Manufacturing process for ducts

Info

Publication number
DE801916C
DE801916C DE1948P0002980 DEP0002980D DE801916C DE 801916 C DE801916 C DE 801916C DE 1948P0002980 DE1948P0002980 DE 1948P0002980 DE P0002980 D DEP0002980 D DE P0002980D DE 801916 C DE801916 C DE 801916C
Authority
DE
Germany
Prior art keywords
concrete
walls
channel
duct
slabs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE1948P0002980
Other languages
German (de)
Inventor
Ludwig Conze
Walther Dipl-Ing Simon
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Zosen Inova Steinmueller GmbH
Original Assignee
L&C Steinmueller GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by L&C Steinmueller GmbH filed Critical L&C Steinmueller GmbH
Priority to DE1948P0002980 priority Critical patent/DE801916C/en
Application granted granted Critical
Publication of DE801916C publication Critical patent/DE801916C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Sewage (AREA)

Description

Leitungskanäle, z. B. solche für Fernheizungen, wurden bisher nach dem Baukastensystem aus Betonklötzen oder unter Verwendung einer Holzverschalung durch Ausgießen der Wände mit Beton hergestellt. Beide Bauarten sind wegen der hohen Kosten für den Transport der schweren Betonklötze oder des benötigten Holzes unrentabel.Ducts, e.g. B. those for district heating, were previously after the modular system made of concrete blocks or using wooden cladding made by pouring the walls with concrete. Both types are because of the high The costs of transporting the heavy concrete blocks or the wood required are unprofitable.

Gemäß dem Verfahren nach der Erfindung werden die Kanalwände und der Boden aus dünnen Beton- oder Eisenbetonplatten so gebildet, daß zwischen diesen Platten und dem Erdreich ein der beabsichtigten Wandstärke entsprechender Raum frei bleibt, der dann mit Beton eingeschlemmt wird.According to the method according to the invention, the channel walls and the Floor made of thin concrete or reinforced concrete slabs so that between them Plates and the ground free a space corresponding to the intended wall thickness remains, which is then swallowed up with concrete.

Auf diese Weise ist es möglich, jeweils längere Strecken des Kanals in einem Arbeitsgang fertigzustellen. Die Platten können mit Aussparungen, Leisten oder Ansätzen versehen sein, um Stützen zu halten oder z. B. auch elektrische Leitungen zu tragen. Für das Auseinanderhalten der Wände @v<ibrend des Baues kann man z. B. in der Länge einstellbare .Rohre benutzen. Ein Vorteil des Verfahrens besteht auch darin, daß die Wände ohne Fugen hergestellt werden können, also wasserdicht sind. Die Deckenplatten können ebenfalls an der 11)aiistelle gegossen werden.In this way it is possible to cover longer stretches of the canal to be completed in one operation. The panels can have recesses, strips or approaches be provided to hold supports or z. B. also electrical cables to wear. For the separation of the walls @v <ibrend of the building you can z. B. Use adjustable length tubes. There is an advantage to the procedure also in the fact that the walls can be made without joints, i.e. watertight are. The ceiling tiles can also be poured at the 11) point of use.

Wenn der Boden, in welchen die Kanäle eitigebettet werden, sehr nachgiebig ist, z. B. aus Sand besteht, dann kann man die geschilderte Bauweise dahin ergänzen, daß man die Innen- und Außenseite der Kanalwandung aus dünnen Betonplatten bildet und dann die Zwischenräume zwischen diesen Platten mit flüssigem Beton ausfüllt. Auch dann wird eine erhebliche Ersparnis an Baukosten erzielt werden.If the soil in which the channels are embedded is very flexible is e.g. B. consists of sand, then you can add to the construction method described, that one forms the inside and outside of the channel wall from thin concrete slabs and then fill the spaces between these slabs with liquid concrete. Even then, a considerable saving in construction costs will be achieved.

In der Zeichnung zeigt Abb. i einen Querschnitt und Abb. 2 eine Draufsicht auf einen nach der Erfindung hergestellten Leitungskanal. Abb.3 zeigt einen Querschnitt durch einen in losem Sand verlegten Leitungskanal.In the drawing, Fig. 1 shows a cross section and Fig. 2 shows a plan view on a duct made according to the invention. Fig.3 shows a cross section through a duct laid in loose sand.

In dem Erdreich wird zunächst der Graben A-B-C-D ausgehoben. Darauf werden die seitlichen Betonplatten 1, 2 und die Bodenplatte 3 eingesetzt. Die Stützen ,4 bestimmen die Dicke des Betonbodens und tragen die Bodenplatte 3. Der Raum 5 zwischen den Betonplatten und dem Erdreich wird mit flüssigem Beton ausgefüllt, welcher erhärtet und sich mit den Betonplatten 1, 2 und 3 zu einem festen Körper verbindet. Auf diese Weise wird ein Leitungskanal von beliebiger Wandstärke hergestellt, ohne daß schwere Betonklötze zusammengebaut werden müssen. Die Ausfüllung des Zwischenraumes zwischen Erdreich und Betonplatten wird gemäß Abb.2 so ausgeführt, daß sich die Stoßstellen 6 zwischen den streckenweise hergestellten Betonwänden 5, nicht mit den Stoßstellen der Platten 1, 2 und 3 treffen, so daß unter allen Umständen ein durchaus wasserdichter Kanal erzeugt wird. Abb. 3 zeigt einen Querschnitt durch einen in Sand verlegten Kanal. Die Platten 1, 2 und 3 werden von den Platten 7, 8 und 9 in gewünschtem Abstand umgeben, und der Zwischenraum io wird mit flüssigem Beton ausgefüllt. Dadurch wird ebenfalls ein Kanal beliebiger Wandstärke erzeugt, welcher von der Art des umgebenden Erdreichs an sich unabhängig ist.First, trench A-B-C-D is dug in the ground. Thereon the lateral concrete slabs 1, 2 and the floor slab 3 are used. The pillars , 4 determine the thickness of the concrete floor and support the floor slab 3. The room 5 between the concrete slabs and the ground is filled with liquid concrete, which hardens and becomes a solid body with the concrete slabs 1, 2 and 3 connects. In this way, a duct of any wall thickness is created, without having to assemble heavy concrete blocks. The filling of the space between the ground and concrete slabs is carried out as shown in Fig Joints 6 between the concrete walls 5 produced in sections, not with meet the joints of plates 1, 2 and 3, so that under all circumstances a a completely watertight channel is created. Fig. 3 shows a cross section through a sewer laid in sand. The plates 1, 2 and 3 are replaced by the plates 7, Surround 8 and 9 at the desired distance, and the space io is filled with liquid Filled in concrete. This also creates a duct of any wall thickness, which is independent of the nature of the surrounding soil.

Ist ein Kanal fertiggestellt, so kann er durch obereAbschlußplatten i i verschlossen und dann mit Erde bedeckt werden. Wie die Abb. i zeigt, können die Wände i und 2, welche an Ort und Stelle gegossen werden, mit Tragnocken 12 für kleinere Leitungen versehen werden, während die Bodenplatte 3 mit Tragstützen 13 versehen werden kann, welche z. B. die Leitungsrohre 14 einer Fernheizleitung tragen. Zum Auseinanderhalten der Wände i und 2 kann man z. B. Stempel i5 benutzen, welche in der Mitte geteilt und mit Rechts- und Linksgewinde versehen, durch eine Überwurfmutter 16 verbunden sind. Der genaue Abstand kann dann durch. Drehen der Mutter 16 leicht eingestellt werden. Man kann auch ineinandergesteckte Rohre benutzen, deren Gesamtlänge durch geeignete Knebel festgehalten wird.When a channel is completed, it can be opened through upper end plates i i sealed and then covered with earth. As Fig. I shows, can the walls i and 2, which are cast in place, with support cams 12 for smaller lines are provided, while the base plate 3 is provided with support supports 13 can be provided which z. B. carry the pipes 14 of a district heating line. To keep the walls i and 2 apart you can, for. B. use stamp i5, which Divided in the middle and provided with right and left-hand threads by a union nut 16 are connected. The exact distance can then go through. Turn the nut 16 easily can be set. You can also use nested tubes, the total length of which is held in place by suitable toggles.

Es ist klar, daß die geschilderte Bauweise es gestattet, jede beliebige Art von Leitungskanälen herzustellen. Insbesondere kann man sich den örtlichen Verhältnissen anpassen und die Kanäle in beliebiger Krümmung ausführen und sie auch in der Höhenlage den Verhältnissen anpassen, da man die Betonplatten ja an Ort und Stelle entsprechend anfertigen kann. Auch kann man die Platten mit den jeweils gewünschten Tragnocken oder Tragleisten ausstatten, so daß jede Nacharbeit für die Unterstützung der Leistungen überflüssig wird.It is clear that the construction described allows any Manufacture type of ducts. In particular one can look at the local conditions adjust and run the channels in any curvature and they also in the altitude Adapt to the circumstances, as you have to put the concrete slabs on the spot accordingly can make. The plates can also be fitted with the desired support cams or equip support strips, so that any rework for the support of the services becomes superfluous.

Claims (2)

PATENTANSPRÜCHE: i. Herstellungsverfahren für Leitungskanäle, dadurch gekennzeichnet, daß in einem Graben (A-B-C-D) aus Betonplatten (1, 2 und 3) ein Kanal eingebaut wird, dessen innere Abmessungen dem gewünschten inneren Kanalprofil entsprechen und dessen Platten (1, 2 und 3) einen der Dicke der gewünschten Kanalwandung entsprechenden Abstand von den Grabenwänden besitzen, worauf der Zwischenraum (5) zwischen den Graben- und Kanalwänden durch flüssigen . Beton ausgefüllt wird. PATENT CLAIMS: i. Manufacturing process for ducts, characterized in that a duct is installed in a trench (ABCD) made of concrete slabs (1, 2 and 3), the internal dimensions of which correspond to the desired internal duct profile and the slabs (1, 2 and 3) of which correspond to the thickness of the Desired channel wall have a corresponding distance from the trench walls, whereupon the gap (5) between the trench and channel walls by liquid. Concrete is filled. 2. Verfahren nach Anspruch i, zur Herstellung eines Leitungskanals in sandigem Boden, dadurch gekennzeichnet, daß die äußeren Flächen des Kanals durch Betonplatten (7, 8 und gebildet werden und der Zwischenraum (io) zwischen diesen und den die Innenwände des Kanals bildenden Platten (1, 2, 3) durch flüssigen Beton ausgefüllt wird.2. Method according to claim i, for the production of a duct in sandy soil, characterized in that the outer surfaces of the channel are covered by concrete slabs (7, 8 and are formed and the space (io) between these and the inner walls of the channel forming plates (1, 2, 3) is filled with liquid concrete.
DE1948P0002980 1948-10-02 1948-10-02 Manufacturing process for ducts Expired DE801916C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE1948P0002980 DE801916C (en) 1948-10-02 1948-10-02 Manufacturing process for ducts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE1948P0002980 DE801916C (en) 1948-10-02 1948-10-02 Manufacturing process for ducts

Publications (1)

Publication Number Publication Date
DE801916C true DE801916C (en) 1951-01-25

Family

ID=577826

Family Applications (1)

Application Number Title Priority Date Filing Date
DE1948P0002980 Expired DE801916C (en) 1948-10-02 1948-10-02 Manufacturing process for ducts

Country Status (1)

Country Link
DE (1) DE801916C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2522779A1 (en) * 1982-03-05 1983-09-09 Markovic Marc Pipeline installation for cold countries - utilises concrete housing provided with heating mechanisms

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2522779A1 (en) * 1982-03-05 1983-09-09 Markovic Marc Pipeline installation for cold countries - utilises concrete housing provided with heating mechanisms

Similar Documents

Publication Publication Date Title
DE3016963A1 (en) INSERT BLOCK FOR BUILDING WALLS AND METHOD FOR CONSTRUCTING BUILDINGS USING SUCH BLOCKS
DE2438890A1 (en) PREFABRICATED ELEMENTS FOR PARTITION WALLS AND MASONRY AND WALLS AND WALLS BUILT WITH SUCH ELEMENTS
DE2425335A1 (en) PREFABRICATED TRANSPORTABLE ROOM ELEMENT FOR ERECTING BUILDINGS
EP0751262B1 (en) Wall element for rising structures and method of manufacturing the same
DE801916C (en) Manufacturing process for ducts
DE2514063A1 (en) PRE-FABRICATED PANEL AND METHOD FOR MANUFACTURING WALLS USING THESE PRE-FABRICATED COMPONENTS
DE2422586A1 (en) Underground or sunken wall prefabricated concrete component - comprises integral panel and ribs at equal intervals
DE1609454A1 (en) Processes and components for the construction of buildings from prefabricated, large-format panels
DE2145817A1 (en) CABLE SHAFT FOR THE TRACK AREA OF RAILWAY SYSTEMS MADE FROM PREFABRICATED CONCRETE PARTS
DE10103470A1 (en) Formwork element and base plate of a building made with it
DE3218516C2 (en)
DE8031457U1 (en) FILLER BODY FOR THERMAL INSULATING BUILDING CEILINGS
DE102017114619A1 (en) Prefabricated wall element
DE202017007193U1 (en) Prefabricated wall element
WO2001096671A1 (en) Boarding element and flooring of a building produced therewith
EP0063616B1 (en) Tubing made of cast-in-situ concrete, and method for its production
DE821538C (en) Process for pouring or ramming masonry with permanent formwork and shaped stone for this purpose
DE2817874A1 (en) VACUUM SLAB CEILING MADE FROM PREFABRICATED REINFORCED CONCRETE OR PRECAST PRECAST REINFORCED CONCRETE ELEMENTS
AT300681B (en) Channel or the like. from prefabricated parts that can be assembled at the installation site
DE2246394C3 (en) Method for producing a formwork for concrete or reinforced concrete components
AT319544B (en) Prefabricated strips, preferably for ceilings and methods for producing a prefabricated strip
DE1609701C (en) Reinforced concrete beams
DE931319C (en) Process for the production of an insulating, double-shell wall or wall
AT267146B (en) Multipurpose building block and masonry from such building blocks
DE10039038A1 (en) Method for producing a wall element, in particular, a load-carrying wall element consists of positioning two fiber concrete plate elements on a base and filling the space between them with concrete