Co Method for rolling hot metal workpieces
JPS591401B2 (en) * 1976-04-26 1984-01-12 東洋インキ製造株式会社 UV curable composition
US4675974A (en) * 1985-10-17 1987-06-30 Tippins Machinery Co., Inc. Method of continuous casting and rolling strip
JPS63309306A (en) * 1987-06-11 1988-12-16 Hitachi Ltd Device and method for rolling of continuously cast billet
EP0327855B1 (en) * 1988-02-10 1992-04-22 Sms Schloemann-Siemag Aktiengesellschaft Installation for rolling strip immediately behind the continuous casting installation
JP2593534B2 (en) * 1988-11-11 1997-03-26 株式会社日立製作所 Hot rolling equipment

Also Published As

Publication number Publication date
DE69106596T2 (en) 1995-05-18
DE69106596T3 (en) 1999-12-23
EP0461743A2 (en) 1991-12-18
DE69106596D1 (en) 1995-02-23
JPH0446602A (en) 1992-02-17
EP0461743B1 (en) 1995-01-11
EP0461743A3 (en) 1992-03-11

Similar Documents

Publication Publication Date Title
EP0415987B1 (en) Process for continuous production of steel strip or steel sheet from flat products made by the circular-arc type continuous casting process
US5307864A (en) Method and system for continuously producing flat steel product by the continuous casting method
US7478664B2 (en) Method and continuous casting and rolling plant for semi-endless or endless rolling by casting a metal strand, especially a steel strand, which is cut to length as required after solidification
JP3152241B2 (en) Hot thin plate manufacturing equipment and manufacturing method
SK285199B6 (en) Method for manufacturing of steel strip and device for making the same
DE69606137T3 (en) Method and plant for rolling strips and sheets
BG60451B1 (en) Method and an installation for producing steel strip reels
RU98103651A (en) HIGH SPEED INSTALLATION FOR MANUFACTURING THIN INGOTS
RU2003106118A (en) METHOD FOR PRODUCING THIN FLAT PRODUCTS AND INSTALLATION FOR ITS IMPLEMENTATION
RU2106212C1 (en) Method for production of hot-rolled steel strip and plant for its embodiment
KR890005115B1 (en) Method of increasing the productivity of reversing plate mills
US5430930A (en) Method of manufacturing hot strip
RU2036030C1 (en) Method for producing steel strip or sheet and a facility to implement it
JPS6349302A (en) Production of shape
EP0461743B2 (en) Hot roughing mill installation
US4848127A (en) Method of reducing slab in widthwise direction
EP0665296A1 (en) Process and plant for manufacturing hot-rolled strip steel
NZ196105A (en) Method for modernising a hot strip mill
US5689991A (en) Process and device for producing hot-rolled steel strip
JP3399381B2 (en) Hot rolling equipment with shearing machine
JPS62275507A (en) Manufacturing assembly for base metal for aluminum foil
GB2030491A (en) Process for rolling plates, and plate mill therefor
JPS5816707A (en) Production of steel strip
JPS57121809A (en) Production of steel material by direct rolling
JP3991142B2 (en) Hot sheet rolling line

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): DE FR GB IT

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): DE FR GB IT

17P Request for examination filed

Effective date: 19920824

17Q First examination report despatched

Effective date: 19930317

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): DE FR GB IT

REF Corresponds to:

Ref document number: 69106596

Country of ref document: DE

Date of ref document: 19950223

ITF It: translation for a ep patent filed

Owner name: MODIANO & ASSOCIATI S.R.L.

ET Fr: translation filed
PLBI Opposition filed

Free format text: ORIGINAL CODE: 0009260

26 Opposition filed

Opponent name: SMS SCHLOEMANN-SIEMAG AG

Effective date: 19951010

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

PLAW Interlocutory decision in opposition

Free format text: ORIGINAL CODE: EPIDOS IDOP

PLAW Interlocutory decision in opposition

Free format text: ORIGINAL CODE: EPIDOS IDOP

PUAH Patent maintained in amended form

Free format text: ORIGINAL CODE: 0009272

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: PATENT MAINTAINED AS AMENDED

27A Patent maintained in amended form

Effective date: 19990804

AK Designated contracting states

Kind code of ref document: B2

Designated state(s): DE FR GB IT

ITF It: translation for a ep patent filed

Owner name: MODIANO & ASSOCIATI S.R.L.

ET3 Fr: translation filed ** decision concerning opposition
REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20100223

Year of fee payment: 20

Ref country code: IT

Payment date: 20100220

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20100312

Year of fee payment: 20

Ref country code: GB

Payment date: 20100224

Year of fee payment: 20

REG Reference to a national code

Ref country code: DE

Ref legal event code: R071

Ref document number: 69106596

Country of ref document: DE

REG Reference to a national code

Ref country code: GB

Ref legal event code: PE20

Expiry date: 20110226

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20110226

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20110227