DE3214033A1 - Method of installing pipe structures underground and apparatus for carrying out the method - Google Patents

Method of installing pipe structures underground and apparatus for carrying out the method

Info

Publication number
DE3214033A1
DE3214033A1 DE19823214033 DE3214033A DE3214033A1 DE 3214033 A1 DE3214033 A1 DE 3214033A1 DE 19823214033 DE19823214033 DE 19823214033 DE 3214033 A DE3214033 A DE 3214033A DE 3214033 A1 DE3214033 A1 DE 3214033A1
Authority
DE
Germany
Prior art keywords
auxiliary pipe
pipe
auxiliary
cross
structures
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE19823214033
Other languages
German (de)
Other versions
DE3214033C2 (en
Inventor
Des Erfinders Auf Nennung Verzicht
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wayss and Freytag AG
Original Assignee
Wayss and Freytag AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wayss and Freytag AG filed Critical Wayss and Freytag AG
Priority to DE19823214033 priority Critical patent/DE3214033C2/en
Publication of DE3214033A1 publication Critical patent/DE3214033A1/en
Application granted granted Critical
Publication of DE3214033C2 publication Critical patent/DE3214033C2/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Abstract

In the production of pipe structures of small diameter in a closed type of construction which are no longer accessible through walking or crawling, accurate control and the removal of obstacles present problems. The method according to the invention provides for pipe structures of this type to be installed by driving an auxiliary pipe. An auxiliary pipe (1) having a cross-section accessible at least through crawling is driven from a starting shaft (2) to the next shaft (4), the clear cross-section (5) of the auxiliary pipe enclosing all cross-sections (6, 7) of the final pipe structures. After the target shaft (4) is reached, the final pipe structures (6, 7) are installed in their desired position inside the auxiliary pipe (1). The auxiliary pipe (1) can then be pulled back into the starting shaft (2) and recovered. <IMAGE>

Description

32U03332U033

Verfahren zum unterirdischen Einbau von Rohrbauwerken und Vorrichtungen zur Durchführung des Verfahrens Method for the underground installation of pipe structures and devices for carrying out the method

Die Erfindung betrifft ein Verfahren zum unterirdischen Einbau von Rohrbauwerkeii - Tunneln oder Leitungen mit kleinen, vornehmlich nicht mehr bekriechbaren Querschnitten.The invention relates to a method for underground Installation of Rohrbauwerkeii - tunnels or lines with small, mainly no longer creepable cross-sections.

In zunehmendem Maße -wird es erforderlich, Hohrbauwerke kleinen Durchmessers in geschlossener Bau-weise herzustellen. Bei der Herstellung-derartiger Kleintunnel in Durchmessern, die nicht mehr begehbar oder bekriechbar sind, stellen' die exakte Steuerung und die Beseitigung von Hindernissen Probleme dar. Insbesondere das Auftreffen des Bohrkopfes auf Hindernisse-führt häufig dazu, daß diese Hindernisse durch Grabung von der Erd- ·; Ό c-r fläche Ia<?r Tr^i^olsgt und oesoi';::-.;^ΐ vdD~* claij :-r.a Tunnel aufgegeben werden müssen. Ss ist auch bekannt, Rohrleitungen mit nicht begehbaren Durchmessern in einem zuvor hergestellten größeren Tunnel zu verlegen. Der Nachteil dieser Lösung ist der große bleibende Raumbedarf im Erdreich. "Weiterhin ist bekannt, daß zur Herstellung von Rohrbauwerken mit nicht begehbaren Durch-Increasingly, it is necessary to build small diameter ceilings in a closed construction. In the production of such small tunnels in diameters that can no longer be walked on or crawled over, the exact control and the removal of obstacles pose problems - ·; ? Ό cr surface Ia <r Tr ^ i ^ olsgt and oesoi ';:: -;. ^ Ϊ́ VDD ~ * claij: ra tunnel must be abandoned. It is also known to lay pipelines with inaccessible diameters in a previously created larger tunnel. The disadvantage of this solution is the large amount of space that remains in the ground. "It is also known that for the production of pipe structures with non-accessible through-

•-0 messern zimächst eine Pilotbohrung in der späteren Tunnel achse durchgeführt; wurde Lind in einem zweiüsn Schritt das Rohr dos Endausbaus mit Hilfe des Bohrgestänges oder einer anderweitigen Zugvorrichtung bei gleichzeitiger Verwendung eines Erweiterungsbohrkopfes eingezo-• -0 knives a pilot hole in the later tunnel axis carried out; Lind became in a two-step step the pipe dos final expansion with the help of the drill rod or some other pulling device at the same time Use of an extension drilling head retracted

'-5 gen wurde. Dio Nachteile dieses Verfahrens liegen da.rin,'-5 gen. The disadvantages of this method are there.

on PY BAD ORIGINALon PY BAD ORIGINAL

• 32U033• 32U033

daß das iiolir beir. Dinzielion hoch belastet wxi-d Lind trotzdem ein satter An.sch.lui3 an das Erdreich nicht gewährleistet irerden kann. .that the iiolir beir. Dinzielion highly charged wxi-d Lind Nevertheless, a full An.sch.lui3 on the ground is not guaranteed can earth. .

Aufgabe der Erfindung war es, ein Verfahren zu entwickeln, das es auf wirtschaftliche "Weise gestattet, Rohrbauwerke mit kleinen, vornehmlich mit nicht mehr" bekriech.ba.rem Querschnitt, einzeln oder in Bündeln unterirdisch herzustellen und dazu für die im Boden verbleibenden Rohre "Werkstoffe mit bestimmten ausge-The object of the invention was to develop a method that allows in an economical "way, Pipe structures with small, primarily with no more " kriech.ba.rem cross-section, singly or in bundles underground and for this purpose, for the pipes remaining in the ground, "materials with certain specific

- j- j

wählten Eigenschaften - z.3, Kunststoffrohre mit Beständigkeit gegen Korrosionsangriff von innen und_außen verwenden zu können, die zwar gegen die Beanspruchungen des Gebrauchszustands eine optimale Eignung besitzen, den Belastungen beim Einsatz in einem üblichen Vortriebsverfahren jedoch nicht gewachsen waren.chose properties - e.g. 3, plastic pipes with durability use against corrosion attack from inside and outside to be able to, although they have an optimal suitability against the stresses of the state of use, the loads when used in a conventional tunneling method but had not grown.

Die Aufgabe wird durch das im kennzeichnenden Teil des Anspruchs 1 beschriebene Verfahren gelöst.The task is carried out by the in the identifying part of the Claim 1 described method solved.

Das erfindungsgemäße Verfahren erlaubt es, Leitungen mit beliebigem Durchmesser und beliebiger Querschnittsform und mit dem der gegebenen Beanspruchung angepaßten "Werkstoff in geschlossener Bauweise in den Untergrund zu bringen. Das Verfahren ist wirtschaftlich, da das Hohr für den Ausbau des Hilfsvortriebs wieder gewinnbar und durch die- Möglichkeit der freien !-fahl <3es zweckmäßigen Durclunessers für das Hilfsrohr für wiederholten Einsatz verwendbar ist. Durch den Rückbau desThe method according to the invention allows pipes with any diameter and any cross-sectional shape and with the material adapted to the given load to be brought into the subsoil in a closed construction. Possibility of free! -Fahl <3 it is expedient Durclunessers for the auxiliary pipe for repeated use

copycopy

Hilfsrohrs wird im Straßenraura nur dez" unbedingt notwendige Platz für die !(ohrbauwerke beansprucht.Auxiliary pipe is only dec "absolutely necessary in the street raucation Space for the! (Ear structures claimed.

Das bekriechbare Hilfsrohr ermöglicht, notfalls manuell Hindernisse vor Ort zu beseitigen, Reparaturen am Schneidkopf und Manipulationen zur Steuerung durchzuführen. The crawlable auxiliary pipe allows, if necessary, manually To remove obstacles on site, to carry out repairs to the cutting head and manipulations to the control.

Zweckmäßige Ausgestaltungen der Erfindung sind in den Unteransprüclien beschrieben. Durch die darin beschriebene gezielte Auswahl und Behandlung des Füllmateriais kann die Dichte,, der Korrosiunsschutz und d:Le Belastbarkeit der endgültigen JRohrbauwerke verbessert werden.Appropriate refinements of the invention are shown in Described subclaims. Through the described therein Targeted selection and treatment of the filling material can be the density, the corrosion protection and the load capacity of the final I pipe structures are improved.

Das erfindungsgemäße Verfahren wird durch die Figuren und 2 erläutert.The method according to the invention is illustrated by the figures and 2 explained.

Es zeigenShow it

xai c c xai cc

α arc Ii omen /oi-cri s esa bscimi υ mit Hilfsrohr z-.-ischen zwei Kontrollfchächton, und zwar zu einen Zeitpunkt während c es Zurückzichens des Ililfsrohrs,α arc Ii omen / oi-cri s esa bscimi υ with auxiliary pipe z -.- ischen two control shafts, namely at a point in time during the drawing back of the auxiliary pipe,

Fig. 2 den zugehörigen Querschnitt durch, das Hilfsrohr unmittelbar vor dorn Verschlußdeckel.Fig. 2 shows the associated cross section through the auxiliary tube immediately in front of the mandrel closure cover.

Der Vortrieb des Hilfsrohrs 1 ist vom Startschacht 2 über dio Vortrir-bss crcc'co 3 nach dem Ziel schach.- 4 erfolgt. Der lieh'; ο Cuoi'sclmit b 5 des Hilfsrohrs umschließt i:n dargestellten Beispiel zwei endgültig© liohr bauwprke 6,7. Das Hilfsrohr ist an seinem Erde durchThe propulsion of the auxiliary pipe 1 was carried out from the starting shaft 2 via dio Vortrir-bss crcc'co 3 to the target schach.- 4. Who lent '; ο Cuoi'sclmit b 5 of the auxiliary pipe encloses in the example shown two final © liohr bauwprke 6,7. The auxiliary pipe is through to its ground

BAD ORIGINALBATH ORIGINAL

den Deckelverschluß 8 verschlossen. Der Declcelverschluß weist Durchgänge 9 auf, die im Beispiel mit Stopfbüchsen gedichtet sind und durch dia die Rohrbauwerke 6,7 beim Zurückziehen gleiten. Die Durchstoßöffnung des Hilfsrohrs 1 im Zielschacht h ist durch den Verschluß 10 dicht verschlossen, der ebenfalls mit abgedichteten Durchführungen 11 für die liohre 6,7 versehen ist. Der beim Rückbau des Hilfsrohrs 1 entstehende Hohlraum 12 wird durch die Verpreßleitung 13 kontinuierlich mit Füllmaterial verpreßt.the lid lock 8 closed. The Declcelverschluß has passages 9, which are sealed in the example with stuffing boxes and slide through which the pipe structures 6.7 when retracting. The penetration opening of the auxiliary pipe 1 in the target shaft h is tightly closed by the closure 10, which is also provided with sealed ducts 11 for the liohre 6,7. The cavity 12 created when the auxiliary pipe 1 is dismantled is continuously pressed with filler material through the press line 13.

BAD ORIGINALBATH ORIGINAL

LeerseiteBlank page

Claims (1)

PatentansprücheClaims 1. Verfahren zum unterirdischen Einbau von Sohrbauwerken - Tunneln oder Leitungen - mit kleinen, vornehmlich nicht mehr bekriechbaren Querschnitten, gekennzeichnet durch folgende Einzelschritte: 1. Procedure for the underground installation of sohr structures - Tunnels or lines - with small, mainly no longer creepable cross-sections, characterized by the following individual steps: 1. Ein Hilfsrolir (-1 ) , vornehmlich ein Stahlrohr, mit mindestens bekriechbarem Querschnitt wird aus einem Startschacht (2) heraus auf die Länge eines, üblichen Kontrollabschnitts (3) (in der Regel ca. 6o m) zum nachten Schacht ('[-) nach einer der bekannten--Me-tho den vorgetrieben, wobei die Vortriebsachse so gewählt ist, daß der lichte Querschnitt (5) des rlilfsrohrs alle Querschnitte (6, 7) der endgültigen Rohrbauwerke umschließt. 1. An auxiliary roller blind (-1), primarily a steel tube, with at least a crawlable cross-section is from a starting shaft (2) out to the length of a normal Control section (3) (usually approx. 6o m) to the night shaft ('[-) according to one of the well-known methods driven forward, wherein the propulsion axis is chosen so that the clear cross section (5) of the auxiliary pipe all Enclosing cross-sections (6, 7) of the final pipe structures. 2. Mach dem Durchfahren des Streckenabschnitts (3) wird im Zielschacht (k) der Schneidkopf des Hilfsrohrvortriebs entfernt, werden die endgültigen itohrbauwerke (6, 7) in ihrer Sollage innerhalb des Hilfsrohrs (1) eingebaut und wird das Hilfsrohr (1) mit einem Verschlußdeckel (S) versehen, der Durchgänge (9) enthält, in denen die endgültigen Sohrbauwerke dicht und gleitend gehalten sind, Hach dem Zurückziehen des Hilfsrohrs (1) um ein geringes Maß aus dem Zielschacht {k) erhält der Zielschacht (k) an der1 Durchstoßöffnung des Hilfsrohrs (i) ebenfalls einen dichten Verschluß ( Iu), γ!ργ ei ich';'.: Durch l'iili..run; n;on ( I l) Γα." die Kuhrbuu-■werke ( 6 , 7 ) auf ve i s t.2. After driving through the route section (3) the cutting head of the auxiliary pipe jacking is removed in the target shaft (k) , the final itohr structures (6, 7) are installed in their intended position within the auxiliary pipe (1) and the auxiliary pipe (1) is fitted with a the cap (S) which includes said passages (9) in which tightly the final Sohrbauwerke and are slidably held, Hach retracting the auxiliary pipe (1) by a small amount from the target shaft {k) is the target shaft (k) at the 1 opening of the auxiliary pipe (i) also a tight seal (Iu), γ! Ργ ei i ';' .: Through l'iili..run ; n ; on (I l) Γα. "the Kuhrbuu- ■ works (6, 7) on ve is t. BADBATH 32H03332H033 3. Das Hilfsrohr (1) wird an den sndgültigen Iiohrbauwerken entlang gleitend in den S^arrschacht (,?) zurückgezogen, dort wiedergewonnsn und abgebaut.3. The auxiliary pipe (1) is attached to the final Iiohrbauwerken sliding along into the S ^ arrschacht (,?) withdrawn, regained there and dismantled. 'l·. Der vom Hilfsrohr ( l) beim Zurückbauen freigegebene unterirdische Hohlraum (12) wird durch eine 7erpreßleitung 03) kontinuierlich mit; geeignetem Füllmaterial verpreßt.'l ·. The one released by the auxiliary pipe (l) when dismantling underground cavity (12) is through a 7erpreßleitung 03) continuously with; suitable Filling material pressed. 2. Verfahren nach Anspruch 1 , dadurch ^e kenn zeichnet, daß Sohrbauwerke (6,7) beliebiger Querschni-ctsform verwendbar sind.2. The method according to claim 1, characterized ^ e kenn draws that Sohrbauwerke (6,7) of any cross-sectional shape are usable. 3. Verfahren nach Ansprüchen 1,2, dadurch gekennzeichnet, daß dem Füllmaterial des Hohlraums (12) zwischen den Rohrbauwerken (6,7) und dem Erdreich ein Korrosionsschutzmittel zugesetzt wird, das dio Au:?.onkorrosioa :.ui dem oder den Prrvhik-robLr^n verhindert.3. The method according to claims 1, 2, characterized in that that the filling material of the cavity (12) between the pipe structures (6,7) and the An anti-corrosion agent is added to the ground, das dio Au:?. onkorrosioa: .ui dem or den Prrvhik-robLr ^ n prevented. '+. Verfahren nach Ansprüchen 1, 2, d a d u r e h ,^' ο kennzeichne t, daß dem Füllmaterial! des Hohlraums (12) zwischen den Produktrohren und dc2m Erdreich ein Dichtungsmittel zugesetzt wird.'+. Method according to claims 1, 2, d a d u r e h, ^ 'ο characterize t that filler material! of the cavity (12) between the product pipes and dc2m soil a sealant is added. 5. Verfahren nach Ansprüchen 1,2, dadurch gekennzeichnet, daß dem Füllmaterial des Hohlraums (12) Zement oder Chemikalien zugesetzt werden, die eine Verfestigung bewirken.5. The method according to claims 1, 2, characterized in that that cement or chemicals are added to the filling material of the cavity (12), which cause a solidification. 6. Verfahren nach Ansprüchen 1 bis 5, dadurch ge kennzeichne t, daß bei ausreichender Tiefen-6. The method according to claims 1 to 5, characterized ge indicate that with sufficient depth BAD ORIGINALBATH ORIGINAL lage des Bauwerks der VerproiMruck für das Füllmaterial so hoch gewählt wird, daß die für das Rückziehen des Hüfsrohrs (i) erforderliche Kraft ganz oder mindestens teilweise durch, den Druck auf den Verschlußdeckel (8) beim Einpumpen des Verpreßgutes erzeugt wird.location of the structure of the VerproiMruck for the filling material is chosen so high that the retraction of the auxiliary tube (i) all or at least part of the force required through, the pressure on the cap (8) is generated when pumping in the grout. 7. Stahlrohr für den Hilfsrohrvortriet» zur Durchführung des Verfahrens'nach Anspruch 1, dadurch g· e kennz e i chne t, daß die Verbindungen der Stahlrohre untereinander im wesentlichen als druckfeste Verbindungen ausgebildet sind und für das Zurückziehen des Hilfsrohrs (1) ein separates Zugglied verwendet wird.7. Steel pipe for the auxiliary pipe lead »for implementation of the method according to claim 1, characterized in that E i chne t that the connections between the steel pipes are essentially pressure-resistant Connections are formed and a separate tension member is used for the retraction of the auxiliary pipe (1) will. 8. Stahlrohr nach Anspruch 7? dadurch gekennzeichnet, daß anstelle eines geschlossenen Stahlrohrs aus mindestens zwei Segmenten zusammengesetzte Hohre8. Steel pipe according to claim 7? characterized, that instead of a closed steel tube composed of at least two segments tube fiur r; Ii 1 '■"'.'niQnco·; verton, as-ron ri'Hmeoeneii'ai'J Aciise aea .1HS3-rohrs (1) verlaufen un-cl die miteinander durch geeignete Verbindungen, beispielsweise Verschraubungen oder Gelenice, zusammengefügt sind.for r; Ii 1 '■ "'. 'NiQnco ·; verton, as-ron ri'Hmeoeneii'ai'J Aciise aea .1HS3- pipes (1) run and are joined together by suitable connections, for example screw connections or gels.
DE19823214033 1982-04-16 1982-04-16 Process for the underground installation of pipe structures Expired DE3214033C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19823214033 DE3214033C2 (en) 1982-04-16 1982-04-16 Process for the underground installation of pipe structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19823214033 DE3214033C2 (en) 1982-04-16 1982-04-16 Process for the underground installation of pipe structures

Publications (2)

Publication Number Publication Date
DE3214033A1 true DE3214033A1 (en) 1983-10-27
DE3214033C2 DE3214033C2 (en) 1985-05-23

Family

ID=6161063

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19823214033 Expired DE3214033C2 (en) 1982-04-16 1982-04-16 Process for the underground installation of pipe structures

Country Status (1)

Country Link
DE (1) DE3214033C2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3340256A1 (en) * 1983-11-08 1985-05-23 Krings, Josef, 5138 Heinsberg Method and device for producing concrete pipes in an earth bore hole
DE3412198A1 (en) * 1984-04-02 1985-10-10 Witte Bohrtechnik GmbH, 3060 Stadthagen METHOD AND DEVICE FOR THE CONTROLLED UNDERGROUND DRIVING OF TUBES IN THE UNMATCHABLE DIAMETER AREA

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19919171C1 (en) * 1999-04-28 2000-08-24 Hauff Technik Gmbh & Co Kg Wall passage making process, involving using driving tube as protective tube passing through ground region into core boring

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2537365B1 (en) * 1975-08-22 1977-01-13 Baumann & Burmeister Kg Hydraulic method pipeline laying - which consists of sections mounted at various angles to one another

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2537365B1 (en) * 1975-08-22 1977-01-13 Baumann & Burmeister Kg Hydraulic method pipeline laying - which consists of sections mounted at various angles to one another

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"ETR-Eisenbahntechnische Rundschau", Bd. 22, 12, 1973, S. 508/511 *
"Wayss & Freitag, Technische Blätter", 1, 1965 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3340256A1 (en) * 1983-11-08 1985-05-23 Krings, Josef, 5138 Heinsberg Method and device for producing concrete pipes in an earth bore hole
DE3412198A1 (en) * 1984-04-02 1985-10-10 Witte Bohrtechnik GmbH, 3060 Stadthagen METHOD AND DEVICE FOR THE CONTROLLED UNDERGROUND DRIVING OF TUBES IN THE UNMATCHABLE DIAMETER AREA

Also Published As

Publication number Publication date
DE3214033C2 (en) 1985-05-23

Similar Documents

Publication Publication Date Title
US4112637A (en) Removable press anchor with destructible anchor body
DE2120178A1 (en) Slidable lining and support structure and methods of lining tunnels and manholes
DE2824915A1 (en) METHOD OF MANUFACTURING BOTH OPEN EARTH HOLES
DE3044148A1 (en) METHOD AND DEVICE FOR CONNECTING TUBES
DE19817873A1 (en) Apparatus for the trench-less laying of pipe-work underground
EP2390543A1 (en) Method for laying pipes
EP0622583A1 (en) Method and apparatus for installment of undergroud pipelines
DE4102266C1 (en) Multilayer resilient roadway or tunnel lining - has temporary lining reinforced by heavy duty textile fabric roller mats
DE3903864C1 (en) Method and apparatus for redeveloping old pipes
DE3214033A1 (en) Method of installing pipe structures underground and apparatus for carrying out the method
DE2354764B2 (en) Method and device for the watertight implementation of a built-in component to be introduced into the ground through a building wall or excavation pit wall or floor
DE3818998C2 (en) Method and device for laying supply lines
DE10257392B4 (en) Channel drilling procedure and device
EP0496981B1 (en) Apparatus for laying pipelines without excavation
EP1271728A1 (en) Inliner for fastening cables in a sewage pipe
DE3545084A1 (en) TUNNEL CONSTRUCTION
CH683436A5 (en) A method for producing a composite effective plastic piping.
EP0414891A1 (en) Method and device for trench-free laying of pipelines
DE4403267C1 (en) System for underground laying of coupling pipes
CH374819A (en) Process for the production of prestressed anchors for structures such as retaining walls, excavation securing devices and the like and prestressing anchors produced according to this process
DE10042725C1 (en) Lining injection anchor, supporting walls of excavations for foundations, includes sliding, high-pressure, transverse-jetting nozzle assembly
DE19527608C2 (en) Underwater composite piles
DE4003747A1 (en) Forward thrust piece for pipe laying - consists of perforated thrust cone and cable and rocket assembly
DE3431233A1 (en) Method of laying pipelines without trenching
DE3200717C2 (en) Method and device for the watertight implementation of at least one rod-like built-in part, in particular a grouting anchor with one or more tendons, through a water-retaining construction pit wall

Legal Events

Date Code Title Description
OP8 Request for examination as to paragraph 44 patent law
D2 Grant after examination
8363 Opposition against the patent
8365 Fully valid after opposition proceedings
8339 Ceased/non-payment of the annual fee