DE1634828C - Drilling grapple - Google Patents

Drilling grapple

Info

Publication number
DE1634828C
DE1634828C DE19671634828 DE1634828A DE1634828C DE 1634828 C DE1634828 C DE 1634828C DE 19671634828 DE19671634828 DE 19671634828 DE 1634828 A DE1634828 A DE 1634828A DE 1634828 C DE1634828 C DE 1634828C
Authority
DE
Germany
Prior art keywords
gripper
shells
drilling
rod
pull rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE19671634828
Other languages
German (de)
Other versions
DE1634828A1 (en
Inventor
Robert 6600 Saarbrücken Hochstrasser (verstorben) E21b 17 042
Original Assignee
Hochstrasser geb Wack, Elisabeth, Hochstrasser, Jürgen, 6600 Saarbrücken
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hochstrasser geb Wack, Elisabeth, Hochstrasser, Jürgen, 6600 Saarbrücken filed Critical Hochstrasser geb Wack, Elisabeth, Hochstrasser, Jürgen, 6600 Saarbrücken
Publication of DE1634828A1 publication Critical patent/DE1634828A1/en
Application granted granted Critical
Publication of DE1634828C publication Critical patent/DE1634828C/en
Expired legal-status Critical Current

Links

Description

35 Ein weiterer Vorteil besteht, darin, daß zufolge der ruckartigen öffnung der Greiferschalen durch die Federn auch klebriges Erdreich sich einwandfrei aus35 Another advantage is that, according to the jerky opening of the gripper shells by the springs sticky soil also looks good

Das Hauptpatent 1280 776 bezieht sich auf einen den Greiferschalen löst, was bei den bisher für dieseThe main patent 1280 776 refers to one of the gripper shells, which has been the case so far for this

Bohrgreifer, dessen Greiferschalen durch Federkraft Zwecke eingesetzten .Bohrgreifern nicht erfolgt, soDrill grab whose grab shells are not used by spring force, so

geöffnet und durch den Seilzug eines Windenseiles 40 daß bei diesen das in den Greiferschalen auf Grundopened and by the cable pull of a winch cable 40 that this in the gripper shells due to

entgegen der Federkraft geschlossen werden und bei der klebrigen Beschaffenheit haften bleibende Erd-are closed against the spring force and the sticky nature of the earth sticks

dem zwischen dem Greiferkörper und dem durch die reich von Hand mit Spaten aus den Greiferschalenthe one between the gripper body and the one by hand with a spade from the gripper shells

Zugstange betätigbaren Schließmechanismus der entfernt werden muß, wodurch erhebliche Zeitverlu-Drawbar actuated locking mechanism that has to be removed, resulting in considerable loss of time.

Greiferschalen die Federkraft angreift, die geringer ste beim Arbeiten? bedingt sind.The gripper shells are attacked by the spring force, which is the lowest when working? are conditional.

ist als jene Kraft, die das Gewicht des Greiferkörpers 45 Beim Ausheben von Gräben eignet sich somit deris the force that bears the weight of the gripper body 45 when digging trenches

erzeugt, jedoch so groß ist, daß sie während des FaI- erfindungsgemäße Greifer in besonders vorteilhaftergenerated, but is so large that it is particularly advantageous during the FaI gripper according to the invention

lens des Greifers unter zusätzlicher Beschleunigung Weise, da einmal ein Greifer großer Abmessungenlens of the gripper with additional acceleration manner, as once a gripper of large dimensions

des Windenseiles und der Windentrommel die benutzt werden kann und zum anderen· eine schnellethe winch rope and the winch drum that can be used and, on the other hand, a fast one

Greiferschalen öffnet. Ein derartiger Greifer ist be- Arbeitsweise möglich ist, da das von dem Greifer auf-Grab shells opens. Such a gripper is possible because the gripper

kannt. Er besitzt den Vorteil, daß beim freien Fall 50 genommene Erdreich, das insbesondere in der Näheknows. It has the advantage that 50 soil taken during free fall, especially in the vicinity

des Greifers unter Beschleunigung des Hubseiles sich der Erdoberfläche klebrig ist, einwandfrei beim öff-of the gripper under acceleration of the hoist rope the surface of the earth is sticky, perfect when opening

die Greiferschalen unter der Wirkung der Federn öff- nen des Greifers gelöst wird.the gripper shells are released under the action of the spring opening of the gripper.

nen, so daß die Möglichkeit besteht, diesen .Greifer Die Zeichnung zeigt eine beispielsweise Ausfüh-so that it is possible to use this .Greifer The drawing shows an example of an execution

wiederholt auf das Erdreich auffallen zu lassen, um rungsform des erfindungsgemäßen Greifers,repeatedly to fall on the ground in order to approximate shape of the gripper according to the invention,

die von ihm erfaßte Menge zu erhöhen. Bei dem be- 55 Der Greifer besitzt eine Zugstange d, die an einerto increase the amount it covers. In the case of the 55 The gripper has a pull rod d which is attached to a

kannten Greifer ist die die öffnung der Greiferscha- nicht dargestellten Freifallwinde befestigt ist. BeimKnown gripper is the opening of the gripper shell, not shown, is attached to the free fall winch. At the

len beim freien Fall bewirkende Feder um die Zug- Hochziehen des Greifers bewegt sich zuerst die Stan-len in the free fall causing the spring to pull up the gripper, the rod moves first

stange angeordnet. Diese- Maßnahme ist insofern ge d nach oben in die Stellung i und bringt dierod arranged. This measure is so far ge d up in the position i and brings the

nachteilig, als durch die Anordnung der Feder um die Greiferschalen b gegen die Wirkung der Federn e disadvantageous than the arrangement of the spring around the gripper shells b against the action of the springs e

Zugstange sich der Bau größerer Bohrgreifer verbie- 60 über die Gelenkstange c und die Arme / der Greifer-The construction of larger drilling grabs can be bent 60 via the articulated rod c and the arms / the gripper

tet, da bei größeren Bohrgreifern die Bauhöhe des schalen b in die Schließstellung. Der so geschlossenetet, since with larger drill grabs the overall height of the shell b in the closed position. The one so closed

Greiferkörpers infolge der aufzubringenden Feder- Greifer wird bei weiterem Einziehen der Winde vomGripper body as a result of the spring gripper to be applied is pulled in further by the winch

kraft und der dadurch gegebenen Federlänge zu groß Boden angehoben. Wenn der Greifer in das Erdreichforce and the resulting length of the spring raised too large ground. When the grapple is in the ground

wird, als daß eine wirtschaftliche Verwendung mög- abgesenkt wird, wird er beispielsweise in einer Höheis, as that an economic use is possible is lowered, it is, for example, at a height

lieh ist. ( 65 von 2 m über der Bohrsohle durch die Winde freige-is borrowed. ( 65 from 2 m above the drilling floor cleared by the winch

Hier setzt das Hauptpatent ein, bei dem an Stelle geben, so daß er im freien Fall nach unten sich be-This is where the main patent comes in, giving in place so that it moves downwards in free fall

einer' einzigen, um die Zugstange angeordneten wegt. Hierbei öffnen die Federn e die Greiferscha- i\ a 'single, arranged around the pull rod moves away. Here, the springs e i Open the Greiferscha- \

Druckfeder die Federkraft .von mehreren, beispiels- len b, die somit in geöffnetem Zustand in die Bohr- '3Compression spring, the spring force of several, for example b, which are thus in the open state in the drilling '3

■ .' ■ I■. ' ■ I

sohle eindringen können. Beim folgenden Einziehen des Windenseiles schließen sich die Greiferschalen b in der vorerwähnten Weise unter Erfassung einer bestimmten Menge an Bohrgut.can penetrate the sole. At subsequent retraction of the hoist rope, the grab shells close b in the aforementioned manner upon detection of a certain amount of drill cuttings.

Ist durch diese Menge der Greifer nicht gefüllt, kann man ihn einmal oder mehrmals fallen lassen, bis eine ausreichende Füllung der Greiferschalen erreicht ist und der Greifer aus dem Bohrloch herausgezogen werden kann. Die Stange d ist unabhängig von den Federn e und deren Teleskopführungen /, so daß sie kürzer sein kann, als die Federn e. In der Offenstellung der Greiferschalen b liegt das Ende der Stange d bei h innerhalb des Greiferkörpers. Die Bohrgreiferschalen sind in ihrer Form dem Verwendungszweck angepaßt und besitzen in der Abteufrichtung eine größere, und zwar eine vielfache Länge gegenüber der Breite. Der auf diese Weise flach ausgebildete Bohrgreifer ermöglicht das Ausheben von engen Gräben; die Greiferschalen besitzen einander parallele Seitenflächen, während die Bodenfläche kreisbogen-If the gripper is not filled by this amount, it can be dropped once or several times until the gripper shells are sufficiently full and the gripper can be pulled out of the borehole. The rod d is independent of the springs e and their telescopic guides /, so that it can be shorter than the springs e. In the open position of the gripper shells b , the end of the rod d lies at h within the gripper body. The shape of the drill gripper shells is adapted to the intended use and has a greater length in the sinking direction, namely a multiple of the length compared to the width. The drill grab, which is flat in this way, enables the digging of narrow trenches; the gripper shells have side surfaces that are parallel to one another, while the bottom surface is arcuate

o förmig ausgebildet oder senkrecht zu den Seitenflächen liegen kann.o Shaped or perpendicular to the side surfaces can lie.

Hierzu 1 Blatt Zeichnungen1 sheet of drawings

Claims (1)

1 2 weise von zwei, außerhalb der Zugstange und beider- Patentansprüche: seits neben der Zugstange angeordneten,- auf Führungsstangen geführten Federn gebildet ist, die mit1 2 wise of two, outside of the pull rod and both- claims: on the side next to the pull rod, - is formed on guide rods guided springs with 1. Bohrgreifer, dessen Greiferschalen durch ihrem einen Ende am Boden des Greiferkörpers dreh-1. Drilling gripper, the gripper shells of which rotate through one end at the bottom of the gripper body. Federkraft geöffnet und durch den Seilzug eines 5 bar abgestützt sind und mit ihrem anderen Ende imSpring force are open and supported by the cable of a 5 bar and with their other end in the Windenseiles entgegen der Federkraft geschlossen mittleren Bereich des durch eine Gelenkstange mitWinch rope against the spring force closed the middle area of the by a toggle rod werden und bei dem zwischen dem Greiferkörper der Zugstange verbundenen Armes der Greiferscha-and with the arm of the gripper shell connected between the gripper body of the tie rod und dem durch die Zugstange betätigbaren len gelenkig angreifen. Nach dem Hauptpatent lassenand articulately attack the len actuatable by the pull rod. Let after the main patent Schließmechanismus der Greiferschalen die sich auch Bohrgreifer größerer Abmessungen bauen,Closing mechanism of the gripper shells, which can also be used to build drilling grabs of larger dimensions, Federkraft angreift, die geringer ist als jene Kraft, io da durch die Anordnung von zwei Federn die Feder-Attacking spring force, which is less than that force, io since the arrangement of two springs the spring die das Gewicht des Greiferkörpers erzeugt, je- länge gegenüber dem bekannten Bohrgreifer um diewhich generates the weight of the gripper body, depending on the length of the known drilling gripper doch so groß ist, daß sie während des Fallens des Hälfte kürzer ist; zum anderen ist die Zugstange zwi-but is so great that it is shorter as the half falls; on the other hand, the pull rod is between Greifers unter zusätzlicher Beschleunigung des sehen den Federn angeordnet, was zu einer weiterenGripper under additional acceleration of the see the springs arranged, resulting in a further Windenseiles und der Windentrommel die Verkürzung der Bauhöhe führt.The winch rope and the winch drum shorten the overall height. Greiferschalen öffnet, wobei die Federkraft von' 15 Die vorliegende Anmeldung stellt eine vorteilhafteGripper shells opens, with the spring force of '15 The present application represents an advantageous mehreren, außerhalb der Zugstange und beider- Weiterbildung des Hauptpatentes dar, die sich da-several, outside of the tie rod and both - further development of the main patent, which are there- seits neben der Zugstange angeordneten, auf Füh- durch kennzeichnet, daß die Greiferschalen in derside arranged next to the pull rod, on Füh- indicates that the gripper shells in the rungsstangen geführten Federn gebildet ist, die Abteufrichtung eine größere Länge besitzen als senk-springs guided by rods are formed, the direction of sinking has a greater length than vertical mit ihrem einen Ende am Boden des Greiferkör- recht zur Ateufrichtung. Zweckmäßigerweise beträgtwith one end on the bottom of the gripper head for erecting. Appropriately amounts to pers abgestützt sind und mit ihrem anderen Ende ao die Länge der Greiferschalen in Abteufrichtung einpers are supported and with their other end ao the length of the grab shells in the sinking direction am mittleren Bereich des durch eine Gelenk- Vielfaches ihrer Breite. Die Anmelder haben erkannt,at the middle area of the joint multiple of its width. Applicants have recognized stange mit der Zugstange verbundenen Armes der daß sich der Greifer nach dem Hauptpatent, der alsrod with the tie rod connected arm that the gripper according to the main patent, which as Greiferschalen gelenkig angreifen, nach Patent Bohrgreifer mit halbkreisförmigen GreiferschalenAttack gripper shells in an articulated manner, according to the patent drilling gripper with semicircular gripper shells 1 280776, dadurch gekennzeichnet, ausgebildet ist, mit besonderem Vorteil auch verwen-1 280776, characterized in that it is designed to also use with particular advantage daß die Greiferschalen Qb) in der Ablauf richtung as den läßt für das Ausheben von Gräben. Derartigethat the gripper shells Qb) in the flow direction as the leaves for digging trenches. Such eine größere Länge besitzen als senkrecht zur Ab- Gräben müssen teilweise bis zu Tiefen von 15 bishave a greater length than perpendicular to the ab- trenches must sometimes be down to depths of 15 to laufrichtung. 20 m ausgehoben werden für Fundamente und Stütz-running direction. 20 m are excavated for foundations and support . 2. Bohrgreifer nach Anspruch 1, dadurch ge- wände, insbesondere beim Straßenbau. Der Bohrgrei-. 2. Drilling grab according to claim 1, characterized ge walls, in particular in road construction. The drill kennzeichnet, daß die Länge der Greiferschalen fer nach der Erfindung eignet sich wegen seiner ge-indicates that the length of the gripper shells fer according to the invention is suitable because of its ge in Ablaufrichtung ein Vielfaches ihrer Breite be- 30 ringen Bauhöhe vorzüglich für derartige Arbeiten, daIn the direction of drainage, a multiple of its width makes the overall height ideal for such work, since trägt. er trotz großer Abmessungen auf Grund seiner geringen Bauhöhe überall eingesetzt werden kann, auch dort, wo unter Leitungen oder Überführungen gearbeitet werden muß.wearing. despite its large dimensions, it can be used anywhere due to its low overall height, too where work has to be carried out under pipes or overpasses.
DE19671634828 1967-06-23 1967-06-23 Drilling grapple Expired DE1634828C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DEH0063116 1967-06-23
DEH0063116 1967-06-23

Publications (2)

Publication Number Publication Date
DE1634828A1 DE1634828A1 (en) 1971-04-01
DE1634828C true DE1634828C (en) 1973-03-08

Family

ID=

Similar Documents

Publication Publication Date Title
DE2801458A1 (en) DEVICE AND METHOD FOR CONNECTING A LINE TO AN UNDERWATER STATION
DE1812304A1 (en) Device and method for the vertical storage and handling of drill string sections
EP3798367B1 (en) Slotted wall gripper, method for operating same, and civil engineering method
DE2237133B2 (en) Ram hammer with sound-absorbing jacket
DE1912188A1 (en) Catching device for gripping parts in bores, in particular deep bores
DE1634828C (en) Drilling grapple
EP0860580B1 (en) Apparatus for handling drill rods
DE1634828B (en) Drilling grapple
DE2550595C3 (en) A ram and a pipe having device for the production of earth bores and in these arranged piles made of poured or compacted concrete
DE1758649C3 (en) Drilling grapple
DE1634828A1 (en) Drilling grab with low installation height
DE3201042C2 (en) Drilling grabs for creating earth boreholes
DE2020165A1 (en) Automatic sinking bucket for drilling purposes
DE10351956B3 (en) Device for extracting earth material from pipe driven into soil has flaps held by cable extending from one end of gripper pipe to other connected to actuator so this lowers cable and flaps drop to outlet position under pressure of soil
DE573399C (en) Grab excavator for earth drilling with circularly arranged blades
DE4225217C2 (en) Recovery device
AT265168B (en) Drill grab
DE2926169C2 (en) Grab with crane hook
DE1280776B (en) Drill grab
DE3000776A1 (en) DRILLING HOLE FOR SOLEING UNDERGROUND SALT WAREHOUSES AND METHOD FOR OPERATING SUCH A DRILLING HOLE
DE2913771C3 (en) Boom equipped with a pulling device for hydraulic excavators
DE4324956A1 (en) Drilling grab
DE3423397A1 (en) DEVICE FOR DRILLING DRILL HOLES AND TRENCHES
DE686106C (en) Gripping drill for deep holes
DE1758649A1 (en) Drill grab