- DE2233751A1 DE2233751A1 DE2233751A DE2233751A DE2233751A1 DE 2233751 A1 DE2233751 A1 DE 2233751A1 DE 2233751 A DE2233751 A DE 2233751A DE 2233751 A DE2233751 A DE 2233751A DE 2233751 A1 DE2233751 A1 DE 2233751A1
- Authority
- DE
- Germany
- Prior art keywords
- sub
- expansion
- elements
- expansion element
- element according
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005065 mining Methods 0.000 claims description 21
- 238000010276 construction Methods 0.000 claims description 5
- 238000000605 extraction Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000000149 penetrating effect Effects 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 239000013590 bulk material Substances 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 230000001427 coherent effect Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000001771 impaired effect Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/0052—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor with advancing shifting devices connected therewith
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Pinball Game Machines (AREA)
Description
PATENTANWALT BODE · 4033 HÖSEL -POSTFACH 1140 . TELEFON 02102-61701 · TELEX 8585166PATENT ADVERTISER BODE4033 HÖSEL -POSTBOX 1140. TELEPHONE 02102-61701 TELEX 8585166
R 1 - 378R 1-378
GULLICK DOBSON LIMITED Ince, Wigan, Lancashire, EnglandGULLICK DOBSON LIMITED Ince, Wigan, Lancashire, England
Wanderndes AusbauelementWandering expansion element
Die Erfindung betrifft ein wanderndes Ausbauelement für den Strebausbau im untertägigen Grubenbetrieb, mit einer Rückvorrichtung zum Vorrücken gegen 'die Abbaufront.The invention relates to a moving support element for longwall mining in underground mining operations, with a rear device to advance against 'the dismantling front.
Beim Strebbau mit wanderndem Ausbau und stempelfreier Abbaufront ist es bekannt, eine zwischen Ausbau und Abbaufront angeordnete durchlaufende Schiene zu verwenden,- an der die Rückvorrichtungen der. Ausbauelemente angreifen, wobei diese Schiene als Widerlager für die Ausbauelemente dienen kann. Weiterhin kann die Schiene gegebenenfalls mit dem zwischen Ausbau und Abbaufront angeordneten Förderer verbunden sein. Die Schiene untergliedert sich beim bekannten Ausbau in einzelne, gelenkig miteinander verbundene Abschnitte, so daß die Schiene auch dann unzerlegt vorgerückt werden kann, wenn nicht alle an der Schiene angreifenden Rückvorrichtungen gleichzeitig ausgefahren werden. Dieses Vorschieben der unzerlegten Schiene bedingt jedoch, daß die Vorrückweite der einzelnen Rückvorrichtungen nicht allzu groß ist«.In longwall mining with a moving extension and a stamp-free mining front, it is known to be between the extension and the mining front arranged continuous rail, - on which the rear devices of the. Attack expansion elements, these Rail can serve as an abutment for the expansion elements. Furthermore, the rail can optionally with the between Expansion and dismantling front be connected to the conveyor. In the known expansion, the rail is subdivided into individual, articulated sections, so that the rail can also be advanced without dismantling, if not all rear devices engaging the rail are extended at the same time. This advancement of the undisassembled Rail requires, however, that the advance distance of the individual rear devices is not too great «.
Die Aufgabe der Erfindung besteht darin«, einen Strebausbau zu schaffen, der extrem große Vorrückweiten Ccao 6 m) zuläßt, und bei dem trotzdem vor dem Ausbau eine sich in Streblängsrichtung erstreckende Schien® vorhanden ietD die %T'?svöa·^-- lichenfalle sls Widerlager ffe? dl® Rü©kvc&"-*-2,'jfotimg'3& di.^n^ The object of the invention is "to create a mine roof, the extremely large Vorrückweiten CCA o 6 m) permits, and the still before removing extending in longwall longitudinal direction Schien® available iet D, the% T 'svöa · ^? - - lichen trap sls abutment ffe? dl® Rü © kvc &"- * - 2, 'jfotimg'3 & di. ^ n ^
ftft
PATENTANWALT BODE · 4033 HOSEL · POSTFACH 1140 · TELEFON 02102-61701 · TELEX 8585160PATENT ADVERTISER BODE 4033 HOSEL POST BOX 1140 TELEPHONE 02102-61701 TELEX 8585160
— 2 —- 2 -
kann und insbesondere dazu verwendet werden soll, eine klare Trennung zwischen dem Bereich des Strebes zu schaffen, in dem sich der Ausbau befindet, und den Bereich des Strebes, in dem das Haufwerk gewonnen und abgefördert wird. Diese Erfordernisse sind insbesondere bei einem Abbauverfahren wichtig, bei dem zur Gewinnung vor dem Ausbau in Streblängsrichtung mit einer auf einem Fahrwerk fahrenden Gewinnungsmaschine (Continuous Miner) gearbeitet wird und sur Abförderung des Haufwerkes Fahrzeuge (Shuttle Cars) verwendet werden.can and in particular should be used to create a clear separation between the area of the strut in which the expansion is located, and the area of the strut in which the debris is extracted and removed. These requirements are particularly important in a mining process in which for extraction before expansion in the longitudinal direction of the face a mining machine (Continuous Miner) that moves on a chassis is used and the removal of the Haufwerkes vehicles (shuttle cars) are used.
Gegenstand der Erfindung ist ein· wanderndes Ausbauelement für den Strebausbau im untertägigen Grubenbetrieb, mit einer Rückvorrichtung zum Vorrücken gegen die Abbaufront, das sich da-, durch kennzeichnet, daß» die Rückvorrichtung oder ein von der Rückvorrichtung vorrückbarer Teil des AuSbauelementes mit einem Schienenabschnitt verbunden ist, der nach dem Vorrücken mit separaten, in gleicher Weise mit benachbarten Ausbauelementen verbundenen Schienenabschnitten ia einer Linie angeordnet ist.The subject of the invention is a moving support element for longwall mining in underground mining operations, with a rearward device for advancing towards the mining front, which is characterized by the fact that the rearward device or a part of the external structural element that can be advanced by the rearward device is connected to a rail section which is arranged after the rise with separate, connected in the same way with adjacent expansion elements rail sections ia a line.
Infolge der Verwandung separater Schienenabschnitte wird die mögliche Rückweite durch die Schiene nicht behindert. Dadurch j daß sich nach dem Vorrücken sämtliche Schienenabschnitte in einer Linie befindens bildet die Schiene während der Gewinnung und Förderung eine durchgehende Trennungslinie zwischen dem Ausbaubereich des Strebes und dem Gewinnungsund Förderbereich des Str-ebes.As a result of the use of separate rail sections, the possible back distance is not hindered by the rail. Characterized j that are located after the rise all rail sections in a line s is the rail during the recovery and promotion of a continuous line of separation between the expansion region of the longwall face and the Gewinnungsund conveying region of the longwall.
Um die Schiene erforderlichenfalls auch als Widerlager für die Rückvorriehtungen verwenden au können, ist weiterhin vor- g-Λ? 7.-h/i,ii: da& ciey Süiiißnesaöschnitt mit Verbindungselement en λ-^SiC. ■:,-:■?. c^^is&n *?■:■■ :--~~.inaisn aiit benachbarten Seriie.v^nab-chnitten V 'itfiWil ίΐΐοIn order to be able to use the rail as an abutment for the rear fixtures if necessary, it is still possible to use g-Λ? 7.-h / i, ii : da & ciey Süiiißnesaöschnitt with connecting element en λ- ^ SiC. ■:, -: ■ ?. c ^^ is & n *? ■: ■■: - ~~ .ina i sn aiit neighboring Seriie.v ^ nab-chcut V'itfiWil ίΐΐο
PATENTANWALT BODE · 4033 HÖSEL . PuSiI=ACH 1140 · TELEFON 02102-61701 · TELEX 8585166PATENT ADVERTISER BODE · 4033 HÖSEL. PuSiI = ACH 1140 TELEPHONE 02102-61701 TELEX 8585166
Besondere Vorteile bietet die Erfindung bei Verwendung von an und für sich bekannten Ausbauelementen mit mindestens zwei Teilelementen, die nacheinander vorrückbar sind und beim Vorrücken einander abwechselnd als Widerlager dienen, wenn mindestens eines der Teilelemente mit als Schiene dienenden Verbindungsmitteln zum zeitweisen Verbinden mit einem Teilelement des benachbarten Ausbauelementes versehen ist, so daß" dieses als Widerlager für die Rückvorrichtung des Ausbauelemen· tes verwendbar ist. In diesem Falle, ist die Schiene als Verbindungsmittel zwischen den Fußteilen zweier benachbarter abbaustoßseltiger Teilelemente ausgebildet und kann, falls wegen schlechter Gebirgsverhältnisse ein abbaustoßseitiges Teilelement einmal nicht in der erforderlichen Weise zwischen Hangendem und Liegendem verspannt werden kann, eine Verbindung zum benachbarten abbaustoßseitigen Teilelement herstellen, so daß dieses aushilfsweise als Widerlager für die Rückvorrichtung dienen kann.The invention offers particular advantages when using extension elements known per se and having at least two Sub-elements that can be advanced one after the other and when advancing alternately serve as an abutment when at least one of the sub-elements is used as a rail Connection means is provided for temporary connection with a sub-element of the adjacent expansion element, so that " this can be used as an abutment for the rear device of the expansion element. In this case, the rail is as Connecting means are formed between the foot parts of two adjacent breakdown joint sub-elements and can, if due to poor rock conditions, a mine face Partial element cannot be braced in the required way between hanging and lying, a connection to the adjacent partial element on the working face side, so that this can be used as a temporary abutment for the rear device can serve.
Zweckmäßig weisen der Schienenabschnitt oder die Verbindungsmittel ein Abschirmblech auf oder sind als Abschirmblech ausgebildet, das an der Vorderseite des Ausbauelementes oder desjenigen Teilelementes des Ausbauelementes befestigt, ist, das beim Vorrücken als erstes vorgerückt wird. Hierdurch wird ein Übertreten des Haufwerkes über die von der Schiene gebildete Trennlinie hinweg in den Strebbereich des Ausbaues vermieden.The rail section or the connecting means expediently have a shielding plate or are designed as a shielding plate on the front of the expansion element or that sub-element of the expansion element is attached, which is advanced first when advancing. This means that the bulk material is traversed by the rail formed dividing line away in the longwall area of the expansion avoided.
Bei Ausbauelementen mit zwei Teilelementen sind die Kappenkonstruktionen der beiden Teilelemente mit gegenseitig zusammenwirkenden Führungsmitteln versehen, die zur Führung der beiden Teilelemente während des Rückens dienen. Weiterhin sind zwischen den Teilelementen geeignete Rückvorrichtungen mit zwischen den Kappenkonstruktionen und/oder denIn the case of extension elements with two sub-elements, the cap constructions are of the two sub-elements are provided with mutually cooperating guide means for guiding of the two sub-elements serve during the back. Furthermore, there are suitable rear devices between the sub-elements with between the cap constructions and / or the
2098«b/08782098 «b / 0878
- H Fußplatten angeordneten Hydraulikzylindern vorgesehen.- Hydraulic cylinders arranged in H base plates are provided.
Beispielsweise Ausführungsformen des Gegenstandes der Erfindung werden im folgenden an Hand der Zeichnung näher erläutert, in derFor example embodiments of the subject matter of the invention are explained in more detail below with reference to the drawing in which
Fig. 1 eine Seitenansicht eines Ausbauelementes zeigt,Fig. 1 shows a side view of an expansion element,
dessen Teilelemente sich in der£tellung befinden, die sie nach Hereingewinnung einer Schnittbreite des an der Abbaufront anstehenden Materials einnehmen; Iwhose sub-elements are in the position that they are after having gained a cutting width take in the material standing at the mining front; I.
Fig. 2 zeigt das in Fig. 1 dargestellte Ausbauelement, wobei sich die Teilelemente in der Stellung befinden, die sie vor der .Hereingewinnung einer weiteren Schnittbreite des an der Abbaufront anstehenden Materials einnehmen.Fig. 2 shows the expansion element shown in Fig. 1, wherein the sub-elements are in the position which they before Ingesting materials.
Fig. 3 ist.eine Aufsicht auf zwei benachbarte Ausbauelemente , der in den Fig. 1 und 2 dargestellten Art.Fig. 3 is a plan view of two adjacent expansion elements , of the type shown in Figs. 1 and 2.
Fig. 4 zeigt eine Aufsicht auf eine Reihe von Ausbauelementen in einem Streb in schematischer Darstellung, wobei sich die Teilelemente der Ausbauelemente in der Position befinden, die sie während der Durchfahrt einer Gewinnungsmaschine einnehmen, die vor den Ausbauelementen das an der Abbaufront anstehende Material hereingewinnt.Fig. 4 shows a plan view of a number of expansion elements in a longwall in a schematic representation, the sub-elements of the extension elements are in the position they occupy during the passage of a mining machine, which wins in the material at the front of the dismantling in front of the extension elements.
Fig. 5 ist eine Seitenansicht zu Fig. 4 in Streblängs richtung gesehen.Fig. 5 is a side view of FIG. 4 in the longitudinal direction seen.
Fig. 6. zeigt eine weitere Aufsicht auf im Streb angeordnete Ausbauelemente in schematischer Darstellung, wobei die Teilelemente der links angeordneten Ausbauelemente sich in der Stellung befinden, die sie unmittelbar nach Durchgang der Gewinnungsmaschine einnehmen.Fig. 6 shows a further plan view of expansion elements arranged in the longwall in a schematic representation, wherein the sub-elements of the expansion elements arranged on the left are in the position which take them immediately after passing through the extraction machine.
20988S/087820988S / 0878
PATENTANWALT BODE . 4033 HÖSEL.. POSTFACH 1140 · TELEFON 02102-61701 · TELEX 8585166PATENT ADVERTISER BODE. 4033 HÖSEL .. POST BOX 1140 TELEPHONE 02102-61701 TELEX 8585166
Fig. 7 ist eine Seitenansicht zu Fig. 6 in Streblängsrichtung gesehen. · ,FIG. 7 is a side view of FIG. 6 seen in the longitudinal direction. ·,
Fig. 8 zeigt eine weitere Aufsicht auf im Streb angeordnete Ausbauelemente in schematischer Darstellung, wobei sich die Teilelemente der Ausbauelemente in der Stellung befinden, die sie bei der Zurückfahrt der Gewinnungsmaschine vom Strebende zum Strebanfang einnehmen.Fig. 8 shows a further plan view of expansion elements arranged in the longwall in a schematic representation, the partial elements of the extension elements being in the position that they take when returning the mining machine from the end of the longwall to the beginning of the longwall.
Fig. 9 ist eine Aufsicht auf eine weitere Ausführungsform des -Ausbaues gemäß der Erfindung. Fig. 9 is a plan view of a further embodiment of the expansion according to the invention.
Die in den Fig. 1, 2 und 3 dargestellten Ausbauelemente bestehen je aus zwei Teilelementen, von denen das versatzseitige Teilelement mit dem Bezugszeichen 10 und das abbaustoßseitige Teilelement mit dem Bezugszeichen 11 bezeichnet ist. Das versatzseitige Teilelement 10 weist eine Grundplatte 12 auf, auf der vier hydraulisch ausfahrbare Teleskopstempe.l 13 angeordnet sind, die mit ihren Oberteilen eine rechteckige Kappe 14 tragen. Auf der Grundplatte 12 des versatzseitigen Teilelementes sind weiterhin nebeneinander zwei hydraulisch ausfahrbare Teleskopstempel 15 und 16 angeordnet, von dene jeder eine Vorpfändkappe 17 bzw. 18 unterstützt. Die Vorpfändkappen 17 und 18 sind bei 19 und 20 gelenkig an der Kappe IH befestigt.The expansion elements shown in FIGS. 1, 2 and 3 exist each of two sub-elements, of which the offset-side sub-element with the reference number 10 and the working face side Partial element is denoted by the reference numeral 11. The offset-side sub-element 10 has a base plate 12, on the four hydraulically extendable Teleskopstempe.l 13 are arranged, the upper parts of which have a rectangular cap 14 wear. On the base plate 12 of the partial element on the offset side, there are also two hydraulically extendable ones next to one another Telescopic ram 15 and 16 arranged, each of which supports a pre-pledging cap 17 and 18, respectively. The pre-pledging caps 17 and 18 are hingedly attached to the cap IH at 19 and 20.
Das abbaustoßseitige Teilelement 11 weist eine Grundplatte auf, auf der ein einzelner hydraulisch ausfahrberer Teleskopstempel 22 angeordnet ist, an dessen Oberteil eine Kappe 2 3 befestigt ist, die in Rückrichtung wesentlich kürzer als die Vorpfändkappen 17 und 18 ausgebildet ist. Die Kappe 2 3 ist in Längsrichtung beweglich und wird zwischen den Vorpfändkappen 17 und 18 des versatzseitigen Teilelemente 10 geführt. Während dieser Bewegung, d.h. wenn das abbaustoßseitige Teilelement vorgerückt wird, erfolgt die Führung der Kappe 2 3 durchThe partial element 11 on the working face side has a base plate on which a single hydraulically extendable telescopic ram 22 is arranged, on the upper part of which a cap 2 3 is attached, which is much shorter than that in the rearward direction Vorpfändkappen 17 and 18 is formed. The cap 2 3 is movable in the longitudinal direction and is between the Vorpfändkappen 17 and 18 of the offset-side sub-elements 10 out. During this movement, i.e. when the face-side sub-element is advanced, the leadership of the cap 2 3 takes place through
- 6 209885/08 7 8- 6 209885/08 7 8
Drahtseilabschnitte 21, deren Enden an den Vorpfadkappen 17 und 18 bei 25 und 25a befestigt sind. Die Drahtseilabschnitte 24 verlaufen durch vertikal aufgeweitete Führungsösen, die in Ansätzen 26 und 27 der Kappe 23 vorgesehen sind.Cs. Fig.2) Durch die Führung wird verhindert, daß sich die Kappe 2 3 während des Vorrückens um die Längsachse des Stempels 22 verdreht und sich unter oder über die Vorpfändkappen 17 bzw. 18 legt. Hierdurch würde die einwandfreie Anlage aller drei Kappen an das Hangende beeinträchtigt. Auf ähnliche Weise wird das versatzseitige Teilelement während seines Vorrückens durch die Drahtseilabschnitte 2U geführt, die sich durch die Führungsösen in den Ansätzen 26 und 27 erstrecken.Wire rope sections 21, the ends of which at the fore path caps 17 and 18 are attached at 25 and 25a. The wire rope sections 24 run through vertically widened guide eyes, which are provided in lugs 26 and 27 of the cap 23. Cs. Fig. 2) The guide prevents the cap 23 from rotating about the longitudinal axis of the punch 22 during the advancement and lies under or over the pre-pledging caps 17 and 18, respectively. This would ensure the perfect installation of all three caps impaired to the hanging wall. Similarly, the offset-side sub-element as it is advanced through the Wire rope sections 2U passed through the guide eyes in approaches 26 and 27 extend.
Die zur Führung dienenden Drahtseilabschnitte 2h sind einerseits für Führungszwecke gut geeignet und haben andererseits den Vorteil, daß sie bei Anpassung der beiderseitigen Kappenkonstruktionen an Unregelmäßigkeiten des Hangenden die notwendige Bewegungsfreiheit belassen.The wire rope sections 2h serving for guidance are on the one hand well suited for guiding purposes and on the other hand have the advantage that they leave the necessary freedom of movement when adapting the cap constructions on both sides to irregularities in the hanging wall.
Die Relativbewegung zwischen dem versatzseitigen Teilelemnt 10 und dem abbaustoßseitigen Teilelement 11 bei Vorrücken des Ausbauelementes wird durch oben und unten angeordnete, doppeltwirkende Hydraulikzylinder 28 und 29 bewirkt. Der Hydraulikzylinder 28 ist mit seinem Zylinderteil über Zapfen 30 in der Kappe 2 3 des abbaustoßseitigen Teilelementes 11 und mit seinem Kolben bei 31 an der Kappe IU des versatzseitigen TeilelementesThe relative movement between the partial element 10 on the offset side and the partial element 11 on the working face side when the Expansion element is effected by double-acting hydraulic cylinders 28 and 29 arranged above and below. The hydraulic cylinder 28 is with its cylinder part on pin 30 in the cap 23 of the working face-side sub-element 11 and with his Piston at 31 on the cap IU of the partial element on the offset side
10 befestigt. Der untere Hydraulikzylinder 29 hingegen ist mit seinem Zylinderteil in der Grundplatte 12 des versatzseitigen Teilelementes 10 durch nicht dargestellte Zapfen und mit seinem Kolben an der Grundplatte 21 des abbaustoßseitigen Teilelementes10 attached. The lower hydraulic cylinder 29, however, is with his cylinder part in the base plate 12 of the offset-side sub-element 10 by pins, not shown, and with his Piston on the base plate 21 of the partial element on the working face side
11 bei 32 befestigt.11 attached at 32.
2098 8 5/08782098 8 5/0878
Erfindungsgemäß sind an der Vorderseite der Fußplatte 21 des abbaustoßseitigen Teilelementes als Schiene dienende Verbindungsmittel 33 befestigt, die eine Abschirmplatte 34 aufweisen bzw. in Form einer Abschirmplatte ausgebildet sind. Diese Abschirmplatte verhindert das Eindringen von Haufwerk in den Bereich des Strebes, in dem sich das zugeordnete Ausbauelement befindet. Die Befestigung erfolgt über in Schlitze 34a eingesteckte Stifte. Diese Art der Verbindung erlaubt eine gewisse vertikale Verschiebung der Abschirmplatte 34 bzw. eine Verstellbarkeit derselben in vertikaler Richtung.According to the invention, on the front side of the base plate 21 of the partial element on the working face side serving as a rail connection means 33 attached, which have a shielding plate 34 or are designed in the form of a shielding plate. This shielding plate prevents debris from penetrating into the area of the strut in which the associated support element is located is located. It is fastened by means of pins inserted into slots 34a. This type of connection allows one certain vertical displacement of the shielding plate 34 or an adjustability of the same in the vertical direction.
Die Bewegungsabläufe beim Rücken gehen aus den Fig. 4-8 hervor. Fig. 8 zeigt eine Stellung der Ausbauelemente, bei der die abbaustoßseitigen Teilelemente 11 relativ zu den versatzseitigen Teilelementen 10 vorgerückt sind und die Gewinnungsfahrt der Gewinnungsmaschine M beginnen kann.The movements in the back are shown in Figs. 4-8. Fig. 8 shows a position of the expansion elements at which the working face-side sub-elements 11 are advanced relative to the offset-side sub-elements 10 and the mining run the mining machine M can begin.
Nach Vorbeifahrt der Gewinnungsmaschine M an den Ausbauelementen werden deren versatzseitige Teilelemente 10 durch Einfahren der Hydraulikzylinder 28 und 29 vorgerückt, so daß die Vorpfändkappen 17 und 18 die neu freigelegte Han gendfläche unmittelbar nach Durchgang der Maschine M unterstützen (s. Fig. 7). Während dieses Rückvorganges verbleiben die abbaustoßseitigen Teilelemente 11 in der Verspannung zwischen Hangendem und Liegendem und dienen als Widerlager für die Hydraulikzylinder 28 und 29, so daß diese die zeitweilig aus der Verspannung gelösten versatzseitigen Teilelemente 10 vorrücken können. Bei sehr schlechten Verhältnissen am Hangenden und/oder am Liegenden kann es vorkommen, daß das abbaustoßseitige Teilelement 11 nicht richtig verspannt werden kann, so daß es sich beim Nachziehen des zugehörigen Versatzseitigen Teilelementes 10 verschieben würde. Um dies zu verhindern, kann das abbaustoßseitige Teilelement 11 zeitweise über die Verbindungsmittel 33 und dieAfter the mining machine M has passed the expansion elements, their offset-side sub-elements 10 are retracted by the Hydraulic cylinders 28 and 29 advanced so that the Vorpfändkappen 17 and 18, the newly exposed Han gendfläche directly support after the machine M has passed (see Fig. 7). While During this reverse process, the partial elements 11 on the side of the mine face remain in the bracing between the hanging wall and the lying surface and serve as an abutment for the hydraulic cylinders 28 and 29, so that these are temporarily released from the tension offset-side sub-elements 10 can advance. In very poor conditions on the hanging wall and / or on the floor it can happen that the partial element 11 on the working face side cannot be correctly braced, so that it is retightened when it is tightened of the associated sub-element 10 on the offset side would move. In order to prevent this, the working face can be used Partial element 11 temporarily via the connecting means 33 and the
r 8 209885/0878 r 8 209885/0878
entsprechenden Verbindungsmittel der benachbarten abbaustoßseitigen Teilelement 11 mit dem einen oder dem anderen benachbarten abbaustoßseitigen Teilelement 11 verbunden werden, wie bei 33a angedeutet ist. Beispielsweise können die Enden der Abschirmplatten 34 mit an entsprechenden Vorsprüngen angeordneten Einstecköffnungen versehen sein, durch die zur Verbindung zweier Abschirmplatten 34 dienende Bolzen durchgesteckt werden.corresponding connecting means of the neighboring mine face Partial element 11 are connected to one or the other adjacent working face-side partial element 11, such as is indicated at 33a. For example, the ends of the shielding plates 34 can be arranged on corresponding projections Insertion openings can be provided through which bolts serving to connect two shielding plates 34 are inserted.
Bei Zurückfahrt der Gewinnungsmaschine M vom Strebende zum Strebanfang können jeweils hinter der Maschine die abbaustoßseitigen Teilelemente 11 durch Ausfahren der Hydraulikzylinder 28 und 29 vorgerückt werden (s. Fig. 8), so daß der gesamte Strebausbau sich wieder in der in den Fig. 4 und 5 dargestellten Lage befindet, wenn die Gewinnungsmaschine den Strebanfang erreicht hat. Die nachfolgende Gewinnungsfehrt der Gewinnungsmaschine M kann dann sofort beginnen.When the mining machine M moves back from the end of the longwall to the beginning of the longwall, those on the working face side can in each case behind the machine Partial elements 11 are advanced by extending the hydraulic cylinders 28 and 29 (see. Fig. 8), so that the entire Longwall mining is again in the position shown in FIGS. 4 and 5 when the mining machine reaches the start of the longwall Has. The subsequent extraction guides the extraction machine M can then begin immediately.
Die Abschirmplatten 34, die einzeln zusammen mit den Ausbauelementen vorgerückt werden, bilden erfindungsgemäß gemeinsam eine zusammenhängende Barriere vor den Ausbauelementen und verhindern das Eindringen von-Haufwerk in den Bereich des Strebes, in dem sich die Ausbauelemente befinden.The shielding plates 34, which are individually together with the expansion elements are advanced, form together according to the invention a coherent barrier in front of the extension elements and prevent debris from penetrating into the area of the strut, in which the expansion elements are located.
Eine weitere Ausführungsform der Erfindung ist in Fig. 9 dargestellt. Der dort dargestellte Ausbau ist in verschiedener Hinsicht dem oben beschriebenen Ausbau ähnlich, so daß zur Bezeichnung der einander entsprechenden Teile die gleichen Bezugszeichen verwendet werden konnten. Die Ausbauelemente dieses Ausbaus bestehen jedoch aus einer einzigen Einheit, sind also als sogenannte Ausbauböcke ausgebildet, wobei jeweils zwei derartige Ausbauböcke als Paar zusammenwirken. Die Ausbauböcke jedes Paares sind jeweils mit Al und Bl, A2 und B2 etc. bezeichnet. Jeder Ausbaubock weist eine Gründplatte 35 auf,Another embodiment of the invention is shown in FIG. The expansion shown there is similar in various respects to the expansion described above, so that the designation the same reference numerals could be used for corresponding parts. The expansion elements of this However, extensions consist of a single unit, so they are designed as so-called extension blocks, with two such extension blocks working together as a pair. The extension jacks of each pair are designated with A1 and B1, A2 and B2, etc., respectively. Each support frame has a base plate 35,
- 9 20988Ö/0878 - 9 20988Ö / 0878
auf der vier Hydraulikstempel 36 befestigt sind, die mit ihren Oberteilen eine Kappenkonstruktion unterstützen. Die ausfahrbaren Teile 37 der Rückzylinder 38 von je zwei als Paar zusammenwirkenden Ausbauböcken sind mit einem Schienenabschnitt 39 verbunden, der eine Abschirmplatte trägt oder selbst in Form einer Abschirmplatte ausgebildet ist. Die Schienenabschnitte 39 sind bei 40 mit Verbindungselementen versehen, durch die benachbarte Schienenabschnitte 39 zeitweilig miteinander verbunden werden können.on the four hydraulic rams 36 are attached, with their Tops support a cap construction. The extendable parts 37 of the rear cylinder 38 of two cooperating as a pair Support blocks are connected to a rail section 39 which carries a shielding plate or itself in the form a shield plate is formed. The rail sections 39 are provided at 40 with connecting elements through which adjacent rail sections 39 can be temporarily connected to one another.
Der Bewegungsablauf gestaltet sich bei diesem Ausbau wie folgt:The sequence of movements for this expansion is as follows:
Zunächst werden die ausfahrbaren Teile 37 der Rückzylinder 38 der zu einem Paar zusammengefaßten Böcke Al, Bl ausgefahren, so daß der zugehörige. Schienenabschnitt 39 von der in ausge-First, the extendable parts 37 of the rear cylinders 38 of the brackets A1, B1, which are combined to form a pair, are extended. so that the associated. Rail section 39 from the
- zogenen Linien dargestellten Lage in die in gestrichelten Linien dargestellte Lage verschoben wird. Dieser Schienenabschnitt 39 wird dann mit Hilfe der Verbindungselemente HO an den Schienenabschnitt 39 eines benachbarten, vorher vorgerückten Paares von Ausbauböcken (nicht dargestellt) befestigt, das sich rechts von dem Paar Al, Bl befindet. Dann werden die Stempel 36 des Ausbaubockes Bl und der zugehörige Rückzylinder 38 eingefahren, so daß der Ausbaubock Bl vorrückt. Anschließend wird dieser Ausbaubock in der vorgerückten Lage wieder zwischen Hangendem und Liegendem verspannt. Sodann werden die Stempel des Ausbaubockes Al und der zugehörige Rückzylinder 38 eingefahren, so daß auch dieser Ausbaubock vorrückt und verspannt- The position shown in solid lines in the position shown in dashed lines Lines shown position is shifted. This rail section 39 is then connected with the aid of the connecting elements HO attaches the rail section 39 of an adjacent, previously advanced pair of trestles (not shown) which is to the right of the pair Al, Bl. Then the punch 36 of the support frame Bl and the associated rear cylinder 38 retracted so that the trestle Bl advances. Then this trestle is in the advanced position again between Hanging and lying tensioned. Then the rams of the support frame Al and the associated rear cylinder 38 are retracted, so that this trestle also advances and braces
werden kann. Die Verbindungselemente 40 werden bis zum nächsten Vorrücken des Schienenabschnittes 39 nicht gelöst. Die Paare von Ausbauböcken A2, B2 etc. werden auf gleiche Weise vorgerückt. .can be. The connecting elements 40 are not released until the next advance of the rail section 39. The couples from extension blocks A2, B2 etc. are advanced in the same way. .
Die zeitweilig untereinander verbundenen Schienenabschnitte dienen in Verbindung mit den in der Verspannung zwischenThe temporarily interconnected rail sections are used in conjunction with the tension between
- 10 209b 8-5/087a - 10 209b 8-5 / 087a
Hangendem undüegenden befindlichen Ausbauböcken als Widerlager für die Rückzylinder beim Vorrücken der Ausbauböcke.Hanging and undüegenden supporting trestles as abutments for the rear cylinders when advancing the support frames.
Patentansprüche: Patent claims :
II /BoII / Bo
- 11 —- 11 -
209885/08 7209885/08 7
Claims (13)
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB3342471A GB1394675A (en) | 1971-07-16 | 1971-07-16 | Mine roof support systems |
Publications (1)
Publication Number | Publication Date |
---|---|
DE2233751A1 true DE2233751A1 (en) | 1973-02-01 |
Family
ID=10352787
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE2233751A Pending DE2233751A1 (en) | 1971-07-16 | 1972-07-08 | HIKING EXTENSION ELEMENT |
Country Status (4)
Country | Link |
---|---|
US (1) | US3812681A (en) |
AU (1) | AU464062B2 (en) |
DE (1) | DE2233751A1 (en) |
GB (1) | GB1394675A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2942943A1 (en) * | 1979-10-24 | 1981-05-07 | Hermann Hemscheidt Maschinenfabrik Gmbh & Co, 5600 Wuppertal | DEVICE FOR MAINTAINING THE SPECIFIC CENTER DISTANCE OF THE REMOVAL ELEMENTS OF A SCREW EXTENSION FOR THE LONG FRONT DEGRADING |
DE19712413C1 (en) * | 1997-03-25 | 1998-02-26 | Georg Gottschlich | Hydraulic consolidation frame for coal face work |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2928150C2 (en) * | 1979-07-12 | 1981-12-17 | Bochumer Eisenhütte Heintzmann GmbH & Co, 4630 Bochum | Shield support frame |
DE2928151C2 (en) * | 1979-07-12 | 1982-06-16 | Bochumer Eisenhütte Heintzmann GmbH & Co, 4630 Bochum | Extension frame |
DE3024465A1 (en) * | 1980-06-28 | 1982-01-28 | Gewerkschaft Eisenhütte Westfalia, 4670 Lünen | PROGRESSIVE EXTENSION FOR UNDERGROUND EXTRACTION COMPANIES, IN PARTICULAR SHIELD REMOVAL |
AT504265B1 (en) * | 2006-07-28 | 2011-02-15 | Voest Alpine Bergtechnik | SUPPORT DEVICE FOR AN OPERATOR OR MACHINE |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB892179A (en) * | 1960-01-20 | 1962-03-21 | Hoesch Bergbautechnik Gmbh | Improvements in or relating to hydraulically actuated self advancing roof props |
GB930838A (en) * | 1960-08-31 | 1963-07-10 | Gullick Ltd | Improvements in or relating to roof supports for mines and the like |
DE1142331B (en) * | 1961-02-11 | 1963-01-17 | Rheinstahl Gmbh Wanheim | Removal arrangement at the transition from the longwall to the mining section |
US3333426A (en) * | 1964-04-11 | 1967-08-01 | Gullick Ltd | Self-advancing hydraulically extensible mine roof supports |
DE1758675B1 (en) * | 1967-07-19 | 1972-05-31 | Gullick Ltd | Migrating hydraulic longwall mining |
GB1234661A (en) * | 1968-01-17 | 1971-06-09 | ||
US3536433A (en) * | 1968-03-12 | 1970-10-27 | Ingbuero Konrad Grebe | Traveling prop system for a mine working face having a steep,or semi-steep,or flat orientation |
GB1287096A (en) * | 1968-10-17 | 1972-08-31 | Karl Maria Groetschel | Improvements relating to advancing roof supports for mine workings |
-
1971
- 1971-07-16 GB GB3342471A patent/GB1394675A/en not_active Expired
-
1972
- 1972-07-08 DE DE2233751A patent/DE2233751A1/en active Pending
- 1972-07-11 US US00270617A patent/US3812681A/en not_active Expired - Lifetime
- 1972-07-14 AU AU44597/72A patent/AU464062B2/en not_active Expired
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2942943A1 (en) * | 1979-10-24 | 1981-05-07 | Hermann Hemscheidt Maschinenfabrik Gmbh & Co, 5600 Wuppertal | DEVICE FOR MAINTAINING THE SPECIFIC CENTER DISTANCE OF THE REMOVAL ELEMENTS OF A SCREW EXTENSION FOR THE LONG FRONT DEGRADING |
DE19712413C1 (en) * | 1997-03-25 | 1998-02-26 | Georg Gottschlich | Hydraulic consolidation frame for coal face work |
Also Published As
Publication number | Publication date |
---|---|
AU4459772A (en) | 1974-01-17 |
AU464062B2 (en) | 1975-08-14 |
GB1394675A (en) | 1975-05-21 |
US3812681A (en) | 1974-05-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2128023B2 (en) | Migrating longwall construction with side-by-side support shields | |
DE1302918C2 (en) | HIKING STREET STRUCTURE | |
DE2732339C2 (en) | Longwall mining, especially longwall mining | |
DE2233751A1 (en) | HIKING EXTENSION ELEMENT | |
DE2250296C3 (en) | Knife shield propulsion device for propelling underground cavities, such as in particular tunnels, tunnels and the like | |
DE1458684A1 (en) | Migrating expansion element for underground mining operations | |
DE2363487C3 (en) | Progressive expansion of the route | |
DE3300167A1 (en) | Arrangement for working steep deposits, in particular coal seams | |
DE2211605C3 (en) | Wandering route expansion | |
DE1583039B1 (en) | Longwall equipment with mining machine for a short longwall | |
DE3237969A1 (en) | HIKING ROUTE OR STABLE REMOVAL | |
DE2808487A1 (en) | Mine support and conveyor system - has roof member overhanging face conveyor and rear shield diverting roof material onto rear conveyor | |
DE1932378A1 (en) | Self-advancing pit support element | |
DE1921314B2 (en) | Mine heading machine advancing system - has powered side frames which advance at right angles to machine sled between | |
DE1199725B (en) | Longwall construction, consisting of frame-like, height-adjustable support frames set up at a distance from one another, which can be pulled forward by means of back cylinders | |
DE7225603U (en) | Wandering expansion element | |
DE2453225A1 (en) | Three frame shield for steep seams - with frames advanced via interposed rails forming part of centre frame guide | |
DE3301530C2 (en) | ||
DE1458679C3 (en) | Wandering expansion for underground mining | |
DE3319313A1 (en) | Forepoling device for hydraulic self-advancing powered support assemblies | |
DE2312557C3 (en) | Procedure for operating longwall equipment for underground mining | |
DE2406751C2 (en) | Hydraulic pit lining | |
DE2050602C (en) | Device for dismantling Lagerstat th in underground mining operations, in particular for use in short struts or for driving machine sheds | |
DE3031113A1 (en) | Opening up mine face working area - involves retaining initially guided support units to secure long face entry zone | |
DE977365C (en) | Wandering longwall mining |