DE19525590C2 - Construction of an excavation pit with anchoring below the water table - Google Patents
Construction of an excavation pit with anchoring below the water tableInfo
- Publication number
- DE19525590C2 DE19525590C2 DE1995125590 DE19525590A DE19525590C2 DE 19525590 C2 DE19525590 C2 DE 19525590C2 DE 1995125590 DE1995125590 DE 1995125590 DE 19525590 A DE19525590 A DE 19525590A DE 19525590 C2 DE19525590 C2 DE 19525590C2
- Authority
- DE
- Germany
- Prior art keywords
- pit
- box
- excavation
- wall
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
Unsere Erfindung betrifft ein Verfahren zur Herstellung einer Baugrube in Gebieten mit hohen Grundwasserspiegeln, bei denen zusätzlich ein Absenken nicht zugelassen ist.Our invention relates to a method for producing an excavation pit in areas with high groundwater levels, where an additional Lowering is not permitted.
Der Normalfall für eine Erstellung einer Baugrube in einem solchen Gebiet wäre eine Bauweise, die zumindest zeitlich begrenzt eine Grundwasserabsenkung vorsieht. Bei einer Grundwasserhaltung wird mit Brunnen der Grundwasserspiegel in der Baugrube abgesenkt und das abgepumpte Grundwasser abgeleitet. Der Grundwasserspiegel unter den umliegenden Liegenschaften wird dabei ebenfalls betroffen, da sich der Grundwasserspiegel in Form eines Absenktrichters je nach Durchlässigkeit des Untergrundes, Durchlässigkeit des Grundwasser horizontes, Absenktiefe und Dauer der Absenkung bis in mehrere Kilo meter Entfernung absenken kann.The normal case for creating a construction pit in one The area would be a construction method, at least for a limited time Groundwater lowering. In the case of groundwater management with the well the groundwater level in the excavation pit and the drained groundwater drained off. The water table among the surrounding properties is also affected, since the groundwater level changes depending on the shape of a lowering funnel Permeability of the subsoil, permeability of the groundwater horizons, lowering depth and duration of lowering up to several kilos meters distance.
In manchen Städten bestehen sehr hohe Anforderungen bezüglich der Beeinflussung des Grundwasserstandes, so daß es nicht einmal mög lich ist, für eine Baumaßnahme das Grundwasser 2 bis 3 m abzusen ken. Zudem werden Injektionssohlen, die Baugruben unten mit einer Art Deckel abschließen, nicht immer zugelassen, da sie teilweise mit dem Einbringen von Chemikalien arbeiten und wegen der Auftriebssicherheit sehr tief geführte Baugrubenwänden erforderlich sind. Die Injektions sohle ist wegen der Auftriebssicherheit etwa in gleicher Tiefe unter der Baugrubensohle anzuordnen wie das Grundwasser über der Baugru bensohle steht. Für den Fall, daß Bauherr oder die Genehmigungsbe hörde keine solche Injektionssohle als wasserdichten Sohlabschluß oder keine so tiefen Dichtungswände zuläßt, muß die Sohle der Bau grube mit Unterwasserbeton betoniert werden.In some cities there are very high requirements regarding the Influencing the groundwater level so that it is not even possible Lich is to sink the groundwater 2 to 3 m for a construction measure ken. In addition, injection soles, the construction pits below with a kind Lock the lid, not always approved, since it is partially with the Introducing chemicals work and because of the buoyancy safety very deep excavation walls are required. The injection sole is about the same depth below the ground due to the safety against buoyancy Arrange the pit of the pit like the groundwater above the building plot sole stands. In the event that the client or the approval do not hear such an injection sole as a waterproof sole cover or does not allow such deep sealing walls, the sole of the construction must pit to be concreted with underwater concrete.
Unsere Erfindung befaßt sich mit der Herstellung einer Baugrube unter den Bedingungen, daß kein Grundwasser, auch nicht kurzfristig, abge senkt werden darf und daß eine Sohle aus Unterwasserbeton zu erstel len ist. Bisher konnte in einem solchen Fall die die Baugrube umschlie ßende Baugrubenwand lediglich oberhalb des Grundwasserspiegels verankert werden. Dadurch entstanden für die Baugrubenwände große Spannweiten zwischen der Unterwasserbetonsohle als unteres Aufla ger der Baugrubenwand und den Ankeransatzpunkten als oberes Auf lager. Die Baugrubenwand muß damit wesentlich höhere Biegemo mente und Verformungen aufnehmen als bei tiefer gesetzten Ankeran satzpunkten. Die Biegemomente steigen mehr als quadratisch zum Abstand zwischen den Ankerpunkten, deshalb sind Baugrubenwände mit größerer Spannweite erheblich stärker auszulegen. Die Kosten für die Baugrubenwände, die ja oft nur zeitlich begrenze Auflagen erfüllen müssen, steigen damit entsprechend.Our invention is concerned with the manufacture of an excavation pit the conditions that no groundwater, even in the short term, abge may be lowered and that a sole made of underwater concrete len is. So far, in such a case, the pit could be enclosed The excavation pit wall only above the groundwater table be anchored. This resulted in large ones for the pit walls Spans between the underwater concrete floor as a lower support the top of the pit and the anchor attachment points camp. The pit wall must therefore have a much higher bending rate absorbing elements and deformations than when the anchor is set lower sentence points. The bending moments increase more than quadratically Distance between the anchor points, therefore there are construction pit walls to be designed much stronger with a wider span. The price for the pit walls, which often only meet temporary requirements must rise accordingly.
Unsere Erfindung beseitigt die Nachteile der großen Durchbiegungen der Baugrubenwände durch ein Herstellverfahren, das den Einbau von Ankern unter den genannten restriktiven Verhältnissen auch unterhalb des Grundwasserspiegels zuläßt. Wegen der exponentiellen Zunahme der. Biegemomente und der Durchbiegungen ist das hier vorgesehenen Verfahren gerade bei tiefen Baugruben, die unten von einer Un terwasserbetonsohle und oben von nur einer Ankerlage gesichert wer den können, die zudem oberhalb des Wasserspiegels liegen muß, vorteilhaft.Our invention eliminates the drawbacks of large deflections of the pit walls through a manufacturing process that involves the installation of Anchoring below the restrictive conditions mentioned below of the groundwater level. Because of the exponential increase of the. Bending moments and deflections is what is provided here Procedure especially for deep construction pits, which are marked by an Un water concrete base and above secured by only one anchor layer who can, which must also be above the water level, advantageous.
Die Durchführung unseres erfindungsgemäßen Verfahren läßt sich an hand der Fig. 1 bis 4 erläutern.The implementation of our method according to the invention can be explained with reference to FIGS. 1 to 4.
Fig. 1 Baugrube mit Verankerung gemäß Stand der Technik Fig. 1 pit with anchoring according to the prior art
Fig. 2 Baugrube mit Graben Fig. 2 pit with trench
Fig. 3 Spannen des Ankers im Schutz eines Betonkastens Fig. 3 tensioning the anchor in the protection of a concrete box
Fig. 4 Ausbau der Baugrube Fig. 4 removal of the excavation pit
Fig. 1 (Stand der Technik) stellt einen Schnitt durch eine Baugrube dar. Von der Oberfläche (1) aus werden die begrenzenden Baugrubenwände (2) in den Baugrund eingebracht. Das Grundwasserniveau (4) reicht sehr nahe an die Oberfläche heran. Die Baugrube soll bis zum Niveau (3) ausgehoben werden. Nach dem Stand der Technik würden im Bereich oberhalb des Grundwassers die Anker (5") mit den Verpreßkörpern (6") gesetzt. Das Spannen der Anker kann konventionell oberhalb des Grundwasserspiegels erfolgen. Danach würde der Erdaushub erfolgen, die Baugrube bleibt mit Grundwasser gefüllt stehen. Als Abschluß würde die Sohle aus Unterwasserbeton erstellt und das Wasser abgepumpt. Die Bau grubenwand müßte den gesamten Erddruck zwischen den Punkten A" und B abfangen. Fig. 1 (prior art) depicts a section through a pit. From the surface (1) of the limiting excavation walls (2) are introduced into the ground. The groundwater level ( 4 ) is very close to the surface. The construction pit should be excavated up to level ( 3 ). According to the prior art, the anchors ( 5 ") with the pressing bodies ( 6 ") would be set in the area above the groundwater. The anchors can be tensioned conventionally above the groundwater table. Then the earth would be excavated, the excavation pit remains filled with groundwater. The bottom would be made of underwater concrete and the water would be pumped out. The pit wall would have to absorb the entire earth pressure between points A "and B.
Fig. 2 zeigt das Vorgehen in unserem erfindungsgemäßen Verfahren. Zunächst wird die Baugrubenwand erstellt. Dabei kommen je nach An forderung Schlitzwände oder Stahlspundwände zum Einsatz. Anschlie ßend wird längs der Baugrubenwand ein Graben ausgehoben, der zur Baugrubeninnenseite angeböscht wird. Die Basisbreite des Graben muß einige Meter betragen. Von der Oberfläche (1) der Baugrube aus werden dann die Anker eingebracht. Das Ankergerät (7) steht dabei auf dem ursprünglichen Niveau der Erdoberfläche oder auf einem Planum knapp über dem Grundwasserspiegel. Die Bohrrichtung für das Anker gerät kann über eine Rohrführung des Bohrgestänges vorgegeben werden. Damit können die Anker unterhalb des Grundwasserspiegels im richtigen Winkel gesetzt werden. Gegebenenfalls ist die Rohrführung an der Baugrubenwand (2) zu fixieren. Ist die Baugrubeneinfassung ei ne Schlitzwand, können Aussparungen in der vorher bestimmten Posi tion vorgesehen sein. Falls notwendig kann ein Taucher die Öffnungen nach dem Herstellen des Grabens freilegen und das Bohrgestänge einführen. Bei einer Spundwand ist unter Wasser eine Öffnung her zustellen, nach dem Einsetzen des Bohrgestänges am richtigen An satzpunkt A wird der Anker in üblichen Verfahren hergestellt. Beispiel haft ist in Fig. 2 ein Verpreßanker gezeigt. Der Ankerstab oder das Spannstahlbündel am Ankerkopf muß bei dieser Art der Herstellung ei ne größere Toleranz erhalten, damit nicht das Problem entsteht, daß der Stahl zu kurz aus der Baugrube hervorsteht und beim späteren Spannvorgang nicht richtig erfaßt werden kann. FIG. 2 shows the procedure in our invention. First, the construction pit wall is created. Depending on the requirements, diaphragm walls or sheet piling are used. Then a trench is dug along the wall of the excavation pit, which is then blown open to the inside of the excavation pit. The base width of the trench must be a few meters. The anchors are then introduced from the surface ( 1 ) of the construction pit. The anchor device ( 7 ) is at the original level of the earth's surface or on a level just above the groundwater level. The drilling direction for the anchor device can be specified via a pipe guide of the drill pipe. This allows the anchors to be placed at the correct angle below the water table. If necessary, fix the pipe guide to the construction pit wall ( 2 ). If the pit is a diaphragm wall, recesses can be provided in the previously determined position. If necessary, a diver can uncover the openings after making the trench and insert the drill pipe. In the case of a sheet pile wall, an opening has to be made under water, after the drill pipe has been inserted at the correct point A, the anchor is manufactured using conventional methods. An injection anchor is shown by way of example in FIG. 2. The anchor rod or the prestressing steel bundle on the anchor head must have a greater tolerance in this type of manufacture so that there is no problem that the steel protrudes too short from the excavation pit and cannot be correctly grasped during the later tensioning process.
Fig. 3 zeigt den Spannprozeß des gesetzten Ankers im Grundwasser. Ein Betonkasten (10), der aufgrund seines hohen Gewichts im Grund wasser abgesenkt werden kann, wird über einen Hebeeinrichtung (8) in den mit Wasser gefüllten Graben eingeschwenkt und abgesenkt. Der Betonkasten ist an einer Stirnseite und oben offen. Längs der Beran dung der offenen Kastenseite befindet sich ein Dichtungselement (11). Die Dichtung kann aufblasbar oder über einen Hydraulik bedienbar sein. Ist der Kasten in der Position, die man zum Spannen des Ankers vorgesehen hat, wird die Dichtung aktiviert und der Innenraum vom Wasser entleert. Der Horizontaldruck des außerhalb stehenden Was sers preßt den Kasten an die Dichtwand und man erhält eine gute Dichtigkeit. Eine beispielhafte Größe des Kastens wäre eine Tiefe von 2 bis 4 m, eine Breite von 2 bis 3 m und eine offene Längsseite von 2 bis 6 m. Fig. 3 shows the tensioning process of the set anchor in the groundwater. A concrete box ( 10 ), which can be lowered due to its high weight in the ground water, is pivoted and lowered into the trench filled with water via a lifting device ( 8 ). The concrete box is open at one end and at the top. Along the edge of the open box side there is a sealing element ( 11 ). The seal can be inflatable or operated via a hydraulic system. If the box is in the position intended for tensioning the anchor, the seal is activated and the interior is drained of water. The horizontal pressure of the water standing outside presses the box against the sealing wall and you get a good seal. An exemplary size of the box would be a depth of 2 to 4 m, a width of 2 to 3 m and an open long side of 2 to 6 m.
Im Kasten können dann alle Arbeiten zum Spannen der Anker erfolgen. Der Ankerpunkt A und der spätere Auflagerpunkt der Baugrubenwand an der Unterwasserbetonsohle B liegen mit diesem Verfahren wesent lich näher beieinander. Die Baugrubenwand kann damit erheblich günstiger dimensioniert werden.All work for tensioning the anchors can then be carried out in the box. The anchor point A and the later support point of the excavation wall with this method, the underwater concrete base B is essential closer together. The pit wall can thus be considerable be dimensioned more favorably.
In Fig. 4 wird das weitere Vorgehen skizziert. Nach dem Setzen und Spannen der "Unterwasseranker" wird das Erdreich in der Baugrube ausgehoben. Auf der Aushubsohle wird der Unterwasserbeton (12) eingebracht. Die Betonsohle muß auftriebssicher gestaltet werden. Entweder wird eine Schwergewichtssohle eingebaut oder die Sohle wird nach unten verankert. Anschließend kann man das Grundwasser abpumpen.The further procedure is outlined in FIG. 4. After the "underwater anchors" have been set and tensioned, the soil in the construction pit is excavated. The underwater concrete ( 12 ) is placed on the excavation base. The concrete base must be designed to be buoyancy-proof. Either a heavyweight sole is installed or the sole is anchored down. You can then pump off the groundwater.
Eine weitere Ausführungsform unserer Erfindung verwendet statt des Betonkastens einen Kasten aus Stahl, der eventuell mit Ballast be schwert werden muß.Another embodiment of our invention uses instead of Concrete box, a box made of steel, which may be ballasted must be sword.
11
Oberfläche
surface
22nd
Baugrubenwand
Pit wall
33rd
Baugrubensohle
Excavation pit
44th
Grundwasserspiegel
Groundwater level
55
Anker
anchor
66
Verpreßkörper
Grouting body
77
Ankergerät
Anchor device
88th
Hebezeug
Hoist
99
Aufhängung
suspension
1010th
Kasten
box
1111
Dichtung
poetry
1212th
Unterwasserbetonsohle
Underwater concrete sole
Claims (8)
- 1. a.) zuerst die Baugrubenwand (2) erstellt wird,
- 2. b.) zur Bildung eines Grabens längs der Baugrubenwand (2) das Erdreich innerhalb der Baugrube abgetragen wird,
- 3. c.) von einer Oberfläche (1) oder einem Planum oberhalb des Grundwasserspiegels (4) Anker eingebracht werden, wobei Verankerungsglieder mit Ankeransatzpunkten (A), die mehrere Meter unterhalb des Grundwasserspiegels (4) liegen, hergestellt werden,
- 4. d.) ein oben offener Kasten (10), der auch eine seitliche Öffnung aufweist, in den mit Wasser gefüllten Graben eingebracht wird und der Kasten (10) mit der seitlichen Öffnung an der Baugrubenwand (2) dicht abschließend angeordnet wird,
- 5. e.) der Kasten (10) dann leergepumpt wird, so daß die Verankerungspunkte (A) im Trockenen liegen, wobei
- 6. f.) anschließend die Anker (5) im Trockenen gespannt werden,
- 7. g.) nach Ausführung aller Verankerungen der Kasten (10) entfernt,
- 8. h.) das Erdreich in der Baugrube ausgehoben wird,
- 9. i.) auf der Aushubsohle (3) der Unterwasserbeton (12) eingebracht wird und
- 10. k.) nach Verfestigung des Betons (12) das Grundwasser in der Baugrube abgepumpt wird.
- 1. a.) First the construction pit wall ( 2 ) is created,
- 2. b.) To form a trench along the excavation wall ( 2 ), the soil within the excavation pit is removed,
- 3. c.) Anchors are introduced from a surface ( 1 ) or a flat surface above the groundwater table ( 4 ), anchoring members with anchor attachment points (A) lying several meters below the groundwater table ( 4 ) being produced,
- 4. d.) A box ( 10 ) which is open at the top and also has a side opening, into which the trench filled with water is introduced and the box ( 10 ) with the side opening is arranged in a sealed manner on the construction pit wall ( 2 ),
- 5. e.) The box ( 10 ) is then pumped empty, so that the anchoring points (A) are dry, whereby
- 6. f.) The anchors ( 5 ) are then stretched dry,
- 7. g.) The box ( 10 ) is removed after execution of all anchorings,
- 8. h.) The earth is excavated in the construction pit,
- 9. i.) On the excavation base ( 3 ) of the underwater concrete ( 12 ) and
- 10. k.) After the concrete ( 12 ) has solidified, the groundwater is pumped out in the excavation pit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1995125590 DE19525590C2 (en) | 1995-07-13 | 1995-07-13 | Construction of an excavation pit with anchoring below the water table |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1995125590 DE19525590C2 (en) | 1995-07-13 | 1995-07-13 | Construction of an excavation pit with anchoring below the water table |
Publications (2)
Publication Number | Publication Date |
---|---|
DE19525590A1 DE19525590A1 (en) | 1997-01-16 |
DE19525590C2 true DE19525590C2 (en) | 1999-04-29 |
Family
ID=7766765
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1995125590 Expired - Fee Related DE19525590C2 (en) | 1995-07-13 | 1995-07-13 | Construction of an excavation pit with anchoring below the water table |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE19525590C2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1296571C (en) * | 2004-04-09 | 2007-01-24 | 南京大学 | Method for supporting foundation trench for agitation piles of soil cement with concrete as the core |
IT1392228B1 (en) * | 2008-12-03 | 2012-02-22 | Melegari | PROCEDURE FOR THE CONSOLIDATION AND / OR REINFORCEMENT OF PORT BANKS |
CN103015431B (en) * | 2012-12-04 | 2014-09-10 | 北京建材地质工程公司 | Foundation pit supporting method for manual dig-hole cement-soil steel pile |
CN104532855B (en) * | 2014-12-31 | 2017-03-15 | 云南建工基础工程有限责任公司 | A kind of built pile supporting construction in deep peat swamps evolution |
CN106522251A (en) * | 2016-10-28 | 2017-03-22 | 广州机施建设集团有限公司 | Geological drill hole confined water spewing water head balanced construction method |
CN108611930A (en) * | 2018-06-07 | 2018-10-02 | 重庆工业职业技术学院 | A kind of laying method of track bed |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1137996B (en) * | 1959-06-16 | 1962-10-11 | Ralph Lutz Dr Ing | Method for pulling an anchor for sheet piling or bank walls or similar support structures into the ground |
DE3535319A1 (en) * | 1985-10-03 | 1987-04-09 | Dyckerhoff & Widmann Ag | METHOD AND DEVICE FOR ANCHORING AT LEAST PARTLY UNDER WATER-SIDED BALLS |
-
1995
- 1995-07-13 DE DE1995125590 patent/DE19525590C2/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1137996B (en) * | 1959-06-16 | 1962-10-11 | Ralph Lutz Dr Ing | Method for pulling an anchor for sheet piling or bank walls or similar support structures into the ground |
DE3535319A1 (en) * | 1985-10-03 | 1987-04-09 | Dyckerhoff & Widmann Ag | METHOD AND DEVICE FOR ANCHORING AT LEAST PARTLY UNDER WATER-SIDED BALLS |
Non-Patent Citations (1)
Title |
---|
BEHRENDT, J., Dipl.-Ing.: Die Wand-Sohle- Methode als grundwasserschonende Bauweise. In: Tiefbau, Ingenieurbau, Straßenbau, Nr.8, 1977, S.577-579 * |
Also Published As
Publication number | Publication date |
---|---|
DE19525590A1 (en) | 1997-01-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3653795A2 (en) | Construction trench enclosures | |
DE2558404A1 (en) | DEVICE FOR PROTECTING THE FOOT OF A STRUCTURE RISING OR ERECTING ON THE GROUND OF A WATER SURFACE AGAINST WATER FLOOD | |
DE19525590C2 (en) | Construction of an excavation pit with anchoring below the water table | |
DE10239278B4 (en) | Foundation for hydraulic structures | |
EP1336559A1 (en) | Method for lowering under water the floating body of a floating support | |
DE102007003085B4 (en) | Process for producing a sealing wall with optimized precast concrete elements | |
DE19521986C2 (en) | Process for the production of a dry construction pit for a civil engineering structure below the groundwater table | |
EP1033446A1 (en) | Method of erection of a foundation structure in a water flooded excavation | |
EP1426495A2 (en) | Method and device for the construction of a tunnel or a trench | |
DE3620650A1 (en) | Method for producing multi-storey underground structures, in particular underground garages | |
DE19522150C1 (en) | Building-site trench-formation method with ground-water barrier | |
DE19739106C1 (en) | Construction method for foundations etc. in water-filled excavation | |
DE3204410A1 (en) | Method and apparatus for producing conduits, pipelines and the like | |
DE2030259C3 (en) | Process for the production of a structure below the water table | |
DE4240745C1 (en) | Process for the production of a water passage through a barrier structure, in particular made of concrete, under water pressure | |
CH245930A (en) | Pressed concrete construction process for the production of building structures under water. | |
DE19726240C1 (en) | Method of collection and discharge of ground water container | |
EP1553230B1 (en) | Method for rehabilitating retaining walls | |
DE315867C (en) | ||
DE858973C (en) | Process for the production of compressed air foundations on an inclined and possibly overlaid rock soil | |
DE3716750A1 (en) | Method of constructing and sinking foundation structures | |
DE2851619A1 (en) | Concrete post foundation hole prodn. - involves lowering pipe into ground using vibrator and core is removed using differential air pressure | |
DE3144509A1 (en) | Method and device for concreting underwater structures, preferably tunnels | |
DE2410575A1 (en) | Mast foundation for transmission line pylons - shaft has cov, base and openings through which compression substance is injected | |
DE19632541A1 (en) | Single mast tower building footing e.g. for areal mast |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OP8 | Request for examination as to paragraph 44 patent law | ||
D2 | Grant after examination | ||
8363 | Opposition against the patent | ||
8365 | Fully valid after opposition proceedings | ||
8339 | Ceased/non-payment of the annual fee |