DE1534623C - Procedure for avoiding subsidence during tunnel construction by means of shield driving - Google Patents
Procedure for avoiding subsidence during tunnel construction by means of shield drivingInfo
- Publication number
- DE1534623C DE1534623C DE1534623C DE 1534623 C DE1534623 C DE 1534623C DE 1534623 C DE1534623 C DE 1534623C
- Authority
- DE
- Germany
- Prior art keywords
- cushions
- segments
- hardening mass
- outside
- cushion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 title claims description 3
- 238000000034 method Methods 0.000 title claims 2
- 239000002689 soil Substances 0.000 claims description 8
- 238000004026 adhesive bonding Methods 0.000 claims description 2
- 239000011324 bead Substances 0.000 claims description 2
- 238000002347 injection Methods 0.000 claims description 2
- 239000007924 injection Substances 0.000 claims description 2
- 239000011440 grout Substances 0.000 description 3
- 239000011148 porous material Substances 0.000 description 2
- 210000000188 Diaphragm Anatomy 0.000 description 1
- 240000002057 Secale cereale Species 0.000 description 1
- 230000003466 anti-cipated Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000005538 encapsulation Methods 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 239000012528 membrane Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Description
Die Erfindung betrifft ein Verfahren zum Vermeiden von Setzungen beim Tunnelbau mittels Schildvortriebs, bei dem in den Ringspalt zwischen der Außenseite der Tübbingauskleidung und dem umgebenden Erdreich während und/oder nach dem Vorrücken des Schildes eine erhärtende Masse unter Druck eingebracht wird.The invention relates to a method for avoiding subsidence during tunnel construction by means of shield driving, in the case of the in the annular gap between the outside of the segment lining and the surrounding area Soil a hardening mass under the ground during and / or after the advancement of the shield Pressure is applied.
Bei bekannten Verfahren dieser Art können trotz Einpressens einer erhärtenden Masse in den Ringspalt Setzungen nicht völlig verhindert werden. Diese Erscheinung rindet ihre Erklärung darin, daß die Einpreßmasse in den Porenraum des Korngerüstes des umgebenden Erdreiches eindringt und somit auf das einzelne Korn der Grenzschicht keine gerichtete stützende Kraft ausübt, daher auch eine Bewegung des Korns mit Setzungsfolge nicht verhindern kann. Weiterhin ist es bei den bekannten Verfahren kaum möglich, durch das Verpressen des Ringspaltes in den Tübbingringen einen vorbestimmten Verformungszustand und damit einen vorher festgelegten Spannungszustand zu erzeugen.In known methods of this type, despite a hardening compound being pressed into the annular gap Subsidence cannot be completely prevented. This phenomenon is explained by the fact that the grout penetrates into the pore space of the grain structure of the surrounding soil and thus on the single grain of the boundary layer does not exert a directed supporting force, hence a movement of the Korns with settlement sequence cannot prevent. Furthermore, it is hardly possible with the known methods by pressing the annular gap into the Tubbing rings have a predetermined state of deformation and thus a predetermined state of stress to create.
Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren der eingangs angegebenen Art zu schaffen, bei dem der Ringspalt sofort und zuverlässig kraftschlüssig ausgefüllt wird und die Verformungen der Tübbingringe in gewünschtem Maße vorweggenommen werden.The invention is based on the object of creating a method of the type specified at the beginning which the annular gap is filled immediately and reliably with a force fit and the deformation of the segment rings be anticipated to the desired extent.
Die Aufgabe wird dadurch gelöst, daß an der Außenkante der Tübbings aufweitbare Kissen angeordnet werden und die erhärtende Masse in diese Kissen eingepreßt wird und daß hierbei durch die Höhe des Einpreßdruckes und durch die Reihenfolge des Ausfüllens der Kissen in den Tübbingringen ein vorbestimmter Spannungs- und Verformungszustand herbeigeführt wird.The object is achieved in that expandable cushions are arranged on the outer edge of the segments are and the hardening mass is pressed into this cushion and that this by the The amount of the injection pressure and the order in which the cushions are filled in the segment rings predetermined stress and deformation state is brought about.
Der erreichte technische Fortschritt besteht darin, daß durch die Einschaltung einer aufweitbaren Membrane, die dem Arbeitsfortschritt des Schildvortriebes entsprechend in einzelne Kissen oder Schläuche aufgelöst werden muß, eine Trennung von Ringspalt und Porenraum entsteht. Damit wird der Einpreßmasse die Möglichkeit gegeben, eine gerichtete, das umgebende Korngerüst stützende Kraft auszuüben. Außerdem können mit einem in die Tübbingringe eingeleiteten planmäßigen Spannungszustand auch Setzungen aus der Querschnittsverformung der Tübbingauskleidung vermieden werden.The technical progress achieved consists in the fact that through the inclusion of an expandable membrane, which are broken down into individual cushions or hoses according to the progress of the shield drive must be, a separation of the annular gap and pore space is created. This is the grout given the opportunity to exert a directed force supporting the surrounding grain structure. In addition, a planned state of stress introduced into the segment rings can also lead to subsidence can be avoided from the cross-sectional deformation of the segment lining.
Ein weiterer Vorteil ist, daß durch die Einschließung der Einpreßmasse in aufweitbare Kissen eine Abdichtung des Ringspaltes gegen den Schildraum entfallen kann, falls nicht besondere Verhältnisse des Bodens oder Wasserandrang eine solche erforderlich machen.Another advantage is that the encapsulation of the grout in expandable cushions creates a seal of the annular gap against the shield space can be omitted, if there are no special soil conditions or the rush of water make it necessary.
Eine weitere Ausgestaltung der Erfindung besteht darin, daß in den noch leeren Kissen ein Unterdruck hergestellt wird, damit sie, so lange sie sich noch im Bereich des Schildschwanzes befinden, möglichst flach an den Tübbings anliegen. Außerdem ist vorgesehen, daß nach dem Ausfüllen der Kissen noch vorhandene Zwischenräume zwischen den einzelnen Kissen und zwischen diesen und dem umgebenden Erdreich mit einer erhärtenden Masse vom Tunnelinnern her ausgepreßt werden. ·A further embodiment of the invention consists in the fact that a negative pressure is created in the still empty cushion is made so that they are as flat as possible as long as they are still in the area of the shield tail rest on the segments. It is also provided that after the filling of the cushions still existing ones Gaps between the individual cushions and between them and the surrounding soil a hardening mass are pressed from the inside of the tunnel. ·
Nach einem weiteren Merkmal der Erfindung ist zur Durchführung des Verfahrens eine Tübbingauskleidung vorgesehen, bei der auf der Außenseite der Tübbings aufweitbare Kissen in ein- oder mehrzelliger, gegebenenfalls schlauchartiger Form einzeln oder reihenweise, beispielsweise durch Klebung angebracht sind und mit dem Tunnelinnern über absperrbare Leitungen in Verbindung stehen. Die Kissen können auf der Außenseite der Tübbings in durch Wülste gebildeten Nischen angeordnet werden. Die aus Gummi, Kunststoff oder metallenen Membranen bestehenden Kissen erhalten durch diese Nischenbildung einen besseren Schutz beim Vortrieb des Schildes.According to a further feature of the invention, a segment lining is used to carry out the method provided, in the case of the expandable cushions on the outside of the segments in single or multi-cell, optionally tubular in shape, attached individually or in rows, for example by gluing and are connected to the inside of the tunnel via lockable lines. The pillows can be arranged on the outside of the segments in niches formed by beads. From Cushions made of rubber, plastic or metal diaphragms are preserved through this formation of niches better protection when propelling the shield.
Nachstehend ist die Erfindung an Hand der Zeichnung näher erläutert:The invention is explained in more detail below with reference to the drawing:
ίο Die Zeichnung zeigt im Längsschnitt das obere Schwänzende 1 eines Vortriebschildes mit dem darüberliegenden Erdreich 2. Die rückwärtige Schildschwanzkante ist abgerundet und geglättet ausgebildet. An der Außenseite der Tübbings 3 sind Kissen 4 angeordnet, die im Bereich des Schildschwanzes infolge des in ihnen erzeugten Unterdruckes flach an den Tübbings anliegen, während die bereits mit einer erhärtenden Masse 5 gefüllten Kissen 4' den Ringspalt ausfüllen. Das Innere der Kissen ist mit dem Tunnelinnern durch absperrbare Leitungen 7 verbunden, durch die das Ausfüllen der Kissen erfolgt. Weitere Öffnungen 8 in den Tübbings dienen zum nachträglichen Verpressen noch vorhandener Zwischenräume zwischen den einzelnen Kissen und zwischen diesenίο The drawing shows the upper one in longitudinal section Tail 1 of a jacking shield with the soil above 2. The rear shield tail edge is rounded and smooth. On the outside of the segments 3 are cushions 4 arranged, which is flat in the area of the shield tail due to the negative pressure generated in them the tubbing rest, while the already filled with a hardening mass 5 cushions 4 'the annular gap to complete. The interior of the cushions is connected to the inside of the tunnel by lockable lines 7, through which the cushions are filled. Further openings 8 in the tubbings are used for subsequent Compression of any gaps between the individual cushions and between them
a5 und dem umgebenden Erdreich 2 mit einer erhärtenden Masse vom Tunnelinnern aus.a 5 and the surrounding soil 2 with a hardening mass from the inside of the tunnel.
Claims (5)
Family
ID=
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0002877B1 (en) | Method for the removal of methane | |
DE2103760A1 (en) | Tunnel construction process | |
DE2431652A1 (en) | METHOD AND DEVICE FOR THE PRODUCTION OF UNDERGROUND CAVITIES | |
DE7614295U1 (en) | SHIELD MACHINE WITH A DEVICE FOR PRODUCING A TUNNEL LINING IN IN-SITE CONCRETE | |
DE3626988C2 (en) | ||
DE1534623C (en) | Procedure for avoiding subsidence during tunnel construction by means of shield driving | |
DE1252227B (en) | Process for the expansion of tunnels to be produced by means of shield jacking | |
DE2555780A1 (en) | DEVICE FOR SEALING THE RING GAP BETWEEN THE SHIELD SHIELD AND LINING OF DAMPING SHIELDS | |
DE706171C (en) | Process for the construction of galleries, tunnels or underground channels | |
DE2033142B2 (en) | PROCEDURE FOR LINING A TUNNEL AND SIGN FOR CARRYING OUT THE PROCEDURE | |
DE1101479B (en) | Method for creating a tunnel or adit by driving a tunnel pipe remaining in the ground | |
DE1206938B (en) | Controllable propulsion shield for driving tunnels, routes or the like, and method for producing an in-situ concrete lining with such a propulsion shield | |
DE1534626C3 (en) | Segment lining for carrying out a method to avoid subsidence during tunnel construction by means of shield driving | |
DE1534623B (en) | Procedure for avoiding subsidence during tunnel construction by means of shield driving | |
EP0205853A2 (en) | Method for producing a pipelike underground cavity, e.g. a tunnel, gallery or the like, by means of shield driving, and device for carrying out the method | |
DE699762C (en) | Method and device for creating trench-like construction pits | |
DE2250635B2 (en) | Method of making a tunnel | |
DE2228270A1 (en) | Method of fastening pipes in boreholes | |
DE1534623A1 (en) | Procedure for avoiding subsidence during tunnel construction by means of shield driving | |
DE1934170A1 (en) | Removal of mineral oil impregnant from - vicinity of bore holes | |
DE924685C (en) | Resilient pit lining | |
DE2801616B2 (en) | Method for driving routes or tunnels in water-bearing floating floors using a compressed air propulsion shield | |
DE3507730C2 (en) | ||
DE950519C (en) | Penstock | |
DE615883C (en) | Mine support |