DE1708531B1 - Method for producing a temporary ground anchor - Google Patents

Method for producing a temporary ground anchor

Info

Publication number
DE1708531B1
DE1708531B1 DE19681708531 DE1708531A DE1708531B1 DE 1708531 B1 DE1708531 B1 DE 1708531B1 DE 19681708531 DE19681708531 DE 19681708531 DE 1708531 A DE1708531 A DE 1708531A DE 1708531 B1 DE1708531 B1 DE 1708531B1
Authority
DE
Germany
Prior art keywords
anchor
freezing
ground
producing
ground anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19681708531
Other languages
German (de)
Inventor
Auf Nichtnennung Antrag
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Walter Bau AG
Original Assignee
Dyckerhoff and Widmann AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dyckerhoff and Widmann AG filed Critical Dyckerhoff and Widmann AG
Publication of DE1708531B1 publication Critical patent/DE1708531B1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

Die Erfindung bezieht sich auf ein Verfahren zum Herstellen eines temporären Erdankers, bei dem zunächst eine Bohrung erzeugt und nach dem Einführen des Ankers das Bohrloch z. B. mit einem erhärtenden Material, wie Zementschlempe, verpreßt wird.The invention relates to a method of manufacturing a Temporary ground anchor, in which a hole is first created and after insertion of the anchor the borehole z. B. with a hardening material such as cement pulp, is pressed.

Bei der Errichtung der äußeren Begrenzungen von Erdbaukörpern, beispielsweise der lotrechten Wände von Baugrubenverbauungen, Kaimauern od. dgl. ist es bekannt, die Wände außer durch an denselben anliegende Mittel, wie z. B. in den Erdboden gerammte Spundwände, auch durch Verankerungen in das rückwärtige Erdreich zu sichern. Zu diesem Zweck ist es bekannt, horizontal oder gegen die Horizontale geneigte Bohrungen einzubringen, in diese stählerne Ankerstäbe einzuführen und den verbliebenen Hohlraum zwischen den Ankerstäben und der Bohrlochwand mit einem erhärtenden Material auszufüllen, beispielsweise mit Zementschlempe zu verpressen. Die Zementschlempe dringt dabei in die Unebenheiten der Bohrlochwandung und in geringem Umfang auch in die Hohlräume des Bodens ein und bewirkt bei ihrem Erhärten einen Reibungsverbund mit dem Boden.When building the outer boundaries of earth structures, for example the vertical walls of construction pit sheeting, quay walls or the like, it is known the walls except through to the same adjoining means, such as. B. in the ground To secure rammed sheet piling, also by anchoring in the rear soil. For this purpose it is known to have bores that are horizontal or inclined with respect to the horizontal to bring in, to introduce into this steel anchor rods and the remaining cavity to be filled with a hardening material between the anchor rods and the borehole wall, For example, to grout with cement paste. The cement slurry penetrates it into the unevenness of the borehole wall and, to a lesser extent, into the cavities of the soil and, when it hardens, creates a friction bond with the soil.

Solche Erdanker lassen sich bei rolligen Böden mit Erfolg anwenden. Bei bindigen und schluffigen Böden sind diese Verankerungen weniger wirksam, weil sich keine ausreichend tragfähige, den Reibungsverbund bewirkende, Lastübertragungsfiäche ausbildet. Die Folge davon ist, daß der Verankerungskörper, also die erhärtete Zementschlempe, im Boden gleitet. Dieser Effekt wird noch dadurch verstärkt, daß die Bohrlochwand vom Bohren her aufgeweicht und demzufolge gestört ist. Außerdem sind solche Böden schwer injizierbar.Such ground anchors can be used with success in rolling soils. These anchors are less effective in cohesive and silty soils because there is no sufficiently stable load-transferring surface that causes the frictional connection trains. The consequence of this is that the anchoring body, i.e. the hardened cement paste, slides in the ground. This effect is reinforced by the fact that the borehole wall is softened by drilling and therefore disturbed. Besides, such floors are difficult to inject.

Aufgabe der Erfindung ist es, ein Verfahren zu schaffen, um Erdanker auch in solchen schwierigen Bodenarten mit Erfolg herstellen zu können, bzw. die Ausnützbarkeit von Erdankern in bindigen Böden zu erhöhen.The object of the invention is to create a method for ground anchors to be able to successfully produce even in such difficult soil types, or the To increase the usability of ground anchors in cohesive soils.

Die Erfindung löst diese Aufgabe dadurch, daß im Bereich des Ankerendes durch Anwendung der an sich bekannten Bodenverfestigung durch Gefrieren ein Frostkörper erzeugt und während der Benutzung des Erdankers aufrechterhalten wird.The invention solves this problem in that in the area of the anchor end a frozen body by using the per se known soil consolidation by freezing is generated and maintained during the use of the ground anchor.

Die Erfindung greift insoweit zurück auf die bekannten Verfahren zur Bodenverfestigung durch Gefrieren. Dabei wird durch Einleiten einer Gefrierflüssigkeit in Gefrierrohre, die in den Erdboden eingebracht werden, das im Boden befindliche Wasser gefroren und ein fester Frostkörper aus Boden und Wasser erzeugt, der beispielsweise im Sinne eines Ausbruchs bearbeitet werden kann.In this respect, the invention relies on the known methods Soil consolidation by freezing. This is done by introducing a freezing liquid in freezing pipes that are placed in the ground, the one in the ground Water is frozen and a solid body of frost is created from the ground and water, which for example can be edited in the sense of an outbreak.

Bei der Herstellung der temporären Erdanker mit Hilfe des Gefrierverfahrens können durch geeignete Dimensionierung der Gefrierrohre und Wahl der Frostzeit Frostkörper von beliebigen Abmessungen hergestellt werden, die entlang ihres Umfanges eine ausgezeichnete Haftverbindung mit dem Erdreich eingehen, weil der Boden entlang dem Umfang des Frostkörpers ungestört ist. Es läßt sich so eine flächen im Heizkessel und erlaubt sehr verminderte Umfang und von der Länge des Frostkörpers abhängt.In the manufacture of the temporary ground anchors with the help of the freezing process can freeze bodies by suitable dimensioning of the freezing pipes and choosing the frost time of any dimensions can be made, which along its circumference an excellent Adhesive bond with the soil, because the soil runs along the perimeter of the Frost body is undisturbed. It can be a surface in the boiler and allowed very diminished girth and depends on the length of the frozen body.

Dadurch läßt sich die bisher erforderliche Ankerzahl reduzieren. Trotzdem kommt man mit geringen Bohrlochdurchmessern aus, weil die Bohrlöcher nur den eigentlichen Anker und die Gefrierrohre aufnehmen müssen. Die Erfindung wird nachstehend an Hand der in den Zeichnungen dargestellten Ausführungsbeispielen näher erläutert. Es zeigt F i g. 1 einen Längsschnitt durch einen nach dem Verfahren gemäß der Erfindung hergestellten Erdanker, F i g. 2 einen Schnitt entlang der Linie II-II in der Fig.l, F i g. 3 einen Schnitt entlang der Linie 111-III in der F i g. 1 und F i g. 4 ein weiteres Ausführungsbeispiel für die Anordnung der Gefrierrohre.This allows the previously required number of anchors to be reduced. Nevertheless you get by with small drill hole diameters, because the drill holes are only the actual ones Anchors and the freeze pipes need to accommodate. The invention is hereinafter referred to the exemplary embodiments illustrated in the drawings are explained in more detail. It shows F i g. 1 shows a longitudinal section through one produced by the method according to the invention Ground anchor, F i g. 2 shows a section along the line II-II in Fig.l, F i g. 3 a section along the line III-III in FIG. 1 and F i g. 4 another Exemplary embodiment for the arrangement of the freezing pipes.

Zur Sicherung einer Baugrubenwand 1 sollen Erdanker hergestellt werden. Zu diesem Zweck wird zunächst eine Bohrung 2 im Boden erzeugt. In die Bohrung 2 wird der eigentliche Ankerstab 3 eingeführt. Dieser Ankerstab 3 ist zumindest im Bereich der freien Spannlänge Ls von einem Hüllrohr 4 umgeben, mit dem die Haftung gegen das Verpreßmaterial des Bohrlochs verhindert wird. Das Hüllrohr dient somit der Erhaltung der freien Beweglichkeit des Ankerstabes 3.To secure a construction pit wall 1, ground anchors are to be produced. For this purpose, a hole 2 is first created in the ground. In the hole 2 the actual anchor rod 3 is introduced. This anchor rod 3 is at least in Area of the free span length Ls surrounded by a cladding tube 4 with which the adhesion against the grouting material of the borehole is prevented. The cladding tube thus serves the maintenance of the free mobility of the anchor rod 3.

In das Bohrloch werden weiterhin die Gefrierleitungen eingesetzt. Die Gefrierleitung 5 besteht im Bereich der freien Spannlänge Ls aus isoliertem Rohrmaterial, beispielsweise einem Rohr aus PVC. Dieses Rohr ist bei 6 mit einer Muffe mit einem metallischen Rohr 7 gestoßen. Im Bereich dieses Metallrohrs 7 wird, nachdem das Bohrloch mit Verpreßmaterial 8 verfüllt wurde, der Frostkörper 9 erzeugt, dessen Durchmesser beliebig eingestellt werden kann. Der Frostkörper 9 erfaßt den gesamten Verankerungsbereich mit der Länge Lv.The freeze lines continue to be inserted into the borehole. The freezing line 5 consists of insulated in the area of the free span length Ls Pipe material, for example a pipe made of PVC. This tube is at 6 with a The socket is joined with a metallic pipe 7. In the area of this metal tube 7, after the borehole has been filled with grouting material 8, the frozen body 9 is produced, whose diameter can be adjusted as required. The frost body 9 detects the entire anchoring area with the length Lv.

Die Gefrierleitung 5 wird mit Anschlußleitungen 10 nach außen geführt. Dort befindet sich auch die Verankerung des Ankerstabs 3 in an sich bekannter Art und Weise.The freezing line 5 is led to the outside with connecting lines 10. The anchor rod 3 is also anchored there in a manner known per se.

Nach dem Verpressen des Bohrloches und Herstellen des Frostkörpers 9, der über die Zeit der Benutzung der Verankerung aufrechterhalten werden muß, kann der Ankerstab 3 angespannt werden.After pressing the borehole and creating the frozen body 9, which must be maintained over the period of use of the anchorage, the tie rod 3 can be tightened.

Zur Verwirklichung der Erfindung und zur Herstellung eines Frostkörpers 9 reicht es an sich aus, wenn die Gefrierrohre, wie in den F i g. 1 bis 3 dargestellt, nur in das Bohrloch bis zu seinem Grunde hineinreichen und dort einfach haarnadelartig umkehren. Zur Intensivierung des Gefriervorgangs ist es aber auch möglich, die Gefrierrohre in der in F i g. 4 dargestellten Weise, den Ankerstab 3 wendelförmig umschlingend, vorzusehen.To implement the invention and to produce a body of frost 9 it is sufficient in itself if the freezing tubes, as shown in FIGS. 1 to 3 shown, only reach into the borehole to its bottom and there simply like a hairpin turning back. To intensify the freezing process, it is also possible to use the freezing tubes in the in F i g. 4 shown way, the anchor rod 3 helically wrapped around, to be provided.

Eine weitere Möglichkeit ist die Anordnung von Gefrierrohren mit eingebautem Fallrohr. Außerdem kann die Oberfläche der Gefrierrohre zur Verbesserung des Wärmeüberganges durch angesetzte Rippen od. dgl. wesentlich vergrößert werden.Another option is the arrangement of freeze pipes with built-in Downpipe. In addition, the surface of the freezing pipes can be used to improve the heat transfer by attached ribs or the like. Be significantly enlarged.

Claims (1)

Patentanspruch: Verfahren zum Herstellen eines temporären Erdankers, vor allem in bindigen Böden, bei dem zunächst eine Bohrung erzeugt und nach dem Einführen des Ankers das Bohrloch z. B. mit einem erhärtenden Material wie Zementschlempe verpreßt wird, d a d u r c h g e k e n n -zeichnet, daß zumindest im Bereich des Ankerendes durch Anwendung der an sich bekannten Bodenverfestigung durch Gefrieren ein Frostkörper erzeugt und während der Verwendung des Erdankers aufrechterhalten wird.Claim: Method for producing a temporary ground anchor, especially in cohesive soils, in which a hole is first created and then after Introducing the anchor the borehole z. B. with a hardening material such as cement pulp is pressed, d a d u r c h e k e n n -draws that at least in the area of the Anchor end by using the well-known soil consolidation by freezing a body of frost is created and sustained during the use of the ground anchor will.
DE19681708531 1968-02-29 1968-02-29 Method for producing a temporary ground anchor Withdrawn DE1708531B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DED0055450 1968-02-29

Publications (1)

Publication Number Publication Date
DE1708531B1 true DE1708531B1 (en) 1971-12-02

Family

ID=7056542

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19681708531 Withdrawn DE1708531B1 (en) 1968-02-29 1968-02-29 Method for producing a temporary ground anchor

Country Status (1)

Country Link
DE (1) DE1708531B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2245212A5 (en) * 1973-09-21 1975-04-18 Ichise Yoshio
EP0149716A2 (en) * 1983-09-30 1985-07-31 Linde Aktiengesellschaft Method of securing an anchor
WO2007070905A2 (en) * 2005-12-19 2007-06-28 Atlas Copco Mai Gmbh Heat exchanger
EP3517688A1 (en) * 2018-01-29 2019-07-31 BAUER Spezialtiefbau GmbH Ground anchor element

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2245212A5 (en) * 1973-09-21 1975-04-18 Ichise Yoshio
EP0149716A2 (en) * 1983-09-30 1985-07-31 Linde Aktiengesellschaft Method of securing an anchor
EP0149716A3 (en) * 1983-09-30 1986-06-25 Linde Aktiengesellschaft Method of securing an anchor
WO2007070905A2 (en) * 2005-12-19 2007-06-28 Atlas Copco Mai Gmbh Heat exchanger
WO2007070905A3 (en) * 2005-12-19 2007-10-04 Atlas Copco Mai Gmbh Heat exchanger
EP3517688A1 (en) * 2018-01-29 2019-07-31 BAUER Spezialtiefbau GmbH Ground anchor element

Similar Documents

Publication Publication Date Title
DE2041526C3 (en) Tension member for a grouting anchor
DE2101236A1 (en) Corrosion-protected tie rods for anchoring components in the ground as well as a method for producing tension anchors with corrosion-protected tie rods
CH406081A (en) Method for holding anchors in boreholes in loose and solid soil
EP0976873A1 (en) Injection- or prestressed ground anchor
DE3416679C2 (en)
DE4005032A1 (en) Foundation pile supporting load in loose soil - has device to apply force between baseplate and pile
DE1018820B (en) Procedure for securing shafts by means of anchoring
DE1759561C3 (en) Method for producing grouting anchors and device for carrying out the method
DE1708531B1 (en) Method for producing a temporary ground anchor
DE3838880C1 (en) Method of producing a grouted anchor, and grouted anchor for carrying out the method
DE2034662A1 (en) Method for attaching an anchor in the ground and the like and anchors for carrying out this method
DE1708531C (en) Method for producing a temporary ground anchor
DE1104905B (en) Tie rods for anchoring components in the ground
CH693934A5 (en) Method for earth and rock anchor bore drilling uses drill crown to which drill pipe is attached to define annular space for evacuation of hardened material
DE2039109A1 (en) Method for producing a prestressed ground anchor
DE2412667A1 (en) ANCHORS FOR STRENGTHENING THE MOUNTAIN OF STOLLEN, TUNNEL AND DGL
AT269002B (en) Injection tension anchoring in the ground and process for their production
DE2201950A1 (en) TIE ANCHORS FOR ANCHORING COMPONENTS IN EARTH OR ROCKY GROUND
CH590370A5 (en) Foundation post prodn. process - using injection of freshly mixed concrete material under pressure into hardening on site concrete
CH374819A (en) Process for the production of prestressed anchors for structures such as retaining walls, excavation securing devices and the like and prestressing anchors produced according to this process
DE1271045B (en) Method for producing ground anchors
DE2050292A1 (en) Method for producing earth anchors with an extended anchor foot
DE4226655C2 (en) Procedure for securing construction pit walls by setting tensionable ground anchors
AT239157B (en) Tie rods for anchoring components in the ground
DE2342581C3 (en) Method for producing a grout anchor and device for carrying out the method

Legal Events

Date Code Title Description
E77 Valid patent as to the heymanns-index 1977
EHJ Ceased/non-payment of the annual fee