DE202006012732U1 - Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete - Google Patents
Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete Download PDFInfo
- Publication number
- DE202006012732U1 DE202006012732U1 DE202006012732U DE202006012732U DE202006012732U1 DE 202006012732 U1 DE202006012732 U1 DE 202006012732U1 DE 202006012732 U DE202006012732 U DE 202006012732U DE 202006012732 U DE202006012732 U DE 202006012732U DE 202006012732 U1 DE202006012732 U1 DE 202006012732U1
- Authority
- DE
- Germany
- Prior art keywords
- concrete
- reinforcing rod
- introducing
- feed device
- production line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/08—Producing shaped prefabricated articles from the material by vibrating or jolting
- B28B1/084—Producing shaped prefabricated articles from the material by vibrating or jolting the vibrating moulds or cores being moved horizontally for making strands of moulded articles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/08—Producing shaped prefabricated articles from the material by vibrating or jolting
- B28B1/084—Producing shaped prefabricated articles from the material by vibrating or jolting the vibrating moulds or cores being moved horizontally for making strands of moulded articles
- B28B1/085—Introducing non-longitudinal reinforcing elements, e.g. spirally shaped
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
Abstract
Description
Die Erfindung bezieht sich auf eine Vorrichtung, insbesondere Gleitfertiger, zum Herstellen von profilierten Betonelementen, insbesondere eines vorgespannten oder schlaff armierten Betonelementes, mit einem auf einer Fertigungsbahn bewegbaren Formteil mit Einsatzprofilen und mindestens einer dem Formteil Beton zuführenden und verdichtenden, ebenfalls auf der Fertigungsbahn bewegbaren Einrichtung.The The invention relates to a device, in particular slipformer, for producing profiled concrete elements, in particular one prestressed or limp reinforced concrete element, with one on a production line movable molding with insert profiles and at least one of the molding concrete feeding and compressing, also on the production line movable device.
Die
Im
Weiteren offenbart die
Mit einem aus der Praxis bekannten Gleitfertiger werden vorgespannte oder schlaff armierte Betonelemente im Stranggussverfahren hergestellt. Vor dem Betonieren werden wellenförmige Armierungsstäbe manuell an Spanndrähten befestigt und der Gleitfertiger fährt anschließend darüber. Dieses Anbringen der Armierungsstäbe von Hand ist zeitaufwändig und daher teuer. Darüber hinaus ist eine exakte Arbeitsweise erforderlich.With a slipformer known from practice are preloaded or limp reinforced concrete elements produced by continuous casting. Before concreting, corrugated reinforcing bars become manual on tension wires attached and the slipformer then moves over it. This Attaching the reinforcing bars by hand is time consuming and therefore expensive. About that In addition, a precise procedure is required.
Es ist Aufgabe der Erfindung, eine Vorrichtung der eingangs genannten Art zu schaffen, mit der eine kostengünstige und zuverlässige Fertigung von Betonteilen mit einer Armierung zur Herstellung einer Schubarmierung gewährleistet ist.It Object of the invention, a device of the aforementioned To create kind, with the cost-effective and reliable production of concrete parts with a reinforcement for producing a Schubarmierung guaranteed is.
Erfindungsgemäß wird die Aufgabe dadurch gelöst, dass mindestens eine Zuführeinrichtung zum Einbringen mindestens eines wellenförmigen Armierungsstabes in den Beton vorgesehen ist.According to the invention Task solved by that at least one feeder for introducing at least one wave-shaped reinforcing rod into the concrete is provided.
Demnach wird während der Herstellung des Betonelementes in den frischen Beton der Armierungsstab eingesetzt und von dem Beton fixiert. Durch die Zuführeinrichtung ist der Anteil manueller Tätigkeit bei dem Einbringen des Armierungsstabes wesentlich reduziert, weshalb das Bauteil, beispielsweise ein Deckenträger, ein Fenstersturz, eine Rippen- oder Brückenplatte, verhältnismäßig kostengünstig zu fertigen ist. Im Weiteren ist durch die insbesondere an einen vorhandenen Gleitfertiger anbaubare Zuführeinrichtung ein reproduzierbares Montieren des Armierungsstabes sichergestellt. Selbstverständlich ist die Wellenform des Armierungsstabes frei wählbar bzw. unterschiedliche Wellenformen beliebig miteinander kombinierbar, wobei insbesondere periodische, aperiodische, rechteckförmige, trapezförmige und parallelogrammartige Wellenformen verwendet werden.Therefore is during the production of the concrete element in the fresh concrete of the reinforcing rod inserted and fixed by the concrete. Through the feeder is the proportion of manual activity significantly reduced in the introduction of the reinforcing rod, which is why the component, such as a ceiling support, a lintel, a Rib or bridge plate, relatively inexpensive too finished is. In addition, by the particular to an existing Slipformer attachable feeder ensured a reproducible mounting of Armierungsstabes. Of course it is the waveform of Armierungsstabes freely selectable or different Waveforms can be combined with each other, where in particular periodic, aperiodic, rectangular, trapezoidal and parallelogram-like waveforms are used.
In Ausgestaltung setzt die Zuführeinrichtung den Armierungsstab derart in den Beton ein, dass die Umkehrbögen der einen Seite in den Beton und die Umkehrbögen der gegenüberliegenden Seite ins Freie ragen. An den ins Freie ragenden Umkehrbögen lassen sich weitere Stahlteile, wie z. B. Gittermatten, befestigen, um eine Schubarmierung herzustellen.In Design sets the feeder the Reinforcing rod in such a way in the concrete that the reverse bends of the one side into the concrete and the reverse arches to the opposite Side into the open. Let the reversing bows projecting into the open further steel parts, such as. As grid mats, attach to to produce a Schubarmierung.
Zweckmäßigerweise ist die Zuführeinrichtung der dem Formteil Beton zuführenden und verdichtenden Einrichtung nachgeordnet. Demzufolge werden zunächst die Konturen des Betonteils weitgehend fertig gestellt und anschließend der Armierungsstab in den bereits verdichteten Beton eingefügt.Conveniently, is the feeder the concrete supplying the molding and compacting device downstream. Consequently, first the Contours of the concrete part largely completed and then the Reinforcing bar inserted into the already compacted concrete.
Da mit einem Gleitfertiger oftmals sehr lange und/oder breite Betonteile bzw. gleichzeitig Betonteile in einer größeren Anzahl hergestellt werden, ist vorzugsweise die Zuführeinrichtung zum Eintragen mehrerer hintereinander und/oder beabstandet nebeneinander angeordneter Armierungsstäbe ausgebildet. Selbstverständlich können die Armierungsstäbe sowohl unmittelbar hintereinander als auch in einem vorgegebenen Abstand hintereinander angeordnet werden.There with a slip paver often very long and / or wide concrete parts or simultaneously concrete parts are produced in a larger number, is preferably the feeder for entering several consecutively and / or spaced apart arranged reinforcing rods educated. Of course can the reinforcing rods both immediately behind one another as well as in a given one Distance arranged one behind the other.
Damit der mit Beton bedeckte Abschnitt des Armierungsstabes vollständig von Beton umgeben ist, ist nach einer Weiterbildung der Zuführeinrichtung ein Verdichter nachgeschaltet.In order to the concrete covered section of the reinforcing bar completely from Concrete is surrounded, according to a development of the feeder a Compressor downstream.
Vorzugsweise ist das Formteil zur Bildung mindestens einer Kerbe zur Aufnahme des Armierungsstabes ausgebildet. Die Kerbe erleichtert das Einbringen des Armierungsstabes in den verdichteten Beton und wird bei dem sich an das Einbringen des Armierungsstabes anschließenden Verdichtungsvorgang geschlossen. Falls mehrere Armierungsstäbe nebeneinander montiert werden sollen, werden selbstverständlich Kerben in entsprechender Anzahl vorgesehen.Preferably, the molding is formed to form at least one notch for receiving the reinforcing rod. The notch facilitates the introduction of the reinforcing rod in the compacted concrete and is at the time of the introduction the reinforcing bar subsequent compression process closed. If several reinforcing bars to be mounted side by side, of course, notches are provided in appropriate numbers.
Es versteht sich, dass die vorstehend genannten und nachstehend noch zu erläuternden Merkmale nicht nur in der jeweils angegebenen Kombination, sondern auch in anderen Kombinationen verwendbar sind. Der Rahmen der Erfindung ist nur durch die Ansprüche definiert.It It is understood that the above and below to be explained features not only in the specified combination, but also in other combinations are usable. The scope of the invention is only through the claims Are defined.
Die Erfindung wird im Folgenden anhand eines Ausführungsbeispieles unter Bezugnahme auf die zugehörigen Zeichnungen näher erläutert. Es zeigt:The Invention will be described below with reference to an embodiment with reference on the associated Drawings closer explained. It shows:
Die
als Gleitfertiger ausgebildete Vorrichtung zum Herstellen von profilierten
Betonelementen
Die
Zuführeinrichtung
Mit
dem Gleitfertiger lassen sich in Abhängigkeit von dem Formteil
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE202006012732U DE202006012732U1 (en) | 2006-06-28 | 2006-08-17 | Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102006029861.6 | 2006-06-28 | ||
DE102006029861A DE102006029861A1 (en) | 2006-06-28 | 2006-06-28 | Device for producing profiled concrete elements |
DE202006012732U DE202006012732U1 (en) | 2006-06-28 | 2006-08-17 | Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
DE202006012732U1 true DE202006012732U1 (en) | 2006-11-16 |
Family
ID=37490075
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE202006012732U Expired - Lifetime DE202006012732U1 (en) | 2006-06-28 | 2006-08-17 | Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE202006012732U1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008027301A1 (en) | 2008-06-07 | 2009-12-10 | Rev Renewable Energy Ventures, Inc. | Solar system has photovoltaic module for generating electrical energy from sunlight, where concrete support structure is provided, on which photovoltaic module is arranged |
-
2006
- 2006-08-17 DE DE202006012732U patent/DE202006012732U1/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008027301A1 (en) | 2008-06-07 | 2009-12-10 | Rev Renewable Energy Ventures, Inc. | Solar system has photovoltaic module for generating electrical energy from sunlight, where concrete support structure is provided, on which photovoltaic module is arranged |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3781372B1 (en) | Method for producing a component from curable material | |
DE2817110A1 (en) | METHOD AND DEVICE FOR PRODUCING PANELS O.AE. | |
WO2014040653A1 (en) | Reinforcing element for producing prestressed concrete components, concrete component and production methods | |
DE102015008332A1 (en) | Device for reinforcement mounting in formwork elements | |
DE2614036B2 (en) | Device for the production of prefabricated parts from prestressed concrete with immediate bonding, in particular prestressed concrete sleepers | |
EP1605101A1 (en) | Process and apparatus for the fabrication of a multilayered concrete plate | |
EP2032324B1 (en) | Device and method for the production of profiled concrete elements | |
DE2926581C2 (en) | Process for producing a joint tape for rising building walls in civil engineering and a device for carrying out the process | |
DE2649221C3 (en) | Device for producing components from hardening compounds | |
DE202006012732U1 (en) | Device for making profiled concrete elements has at least one feed device for introducing at least one corrugated reinforcing rod into the concrete | |
EP0239053B1 (en) | Prefabricated roller shutter box composed of assembled brick elements, and method for producing it | |
DE102020120895A1 (en) | Shaped body and method for producing a shaped body | |
DD299976A5 (en) | Plant for the production of prestressed concrete elements, in particular of elongate structural elements | |
DE19604766C1 (en) | Formwork element | |
EP2175079B1 (en) | Method for forming a rigid corner reinforcement for reinforced concrete construction, reinforcement element and rigid corner reinforcement | |
EP0715039A1 (en) | Shuttering element | |
DE3543369A1 (en) | Process for reinforcing prefabricated reinforced-concrete compound units and apparatus for carrying out the process | |
DE202008016759U1 (en) | An element | |
EP1629951A2 (en) | Apparatus and process for the manufacture of manhole shafts | |
DE2345202A1 (en) | Insertable concrete reinforcement component spacer bar - with ends for support on form walling and slits to embrace reinforcing iron | |
DE10046407B4 (en) | Process for producing a formwork element made of fiber cement | |
EP0465755A2 (en) | Process for making reinforced concrete beams, slide-casting apparatus therefor, and reinforced concrete beams obtained thereby | |
DE886817C (en) | Method and devices for producing prestressed concrete beams composed of individual hollow bodies or the like. | |
DE10153367A1 (en) | End wall casing for the face of a concrete wall comprises a middle part having a face corresponding to the surface between reinforcing elements already present in the wall, and one or two side cheeks | |
DE2148145A1 (en) | Method for producing a construction plate, in particular wall or ceiling plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R207 | Utility model specification |
Effective date: 20061221 |
|
R150 | Utility model maintained after payment of first maintenance fee after three years |
Effective date: 20091027 |
|
R082 | Change of representative |
Representative=s name: MUELLER, JOCHEN, DIPL.-ING., DE |
|
R151 | Utility model maintained after payment of second maintenance fee after six years |
Effective date: 20121030 |
|
R152 | Utility model maintained after payment of third maintenance fee after eight years | ||
R152 | Utility model maintained after payment of third maintenance fee after eight years |
Effective date: 20140828 |
|
R071 | Expiry of right |