DE3524747A1 DE19853524747 DE3524747A DE3524747A1 DE 3524747 A1 DE3524747 A1 DE 3524747A1 DE 19853524747 DE19853524747 DE 19853524747 DE 3524747 A DE3524747 A DE 3524747A DE 3524747 A1 DE3524747 A1 DE 3524747A1
Authority
DE
Germany
Prior art keywords
purpose container
container ship
ship
ship according
designed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19853524747
Other languages
German (de)
Inventor
Volker Ing Grad Geschkowski
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Blohm and Voss GmbH
Original Assignee
Blohm and Voss GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Blohm and Voss GmbH filed Critical Blohm and Voss GmbH
Priority to DE19853524747 priority Critical patent/DE3524747A1/en
Publication of DE3524747A1 publication Critical patent/DE3524747A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B25/00Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
    • B63B25/002Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for goods other than bulk goods
    • B63B25/004Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for goods other than bulk goods for containers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B25/00Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
    • B63B25/02Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Ship Loading And Unloading (AREA)

Abstract

A multi-purpose container ship with three hatchways arranged next to one another is characterised in that, in the case of a ship size of PAN MAX dimensions, side tanks (B) are arranged on both sides of the centre cargo space provided as a bulk space, and the outer walls of the ship are of open construction. <IMAGE>

Description

Die Erfindung betrifft ein Mehrzweck-Containerschiff, d. h. einen kombinierten Schiffstyp, der weltweit einsetzbar ist und eine Kombination zwischen Bulk-Carriern und reinem Con­ tainerschiff darstellt.The invention relates to a multi-purpose container ship, i. H. a combined type of ship that can be used worldwide and a combination between bulk carriers and pure con represents tainer ship.

Der Erfindung liegt die Aufgabe zugrunde, mit einem solchen Schiff eine bessere wirtschaftliche Ausnutzung zu erzielen. Die Lösung dieses Problems ist in den Ansprüchen beschrieben. Ein Beispiel eines erfindungsgemäßen Mehrzweck-Containerschif­ fes ist zeichnerisch in Fig. I-III dargestellt und zeigt inThe invention has for its object to achieve better economic exploitation with such a ship. The solution to this problem is described in the claims. An example of a multipurpose container ship according to the invention is shown graphically in FIGS. I-III and shows in

Fig. I einen Querschnitt, in Fig. I a cross section, in

Fig. II eine Draufsicht und in Fig. II is a plan view and in

Fig. III eine Beispiel für massive Führungselemente für die Container. Fig. III an example of massive guide elements for the containers.

Die in Fig. I-III eingeschriebenen Abmessungen sind als Ver­ hältniswerte anzusehen.The dimensions inscribed in Fig. I-III are to be regarded as ratio values.

Wie Fig. I gut erkennen läßt, sind gemäß der Erfindung die üb­ licherweise bei Containerschiffen außen angeordnten Seiten­ tanks nach innen, seitlich des mittleren Laderaums, des eigent­ lichen Bulkraums angeordnet.As can be clearly seen in FIG. I, according to the invention, the tanks arranged on the outside, in the case of container ships, are arranged on the inside, on the side of the central cargo space, of the bulk space itself.

Die Außenwände können als offene Konstruktion vorgesehen werden, eventuell mit oben liegendem "Box-Girder" (B-G). Der Betriebs­ gang (Be-Ga) könnte über den mittleren Längstank angeordnet werden.The outer walls can be provided as an open construction, possibly with a box girder (BG) on top. The operating aisle (Be-Ga) could be arranged over the middle longitudinal tank.

Die Haupthorizontalträger für die Containerfüllung sollten in jeder zweiten Containerebene angeordnet werden, um dort die ho­ rizontalen Kräfte aus der Containerladung einzuleiten. Die seit­ lichen Laderäume werden wie normale Containerladeräume ausgeführt, eventuell mit Mittelrahmen für 20′-Container. In dem mittleren Laderaum, dem Bulkraum werden massive Führungselemente vorgese­ hen, wie sie Fig. III zeigt.The main horizontal girders for container filling should be arranged in every second container level in order to introduce the horizontal forces from the container load. The loading spaces since are carried out like normal container holds, possibly with a central frame for 20'-containers. In the middle loading space, the bulk space, massive guide elements are provided, as shown in FIG. III.

Es wird davon ausgegangen, daß genügend massive, fest einge­ baute Führungselemente von den Greifern beim Be- und Entladen von Erz nicht beschädigt werden. Andererseits könnte auch ganz auf Führungselemente verzichtet werden, wenn die im Bulkraum ge­ fahrenen Container mit herkömmlichen, losen Baustücken gegen unkontrollierte Bewegung während der Fahrt gesichert würden. Leider ist dieser Ladevorgang sehr zeitaufwendig.It is believed that enough massive, solid built guiding elements from the grippers during loading and unloading not be damaged by ore. On the other hand, it could be quite  no guide elements if the ge in the bulk room used container with conventional, loose construction pieces uncontrolled movement would be secured while driving. Unfortunately, this loading process is very time consuming.

Die Skizze II zeigt eine Draufsicht mit den erforderlichen Laderaumbreiten und den sich daraus ergebenden Breiten der Längstanks und Seitenversteifungen in der Außenhaut.Sketch II shows a top view with the required ones Loading widths and the resulting widths of the Longitudinal tanks and side stiffeners in the outer skin.

Fig. III zeigt ein fest mit der Laderaumwand verbundenes Füh­ rungselement in der Form eines "U" mit abgeschrägten Schenkeln und darin angeordneten Stegblechen, die mit den U-Schenkeln nicht verschweißt, sondern nur in jeder zweiten Lage durch die Schenkel durchgesteckt und in jedem Fall nur mit der Laderaum­ wandung und dem U-Grundprofil verschweißt werden, an dem außen das eigentliche Führungsprofil (120 x 120) vorgesehen ist. Fig. III shows a fixed to the load compartment Füh guiding element in the form of a "U" with beveled legs and web plates arranged therein, which are not welded to the U-legs, but only inserted in every second position through the legs and in any case only be welded to the load compartment wall and the U base profile, on which the actual guide profile (120 x 120) is provided on the outside.

Claims (5)

1. Mehrzweck-Containerschiff mit drei nebeneinander angeordne­ ten Luken, dadurch gekennzeichnet, daß bei einer Schiffsgröße in PAN-MAX-Abmessungen zu beiden Seiten des als Bulkraum vorge­ sehenen mittleren Laderaums Seitentanks (B) angeordnet und die Schiffsaußenwände in offener Konstruktion ausgeführt sind.1. Multi-purpose container ship with three side-by-side hatches, characterized in that with a ship size in PAN-MAX dimensions, side tanks (B) are arranged on both sides of the middle cargo space provided as bulk space and the outer walls of the ship are designed in an open construction. 2. Mehrzweck-Containerschiff nach Anspruch 1, dadurch gekenn­ zeichnet, daß in dem mittleren, als Bulkraum ausgebildeten Raum, massive in geschlossener Bauweise ausgebildete Führungs­ winkel für die Stauung von 40′-Containern vorgesehen sind. (Fig. III)2. Multi-purpose container ship according to claim 1, characterized in that in the middle, designed as a bulk space, massive, trained in a closed construction guide angle are provided for the stowage of 40'-containers. ( Fig. III) 3. Mehrzweck-Containerschiff nach Anspruch 1 oder 2, dadurch ge­ kennzeichnet, daß eine horizontale Abstützung der Container in jeder zweiten Containerebene erfolgt.3. Multi-purpose container ship according to claim 1 or 2, characterized ge indicates that a horizontal support of the container in every second container level. 4. Mehrzweck-Containerschiff nach einem der Ansprüche 1-3, dadurch gekennzeichnet, daß die mittlere Luke durch ein Hub- und Rolldeckelsystem verschlossen wird, das längsverfahrbar an­ geordnet ist.4. Multi-purpose container ship according to one of claims 1-3, characterized in that the middle hatch by a lifting and roller cover system is closed, the longitudinally movable is ordered. 5. Mehrzweck-Containerschiff nach Anspruch 4, dadurch gekenn­ zeichnet, daß das Lukendeckelsystem der mittleren Luke gleich­ zeitig als von bordnehmbares Pontondeckelsystem ausgebildet ist.5. Multi-purpose container ship according to claim 4, characterized records that the hatch cover system is the same as the middle hatch is designed as a pontoon lid system that can be taken on board.
DE19853524747 1985-07-11 1985-07-11 Multi-purpose container ship Withdrawn DE3524747A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19853524747 DE3524747A1 (en) 1985-07-11 1985-07-11 Multi-purpose container ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19853524747 DE3524747A1 (en) 1985-07-11 1985-07-11 Multi-purpose container ship

Publications (1)

Publication Number Publication Date
DE3524747A1 true DE3524747A1 (en) 1987-01-15

Family

ID=6275482

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19853524747 Withdrawn DE3524747A1 (en) 1985-07-11 1985-07-11 Multi-purpose container ship

Country Status (1)

Country Link
DE (1) DE3524747A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018099906A1 (en) * 2016-11-29 2018-06-07 Maersk Line A/S Container ship with reinforced hull

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018099906A1 (en) * 2016-11-29 2018-06-07 Maersk Line A/S Container ship with reinforced hull

Similar Documents

Publication Publication Date Title
EP2581301B1 (en) Containers stowage device
DE1295396C2 (en) Cargo ship for the transport of barges
DE602004003795T2 (en) cargo ship
DE3524747A1 (en) Multi-purpose container ship
DE69012120T2 (en) CONTAINER SHIP.
EP0057361B1 (en) Insert element for fastening containers
EP2093143A1 (en) Service vessel
DE2410478A1 (en) CONTAINER AND / OR GENERAL FREIGHT SHIP
EP0384237B1 (en) Vessel&#39;s hull, especially for a container ship
DE4333083C2 (en) Cargo ship, especially a refrigerated ship with palletized cargo
DE4022504C2 (en)
DE3423461C1 (en) Freighter with a cargo hatch
DE1756863A1 (en) Hatch cover for container ships
DE2542756C3 (en) Board crane for container ships
DE970279C (en) Cargo ship
DE1816487C3 (en) Open-type container ship
DE6609332U (en) CARGO STORAGE DEVICE FOR CONTAINER SHIPS
DE2512379C3 (en) Container Ship
DE2519523C3 (en) Ship door combined cargo
DE1816487B2 (en) Open type container ship - with container stacks replaced with open profile boxes to carry bulk cargo
DE7530368U (en) SHIP WITH A PILLAR FOR HOLDING AN ON-BOARD CHARGER
DE4224193A1 (en) Freighter with cargo containers - with large mobile containers, which completely fill hatch-ways and project above weather deck
DE2945978B1 (en) Slidable deck house for ships
DE1531644C (en) Bracket for detachable bulkheads on a container ship
DE2131119A1 (en) CARGO SHIP

Legal Events

Date Code Title Description
8139 Disposal/non-payment of the annual fee