DE950178C DEB14169A DEB0014169A DE950178C DE 950178 C DE950178 C DE 950178C DE B14169 A DEB14169 A DE B14169A DE B0014169 A DEB0014169 A DE B0014169A DE 950178 C DE950178 C DE 950178C
Authority
DE
Germany
Prior art keywords
bucket wheel
excavator
wheel excavator
handle
support position
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DEB14169A
Other languages
German (de)
Inventor
Erwin Bargmann
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DEB14169A priority Critical patent/DE950178C/en
Application granted granted Critical
Publication of DE950178C publication Critical patent/DE950178C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/02Conveying equipment mounted on a dredger
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/18Dredgers; Soil-shifting machines mechanically-driven with digging wheels turning round an axis, e.g. bucket-type wheels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/18Dredgers; Soil-shifting machines mechanically-driven with digging wheels turning round an axis, e.g. bucket-type wheels
    • E02F3/185Dredgers; Soil-shifting machines mechanically-driven with digging wheels turning round an axis, e.g. bucket-type wheels with digging unit mounted in a plane which is inclined to the direction of travel; with tools digging laterally with respect to the frame

Description

Schaufelradbagger mit in Form eines liegenden U ausgebildetem Unterteil Bei Schaufelradbaggern wird erstrebt, möglichst wenig Übergangsstellen für das Baggergut, d. h. also, eine möglichst geringe Zahl von Förderbändern einzuschalten. Die einfachste Lösung sieht die Lagerung des Abwurfbandes unmittelbar auf dem drehbaren Oberteil im Anschluß an das am Schaufelradausleger angeordnete Förderband vor. Da der Oberteil sich aber während der Grabarbeit dauernd hin und her dreht, muß das Abwurfband, dessen Abwurfende z. B. über dem Abwurfwagen stillstehen soll, mit einer besonderen Schaltvorrichtung dauernd gegenläufig verschwenkt werden. Außerdem wird wegen des besseren Aufbaues die Schwenkachse des Abwurfbandes auf dem Oberteil zumeist außermittig gelegt, wodurch beim Drehen des Oberteils noch eine stetige Veränderung der Ausladung und damit eine Verschiebung des Abwurfbandes. auftritt. Günstiger ist daher diejenige Lösung, bei der das Abwurfband im Baggerunterteil gelagert ist, weil es dann die Bewegungen des Oberteils nicht mitmacht und daher immer an der gleichen Stelle abwerfen kann. Bei solchen Schaufelradbaggern ist es zur Ermöglichung der für den Betrieb notwendigen seitlichen V erschwenkung des Abwurfbandes bekannt, den Baggerunterteil in der Form eines liegenden U auszubilden und die senkrechten Streben seines Gerüstes möglichst weit zurückzusetzen, damit sie die Schwenkbewegung des Abwurfauslegers nicht allzusehr begrenzen. Trotzdem reicht die hierdurch ermöglichte Seitenverschwenkung des Abwurfauslegers meist nur zur Arbeit des Gerätes an der Strosse aus. Auch ist hierbei der obenliegende Schenkel des U-förmigen Baggerunterteiles, der als Plattform zur Aufnahme des Drehkranzes für den drehbaren Oberteil des Baggers ausgebildet ist, nur etwa auf seiner Hälfte unterstützt. Wenn der Schaufelradausleger, wie es bei Planierarbeiten und bei der Arbeit im Einschnitt erforderlich ist, über diese unterstützte Fläche hinaus verschwenkt wird und somit der Schwerpunkt des Oberteils aus dem Bereich der unterstützten Fläche der Laufbahn herausfällt, wird der U-förmige Baggerunterteil ungünstig belastet und beansprucht. Diese Nachteile werden gemäß .der Erfindung dadurch vermieden, daß am freien Ende des oberen Schenkels des Unterteils an jeder Ecke desselben ein Stiel aufgehängt ist, der je nach Bedarf wechselweise mit dem anderen Stiel in die Abstützstellung oder aus dieser heraus schwenkbar ist.Bucket wheel excavator with a lower part designed in the form of a lying U With bucket wheel excavators, the aim is to have as few transition points as possible for the dredged material, d. H. in other words, using as few conveyor belts as possible. The easiest The solution sees the storage of the discharge belt directly on the rotatable upper part following the conveyor belt arranged on the bucket wheel arm. Because the top but turns back and forth during the digging work, the discharge conveyor, whose drop end z. B. should stand still over the drop trolley, with a special Switching device are continuously pivoted in opposite directions. In addition, because of the Better structure, the pivot axis of the discharge conveyor on the upper part is mostly eccentric placed, whereby when turning the upper part a constant change of the projection and thus a shift in the discharge conveyor. occurs. That is why it is cheaper Solution in which the discharge conveyor is stored in the lower part of the excavator, because it is then the Does not go along with the movements of the upper part and therefore always throw it off at the same point can. With such bucket wheel excavators it is necessary to enable the operation necessary lateral pivoting of the discharge conveyor known, the bottom part of the excavator in the shape of a lying U and the vertical struts to set back its scaffolding as far as possible so that the pivoting movement of the Do not limit the discharge boom too much. Nevertheless, the one made possible by this is sufficient Side pivoting of the discharge boom mostly only to work on the device Streak out. Also here is the overhead leg of the U-shaped excavator lower part, as a platform to accommodate the turntable for the rotatable upper part of the excavator is trained, supported only about on its half. If the bucket wheel boom, as required in leveling and working in the cut, over this supported area is pivoted out and thus the center of gravity of the Upper part falls out of the area of the supported surface of the running track the U-shaped bottom part of the excavator is unfavorably loaded and stressed. These disadvantages are avoided according to .der invention that at the free end of the upper leg of the lower part at each corner of the same a stem is hung, depending on the needs alternately with the other handle in or out of the support position is pivotable.

Da bei der Baggerarbeit der eine der beiden Stiele jeweils in in Abstützstellung stehen soll, gewinnt der Unterteil an Steifigkeit, und die unterstützte Fläche des Drehkranzes wird beträchtlich vergrößert.Since one of the two sticks is in the support position during excavation work should stand, the lower part gains stiffness, and the supported surface of the The slewing ring is enlarged considerably.

Die durch den in Abstützstellung stehenden Stiel verursachte Beschränkung des Schwenkweges des Abwurfauslegers bedeutet für den Bagger, der zumeist in einer Richtung arbeitet, keine Behinderung. 'Bei Umkehr der Arbeitsrichtung wird der bisher als Stütze dienende Stiel herausgeschwenkt und der auf der Gegenseite aufgehängte Stiel in Stützstellung gebracht. Die Aufhängung beider Stiele in je einer Schwenkachse am freien Ende des oberen Schenkels des Unterteils hat den Vorteil, daß sie ohne Schwierigkeit und größeren Zeitaufwand in die Abstützstellung eingeschwenkt und ebenso wieder aus ihr herausgeschwenkt werden können.The restriction caused by the stem in the support position the swivel path of the discharge boom means for the excavator, which is mostly in a Direction works, no obstruction. 'If the working direction is reversed, the previous The handle that serves as a support is swiveled out and the one hung on the opposite side Handle brought into support position. The suspension of both handles in a pivot axis each at the free end of the upper leg of the lower part has the advantage that it is without Difficulty and greater expenditure of time swiveled into the support position and can also be pivoted out of it again.

Damit dem Unterteil in jedem Falle die durch den Erfindungsgegenstand erstrebte zusätzliche Festigkeit erteilt wird, sind gemäß der weiteren Erfindung die beiden Stiele derart gegeneinander verriegelt, daß der eine Stiel nur dann hochgeschwenkt werden kann, wenn, der andere Stiel die Stützstellung einnimmt. Dadurch ist die Gewähr gegeben, daß der Oberteil stets ausreichend abgestützt ist und der wechselseitige Ein- und Ausbau der Stiele keine Schwierigkeiten macht.So that the lower part in each case by the subject matter of the invention desired additional strength is granted, are according to the further invention the two handles are locked against each other in such a way that one handle is only pivoted upwards can be, if, the other stem assumes the support position. This is the Guaranteed that the upper part is always adequately supported and the reciprocal Installation and removal of the stems are no problem.

Zur Erleichterung des Einbaues und zum Ausgleich bzw. zur Abstellung von Ungenauigkeiten sind gemäß der weiteren Erfindung die Stiele in ihrer Länge veränderlich.To facilitate installation and to compensate or to set aside According to the further invention, the stems are of inaccuracies in their length changeable.

In der Zeichnung sind zwei Ausführungsbeispiele der Erfindung dargestellt.Two exemplary embodiments of the invention are shown in the drawing.

Abb. I ist die Seitenansicht einer ersten Ausführungsform des Schaufelradbaggers, Abb.2 eine Draufsicht auf den Unterteil des Baggers nach Abb. I, und Abb.3 zeigt das U-förmig ausgebildete Gerüst des Unterteils einer zweiten Ausführungsform des Schaufelradbaggers.Fig. I is a side view of a first embodiment of the bucket wheel excavator, Fig.2 shows a top view of the lower part of the excavator according to Fig. I, and Fig.3 shows the U-shaped frame of the lower part of a second embodiment of the Bucket wheel excavator.

Der Schaufelradbagger besteht aus dem Oberteil I, auf dem der das Schaufelrad :2 tragende Ausleger 3 in vertikaler Ebene schwenkbar und nach Bedarf in seiner Längsrichtung verschiebbar gelagert ist, und dem U-förmigen Unterteil 4, auf dessen oberem als Plattform ausgebildetem Schenkel der Drehkranz 5 (Abb. 2) für den in vollem Kreise drehbaren Oberteil I angeordnet ist. Das Baggergut wird in Baggermitte über geeignete Schurren auf das darunterliegende Abwurfband 6 abgegeben, das es an seinem Ende 7 abwirft. Da der das Abwurfband tragende Ausleger die nötige Beweglichkeit zum Beladen von Wagen, Beschütten von Bunkern oder Verteilen des Baggergutes haben muß, ist er bei 8 um eine senkrechte Achse drehbar gelagert. Da sich der 'Ausleger des Abwurfbandes 6 aus seiner in Abb. I gezeichneten Mittellage nach jeder Seite um einen möglichst großen Winkel heraus schwenken lassen muß, sind die senkrechten Streben 9 und Io des Unterteiles 4 entsprechend weit zurückgesetzt. Sie bilden so gewissermaßen den Steg eines liegenden U. Die Drehachse 8 des Abwurfbandes, die auch in der Mitte des Unterteiles liegen könnte, ist bei den dargestellten Ausführungsbeispielen um ein gewisses Maß nach außen verschoben, damit die Streben 9 und Io nicht zu weit zurückgesetzt werden müssen. Bei dieser Anordnung entspricht der zwischen den beiden Streben 9 und Io liegende unterstützte Teil des Drehkranzes 5 einem Kreisabschnitt von nicht ganz I8o°. Trotzdem bleibt der Schwerpunkt des Oberteiles, der beim Graben nach dem Schaufelrad 2 zu liegt, bei der Arbeit des Baggers an der Strosse innerhalb des unterstützten Kreisabschnittes. Der Grabschnitt des Baggers ist durch die Linie II bezeichnet. Das Schaufelrad 2 wird etwa zwischen der Stellung I2 nach Abb. 2 und einer Stellung senkrecht zur Böschung, die der Abb. I entspricht, hin und her verschwenkt. Der Schwerpunkt des Baggeroberteils I wandert dabei auf dem ausgezogenen Teil I3 des Schwerpunktkreises. Schon beim Planieren vor dem Bagger, wobei der Ausleger 3 vor dem Fahrwerk des Unterteils hin und her schwenkt, wandert der Schwerpunkt aber in den strichpunktierten Teil 14 des Kreises hinein und liegt bald sehr weit neben dem unterstützten Teil der Laufbahn.The bucket wheel excavator consists of the upper part I on which the Bucket wheel: 2 supporting arms 3 can be swiveled in a vertical plane and as required is mounted displaceably in its longitudinal direction, and the U-shaped lower part 4, on the upper leg of which is designed as a platform, the turntable 5 (Fig. 2) is arranged for the upper part I, which can be rotated in a full circle. The dredged material will released in the middle of the excavator via suitable chutes onto the discharge conveyor 6 below, that it throws off 7 at its end. Since the boom carrying the discharge conveyor provides the necessary Mobility for loading wagons, pouring bunkers or distributing the dredged material must have, it is rotatably mounted at 8 about a vertical axis. Since the 'boom of the discharge belt 6 from its central position shown in Fig. I to each side must be allowed to pivot out as large an angle as possible are the vertical ones Struts 9 and Io of the lower part 4 are set back accordingly. You make so as it were the web of a lying U. The axis of rotation 8 of the discharge conveyor, the could also be in the middle of the lower part, is in the illustrated embodiments Shifted outwards by a certain amount so that the struts 9 and Io are not too far need to be reset. In this arrangement, that corresponds to that between the two Struts 9 and Io lying supported part of the slewing ring 5 is a segment of a circle of not quite 180 °. Nevertheless, the center of gravity of the upper part remains when digging after the bucket wheel 2 is to be found in the work of the excavator on the stope within of the supported circle segment. The back section of the excavator is through the line II designated. The paddle wheel 2 is approximately between the position I2 according to Fig. 2 and a position perpendicular to the slope, which corresponds to Fig. I, back and forth pivoted. The center of gravity of the excavator upper part I moves on the extended one Part I3 of the focus group. Even when leveling in front of the excavator, with the boom 3 swings back and forth in front of the chassis of the lower part, the center of gravity shifts but in the dash-dotted part 14 of the circle and is soon very far next to the supported part of the career.

Erfindungsgemäß sind nun zwischen dem oberen Schenkel des U-förmigen Unterteils q. und dessen unterem Schenkel an. den beiden freien Ecken um eine waagerechte Achse vierschwenkbare Stiele 15, 16 angeordnet. Einer dieser beiden Stiele steht immer in Abstützstellung, während der andere herausgeschwenkt ist. In Abb.2 ist der Stiel 15 in Abstützstellung und vergrößert dadurch den unterstützten Kreisabschntitt des Drehkranzes 5 erheblich, z. B. über einen Winkel von etwa 2q.0°. Die Stiele können als vierkantige oder runde Stäbe in der Ecke der Plattform angeordnet sein, sie können aber auch große Eckwinkel bilden, die in beide Seitenwände der Plattform des Unterteils hineinragen. Werden sie, wie in Abb. 2 dargestellt, in der dem Abwurfausleger 6 zugekehrten Wand breit ausgeführt, dann schützen sie das senkrechte Gerüst des Unterteils wirksam gegen Verdrehungen. Eine wesentliche Beschränkung bei Arbeiten des Baggers tritt nicht ein, da das Beladen der Abfuhrwagen in den Stellungen I7 und I8 des Abwurfauslegers erfolgen kann und die etwas über die Mittellage gehende Stellung I9 zum Abwurf bei größter Ausladung ausreicht. Durch den in Stützstellung eingeschwenkten Stiel I5 ist auch der Teil des Drehkranzes 5 unterstützt, der den strichpunktierten Schwerpunktteilkreis 14 enthält. Das Schaufelrad kann also sicher bis zur Stellung 2o (Abb. 2) durchschwenken und daher einen Einschnitt herstellen, der durch die strichpunktierte Linie 2I bezeichnet ist, die sich an die angezogene Linie II anschließt. Da der Ausleger des Abwurfbandes 6 aus seiner Mittellage nach Abb. I weit über 9o° herausgeschwenkt werden kann bis in die Stellung 22, so kann der im Einschnitt arbeitende Bagger bei I7 und I8 zweigleisig die Kohle und bei 22 und 23 ebenfalls zweigleisig das Mittel laden.According to the invention are now between the upper leg of the U-shaped Lower part q. and its lower leg. the two free corners around a horizontal one Axis four-pivotable stems 15, 16 arranged. One of these two stems is standing always in the support position while the other is swiveled out. In Fig 2 is the stem 15 in the support position and thereby enlarges the supported circular section of the slewing ring 5 considerably, for. B. over an angle of about 2q.0 °. The stems can be arranged as square or round bars in the corner of the platform, but they can also form large corner angles in both side walls protrude into the platform of the lower part. Are they, as shown in Fig. 2, in the wall facing the discharge boom 6 made wide, then protect them the vertical frame of the lower part is effective against twisting. An essential one There is no restriction in the work of the excavator, since the loading of the truck can be done in positions I7 and I8 of the discharge boom and the slightly above the central position I9 is sufficient for dropping with the largest projection. By the handle 15 swiveled into the support position is also part of the slewing ring 5, which contains the dot-dashed center of gravity sub-circle 14. The paddle wheel can therefore safely pivot through to position 2o (Fig. 2) and therefore make an incision produce, which is indicated by the dash-dotted line 2I, which is to the drawn line II connects. Since the boom of the discharge conveyor 6 from his The central position according to Fig. I can be swiveled out well over 90 ° up to the position 22, the excavator working in the cut can double-track coal at I7 and I8 and at 22 and 23 also load the agent in two tracks.

Wird in Abb. 2 der Stiel I6 in die Abstützstellung eingeschwenkt und der Stiel I5 aus ihr herausgeschwenkt, dann kann der Bagger in gleicher Weise in entgegengesetzter Richtung arbeiten.If the handle I6 is swiveled into the support position in Fig. 2 and the stick I5 swung out of it, then the excavator can in the same way in work in the opposite direction.

In Abb. 3 ist die Aufhängung. und Ausbildung der Stiele im Unterteil dargestellt. Am freien Ende der oberen Plattform des, Unterteils 4 sind Bolzen 24 angebracht, an denen die Stiele I5, I6 in lotrechter Ebene verschwenkbar aufgehängt sind. Zum Herausschwenken des hier in Abstützstellung gezeichneten Stieles I6 wird die untere Verbindung 25 gelöst und der Stiel in die Lage 26 hochgeschwenkt, in der er durch ein Seil oder einen Halter 27 an einem dafür vorgesehenen Tragarm 28 gehalten wird. Der gegenüberliegende Stiel I5 muß dabei in Abstützstellung sein. Um zu verhindern, daß beide Stiele gleichzeitig angehoben werden, sind sie derart gegeneinander verriegelt, daß der eine Stiel nur dann hochgeschwenkt werden kann, wenn der andere Stiel die Stützstellung einnimmt.In Fig. 3 is the suspension. and formation of the stems in the lower part shown. At the free end of the upper platform of the lower part 4 are bolts 24 attached, on which the stems I5, I6 are suspended pivotably in a vertical plane are. To pivot out the handle I6 drawn here in the support position the lower connection 25 released and the handle pivoted up into position 26, in which it is held by a rope or a holder 27 on a support arm 28 provided for this purpose is held. The opposite handle I5 must be in the support position. In order to prevent both stems from being lifted at the same time, they are like this interlocked against each other so that one handle can only be swung up when the other stem assumes the support position.

Zur Einstellung der richtigen Länge zwischen den Befestigungspunkten 24 und 25 können die Stiele aus zwei gegeneinander verschiebbaren Teilen bestehen, die durch Schraubenbolzen 2g verbunden sind. Soll die Längenänderung bei einem in Stützstellung befindlichen Stiel erfolgen, dann können Spindeln vorgesehen sein., die die Abstützung vornehmen.To set the correct length between the attachment points 24 and 25, the stems can consist of two parts that can be slid against each other, which are connected by bolts 2g. If the change in length for an in Support position located handle take place, then spindles can be provided., who make the support.

Claims (3)

PATENTANSPRÜCHE: I. Schaufelradbagger mit in Form eines liegenden U ausgebildetem Unterteil zur Aufnahme des Seitenschwenklagers des. Abwurfauslegers, dadurch gekennzeichnet, daß am freien Ende des oberen Schenkels des Unterteiles (4) an jeder Ecke desselben ein Stiel (I5 bzw. I6) aufgehängt ist, der je nach Bedarf wechselweise mit dem anderen Stiel (I5 bzw. I6) in die Abstützstellung oder aus dieser heraus verschwenkbar ist. PATENT CLAIMS: I. Bucket wheel excavator with in the form of a lying U-shaped lower part for receiving the side pivot bearing of the discharge boom, characterized in that at the free end of the upper leg of the lower part (4) A handle (I5 or I6) is hung on each corner of the same, which can be used as required alternately with the other support (I5 or I6) in the support position or off this can be pivoted out. 2. Schaufelradbagger nach Anspruch I, dadurch gekennzeichnet, daß die Stiele (I5, I6) derart gegeneinander verriegelt sind, daß der eine Stiel nur dann hochgeschwenkt werden kann, wenn der andere Stiel die Stützstellung einnimmt. 2. Bucket wheel excavator according to claim I, characterized in that that the stems (I5, I6) are locked against one another in such a way that one stem can only be swiveled up when the other handle is in the support position. 3. Schaufelradbagger nach Anspruch i oder 2, dadurch gekennzeichnet, daß die Stiele (15, 16) in ihrer Länge veränderlich sind. In Betracht gezogene Druckschriften: Aufsatz »Schaufelradbagger« in der Zeitschrift »Tonindustrie«, 1926, S.888.3. Bucket wheel excavator according to claim i or 2, characterized in that the stems (15, 16) are variable in length. Publications considered: Article "Bucket wheel excavator" in the magazine "Tonindustrie", 1926, p.888.
DEB14169A 1951-03-14 1951-03-14 Bucket wheel excavator with a lower part in the form of a lying U Expired DE950178C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEB14169A DE950178C (en) 1951-03-14 1951-03-14 Bucket wheel excavator with a lower part in the form of a lying U

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEB14169A DE950178C (en) 1951-03-14 1951-03-14 Bucket wheel excavator with a lower part in the form of a lying U

Publications (1)

Publication Number Publication Date
DE950178C true DE950178C (en) 1956-10-04

Family

ID=6957864

Family Applications (1)

Application Number Title Priority Date Filing Date
DEB14169A Expired DE950178C (en) 1951-03-14 1951-03-14 Bucket wheel excavator with a lower part in the form of a lying U

Country Status (1)

Country Link
DE (1) DE950178C (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Similar Documents

Publication Publication Date Title
DE1219399B (en) Device for picking up and removing bulk goods from a storage location
DE950178C (en) Bucket wheel excavator with a lower part in the form of a lying U
DE600965C (en) Bucket wheel excavator
DE3236572C2 (en)
DE3912215A1 (en) Mobile two-section slope conveyor
DE1484742C3 (en) Bucket wheel boom for a bucket wheel excavator, with a bucket wheel chute and with a conveyor belt
DE1759306A1 (en) Swing loader or excavator
DE605187C (en) Mobile depositing device intended for tipping up and down goods
DE968798C (en) Open pit mine with an excavator, in particular a bucket wheel excavator, and with a loading system
DE2924550A1 (en) DISMANTLING AND DRIVING MACHINE
DE939019C (en) Spreader with a rocker that combines the boom of the discharge conveyor and the counterweight boom
DE4025705A1 (en) Remote-controlled emptying device for containers of loose material - has container pick=ups supported by yokes connected to eccentric joint
DE2743988A1 (en) CHARGER FOR USE IN TUNNELS AND OTHER CONSTRUCTION SITES WITH A LOW HEIGHT
DE727518C (en) Composite excavator
DE755273C (en) Extraction system with several extraction devices arranged one above the other
DE918085C (en) Schraem loader
DE3045002C2 (en) Movable bucket wheel excavator
DE548897C (en) Overburden conveyor
DE1114443B (en) Excavator with a conveyor belt bridge
DE710490C (en) Small excavator with conveyor belt for excavating construction pits, for road construction works and similar earthworks of smaller size
DE752958C (en) Bucket wheel excavator with a swiveling superstructure that supports the longitudinally displaceable, liftable and lowerable bucket wheel boom
DE1009157B (en) Peat excavator
DE2331631C3 (en) Reclaimer
DE1160796B (en) Device for the continuous loading of ships
DE971300C (en) Weaners