DEP0006397DA - - Google Patents

Info

Publication number
DEP0006397DA
DEP0006397DA DEP0006397DA DE P0006397D A DEP0006397D A DE P0006397DA DE P0006397D A DEP0006397D A DE P0006397DA
Authority
DE
Germany
Prior art keywords
vertical
pulling
masonry
stone
όοη
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
Other languages
German (de)

Links

Description

PATENTANWALT
-in,- »-'. GUTHKNECHT
Dortmund, MDHLENSTR 9 Dortmund, den 6. Februar 195C.
PATENT ADVOCATE
-in,- "-'. GUTHKNECHT
Dortmund, MDHLENSTR 9 Dortmund, February 6 , 195C.

Architekt Ferd. Knooh, Dortmunä-Mrünninghausen, MeidkopfArchitect Ferd. Knooh, Dortmunä-Mrünninghausen, Meidkopf

Patentanmeldung.Patent application.

"ferfahren zum Mochziehen υοη Mauerwerk' P. 6397 V/37CL."drive away to Mochzieh υοη masonry ' P. 6397 V / 37CL.

Seim * te derail f bau zertrümmerter Häuser und Wohnblocks, ja ganzer Staate, ist, falls am alten Platz gebaut werden soll, die frumerbesettigung die vordringlichste und nicht abdingbare Voraussetzung, denn, wo gebaut werden soll, muß auch ein Bauplatz vorhanden sein. Die Beset tigung der Trümnermassen kann nun auf Oerschiedene Art und Seise vor stan gehen» ßo Hat man z. B. KIeinbahmysterne bis zum Mittelpunkt zerstörter Städte ausgebaut, mittels welcher die Trümmer, so, wie sie anfallen, in das Vorfeld aer Städte geschafft werden, wo sie bestenfalls als Aufschüttgut für Bodensenkungen dienen. Der hierdurch erzielbare Mutzen und die dadurch entstehenden Unkosten stehen in keinem Verhältnis zu dem ferlust wertvollen Baustoffes, der, wie man weiß, aus äen Trammer ma ssen zu gewinnen ist, ganz abgesehen daoon, daß man sich gezwungen sieht, neues Material, um zwar zum feil aus äen entlegensten Stellen, wieder an ate Baustellen heranzubringen. Man ist aber in dieser Erkenntnis auch schon dazu übergegangen, Zerkleinerungs- und SiebaUlagen im Trümmergelünde aufzustellenSeim * te derail for the construction of shattered houses and apartment blocks, yes whole state, if the old place is to be built, frumerbesettigung is the most urgent and an indispensable requirement, because where to build a building site must also be available. The debris can now be filled in various ways So go ahead. B. KIeinbahmysterne expanded to the center of destroyed cities, by means of which the rubble, as it arises, in the apron aer cities, where at best they serve as bulk material for subsidence. The resulting hood and the resulting costs are out of proportion to the need for valuable building material, which, as we know, can be obtained from a hitchhiker, Quite apart from that daoon that one feels compelled to come up with something new Material to sell from the most remote places, to bring them back to ate construction sites. With this knowledge, however, one has already gone over to setting up crushing and sieving systems in the rubble ground

und aas dem hierin anfallenden Matertal an Ort und Stelle Bausteine herzustellen. Bei diesen bekannten Anlagen fällt jedoch noch ein erheblicher Anteil des gewonnenen Matertals für die unmittelbare Verwertung aus, weil er sich für die Herstellung üon Bausteinen der bekannten Art nicht eignet, oder durch zusätzliche kostspielige V erarbeitungs verfahr en erst in diesen zustand versetzt werden muß* Demgegenüber ist es bein Arbeiten nach der vorliegenden Erfindung möglich, mit dem geringsten Aufwand an Arbeitsleistung und praktisch ohne Verlust an hochwertigem Saustoff fast den gesamten Schutt an Ort und Stelle zum Wiederaufbau zu verwenden. Zu diesem Zweck hat der Srfinder besondere Formsteine entwickelt, die, im Verhältnis etwa 1 ; 6 mit Zement gebunden, den Festigkettsanforderungen in jeder sieht genügen und in geeigneter Weise zusammengesetzt, räume mn großem Ausmaß bilden, in welche eine grobe Füllung je nach Beanspruchung entweder lose oder gebunden eingebracht werden kann, Hierdurch wird die Möglichkeit geschaffen, die ohne Brecherarbett zur Steinherstellung nicht verwendbaren Massen auf billige weiss nutzbar tu machen, da sie nur eine Biebanlage passieren, um sodann in einem Mischer gefüllt und für den vor ermahnten Zweck aufbereitet zu werden. Hierzu eignen sich z. S· alle reinen Steinbrocken und Mörtelmassen von Mull bis 1/4 Ziegel steingröße* Da diese Massen durch eine geeignete, dem Brecher vorgeschaltete Siebanlage von den groben Stücken getrennt werden, tritt eine außerordentlich ins Gewicht fallende Entlastung der kostspieligen und zeitraubenden Brecherarbeit ein. Die zur Verwendung gelangenden neuartigen Füllkörper werden an der Baustelle zusammengesetzt, und zwar weisen die als Läufer verwendeten steinplat- and aas the Matertal accruing here building blocks on the spot. In these known systems, however, a considerable proportion of the material obtained is still left out for immediate use, because it is not suitable for the production of building blocks of the known type, or it must first be converted into this state by additional costly processing methods * On the other hand In working according to the present invention it is possible to use almost all of the rubble on site for reconstruction with the least amount of labor and with virtually no loss of high quality oxygen. For this purpose, the inventor has developed special shaped stones that, in a ratio of about 1 ; 6 bound with cement, meet the requirements of the firm chain and put together in a suitable manner, create large spaces in which a coarse filling can be introduced either loosely or bound, depending on the load, this creates the possibility of stone production without a breaker bed Make unusable masses usable on cheap white, since they only pass one Biebanlage, to then be filled in a mixer and processed for the purpose admonished before. For this purpose, z. S · all pure stone chunks and mortar masses from gauze up to 1/4 brick size * Since these masses are separated from the coarse pieces by a suitable screening plant upstream of the crusher, the costly and time-consuming crusher work is greatly reduced. The new types of packing that are used are put together at the construction site.

ten an den Stirnseiten Muten und die als Binder verwendeten Steinplatten Federn auf, welche in die fluten der Läufer steine eingreifen, soüaß eine große Sfandstcherhett gewährleistet ist. Es entsteht auf diese Meise gewissermaßen eine Verschalung zur Aufnahme üer Füllung, welche aus hochwertigem Baustoff besteht, nicht entfernt wird und ein tragender Bestandteil der Mauer bleibt* Bies hat den großen Vorteil, daß kein teuere® und heute kaum zu be schaffend es Vers σ hai hol ζ benötigt wird, abgesehen wn der Ersparnis der mit dem Zuschneiden, Anbringen und Atederabreißen der Verschalung verbundenen hohen Löhne»ten grooves on the end faces and those used as binders Stone slabs on springs, which intervene in the flow of the runner stones, so that a large Sfandstcherhett is guaranteed is. In a sense, a casing is created on this tit to accommodate filling made of high quality building material exists, is not removed and remains a load-bearing part of the wall * Bies has the great advantage that no expensive® and hardly obtainable today it vers σ hai hol ζ is needed, apart from the saving of the cutting, Attaching and tearing off the casing high wages »

Jn der zeichnung sind die neuartigen formsteine und mehrere AnwendungsbelspieIe zur Erläuterung dargestellt, und zwar zeigen; Fig» 1 den ganzen Läuferstein,The drawing shows the new shaped bricks and several application examples for explanation, namely show; Fig »1 the whole runner stone,

* 2 den halben Läuferstein, * 2 half the runner stone,

" 3 den Winkel eckst ein fur 39 cm stk. Wand,"3 corner the corner for 39 cm wall,

* 4 am Binderstein, * 4 at the Binderstein,

* 5 den Scftstein, * 5 the stone,

m 6 den Binder eck stein für 54 cm stk. "and, m 6 the Binder corner stone for 54 cm pieces. "and,

* 7 äen Bindereckstein für ?o cm stk» rand, * 7 äen binder corner stone for? O cm thick »edge,

* B äen Anschlagstein,* B een stop stone,

0 9 äen Binderanschlagstein, 0 9 äen girder stop stone,

* 10a um 10b eine 3C cm stk. Mauer in isometrischer* 10a by 10b a 3C cm stk. Brick wall in isometric

ansicht und Schnitt,view and section,

m 11 eine 39 cm stk. Mauer, " 12 eine ö4 cm stk. * m 11 a 39 cm piece. Wall, "12 one ö4 cm pieces. *
ww 13 eine 70 cm stk. "13 a 70 cm piece. "

Fig.. 14 einen 39 cm stk. Pfeiler,Fig. 14 a 39 cm stk. Pier,

Fig. 15 einen 54 cm stk. Pfeiler mit eisenarmiertem Füllbeton.Fig. 15 a 54 cm piece. Pillar with iron-reinforced concrete.

* 16 * 70 cn " ** 16 * 70 cn "*

« 17 * 39 cm " "mit AnscKlag,«17 * 39 cm" "with attachment,

" IB " 54 am * * " w "IB" 54 am * * " w

* 19 " 70 cm " " * n " 2G eine 8 cm " Trennwand,* 19 "70 cm""* n " 2G an 8 cm "partition,

" 21 einen Kanal schacht mit Minterbeton,"21 a sewer shaft with minter concrete,

" 22 eine Möschungsmauer mit Mtnterbeton."22 a plaster wall with base concrete.

Die Mngenabmessung des ganzen Läufers beträgt 52,5 cm, die des halben Läufers 21, 25 cn bei 30, 25 cm Höhe und 8 cm jjiclie. Die Binder» und Anschlag steine weisen Lüngenab~ mmungen por 39 em., 54 cm und 7ot5 cm auf bei 30, 25 cm tföfte unä 8 cm Dicke, welche beim Anschlagstein im starken Teil 12 cm und im schwachen Teil 8 cm beträgt. Kit den L" und υ- föruigen Formstetnen fs. Fig. 3,6,7 unä 9) tserden alle Jckoerbande hergestellt. Die Abmessungen der Form" steine nach der Oorliegenden Erfindung und auch die Mauer» stärken sind aus dem Ach&enmaß Όοη 1,25 m unter Merüeksiäh» tigung von IQ »si Fugenstärke errechnet. Für die Sntwurfarbeit ist daher die Anwendung dieses Maßes als Baster erforderlich, wobei zu beachten ist, daß die feilung immer in der Bindermitte liegen muß. Das kleinste Maß wn Bindermitte zu Binäermitte beträgt 31,25 cm. hierdurch wird eine weitgehende Normung erreicht, welche sich nicht nur auf die vielseitige Verwendungsmöglichkeit der Formsteine allein auswirkt, sondern auch auf alle Oeffnungen, wie Fenster und Türen, und auf deren geordnete und tythmtsehe Verteilung und gute Proportionierung in der äußeren Gestaltung. Das gilt auch gleichermaßen für die Tyncrit-az, f teilung unä innere Raumpestal tung. Auch The length measurement of the whole runner is 52.5 cm, that of half the runner is 21.25 cm at a height of 30, 25 cm and a length of 8 cm. The binder "and stop stones have Lüngenab ~ mmungen por 39 em., 54 cm and 7o t 5 cm at 30, 25 cm tföfte UNAE 8 cm thickness which is cm at the stop block in the strong part 12 cm and at the weak portion 8. Kit the L "and oval shaped stones fs. Fig. 3,6,7 and 9) earth all Jckoerbande manufactured. The dimensions of the shaped stones according to the present invention and also the wall thicknesses are from the axis dimension Όοη 1.25 m calculated using the IQ »si joint thickness. For the design work it is therefore necessary to use this dimension as a baster, whereby it should be noted that the filing must always be in the middle of the binder. The smallest dimension from the center of the tie to the center of the binary is 31.25 cm. This results in extensive standardization, which affects not only the versatile use of the shaped bricks, but also all openings, such as windows and doors, and their orderly and regular distribution and good proportions in the external design. This also applies equally to the Tyncrit-az, division and interior design. Also

durch, daß sich die Mauerstärken und Schichthöhen dieser Bauweise mit denjenigen des Normal ziegel formal -Mauerwerks decken, ist es möglich, dieselbe unter Ausnutzung von vorhandenem Ziege !mauerwerk beim Ausbau von Ruinen anzuwenden, Zur Entwicklung als Füllbauweise war insbesondere maßgebend, den Anteil der Formate ine als den teuersten und zeitraube ns ten feil möglichst niedrig zu halten, denn bekanntlich können die Formsteine nur aus gut aufbereiteten Trümmern in kleinerer Korngröße hergestellt werden, mährend für den Füllbeton weniger gut aufbereitete Trümmer und vielfach sogar schaufel- und mischfähiges Trümer gut ohne besondere Aufbereitung verwendet werden kann. Für ein- bis zweigeschossige Mauten eignet sich sogar mit Ziegelsplitt üermengter lehm ganz hervorragend als Füllnasse, »elcher aus dem Erdaushub zu entnehmen märe. Auf diese Meise wird ein billiges und tßärmehal tenües Mauerwerk von großer Tragkraft geschaffen, bei dessen Herstellung weitgehend®t Selbsthilfe und die fermendung von ungelernten Arbeitskräften möglich sind. DU Form und der Füllungstetl der einzelnen Wände beträgt:by that the wall thicknesses and layer heights of these Construction method with those of the normal brick formal masonry cover, it is possible to utilize the same from existing goat! masonry when removing ruins For the development as a fill construction, it was particularly decisive to determine the proportion of formats ine than the most expensive and time-consuming sells as low as possible hold, because as is well known, the shaped stones can only be made from well-prepared rubble in smaller grain size, while less good for the filler concrete processed rubble and often even rubble that can be shoveled and mixed can be used without any special processing. For one- to two-storey tolls Even clay mixed with brick chippings is ideally suited as a filling liquid, »which can be taken from the excavated earth. This tit will be a cheap one and low-temperature masonry with great load-bearing capacity was created, in the manufacture of which largely self-help and the transfer of unskilled workers is possible are. DU shape and the filling tray of the individual walls amounts to:

für die 30er ffand 50 und 41% für die 39er fand 46 und $4%, für die 54er tan a 40 und 6ϋ%> und für die 70er wand 33 und 7Q&. Mit der Stärke der ffand steigt demnach der Füllungsanteil und auch die Wirtschaftlichkeit* Die Vermauerung der Furmsteine in Zementmörtel geschieht in äer Heise, daß die Läuferstoßfugen in den Nuten mit Mörtel versehen unü gegen die Federn der Binder zu einem dichten Fugenüerschluß geschoben werden. Der bereits nach for the 30s ff and 50 and 41% for the 39s found 46 and $ 4%, for the 54s tan a 40 and 6ϋ%> and for the 70s wall 33 and 7Q &. With the strength of the ffand, the proportion of filling increases and so does the economic efficiency The already after

Hurger seit steif gewordene Stoßfugennartel sichert gegen seitliches Ausweichen beim Einbetonieren der Füllmasse. B Biese Füllmasse ist zweckmäßig mit jeder Schicht einzubringen. Der sckverband wird durch ate Formsteine Nr* 3,6, 7 und 9 hergestellt» Me Mauerschicht unter der Balkenlage ist der größeren Beanspruchung megen in jedem Falle mit tragender Betonmischung auszufüllen. Der Eisenhetonpfeil erbau für Geschäftshäuser, Fabriken, Lagergebäude, land" wirtschaftliche Sauten usw. sowie der starkwandige Beton' bau für Bö sehungsmauern (Fig. 22), Brückenbauten, Kanalschächte (Fig. 21) usw. sind mit der neuen Bauweise ohne ferwendung won Schalung ebenso leicht möglich wie der Kletnhaus- und &roßhaus-9 ohnungsbau. Der Eisenbetonpfeilerbau ohne Schalung wird in einfachster Art dadurch ermöglicht, daß der Läuferstein mit dem Bindereckstein kaminartig auf das üorhanäem eisenarmierte Stutzen fundament üermauert, die Stützen armierung hineingestellt und mit den aufgebogenen Fundamente is en Oerbunden wird. Sine starke Böschungsmauer oder ein starker Brückenpfeiler, eine Quaimauer oder ähnliche Mauern werden ohne Schalung in der »eise betoniert, daß zunächst eine 39 cm starke Mohlblockmauer an der Außenseite zwei Schichten hoch aufgemauert unä mit Beton ausgefüllt wird. Sodann wird die übrige Mauerflaehe ausbetoniert. (Fig* 22) Die ser Vorgang wiederholt sich gin- oder zweischichtenwetse bis zur Fertigstellung. Beim Kanalschacht (Fig.21), uer bisher nur mit hochwertigen Radial-Kl inkers te ine η möglich war, ist die neue Bauweise mit ae® halben Läuferstein und dem Binderstein gemäß Fig. 1 und 2 in solt- Hurger butt joint, which has become stiff since then, secures against sideways movement when concreting the filling compound. B This filling compound is expedient to apply with every layer. Is the sckverband by ate conglomerates No. * 3.6, prepared 7 and 9 »Me wall layer under the beam location is the major stress megen in each case with bearing concrete mix to fill. The Eisenhetonpfeil build for commercial buildings, factories, storage buildings, agricultural Sauten etc. as well as the thick-walled concrete 'construction for booth sehungsmauern (Fig. 22), bridge constructions, sewer shafts (Fig. 21) etc. are with the new construction without use won formwork just as easily possible as the Kletnhaus- und & roßhaus-9 ohnungsbau. The reinforced concrete pillar construction without formwork is made possible in the simplest way by the fact that the runner stone with the binding corner stone builds up like a chimney on the iron-reinforced socket foundation, the column reinforcement is placed in it and with the bent foundations A strong embankment wall or a strong bridge pillar, a quay wall or similar walls are concreted without formwork in such a way that first a 39 cm thick cinder block wall is bricked up two layers high on the outside and then filled with concrete concreted out. (Fig * 22) This process repeats itself gin- ode r two-layer weather until completion. In the case of the manhole (Fig. 21), which was previously only possible with high-quality radial clinkers, the new construction with ae® half-runner block and the binder block according to Figs. 1 and 2 is

üester und wirtschaftlichster Art anwendbar, die Stoß" fugen sind Hierbei in sogenannten Schnittfugen lotrecht und ohne Verband anzuordnen. Schichtweise wird dann der übrige Beton bis zum Erdreich als Ziege Isplitt be ton eingebracht, Der bo ausgeführte ßchacht hat feste, glatte Schachtwände wit geringer Fugenzahl, durch die Minterbetonierung große Festigkeitt ist also der bisherigen Ausführung mindestens gleichwertig, und hat zudem noch geholfen, das Trümer- problem zu beseitigen. Für die ntehtbelastete Trennwand /indet der Läuferstein gemäß Fig* 1 oder 2 entweder einfach als 8 cm starke wand oder doppelt als 17 cm starke Wand Verwendung. (Fig* 20) The most economical way to use, the butt joints are to be arranged vertically in so-called kerfs and without a bond. The remaining concrete is then poured in layers down to the ground as goat isplit concrete. Due to the minter concreting, the high strength is at least equivalent to the previous version, and has also helped to eliminate the rubble problem. For the non-loaded partition wall / in the runner block according to Fig. 1 or 2 either as a single 8 cm wall or double Use as a 17 cm thick wall. (Fig * 20)

Patentansprüche, gesondert:Patent claims, separately:

Claims (10)

Pa ten tanspr Uclie. Pat tanspr Uclie . 2. f er fahren zum Moehziehen Όοη Mauerwerk, daäurch gekemzeichnet, daß aus plattenförmigen Formateinen, welche, hochkant aufgestellt, mit Mut und Feder ineinandergreifen, große Hohlräume gebildet und mit tragender oder ntchttra~ gender Füllung versehen werden, 2. Go to Moehzieh Όοη masonry, because it is marked that large cavities are formed from plate-shaped format pieces, which, when placed on edge, interlock with courage and feather, and are provided with load-bearing or non-load-bearing filling, 2.) ferfahren zum Hochziehen Όοη leichtem Mauerwerk nach Anspruch 1* dadurch gekennzeichnet, daß mit einer Schicht als Binder flach verlegten und mit einer schicht als Läufer hochkant aufgestellten plattenartigen Formsteimn Jtoftlräuvie gebildet und mit tragender oder nicht tragender FUl" lung mrsehen werden. 2.) ferfahren to pull up Όοη light masonry according to claim 1 * characterized in that laid flat with a layer as a binder and with a layer as a runner upright plate-like molded stones Jtoftl räuvie are formed and with load-bearing or non-load-bearing filling mrsehen. 3.) Läuferstein zum Hochziehen von Mauerwerk nach Anspruch oder 2t dadurch gekennzeichnet, daß die beiden Schmalseiten nutenförmig ausgebildet sind.3.) runner block for pulling up masonry according to claim or 2 t, characterized in that the two narrow sides are groove-shaped. 4.) Winkel eckstein sum Moehziehen Όοη Mauermerk nach An» spruch 1 oder 2, dadurch gekennzeichnet, daß der längere iinkelschenk el an der Schmalseite nutenförmig ausgebildet ist und sich an der Schmalseite des Kürzeren Winkelschenkels zwei Federn befinden. 4. ) Angle corner stone sum Moehzüge Όοη Mauermerk according to claim 1 or 2, characterized in that the longer iinkelschenk el is groove-shaped on the narrow side and there are two springs on the narrow side of the shorter angle leg. δ,) Binderstein zum Moehziehen Όοη Mauerwerk nach Anspruch oder 2, dadurch gekennzeichnet, daß er auf jeder Seitenfläche in der Mähe der beim Verlegen senkrecht stehenden Kanten je eine von oben naoh unten verlaufende Feder auf" weist*δ,) binder stone for pulling Όοη masonry according to claim or 2, characterized in that it is on each side surface in the vicinity of the vertical when laying Edges each a feather running from top to bottom on " shows * 6.) 3inuereck8tein zum Moehziehen non Mauermerk nach An~ spruch, 1 oder 2, dadurch gekennzeichnet, daß er auf einer Seivenfläche in der Nähe der beim Verlegen senkrecht stehen* den Kanten und. an den Stirnseiten je eine Feder aufweist. 7,) Binuereckstein zum Hochziehen öon Mauerwerk nach Anspruch 2 oaer 2f u2uurc- , oekennzetennet. ügi? e^ ··'- "örtzip zuspe- 6.) 3inuereck8tein to Moehzieh non Mauermerk according to claim, 1 or 2, characterized in that it is on a Seivenfläche in the vicinity of the vertical when laying * the edges and. each has a spring on the end faces. 7,) Binuereckstein for pulling up masonry according to claim 2 or 2 f u2uurc-, oekennzetennet. ügi? e ^ ·· '- "add local zip bildet ist, und sieb in der ffihe einer senkrecht stehendnn Sehe und an den Stirnseiten der beiaen senkrecht stehenden Schenkel je eine Feder befindet,forms is, and sieve in the series of a vertical standingnn See and at the front sides of the two vertical ones Each leg has a spring, β.) Minder eckstein zum äoehztehen von Mauerwerk nach An~ spruch 7t dadurch gekennzeichnet, daß er u-förmig ist und sich in den beiden senkrecht stehenden Schenkeln je eine Mute befindet. β. ) Minder eckstein äoehztehen for masonry according to ~ 7 t demanding characterized in that it is shaped a-and depending is a mute in the two vertical legs. 9.) Anschlagstein zum Hochziehen von Mauerwerk nach 4nspruch 1 oder 2, dadurch gekennzeichnet, daß er auf einer Seite in der Nähe der beim Verlegen senkrecht stehenden Kanten je eine Feder aufweist und auf der Rückseite eine Aussparung zur Aufnahme von Fenster be zw. Türrahmen be~ sitzt, 9.) stop stone for pulling up masonry according to 4n claim 1 or 2, characterized in that it has a spring on one side near the vertical edges when laying and on the back a recess for receiving windows be zw. Door frame owns, 10.) Anschlagstein zum Mochziehen von Mauerwerk nach Anspruch 9, dadurch gekennzeichnet, daß er unförmig ist und an den Stirnseiten der beiden senkrecht stehenden Schenkel Muten aufweist.10.) stop stone for pulling masonry according to claim 9, characterized in that it is misshapen and has grooves on the end faces of the two perpendicular legs.

Family

ID=

Similar Documents

Publication Publication Date Title
DE69611931T2 (en) UNDERGROUND CONSTRUCTION, ESPECIALLY FOR THE PRODUCTION OF TUNNELS, UNDERWAYS, UNDERGROUND GARAGE, ETC. AND ITS MANUFACTURING PROCESS
DE2002621A1 (en) Method of making concrete
EP0361025A1 (en) Noise barrier device
DE19542354A1 (en) Brick with one or more tenons and one or more mortices
DEP0006397DA (en)
EP3696320B1 (en) Bridge abutment with connection between wall reinforcement and wing wall element
EP1210485B1 (en) Reinforced concrete part for producing foundations of buildings
DE803723C (en) Method of pulling up masonry
DE4321730C2 (en) Combination waterproofing for landfills with steep walls to vertical walls and / or embankments as landfill restrictions
EP1885962A1 (en) Constructional component in particular ground floor or cellar for commercial or domestic buildings
DE830806C (en) Road surface made of artificial stones
DE806393C (en) Vault construction with prefabricated components made of Ruettelbeton
DE20120365U1 (en) Formwork stone wall with clay and straw filling
DE202008001309U1 (en) Construction element made of lightweight concrete
AT372734B (en) CONSTRUCTION
DE206878C (en)
DE2351786A1 (en) STRUCTURE AND METHOD FOR MANUFACTURING IT
DE811392C (en) Double-walled masonry
AT311620B (en) Method for creating masonry
AT319544B (en) Prefabricated strips, preferably for ceilings and methods for producing a prefabricated strip
AT166741B (en)
DE811501C (en) Shaped stone and masonry made from the same
DE102022004371A1 (en) Wall element and method for setting such wall elements
DE1659099C (en) Concrete block for the production of a top layer on a building wall embedded in the ground
DE102011000379A1 (en) Hollow-block for constructing decorative walls in building site, has plastic plates arranged parallel to each other at predetermined distance, and connected with each other such that intermediate cavity is fillable with building material