DE2448006A1 - Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access - Google Patents

Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access

Info

Publication number
DE2448006A1
DE2448006A1 DE19742448006 DE2448006A DE2448006A1 DE 2448006 A1 DE2448006 A1 DE 2448006A1 DE 19742448006 DE19742448006 DE 19742448006 DE 2448006 A DE2448006 A DE 2448006A DE 2448006 A1 DE2448006 A1 DE 2448006A1
Authority
DE
Germany
Prior art keywords
pylon
bridge
stems
ropes
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DE19742448006
Other languages
German (de)
Inventor
Ruediger Dipl Ing Kahmann
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fried Krupp AG
Original Assignee
Fried Krupp AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fried Krupp AG filed Critical Fried Krupp AG
Priority to DE19742448006 priority Critical patent/DE2448006A1/en
Publication of DE2448006A1 publication Critical patent/DE2448006A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The bridge pylon has cable attachment points arranged in such a way that the effective lines of the cables or strands, viewed along the line of the bridge, lie in a common plane, on both sides of the pylon. At least in the area where the cable attachment points are situated, the pylon (1) is made up from two pillars (5, 6) mounted with a gap between them. These are interconnected by intervening crosspieces (8) in such a way that easy access is provided to the cable attachment points. The cross pieces may be in the form of bolts in the gap between the two pillars, which may be mutually offset along the line of the bridge, with the cables (3, 4) passing through them and anchored to them. Easy maintenance of the cable attachment points is combined with a pleasing aesthetic appearance.

Description

Brücken-Pylon Es ist bekannt, Brücken-Pylone mit Umlenklagern für die Seile zu versehen. is handelt sich um gewölbte, sattelartige Auflager mit 1O emmvorrichtungen für die Seile. Diese Ausführung ist kostspielig.Bridge pylon It is known to have bridge pylons with deflection bearings for to provide the ropes. It is about arched, saddle-like supports with 1O emming devices for the ropes. This implementation is costly.

Außerdem ist sie nachteilig, wenn auf einer Seite des Pylones Zusatzseile angeschlossen werden müssen, weil die Rückhalteseile auf der einen Pylon-Seite wegen ihres steileren Verlaufes stärkere Zugkräfte übertragen müssen als die auf der anderen Seite des Pylones befindlichen Seile. Hierbei gestaltet sich die Montage schwierig, da es nur sehr schwer zu erreichen ist, daß die über die Umlenklager geführten Seile und die am Pylon veran1eten Zusatzseile alle die gleiche Spannung haben.It is also disadvantageous if there are additional ropes on one side of the pylon must be connected because the restraint ropes are on one side of the pylon their steeper course must transmit stronger tensile forces than those on the other Side of the pylon located ropes. The assembly is difficult here, because it is very difficult to reach that the ropes led over the deflection bearings and the additional ropes attached to the pylon all have the same tension.

Ferner ist es bekannt, die beiderseitigen Seile innerhalb des Pylones mit Hilfe besonderer Verankerungskonstruktionen mit Seilköpfen zu verankern. Diese Ausführung ist nachteilig, weil wegen des beträchtlichen Platzbedarfes der einander gegenüberliegenden Seilköpfe und Verankerungskonstruktionen innerhalb des Pylones viel Platz erforderlich ist und folglich der Pylon in Brücken-Längsrichtung sehr große Abmessungen erhält, was ästhetisch ungünstig ist und außerdem den Nachteil hat, daß die Seilkö-ofe und Verankerungskonstruktionen, die überwacht iie-Lden Tn'LiSSmüssen, scher zugänglich sind.It is also known that the ropes on both sides within the pylon to anchor with the help of special anchoring structures with rope heads. These Execution is disadvantageous because of the considerable space required by each other opposite rope heads and anchoring structures within the pylon a lot of space is required and consequently the pylon is very large in the longitudinal direction of the bridge Obtains large dimensions, which is aesthetically unfavorable and moreover the The disadvantage is that the rope hooks and anchoring structures that are monitored iie-Lden Tn'LiSS must be more accessible.

Ferner ist es bekannt, die Seile von beiden Seiten her durch den Pylon hindurchzustecken und an dessen jeweils gegenüberliegender Seite zu verankern. Hierbei müssen die Seile der einen Sylon-Seite die Seile der anderen Pylon-Seite kreuzen, d.h. die beiderseitigen Seile müssen mit Abständen in Richtung quer zur Brücke aneinander vorbeigeführt werden. Das ergibt eine große Breite des Pylones und dementsprecnend große Abstände quer zur Brücken-Längsrichtung der am Versteifungsträger befindlichen Verankerungen der Seile voneinander, was eine teure Verankerungskonstruktion ergibt.It is also known to pull the ropes through the pylon from both sides put through and anchored on the opposite side. Here the ropes on one side of the sylon must cross the ropes on the other side of the pylon, i.e. the ropes on both sides must be spaced apart in the direction across the bridge be led by. This results in a large width of the pylon and accordingly large distances transverse to the longitudinal direction of the bridge of those on the stiffening girder Anchoring the ropes from one another, resulting in an expensive anchoring structure.

Außerdem sind auch die in Richtung quer zur Brücke großen Abmessungen des Pylones ästhetisch ungünstig.In addition, the dimensions in the direction across the bridge are also large of the pylon aesthetically unfavorable.

Demgegenüber liegt der in den Ansprüchen gekennzeichneten Erfindung die Aufgabe zugrunde, die Seile an einem Brücken-Pylon so anzuschließen, daß man mit einem möglichst geringen Kostenaufwand auskommt, die Befestigungsstellen der Seile leicht überwacht werden können und ein ästhetisch befriedigender Anblick gewährt wird.This is in contrast to the invention characterized in the claims based on the task of connecting the ropes to a bridge pylon in such a way that one gets by with the lowest possible cost, the attachment points of Ropes can be easily monitored and are given an aesthetically pleasing sight will.

Die Brfindung bringt den Fortschritt, daß eine Kreuzung der Seile am Pylon vermieden wird und trotzdem die Seilköpfe und Verankrungsvorrichtungen leicht überwacht werden können. überdies ist ein erSindungsgemäß gestalteter Brücken-Pylon, wenn seine entsprechend Gestaltung bis in den unteren Bereich fortgesetzt wird, auch deshalb vorteilhaft, weil dann die in Brücken-Längsrichtung auf den eingespannten Pylon wirkenden Biegemomente besonders günstig aufgenommen werden, da sich ein Doppel-T-förmiger Querschnitt mit einem verhältnismäßig großen Wiaerstandsmoment ergibt.The discovery brings the progress that a crossing of the ropes on the pylon is avoided and still the rope heads and anchoring devices can be easily monitored. In addition, an inventively designed bridge pylon is if its appropriately designed down to the lower area will, also advantageous because then the clamped in the bridge longitudinal direction on the Bending moments acting on the pylon can be absorbed particularly favorably, since it is a double-T-shaped Cross-section results with a relatively large resistance moment.

Die Erfindung ist anwendbar für alle Arten von Brücken-Pylonen, z.3. für solche von Schrägseilbrücken, Hängebrücken und Zügelgurtbrücken. Im rahmen der Erfindung liegt es im übrigen, wenn zwei oder mehr Seile in geringem Abstand voneinander als Seilstränge geführt werden, z.B. auf dem größten Teil ihrer Länge parallel zueinander zwischen oberen und unteren Verankerungsstellen, wobei es sich beispielsweise um Seilbündel mit Spreizschellen oder um Parallel-Kabel mit Beton-Umhüllung oder Kunststoff-Umwicklung handeln kann.The invention is applicable to all types of bridge pylons, e.g. for cable-stayed bridges, suspension bridges and strap bridges. As part of the In the rest of the invention, it is when two or more ropes are at a short distance from each other be guided as ropes, e.g. parallel to each other over most of their length between upper and lower anchorage points, for example Rope bundles with expansion clamps or around parallel cables with concrete or plastic wrapping can act.

Auf der Zeichnung sind zwei Ausführungsbeispiele des Erfindungsgegenstandes dargestellt; und zwar zeigen Fig. 1 eine Schrägseilbrücke nach dem ersten Ausführungsbeispel in Seitenansicht, Fig. 2 einen Ausschnitt aus Fig. 1, ergänzt durch die Darstellung von Zusatzseilen, in einem größeren Maßstab, Fig. 3 den Schnitt nach der Linie III-III in idg. 2, Fig. 4 den Schnitt nach der Linie IV-IV in Fig. 2, Fig. 5 einen Teil von Fig. 1 in größerem Maßstab, pig. 6 eine entsprechende Darstellung für eine abgewandelte Ausführung des Pylones, rig. 7 u.8 die Schnitte nach den Linien VIl-VIT bzw.The drawing shows two exemplary embodiments of the subject matter of the invention shown; namely, Fig. 1 shows a cable-stayed bridge according to the first exemplary embodiment in side view, FIG. 2 shows a detail from FIG. 1, supplemented by the illustration of additional ropes, on a larger scale, Fig. 3 shows the section along the line III-III in idg. 2, Fig. 4 the section along the line IV-IV in Fig. 2, Fig. 5 shows a part of FIG. 1 on a larger scale, pig. 6 shows a corresponding illustration for a modified version of the pylon, rig. 7 and 8 the sections according to the lines VIl-VIT or

VIII-VIII in Fig. 5 bzw. 6, Fig. 9 einen Querschnitt durch eine Scnrägseilbrücke mit der Ansicht eines Pylones nach dem zweiten Ausfülirungsbeispiel und Sig. 10 einen Ausschnitt aus Fig. 9 in größerem Maßstab. VIII-VIII in Fig. 5 and 6, Fig. 9 shows a cross section through a cable-stayed bridge with the view of a pylon according to the second Ausfülirungsbeispiel and Sig. 10 a detail from Fig. 9 on a larger scale.

in Fig. 1 ist der Pylon mit 1 und der Versteifungsträger mit 2 bezeichnet. Von dem oberen Bereich des Pylones 1 sind Schrägseile 3 zu dem über der Hauptöffnung Defindlichen Teil des Versteifungsträgers geführt, während auf der gegenüberliegenden Seite die Rückspannseile 4 in steilerer Anordnung verlaufen.In Fig. 1, the pylon is designated by 1 and the stiffening beam by 2. Stay cables 3 are from the upper area of the pylon 1 to the one above the main opening Defind part of the stiffening beam guided while on the opposite Side the back tensioning cables 4 run in a steeper arrangement.

Der Pylon 1 ist in zwei Stiele 5,6 aufgeteilt, die in Brücken-Längsrichtung gegeneinander versetzt sind, so daß sich zwischen ihnen ein Spalt 7 befindet. Die beiden Stiele 5 und 6, die in Betonbauweise mit Rechteckquerschnitt ausgeführt sind, sind in gewissen Höhenabständen dadurch Riegel 8 mit rechteckigem Querschnitt miteinander verbunden, so daß sich gemäß Fig. 7 ein Doppelt T-fbrmiger Querschnitt ergibt.The pylon 1 is divided into two posts 5, 6, which are in the longitudinal direction of the bridge are offset from one another, so that there is a gap 7 between them. the two posts 5 and 6, which are made of concrete with a rectangular cross-section, are thereby bars 8 with a rectangular cross-section with each other at certain height intervals connected, so that a double T-shaped cross-section results as shown in FIG.

Die Seile 3 und 1 bilden Seilstränge. Auf der Seite der Hauptöffnung werden die Stränge durch je zwei Seile 3 ge- bildet, die gemäß Fig. 4 parallel zueinander in geringem Abstand verlaufen. Diese Seile sind durch den Stiel 6 hindurchgesteckt und gegenüber diesem auf der dem Spalt 7 zugewandten Seite mit Ihren Seilkö-ofen , verankert. Die Wirkungslinien dieser Seilstränge sind in £lig. 2 und 4 mit 10 bezeichnet. Auf der Rückhalteseite wird jeder Strang durch vier Seile und 4a gebildet, die parallel zueinander mit geringem Abstand so verlaufen, daß die Kittelpunkte ihrer Seilkppfe 11 die ecken eines Quadrates bilden.The ropes 3 and 1 form rope strands. On the side of the main opening the strands are connected by two ropes 3 each forms, which according to Fig. 4 run parallel to each other at a small distance. These ropes are through the Stalk 6 inserted through it and opposite this on the side facing the gap 7 with your rope oven, anchored. The lines of action of these rope strands are in £ lig. 2 and 4 denoted by 10. On the restraint side, each strand goes through four ropes and 4a formed, which run parallel to each other with a small distance so that the Kittelpunkt their Seilkppfe 11 form the corners of a square.

Die Enden der Seile ! und 4a sind durch den Stiel 5 hindurchgesteckt und an diesem mit ihren Köpfen 11 auf der dem Spalt 7 zugewandten Seite verankert. Die Seile 4a jedes dieser Seilstränge sind Zusatzseile der erwähnten Art. Die Wirkungslinien der Seilstränge ti, 4a sind in Fig. 2 und - mit 12 bezeichnet. ,ie lig. ei zeigt, ließen die Wirkungslinien 10 und 12 der auf verschiedenen Eylon-Seiten befindlichen Seil-Stränge 3 bzw. 4a in ein und derselben lotrechten Ebene, welche die lotrechte Lägsmittel ebene der in Mittelträger-Bauweise ausgebildeten Brücke ist.The ends of the ropes! and 4a are pushed through the handle 5 and anchored to this with their heads 11 on the side facing the gap 7. The ropes 4a of each of these rope strands are additional ropes of the type mentioned. The lines of action the cable strands ti, 4a are denoted by 12 in FIGS. , ie lig. egg shows left the lines of action 10 and 12 of those located on different Eylon sites Rope strands 3 and 4a in one and the same vertical plane, which the vertical Lägsmittel level of the bridge, which is designed in a central girder construction.

Jeweils nahe unterhalb dr Seilköpfe 9 und 11 sind Riegel 8 angeordnet. Von diesen aus können die SeilköDfe und die Verankerungskonstruktionen überwacht und erforderlichenfalls nachgespannt werden.Bars 8 are arranged in each case close below the cable heads 9 and 11. The rope heads and anchoring structures can be monitored from here and retightened if necessary.

Längs des Klones ist ein Fahrstuhl 30 eines Aufzuges geführt, und zwar zweckmäßig innerhalb des Spaltes 7 so, daß er an den Riegeln 8 vorbeifahren und ein Bedienungsmann leicht zu den Verankerungsstellen gebracht werden kann.An elevator 30 of an elevator is guided along the clone, and although it is expedient within the gap 7 so that it drives past the latches 8 and an operator can easily be brought to the anchorage points.

Bei der Montage können die Seile jedes der Seilstränge mittels der bequem zugänglichen Seilkö-Dfe leicht so gespannt erden, daß alle Seile des Seilstranges die gleiche belastung haben Das gilt auch für die Seilstränge mit den Zusatz@eilen /:a.During assembly, the ropes can each of the rope strands by means of the easily accessible Seilkö-Dfe so that all ropes of the rope strand have the same load. This also applies to the rope strands with the additional @ rushes /: a.

Bei dem zweiten Ausführungsbeispiel ist der Pylon 13 in zwei Stiele 14, 15 derart unterteilt, daß diese Stiele quer zur Brückenrichtung gegeneinander veL.-setzt sind. Dabei laufen in diesem Fall die beiden Stiele 14 und 15 nur im oberen Teil des Pylones 13 nebeneinander. lach unten hin setzen sie sich in zwei A-förmig gespreizte Schenkel 16,17 fort, zwischen denen sich der Versteifungsträger 18 befinuet. Die beiden Stiele 14 und 15 sind durch Riegel 19 mit rechteckigem Querschnitt miteinander -verbunden, die in gewissen @@@enabständen übereinander angeordnet sind. In diesem Fall sind durchlaufende Seile 20 verwendet. Je zwei mit geringem Abstand nebeneinander liegende Seile 2G bilden einen Seilstrang, dessen ir1ctuigslinie beidersits des Pylones 13 in der lotrechten Längsmittelebene der Brücke liegt. Die Seile sind über Umlenklager 21 geführt, die auf Riegeln 19 sitzen. An den Umlenklagern sind die Seile mit Hilfe von Klemmvorrichtungen befestigt.In the second embodiment, the pylon 13 is in two stems 14, 15 subdivided in such a way that these stems mutually transverse to the bridge direction veL.-sets are. In this case, the two stems 14 and 15 only run in upper part of the pylon 13 side by side. laugh down below they sit in two A-shaped splayed legs 16, 17 continue, between which the stiffening beam 18 befinuet. The two stems 14 and 15 are through bolt 19 with a rectangular cross-section connected to each other, which are arranged one above the other at certain intervals. In this case, continuous ropes 20 are used. Two each with a short distance ropes 2G lying next to one another form a rope strand, the ir1ctuigslinie on both sides of the pylon 13 lies in the vertical longitudinal center plane of the bridge. The ropes are guided over deflection bearings 21 which sit on bolts 19. At the deflection bearings are the ropes are fastened with the help of clamping devices.

Auch bei dieser Bauart können die Verankerungen der Seile 20 innerhalb des zwischen den beiden Stielen 14,15 befindlichen Spaltes 22 bequem überwacht werden.In this design, too, the anchorages of the ropes 20 within of the gap 22 located between the two stems 14, 15 can be conveniently monitored.

Die Fig. 6 und 8 zeigen, daß - in Abwandlung der Ausfü1lrwlg nach Fig. 5-in den unteren Bereich des Pylones 1 die Riegel 8 durch einen Steg 23 ersetzt werden können, der von dem eingespannten Fuß des Pylones nach oben bis hahe unterhalb der unteren Seilbefestigungsstellen reicht. Dieser Steg bildet zusammen mit den beiden Stielen als Flanschen ein Dopel-T-3?iofil, das ein großes Widerstandsmoment gegenüber den in Brückenlängsrichtung auf den Pylon wirkenden Biegemomenten ergibt. Diese Gestaltung des Pylon-'ußes ist zwar aus der Gestaltung des Pylones nach der Erfindung mit Unterteilung in zwei Stiele hergeleitet, doch ist sie auch unabhängig von der Anwendung der vorliegenden Erfindung, wenn also der Pylon im oberen Bereich nicht in Stiele unterteilt ist, im Hinblick auf die günstige Aufnahme der Biegemomente vorteilhaft anwendbar.6 and 8 show that - in a modification of the Ausfü1lrwlg according to Fig. 5 - in the lower area of the pylon 1 the bolt 8 by a Web 23 can be replaced by the clamped foot of the pylon upwards to hahe below the lower rope attachment points. This web forms together with the two stems as flanges a double T-3? iofil, which is a large Moment of resistance compared to that acting on the pylon in the longitudinal direction of the bridge Bending moments results. This design of the pylon-'uss is from the design of the pylon according to the invention with subdivision into two stems, but it is also independent of the application of the present invention, if so the pylon in the upper area is not divided into stems, with regard to the favorable absorption of the bending moments advantageously applicable.

Gemäß der Erfindung könnte auch ein Nylon gestaltet werden, der auf seiner ganzen Höhle eine - im Querschnitt der Brücke betrachtet - A-förmige Gestalt hat. Dann wurde weder der beiden Schenkel für sich zumindest in dem oberen Bereich in zwei gegeneinander versetzte Stiele aufgeteilt werden, die durch Riegel od.dgl.According to the invention, a nylon could also be designed that on its whole cave - viewed in the cross section of the bridge - an A-shaped shape Has. Then neither of the two legs would stand alone, at least in the upper area be divided into two staggered stems, which or the like by bolts.

miteinander verbunden werden.be connected to each other.

Zur Verbindung der beiden Stiele miteinander können auch Laschen verwendet werden, die beiderseits an die Stiele angesetzt werden und den Spalt zwischen ihnen freilassen.Lugs can also be used to connect the two stems to one another that are attached to the stems on both sides and the gap between them set free.

Die Anwendung der Erfindung ist nicht davon abhängig, in welcher Bauweise der Pylon ausgeführt wird. Er kann beispielsweise in Stahlkonstruktion, Beton-Kontruktion oder Stahlveround-F=onstruktion hergestellt sein.The application of the invention does not depend on the type of construction the pylon is running. For example, it can be used in steel construction, concrete construction or Stahlveround-F = construction.

Claims (7)

Patent ansprüche:Patent claims: 1. Brücken-Pylon mit einer solchen Anordnung der Seil-Anschlußstellen, daß die Wirkungslinien der - in Brücken-Läljgsrichtung betrachtet -auf beiden Seiten des Pylons bzw. eines Pylon-Schenkels befindlichen Seile, Seilstränge oder Kabel wenigstens annähernd in einer gemeinsamen Ebene liegen, dadurch gekennzeichnet, daß der Pylon (1; 13) zumindest in dem Bereich, in dem sich die Seil-Anschlußstellen befinden, durch zwei mit Abstand voneinander angeordnete Stiele (5, 6; 14, 15) gebildet wird und daß die beiden Stiele miteinander durch Zwischenmittel (8; 19) in solcher Anordnung verbunden sind, daß die Seil-Anschlußstellen leicht zugänglich sind.1. Bridge pylon with such an arrangement of the rope connection points, that the lines of action of the - viewed in the direction of the bridge - on both sides ropes, strands of rope or cables located in the pylon or a pylon leg lie at least approximately in a common plane, characterized in that that the pylon (1; 13) at least in the area in which the rope connection points are formed by two stems (5, 6; 14, 15) arranged at a distance from one another is and that the two stems together by intermediate means (8; 19) in such Arrangement are connected that the rope connection points are easily accessible. 2. Brücken-Pylon nach Anspruch 1, dadurch gekennzeichnet, daß die Zwischenmittel durch Riegel (8; 19) in dem Spalt (7; 22) zwischen den beiden Stielen gebildet werden.2. bridge pylon according to claim 1, characterized in that the Intermediate means through bolts (8; 19) in the gap (7; 22) between the two stems are formed. 3. Brücken-Pylon nach Anspruch 1 oder 2, dadurch gekennzeichnet, daß die beiden Stiele (5, 6) in Brücken-Längsrichtung gegeneinander versetzt und die Seile (3, 4, 4a) durch die Stiele hindurchgesteckt und an diesen verankert sind.3. bridge pylon according to claim 1 or 2, characterized in that the two stems (5, 6) offset from one another in the longitudinal direction of the bridge and the Ropes (3, 4, 4a) are inserted through the stems and anchored to them. 4. Brücken-Pylon nach Anspruch 3, dadurch gekennzeichnet, daß zumindest im unteren Bereich des Pylons (1) die beiden Stiele anstelle der Riegel durch einen Steg (23) so miteinander verbunden sind, daß ein Doppel-T-Querschnitt des Pylons gebildet wird.4. bridge pylon according to claim 3, characterized in that at least in the lower area of the pylon (1) the two posts instead of the bars by one Web (23) are connected to each other so that a double-T cross-section of the pylon is formed. 5. Brücken-Pylon nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, daß in dem Spalt (7) zwischen den beiden Stielen (5, 6) ein Fahrstuhl (30) eines Aufzuges geführt ist.5. Bridge pylon according to one of claims 1 to 4, characterized in that that in the gap (7) between the two stems (5, 6) an elevator (30) one Elevator is guided. 6. Brücken-Pylon nach Anspruch 2, dadurch gekennzeichnet, daß die beiden Stiele (14, 15) in Richtung quer zur Brücke gegeneinander versetzt und auf Riegeln (19) zwischen den Stielen Umlenklayer (21) für die Seile (20) vorgesehen sind.6. bridge pylon according to claim 2, characterized in that the two stems (14, 15) offset against each other in the direction transverse to the bridge and on Latches (19) are provided between the stems of the deflector (21) for the ropes (20) are. 7. Brücken-Pylon, insbesondere nach einem der Ansprüche 1 bis 5, dadurch gekennzeichnet, daß er in dem unteren Bereich zur Aufnahme der in Brücken-Längsrichtung wirkenden Biegemomente einen Doppel-T-Querschnitt mit einem nach der Brücken-Längsrichtung ausgerichteten Steg (23) und mit versteiften Flanschen 5, 6) hat.7. bridge pylon, in particular according to one of claims 1 to 5, characterized characterized in that it is located in the lower area for receiving the longitudinal direction of the bridge acting bending moments have a double-T cross-section with a longitudinal direction of the bridge aligned web (23) and with stiffened flanges 5, 6). LeerseiteBlank page
DE19742448006 1974-10-09 1974-10-09 Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access Pending DE2448006A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19742448006 DE2448006A1 (en) 1974-10-09 1974-10-09 Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19742448006 DE2448006A1 (en) 1974-10-09 1974-10-09 Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access

Publications (1)

Publication Number Publication Date
DE2448006A1 true DE2448006A1 (en) 1976-04-15

Family

ID=5927841

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19742448006 Pending DE2448006A1 (en) 1974-10-09 1974-10-09 Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access

Country Status (1)

Country Link
DE (1) DE2448006A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3132398A1 (en) * 1981-08-17 1983-03-03 Dyckerhoff & Widmann AG, 8000 München REINFORCEMENT BRACKET FOR A CABLE ROPE
DE3207340A1 (en) * 1981-11-03 1983-05-19 Dyckerhoff & Widmann AG, 8000 München INCLINED CABLE BRIDGE
FR2642449A1 (en) * 1989-01-31 1990-08-03 Freyssinet Int Stup Improvements to cable-stayed bridges and more particularly to their towers and cable stays
FR2663975A1 (en) * 1990-06-29 1992-01-03 Freyssinet Int Stup IMPROVEMENTS ON BRIDGE BRIDGES AND MORE ESPECIALLY THEIR PYLONES AND BRIDGES.

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3132398A1 (en) * 1981-08-17 1983-03-03 Dyckerhoff & Widmann AG, 8000 München REINFORCEMENT BRACKET FOR A CABLE ROPE
DE3207340A1 (en) * 1981-11-03 1983-05-19 Dyckerhoff & Widmann AG, 8000 München INCLINED CABLE BRIDGE
FR2642449A1 (en) * 1989-01-31 1990-08-03 Freyssinet Int Stup Improvements to cable-stayed bridges and more particularly to their towers and cable stays
FR2663975A1 (en) * 1990-06-29 1992-01-03 Freyssinet Int Stup IMPROVEMENTS ON BRIDGE BRIDGES AND MORE ESPECIALLY THEIR PYLONES AND BRIDGES.
EP0465303A1 (en) * 1990-06-29 1992-01-08 FREYSSINET INTERNATIONAL et COMPAGNIE Improvements in cable-stayed bridges, especially in their cables and pillars

Similar Documents

Publication Publication Date Title
EP0514712B1 (en) Formwork for surfaces with varying curvature
CH648623A5 (en) METHOD FOR THE PRODUCTION OF A CABLE ROPE OR TOW BELT BRIDGE.
DE3020322A1 (en) STiffened longitudinal member
DE2426708A1 (en) Wide-area variously curved concrete formwork - with support's shanks laterally movable near membrane, and varying - length chord sections
DE2448006A1 (en) Common-plane-cable-effective-curve bridge pylon - comprising two spaced pillars connected so as to facilitate cable-joint access
DE2807859C2 (en)
DE2260359A1 (en) DEVICE FOR FIXING LATCHES TO LATTICE GIRDS
DE3040638C2 (en) Lattice girders for ring-shaped, arched or door-shaped extensions of underground and tunnel structures made of reinforced concrete as well as extensions made with such lattice girders
DE1684765A1 (en) Cantilever mast and method of erecting such a mast
DE817468C (en) Method for assembling solid bridges from prefabricated bridge sections
DE4031663A1 (en) SPECIALTY ROOF CONSTRUCTION
EP3650616A1 (en) Weather protection roof made of spanneed roof tarpaulin with scaffold boards mounted over the tarpaulin
DE955402C (en) Tensile connection of pit support frames with one another
DE2627840A1 (en) A PRE-TENSIONED COMPONENT WITH A WOOD CONSTRUCTION
DE1582737C (en) Hop frame plant
AT62332B (en) Device for bracing extension masts, booms or the like. By means of traction elements running in two or more directions, fastened to the upper end of the mast or the like, from drums and for supporting the chassis of such structures.
DE1582737B1 (en) Hop framework system
DE1609862C (en) Component for ceiling structures, scaffolding or the like
AT212551B (en) Transmission lattice mast or the like and method for its construction
DE4221388C2 (en) Lattice girders for truss constructions or the like
AT410997B (en) SPACER FOR DOUBLE HANGING CHAINS
DE2613152A1 (en) HV overhead cable concrete pylon insulators - are fastened to bolts protruding from plates on reinforced concrete brackets
DE3437262A1 (en) DEVICE FOR PRELOADING STEEL STRUCTURES
DE2262321A1 (en) METHOD AND DEVICE FOR CLAMPING CONCRETE BEAM
DE3720611A1 (en) Steel girder