DE19828499A1 - Method for laying wheel track bridge sections - Google Patents
Method for laying wheel track bridge sectionsInfo
- Publication number
- DE19828499A1 DE19828499A1 DE1998128499 DE19828499A DE19828499A1 DE 19828499 A1 DE19828499 A1 DE 19828499A1 DE 1998128499 DE1998128499 DE 1998128499 DE 19828499 A DE19828499 A DE 19828499A DE 19828499 A1 DE19828499 A1 DE 19828499A1
- Authority
- DE
- Germany
- Prior art keywords
- track elements
- track
- obstacle
- swivel support
- elements
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D15/00—Movable or portable bridges; Floating bridges
- E01D15/12—Portable or sectional bridges
- E01D15/133—Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Die Erfindung betrifft aus zwei Spurelementen bestehende, von zwei oder mehr Personen per Hand zu verlegende militärische Brücken gemäß dem Oberbegriff des Anspruchs 1 sowie ein Verfahren zum Verlegen.The invention relates to two track elements consisting of two or more people military bridges to be laid by hand according to the preamble of claim 1 and a method of laying.
Zum Übersetzen über Gräben, Bäche und dergleichen werden militärische Kurzbrücken verwendet. Diese bestehen aus zwei Spurelementen, deren Eigengewicht so bemessen ist, daß sie von zwei oder mehr Mann über eine bestimmte Strecke, beispielsweise 10 m, getragen werden können. Das Verlegen der Spurelemente über den Graben, Bach und dergleichen ist jedoch einigermaßen problematisch. Üblicherweise wird das Spurelement am Ufer auf seine Spitze gestellt. Dann läßt man es über das Hindernis fallen. Dieses Verfahren ist nicht immer erfolgreich. Auch können die Spurelemente selbst sowie das gegenüberliegende Ufer beschädigt werden.Military short bridges are used to translate trenches, streams and the like used. These consist of two track elements, the weight of which is dimensioned that two or more men over a certain distance, for example 10 m, can be worn. Laying the track elements over the ditch, stream and However, the like is somewhat problematic. Usually the track element is on Shore on its tip. Then you drop it over the obstacle. This method is not always successful. The track elements themselves as well as that opposite banks are damaged.
Der vorliegenden Erfindung liegt daher die Aufgabe zugrunde, eine aus zwei Spurelementen bestehende militärische Brücke anzugeben, die schonend verlegt werden kann.The present invention is therefore based on the object, one of two track elements to indicate an existing military bridge that can be carefully laid.
Diese Aufgabe wird gelöst durch eine militärische Brücke mit den Merkmalen des Anspruchs 1.This problem is solved by a military bridge with the features of the claim 1.
Die erfindungsgemäße Brückenkonstruktion umfaßt außer den beiden Spurelementen nur noch eine Schwenkauflage und ein Abspannseil, die beide nur für den ersten Teil des Verlegevorgangs benötigt werden. Diese Hilfselemente sind leicht, einfach zu verlegen, leicht aufzunehmen und leicht zu verstauen. Sie verbinden während des Verlegevorgangs die beiden Spurelemente so, daß diese am einen Ufer bequem montiert, dann über das Hindernis geschwenkt und schließlich so vorsichtig abgesenkt werden können, daß Beschädigungen mit Sicherheit vermieden werden.The bridge construction according to the invention comprises only the two track elements only another swivel pad and guy rope, both only for the first part of the Installation process are required. These auxiliary elements are light, easy to install, easy to take up and easy to store. They connect during the laying process the two track elements so that they are conveniently mounted on one bank, then over the Obstacle can be pivoted and finally lowered so carefully that Damage can be avoided with certainty.
Um das Abspannseil schnell und sicher mit den Spurelementen verbinden zu können, sind gemäß einer Weiterbildung der Erfindung an seinen Enden Formhaken befestigt. In order to be able to connect the guy rope to the track elements quickly and safely According to a development of the invention, molded hooks are attached at its ends.
Spurhalter halten die parallel verlegten Spurelemente auf Abstand.Track keepers keep the parallel track elements at a distance.
Um Verschiebungen der Spurelemente zu verhindern, ist gemäß einer Ausgestaltung der Erfindung eine innere Schubsicherung vorgesehen, bestehend aus zwei über Kreuz verlegten Spannseilen.In order to prevent displacements of the track elements, the Invention an internal thrust device provided, consisting of two crosswise installed tension cables.
Um die Position der verlegten Brücke beim Befahren mit Fahrzeugen sicherstellen zu könne, ist eine äußere Schubsicherung vorzusehen, bestehend aus Ankerseilen und Ankern.In order to be able to ensure the position of the installed bridge when driving on vehicles, An external shear protection must be provided, consisting of anchor cables and anchors.
Um auch längere und/oder tragfähigere Brücken von Hand verlegen zu können, ohne daß die Gewichte zu sehr ansteigen, bestehen die Spurelemente gemäß einer Weiterbildung aus Teilspurelementen, die vor Ort zusammengesetzt werden. Da die an der Schwenkauflage montierten Spurelemente sich stets im Gleichgewicht befinden, besteht die Möglichkeit, auch schwerere Lasten überzusetzen und/oder längere Hindernisse zu überqueren, ohne auf die Verlegung von Hand verzichten zu müssen.To be able to lay longer and / or more stable bridges by hand without According to a further development, the track elements consist of the weights increasing too much Partial track elements that are put together on site. Because the on the swivel pad mounted track elements are always in balance, there is the possibility, too to transfer heavier loads and / or to cross longer obstacles without being on the Having to do without laying by hand.
Eine weitere Aufgabe der vorliegenden Erfindung ist es, ein Verfahren zum schnellen und schonenden Verlegen einer aus zwei Spurelementen bestehenden militärischen Brücke über ein Hindernis anzugeben.Another object of the present invention is to provide a quick and easy method careful laying of a military bridge consisting of two track elements to indicate an obstacle.
Diese Aufgabe wird gelöst durch ein Verfahren mit den Merkmalen des Anspruchs 7.This object is achieved by a method with the features of claim 7.
Dieses Verfahren hat den Vorteil, daß nur zwei leichte und preiswerte Hilfsvorrichtungen benötigt werden, um eine aus Spurefementen bestehende militärische Brücke ohne Verwendung von Kränen, Hubschraubern und dergleichen über ein Hindernis zu verlegen. Dabei ist das Überwinden fast beliebig breiter Hindernisse grundsätzlich möglich, da sich die beiden an der Schwenkauflage befestigten und mit dem Abspannseil zu einem V verbundenen Spurelemente gegenseitig stets im Gleichgewicht halten.This method has the advantage that only two light and inexpensive auxiliary devices are needed to build a military bridge made of trace elements without Use of cranes, helicopters and the like to lay over an obstacle. It is basically possible to overcome obstacles of almost any width because the both attached to the swivel support and with the guy rope to a V always keep the connected track elements in balance.
Anhand der Zeichnung soll die Erfindung in Form eines Ausführungsbeispiels näher erläutert werden. Es zeigen jeweils rein schematisch The invention is to be explained in more detail in the form of an exemplary embodiment with reference to the drawing become. Each show purely schematically
Fig. 1 als Seitenansicht eine militärische Brücke während des ersten Verlegeabschnitts, Fig. 1 as a side view a military bridge during the first installation portion,
Fig. 2 eine Draufsicht auf die Vorrichtung der Fig. 1, Fig. 2 is a plan view of the apparatus of Fig. 1,
Fig. 3 als Seitenansicht die militärische Brücke der Fig. 1 und 2 während des zweiten Verlegeabschnitts und Fig. 3 shows a side view of the military bridge of FIGS. 1 and 2 during the second laying section and
Fig. 4 eine Draufsicht auf eine fertig verlegte Brücke. Fig. 4 is a plan view of a finished bridge.
Fig. 1 als Seitenansicht und Fig. 2 als Draufsicht zeigen eine aus zwei Spurelementen 1, 2 bestehende, von Hand zu verlegende militärische Brücke während des ersten Verlegeabschnitts. Fig. 1 as a side view and Fig. 2 as a plan view show a military bridge consisting of two track elements 1 , 2 to be laid by hand during the first laying section.
Wie insbesondere Fig. 2 erkennen läßt, wird am Ufer eines Grabens 10 zunächst eine Schwenkauflage 3 positioniert, an der zwei Spurelemente 1, 2, schwenkbar und lösbar befestigt werden, wobei die beiden Spurelemente 1, 2 zunächst parallel zum Ufer des Grabens 10 liegen. Anschließend wird ein Abspannseil 4, an dessen beiden Enden Formhaken 5 vorgesehen sind, mit den freien Enden der Spurelemente 1, 2 verhakt. Die Länge des Abspannseils 4 ist so bemessen, daß die Spurelemente 1, 2 ein V bilden, dessen Spitze die Schwenkauflage 3 ist. Diese Situation ist in Fig. 1 gut zu erkennen.As can be seen in particular in FIG. 2, a swiveling support 3 is first positioned on the bank of a trench 10 , on which two track elements 1 , 2 are pivotably and detachably fastened, the two track elements 1 , 2 initially lying parallel to the bank of the trench 10 . Then a guy rope 4 , at the two ends of which shaped hooks 5 are provided, is hooked to the free ends of the track elements 1 , 2 . The length of the guy rope 4 is dimensioned so that the track elements 1 , 2 form a V, the tip of which is the pivoting support 3 . This situation can be clearly seen in FIG. 1.
Anschließend werden die beiden über das Abspannseil 4 verbundenen Spurelemente 1, 2 um 90° gedreht, was sehr einfach möglich ist, weil sich die beiden Spurelemente 1, 2 gegenseitig im Gleichgewicht halten. Durch Anheben des landseitigen Spurelementes 2 senkt sich die Spitze des grabenseitigen Spurelementes 1 auf das gegenüberliegende Ufer. Das Abspannseil 4 kann ausgehängt werden.Then the two track elements 1 , 2 connected via the guy rope 4 are rotated by 90 °, which is very simple because the two track elements 1 , 2 keep each other in equilibrium. By lifting the land-side trace element 2 , the tip of the trench-side trace element 1 lowers on the opposite bank. The guy rope 4 can be removed.
Anschließend wird das landseitige Spurelement 2 von der Schwenkauflage 3 gelöst und kann dann bequem von Hand verlegt werden. Diese Situation ist in Fig. 3 dargestellt.Then the land-side track element 2 is detached from the swivel support 3 and can then be conveniently installed by hand. This situation is shown in Fig. 3.
Fig. 4 zeigt als Draufsicht die fertig verlegte militärische Brücke, bestehend aus den zwei parallelen Spurelementen 1, 2. Diese sind durch Abstandhalter 6 auf exakten Abstand gehalten. Eine innere Schubsicherung, bestehend aus zwei über Kreuz verlegten Spannseilen 8, sorgt für eine feste Verbindung der beiden Spurelemente 1, 2, so daß die Brücke problemlos begangen und befahren werden kann. FIG. 4 shows a top view of the completed military bridge consisting of the two parallel track elements 1 , 2 . These are kept at an exact distance by spacers 6 . An internal thrust safety device, consisting of two tension cables 8 laid crosswise, ensures a firm connection of the two track elements 1 , 2 , so that the bridge can be walked on and driven over without any problems.
Eine äußere Schubsicherung aus Ankerseilen 7 und entsprechenden Erdankern sorgt bei Bedarf für eine geeignete Verankerung an beiden Ufern.An external shear protection from anchor cables 7 and corresponding ground anchors ensures suitable anchoring on both banks if necessary.
Wie Fig. 4 schließlich noch erkennen läßt, können die Spurelemente 1, 2 auch aus jeweils zwei oder mehr Teilspurelementen 1.1, 1.2; 2.1, 2.2 bestehen. Jedes Teilspurelement ist beispielsweise so dimensioniert, daß es von zwei Mann getragen werden kann. Die zusammengesetzten Spurelemente 1, 2 lassen sich jedoch mit Hilfe der Schwenkauflage 3 und des Abspannseils 4 genauso verlegen wie beschrieben, weil sie sich stets im Gleichgewicht befinden. . As can be seen Fig 4, finally, the trace elements 1, 2 may also consist of two or more partial trace elements 1.1 to 1.2; 2.1 , 2.2 exist. Each track element is dimensioned, for example, so that it can be carried by two men. The assembled track elements 1 , 2 can, however, be laid with the help of the pivoting support 3 and the guy rope 4 as described because they are always in balance.
Claims (7)
- 1. es ist eine Schwenkauflage (3) vorgesehen,
- 2. die Spurelemente (1, 2) sind an der Schwenkauflage (3) schwenkbar und lösbar zu befestigen,
- 3. ein Abspannseil (4) verbindet die Enden der Spurelemente (1, 2) während des Verlegevorgangs,
- 4. die Länge des Abspannseils (4) ist so bemessen, daß die Spurelemente (1, 2) ein V bilden, dessen Spitze die Schwenkauflage (3) ist.
- 1. a swivel support ( 3 ) is provided,
- 2. the track elements ( 1 , 2 ) are pivotably and detachably fastened to the swivel support ( 3 ),
- 3. a guy rope ( 4 ) connects the ends of the track elements ( 1 , 2 ) during the laying process,
- 4. the length of the guy rope ( 4 ) is dimensioned so that the track elements ( 1 , 2 ) form a V, the tip of which is the swivel support ( 3 ).
- 1. an den Enden des Abspannseils (4) sind Formhaken (5) befestigt.
- 1. Shaped hooks ( 5 ) are attached to the ends of the guy rope ( 4 ).
- 1. Spurhalter (6) halten die Spurelemente (1, 2) auf Abstand.
- 1. Track holder ( 6 ) keep the track elements ( 1 , 2 ) at a distance.
- 1. es ist eine innere Schubsicherung vorgesehen, bestehend aus zwei über Kreuz verlegten Spannseilen (8).
- 1. An internal thrust protection is provided, consisting of two tension cables ( 8 ) laid crosswise.
- 1. es ist eine äußere Schubsicherung vorgesehen, bestehend aus Ankerseilen (7) und Ankern.
- 1. An external thrust protection is provided, consisting of anchor cables ( 7 ) and anchors.
- 1. die Spurelemente (1, 2) sind aus zwei oder mehr Teilspurelementen (1.1, 1.2, 2.1, 2.2) zusammengesetzt.
- 1. the track elements ( 1 , 2 ) are composed of two or more partial track elements ( 1.1 , 1.2 , 2.1 , 2.2 ).
- 1. am Ufer des zu überwindenden Hindernisses (10) wird eine Schwenkauflage (3) positioniert,
- 2. die einen Enden der beiden parallel zum Ufer orientierten Spurelemente (1, 2) werden mit der Schwenkauflage (3) lösbar und schwenkbar verbunden,
- 3. die freien Enden der beiden Spurelemente (1, 2) werden mit Hilfe eines Abspannseils (4) verbunden,
- 4. die Länge des Abspannseils (4) ist so bemessen, daß die Spurelemente (1, 2) ein V bilden, dessen Spitze die Schwenkauflage (3) ist,
- 5. die Spurelemente (1, 2) werden gedreht, bis das hindernisseitige Spurelement (1) das Hindernis (10) überragt,
- 6. durch Anheben des landseitigen Spurelements (2) wird das hindernisseitige Spurelement (1) auf das jenseitige Ufer abgesenkt,
- 7. das Abspannseil (4) wird ausgehängt,
- 8. die Schwenkauflage (3) wird gelöst,
- 9. das landseitige Spurelement (2) wird auf dem hindernisseitigen Spurelement (1) über das Hindernis (10) getragen und parallel abgelegt.
- 1. a swivel support ( 3 ) is positioned on the bank of the obstacle ( 10 ) to be overcome,
- 2. the one ends of the two track elements ( 1 , 2 ) oriented parallel to the bank are detachably and pivotably connected to the swivel support ( 3 ),
- 3. the free ends of the two track elements ( 1 , 2 ) are connected with the help of a guy rope ( 4 ),
- 4. the length of the guy rope ( 4 ) is dimensioned so that the track elements ( 1 , 2 ) form a V, the tip of which is the swivel support ( 3 ),
- 5. the track elements ( 1 , 2 ) are rotated until the obstacle-side track element ( 1 ) projects over the obstacle ( 10 ),
- 6. by lifting the land-side track element ( 2 ), the obstacle-side track element ( 1 ) is lowered onto the beyond bank,
- 7. the guy rope ( 4 ) is unhooked,
- 8. the swivel support ( 3 ) is released,
- 9. the land-side track element ( 2 ) is carried on the obstacle-side track element ( 1 ) over the obstacle ( 10 ) and stored in parallel.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998128499 DE19828499A1 (en) | 1998-06-26 | 1998-06-26 | Method for laying wheel track bridge sections |
NO992602A NO992602L (en) | 1998-06-26 | 1999-05-31 | Military bridge and method of laying it |
SE9902116A SE9902116L (en) | 1998-06-26 | 1999-06-07 | Military bridge and procedure for laying the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998128499 DE19828499A1 (en) | 1998-06-26 | 1998-06-26 | Method for laying wheel track bridge sections |
Publications (1)
Publication Number | Publication Date |
---|---|
DE19828499A1 true DE19828499A1 (en) | 1999-12-30 |
Family
ID=7872094
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1998128499 Withdrawn DE19828499A1 (en) | 1998-06-26 | 1998-06-26 | Method for laying wheel track bridge sections |
Country Status (3)
Country | Link |
---|---|
DE (1) | DE19828499A1 (en) |
NO (1) | NO992602L (en) |
SE (1) | SE9902116L (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007138100A1 (en) * | 2006-05-31 | 2007-12-06 | Ets A. Deschamps Et Fils | Temporary bridge |
CN105463999A (en) * | 2016-01-06 | 2016-04-06 | 秦皇岛天业通联重工股份有限公司 | Segment assembled bridging machine and curve bridging method |
RU2666164C2 (en) * | 2016-05-26 | 2018-09-06 | Александр Николаевич Головин | Assembling of bridge spans with the use of hinge |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3145582A1 (en) * | 1980-11-27 | 1982-08-12 | The Secretary Of State For Defence In Her Britannic Majesty's Government Of The United Kingdom Of Great Britain And Northern Ireland, London | "TRANSPORTABLE BRIDGE AND METHOD FOR DESIGNING THE SAME" |
-
1998
- 1998-06-26 DE DE1998128499 patent/DE19828499A1/en not_active Withdrawn
-
1999
- 1999-05-31 NO NO992602A patent/NO992602L/en not_active Application Discontinuation
- 1999-06-07 SE SE9902116A patent/SE9902116L/en not_active Application Discontinuation
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3145582A1 (en) * | 1980-11-27 | 1982-08-12 | The Secretary Of State For Defence In Her Britannic Majesty's Government Of The United Kingdom Of Great Britain And Northern Ireland, London | "TRANSPORTABLE BRIDGE AND METHOD FOR DESIGNING THE SAME" |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007138100A1 (en) * | 2006-05-31 | 2007-12-06 | Ets A. Deschamps Et Fils | Temporary bridge |
FR2901817A1 (en) * | 2006-05-31 | 2007-12-07 | A Deschamps & Fils Soc Par Act | TEMPORARY BRIDGE |
EA014129B1 (en) * | 2006-05-31 | 2010-10-29 | Этс А. Дешам Э Фис | Temporary bridge |
US8955184B2 (en) | 2006-05-31 | 2015-02-17 | ETS A. Deschamps et Eils | Temporary bridge |
CN105463999A (en) * | 2016-01-06 | 2016-04-06 | 秦皇岛天业通联重工股份有限公司 | Segment assembled bridging machine and curve bridging method |
RU2666164C2 (en) * | 2016-05-26 | 2018-09-06 | Александр Николаевич Головин | Assembling of bridge spans with the use of hinge |
Also Published As
Publication number | Publication date |
---|---|
NO992602L (en) | 1999-12-27 |
SE9902116L (en) | 1999-12-27 |
SE9902116D0 (en) | 1999-06-07 |
NO992602D0 (en) | 1999-05-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2858062C2 (en) | Device for aligning a pipe section on a pipe-laying ship | |
CH660896A5 (en) | ROADWAY BARRIER BAR. | |
DE2120178B2 (en) | LINING SEGMENT AND METHOD OF LINING A TUNNEL | |
EP0391149B1 (en) | Portable bridge and system for placing the bridge | |
DE7415898U (en) | BRIDGING DEVICE FOR AN EXPANSION JOINT IN A ROAD | |
DE19828499A1 (en) | Method for laying wheel track bridge sections | |
DE2361133A1 (en) | FRAMEWORK CRANE | |
DE1658623A1 (en) | Motor vehicle with a device for transporting and laying bridges | |
DE1201441B (en) | Device for laying cables | |
DE19718414C2 (en) | Process for lining a channel with foil | |
DE2932600A1 (en) | Transportable airfield runway paving section - comprises row of concrete slabs hinged together at ends and connected by cables | |
DE202017004574U1 (en) | Apparatus for laying geotextile webs | |
DE3604758C1 (en) | Mobile device for unloading and laying as well as for picking up and loading bridge parts, pontoons or the like. | |
DE2406375A1 (en) | ELEMENT FOR THE FORMATION OF A BASE FOR SKIING | |
DE102017008215B4 (en) | Method and device for laying geotextile sheets | |
EP2966224B1 (en) | Spreading device for a bridge rope dressing | |
EP0336008A1 (en) | Catch-fence arrangement | |
DE3414197C2 (en) | ||
DE69836850T2 (en) | Convertible ground-based traffic control system for lanes | |
DE491887C (en) | Device for the automatic laying of electrical cables | |
DE3504977A1 (en) | Cable shaft for a cable plough | |
DE8323928U1 (en) | Device for laying rollable flooring | |
DE1924341A1 (en) | Anchoring for posts of guardrails, railings or the like. on roadways | |
DE3330098A1 (en) | Device for laying a rollable floor covering | |
DE69511640T2 (en) | Device for supporting trenches |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OM8 | Search report available as to paragraph 43 lit. 1 sentence 1 patent law | ||
8139 | Disposal/non-payment of the annual fee |