DE102015102803A1 - Manhole cover assembly and method of installation - Google Patents

Manhole cover assembly and method of installation Download PDF

Info

Publication number
DE102015102803A1
DE102015102803A1 DE102015102803.4A DE102015102803A DE102015102803A1 DE 102015102803 A1 DE102015102803 A1 DE 102015102803A1 DE 102015102803 A DE102015102803 A DE 102015102803A DE 102015102803 A1 DE102015102803 A1 DE 102015102803A1
Authority
DE
Germany
Prior art keywords
manhole cover
support body
concrete support
shaft
closure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE102015102803.4A
Other languages
German (de)
Inventor
Ralf Sonnenberg
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meierguss Sales and Logistics GmbH and Co KG
Original Assignee
Meierguss Sales and Logistics GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meierguss Sales and Logistics GmbH and Co KG filed Critical Meierguss Sales and Logistics GmbH and Co KG
Priority to DE102015102803.4A priority Critical patent/DE102015102803A1/en
Priority to PL16151930T priority patent/PL3064650T3/en
Priority to EP16151930.1A priority patent/EP3064650B1/en
Publication of DE102015102803A1 publication Critical patent/DE102015102803A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

Die Erfindung betrifft eine Schachtabdeckungsanordnung sowie ein Einbauverfahren einer solchen zur Verwendung im Straßenneubau und in Sanierungsverfahren, mit einem Verschlusselement und einem Schachtabdeckungsrahmen, wobei der Schachtabdeckungsrahmen zweiteilig aus einer Verschlussaufnahme zur Aufnahme des Verschlusselements und einem Betonstützkörper ausgebildet ist, wobei der Betonstützkörper und die Verschlussaufnahme zumindest abschnittsweise form- und stoffschlüssig miteinander verbunden sind, die Verschlussaufnahme den Betonstützkörper in Richtung des Verschlusselements überragt, und der Betonstützkörper eine sich nach unten verjüngende schachtabgewandte Seitenfläche aufweist. Dabei weist die Verschlussaufnahme an der schachtabgewandten Seite der Schachtabdeckungsanordnung einen nach unten abgewinkelten Schenkel auf, der den Betonstützkörper an dessen schachtabgewandter Seite zumindest teilweise umfasst. The invention relates to a manhole cover arrangement and an installation method thereof for use in new road construction and renovation methods, with a closure element and a manhole cover frame, wherein the manhole cover frame is formed in two parts from a closure receptacle for receiving the closure element and a concrete support body, wherein the concrete support body and the closure receptacle at least in sections positively and materially connected to each other, the closure receptacle projects beyond the concrete support body in the direction of the closure element, and the concrete support body has a downwardly tapering shaft facing away side surface. In this case, the closure receptacle on the side facing away from the shaft of the manhole cover arrangement on a downwardly angled leg, which at least partially comprises the concrete support body on the side facing away from the shaft.

Figure DE102015102803A1_0001
Figure DE102015102803A1_0001

Description

Die Erfindung betrifft eine Schachtabdeckungsanordnung gemäß dem Oberbegriff von Anspruch 1 sowie ein Verfahren zum Einbau eines solchen gemäß Anspruch 11. The invention relates to a manhole cover arrangement according to the preamble of claim 1 and to a method for installing such according to claim 11.

Zum Stand der Technik gehören bereits Verfahren zum Sanieren eines Schachtes, wobei eine Schachtabdeckungsanordnung mit einer schrägen Fräskante freigefräst wird. Anschließend wird die Schachtabdeckungsanordnung entfernt und eine neue Schachtabdeckungsanordnung in die freigefräste Öffnung mit den schrägen Fräskanten eingesetzt. Gegebenenfalls wird vor dem Einsetzen der Schachtabdeckungsanordnung zum Ausgleich der Höhenunterschiede ein Vergussmörtel in die Einbauöffnung eingebracht. The prior art already includes methods for rehabilitating a shaft, wherein a manhole cover arrangement is milled with an oblique milling edge. Subsequently, the manhole cover assembly is removed and a new manhole cover assembly inserted into the free-milled opening with the oblique cutting edges. Optionally, a grout is introduced into the installation opening prior to insertion of the manhole cover assembly to compensate for the height differences.

Nachteilig bei diesem Verfahren ist jedoch, dass die Verkehrslasten, welche auf den Schachtabdeckungsdeckel, z.B. durch Fahrzeuge, aufgebracht werden in zu großem Umfang auf den darunterliegenden Schacht weitergegeben werden. Durch die konische Ausfräsung sowie die konische Ausführung des gewählten Schachtabdeckungsrahmens wird zwar eine Teilentlastung des Schachtes erreicht, diese ist für große Verkehrslasten jedoch häufig nicht ausreichend. A disadvantage of this method, however, is that the traffic loads placed on the manhole cover, e.g. be applied by vehicles, be passed on in too large an extent on the underlying shaft. Although a partial relief of the shaft is achieved by the conical cutout and the conical design of the selected manhole cover frame, this is often not sufficient for large traffic loads.

Ein weiterer Nachteil des dort offenbarten Verfahrens besteht in der fehlenden Verfüllung eines Zwischenraums. Speziell bei sehr unterschiedlichen Werkstoffen wie z.B. Gusseisen, oder an dem Gusseisen angebrachten Beton gibt es keine dämpfende Funktion oder ausgleichende Funktion bezüglich der frei gefrästen schrägen Fräskante. Another disadvantage of the method disclosed therein is the lack of backfilling a gap. Especially for very different materials such. Cast iron, or concrete attached to the cast iron, there is no dampening function or compensatory function with respect to the free-milled oblique milling edge.

Um diesem zu begegnen, schlägt die DE 10 2006 056 936 A1 ein Verfahren zum Einbau einer Schachtabdeckung bestehend aus einem Schachtabdeckungsrahmen und einem Deckel, über einem Schacht umfassend die folgenden Schritte vor: Zur Aufnahme des Schachtabdeckungsrahmens wird zunächst eine Einbauöffnung mittels einer Schachtfräsmaschine konisch ausgefräst. Anschließend wird die Einbauöffnung freigeräumt. Ein Schachtabdeckungsrahmen wird zentrisch zur Einbauöffnung in diese eingeführt und ausgerichtet. Verfüllt wird der zwischen der Einbauöffnung und dem Schachtabdeckungsrahmen verbliebene Freiraum mit einem bindenden Verfüllmaterial und der über der Schachtabdeckung liegende Bereich des Betonteils des Rahmens mit Asphalt. To counter this, the beats DE 10 2006 056 936 A1 a method for installing a manhole cover consisting of a manhole cover frame and a lid, above a shaft comprising the following steps: To accommodate the manhole cover frame, a mounting hole is first milled conical by means of a shaft milling machine. Subsequently, the installation opening is cleared. A manhole cover frame is centrally inserted and aligned with the mounting hole in this. The space left between the installation opening and the manhole cover frame is filled with a binding filling material and the area of the concrete part of the frame with asphalt above the manhole cover.

Nachteilig bei dieser Ausführungsform ist jedoch, dass die Anbindung des Asphaltes im Bereich des Betonkörpers der Schachtabdeckung häufig unzureichend ist. Dies liegt insbesondere an den hohen Verkehrslasten, die über den dann nur dünn aufgetragenen Asphalt auf das Bauwerk einwirken. Um diese Deckschichtenproblematik zu entschärfen, wurden im Stand der Technik bereits Dickenveränderungen aller Art vorgenommen, die aber nicht zum gewünschten Ergebnis führten. A disadvantage of this embodiment, however, is that the connection of the asphalt in the concrete body of the manhole cover is often insufficient. This is particularly due to the high traffic loads, which act on the then only thinly applied asphalt on the building. In order to defuse this surface layer problem, thickness changes of all types have already been made in the prior art, but these did not lead to the desired result.

Ein weiterer Nachteil der in DE 10 2006 056 936 A1 gezeigten Lösung ist zudem der hohe Materialeinsatz beim Einbau, welcher sich aus der Ausbildung zweier Fugen ergibt. Die Ausführung zweier Fugen ergibt sich zum Einen aus der Verbindung des dünn aufgetragenen Asphalts mit der Schachtabdeckung und der Verbindung des dünn aufgetragenen Asphalts mit dem bestehenden Straßenbauwerk. Die Herstellung an zwei unterschiedlichen Stellen im Fahrbahnniveau führt zudem zu einer verlängerten Einbauzeit. Another disadvantage of in DE 10 2006 056 936 A1 The solution shown is also the high material usage during installation, which results from the formation of two joints. The execution of two joints results on the one hand from the connection of the thinly applied asphalt with the manhole cover and the connection of the thinly applied asphalt with the existing road structure. The production at two different points in the road level also leads to an extended installation time.

Aufgrund der nur dünnen Überdeckung im Bereich des Übergangs zwischen Schachtabdeckung und Straßenbauwerk, war die Verwendung von offenporigem Asphalt, wie er regelmäßig in der innerstädtischen Einbausituation Anwendung finden soll, nicht darstellbar, da offenporiger Asphalt nur eine geringe Belastbarkeit aufweist. Due to the only thin overlap in the area between the manhole cover and the road construction, the use of open-pored asphalt, as it should regularly be used in the inner-city installation situation, was not feasible, because open-pored asphalt has only a low load capacity.

Ziel der Erfindung ist es, eine Schachtabdeckungsanordnung zur Verwendung im Straßenneubau und in Sanierungsverfahren zu schaffen, sowie ein Verfahren zum Einbau eines erfindungsgemäßen Schachtabdeckungsrahmens bereitzustellen, wobei Verbindungsprobleme und damit verbundene Rissbildungen zwischen Schachtabdeckungsanordnung und dem Asphalt ausgeschlossen werden. Zudem soll die Verwendung von offenporigem Asphalt (OPA-Asphalt) beim Bau der Straße problemlos möglich werden, die Einbaudauer reduziert und die Menge der eingesetzten Materialien, insbesondere Vergussmörtel und Fugenmaterial, vermindert werden. The object of the invention is to provide a manhole cover assembly for use in road construction and rehabilitation processes, as well as to provide a method of installing a manhole cover frame according to the invention, thereby precluding connection problems and associated cracking between manhole cover assembly and the asphalt. In addition, the use of open-pored asphalt (OPA asphalt) in the construction of the road should be easily possible, reduces the installation time and the amount of materials used, in particular grout and grout, are reduced.

Hauptmerkmale der Erfindung sind im kennzeichnenden Teil von Anspruch 1 sowie in Anspruch 11 angegeben. Ausgestaltungen sind Gegenstand der Ansprüche 2 bis 10 und 12. Main features of the invention are specified in the characterizing part of claim 1 and in claim 11. Embodiments are the subject of claims 2 to 10 and 12th

Bei einer Schachtabdeckungsanordnung zur Verwendung im Straßenneubau und in Sanierungsverfahren, mit einem Verschlusselement und einem Schachtabdeckungsrahmen, wobei der Schachtabdeckungsrahmen zweiteilig aus einer Verschlussaufnahme zur Aufnahme des Verschlusselements und einem Betonstützkörper ausgebildet ist, wobei der Betonstützkörper und die Verschlussaufnahme zumindest abschnittsweise form- und stoffschlüssig miteinander verbunden sind, die Verschlussaufnahme den Betonstützkörper in Richtung des Verschlusselements überragt, und der Betonstützkörper eine sich nach unten verjüngende schachtabgewandte Seitenfläche aufweist, sieht die Erfindung vor, dass die Verschlussaufnahme an der schachtabgewandten Seite der Schachtabdeckungsanordnung einen nach unten abgewinkelten Schenkel aufweist, der den Betonstützkörper an dessen schachtabgewandter Seite zumindest teilweise umfasst. In a manhole cover assembly for use in road construction and rehabilitation process, with a closure element and a manhole cover frame, the manhole cover frame is formed in two parts from a closure receptacle for receiving the closure element and a concrete support, wherein the concrete support body and the closure receptacle are at least partially positively and materially connected to each other in that the closure receptacle projects beyond the concrete support body in the direction of the closure element, and the concrete support body has a downwardly tapering side face facing away from the shaft, the invention provides for the closure receptacle to be disposed on the shaft facing away from the shaft Side of the manhole cover assembly has a downwardly angled leg which at least partially surrounds the concrete support body on the side facing away from the shaft.

Durch diese erfindungsgemäße Ausgestaltung ist es möglich, dass im Bereich des Fahrbahnbelags nur noch eine Fuge abgedichtet werden muss. Der nach unten abgewinkelte Schenkel, der den Betonstützkörper an dessen schachtabgewandter Seite zumindest teilweise umfasst, definiert einen sauberen Anschlussabschnitt zum Fahrbahnbelag. Durch den so gebildeten Anschlussabschnitt wird nicht nur eine saubere Fugenausbildung gewährleistet, sondern auch die Trennung des Spannungseintrages aus dem Straßenbauwerk in das Schachtbauwerk bewirkt. With this embodiment according to the invention, it is possible that only one joint has to be sealed in the region of the road surface. The downwardly angled leg, which at least partially surrounds the concrete support body on its side facing away from the shaft, defines a clean connection section to the road surface. The connection section thus formed not only ensures a clean joint formation, but also causes the separation of the voltage input from the road structure in the shaft structure.

Ein typisches Straßenbauwerk beginnt im unteren Bereich mit einer Tragschicht an die sich Schottertragschicht, Asphalttragschicht, Binderschicht und Deckschicht anschließen. Ein Schachtbauwerk wird üblicherweise gebildet aus Schachtabdeckung, Ausgleichsring, Schachtkonus und Schachtring. A typical road construction begins in the lower area with a base course to which the gravel base layer, asphalt base course, binder course and top layer join. A shaft structure is usually formed from manhole cover, balance ring, shaft cone and manhole ring.

Durch den erfindungsgemäßen nach unten abgewinkelten Schenkel, der den Betonstützkörper an dessen schachtabgewandter Seite zumindest teilweise umfasst, treten die im Straßenbauwerk besonders im oberen Bereich auftretenden Spannungen, hervorgerufen durch Setzungen und Verschiebungen, die oftmals aus den starken Verkehrsbelastungen resultieren, aber auch durch unterschiedliche Wärmeausdehnungskoeeffizienten der eingesetzten Materialien bei Temperaturwechseln am Schachtbauwerk, reduziert in Erscheinung, da Schacht- und Straßenbauwerk weitestgehend voneinander getrennt sind. Zudem ist die ausgebildete einzelne Fuge bei der erfindungsgemäßen Ausgestaltung sehr schmal, was zu einem deutlich reduzierten Materialeinsatz führt. Einsparungen beim Vergussmörtel und des Fugenmaterials kommen hier ebenso zum Tragen wie der Wegfall des sonst erforderlichen Asphalts. Zudem ist der Einsatz von Asphalt bei Sanierungen oft schwierig, da Heißasphalt oftmals nicht ganztägig und nur in größeren Mengen zur Verfügung steht. Alternative Materialien wie Kaltasphalt sind sehr teuer. Somit verfügt die erfindungsgemäße Anordnung über eine ganze Reihe von Vorteilen. Due to the downwardly angled leg according to the invention, which at least partially covers the concrete support body on the side facing away from the shaft, the stresses occurring in the roadworks in the upper region, caused by subsidence and shifts that often result from the heavy traffic loads, but also by different thermal expansion coefficients Materials used in case of temperature changes at the shaft structure, reduced in appearance, since shaft and road structure are largely separated. In addition, the trained individual joint in the embodiment according to the invention is very narrow, which leads to a significantly reduced use of materials. Savings in the grouting mortar and grout material are just as important here as the elimination of the otherwise required asphalt. In addition, the use of asphalt in refurbishment is often difficult because hot asphalt is often not available all day and only in larger quantities. Alternative materials such as cold asphalt are very expensive. Thus, the arrangement according to the invention has a whole series of advantages.

Eine Weiterbildung der Erfindung sieht vor, dass der Schenkel L-förmig ist, was die Anbindung an das Straßenbauwerk noch weiter verbessert. Der definierte L-förmige Abschnitt sorgt für optimale Anlageflächen zwischen Verschlussaufnahme und Straßenbauwerk. Zudem verschafft er eine homogene Fugenbreite zwischen Verschlussaufnahme und Straßenbauwerk auf dem gesamten Fugenabschnitt. A development of the invention provides that the leg is L-shaped, which further improves the connection to the road construction. The defined L-shaped section ensures optimal contact surfaces between the lock receptacle and the road construction. In addition, it provides a homogeneous joint width between the closure receptacle and the road structure on the entire joint section.

Idealerweise ist der Schenkel in einem sich nicht verjüngenden Bereich des Betonstützkörpers angeordnet. Die Verjüngung des Betonstützkörpers beginnt dann direkt am Ende des Lförmigen Schenkels. Auf diese Weise werden die Vorteile beider Bauteile des Schachtabdeckungsrahmens perfekt miteinander kombiniert. Ideally, the leg is arranged in a non-tapering region of the concrete support body. The taper of the concrete support body then begins directly at the end of the L-shaped leg. In this way, the advantages of both components of the manhole cover frame are perfectly combined.

Der senkrecht stehende L-förmige Abschnitt sorgt für eine gute Anbindung an die Deckschicht des Straßenbauwerks, was optimal für die Dichtigkeit und Frostsicherheit des Systems ist, während sich der verjüngende Bereich des Betonstützkörpers optimal an der Tragschicht des Straßenbauwerks abstützen kann. Dies führt zu einer hohen Haltbarkeit der gesamten Schachtabdeckungsanordnung. The vertical L-shaped section provides a good connection to the surface layer of the road structure, which is optimal for the tightness and frost resistance of the system, while the tapered portion of the concrete support body can be optimally supported on the supporting layer of the road structure. This leads to a high durability of the entire manhole cover arrangement.

Eine alternative Ausführungsform sieht vor, dass der Schenkel eine Nut oder einen Hinterschnitt aufweist. Die Ausbildung mindestens eines Hinterschnitts führt zu einer optimalen Haftung des Fugenmaterials im Dichtbereich zur Deckschicht. Idealerweise wird dazu ein dauerhaft elastischer Kunststoffmörtel für statisch und dynamisch hochbelastete Fugen verwendet. Alternativ sind auch andere Fugenvergussmassen, die heiß oder kalt verarbeitet werden geeignet. Somit führt der ausgebildete Hinterschnitt/Nut zu einer besonders guten Abdichtung zwischen Schachtabdeckung und dem vorhandenen Straßenbauwerk. Damit wird das Eindringen von Feuchtigkeit bzw. Wasser zwischen Straßenbauwerk und Schachtabdeckung dauerhaft und zuverlässig verhindert, sodass Ausspülungen oder Frostschäden, wie bspw. Abplatzen von Asphalt durch Frost, sicher verhindert werden. An alternative embodiment provides that the leg has a groove or an undercut. The formation of at least one undercut leads to an optimal adhesion of the joint material in the sealing area to the cover layer. Ideally, a permanently elastic plastic mortar is used for statically and dynamically highly stressed joints. Alternatively, other Fugenvergussmassen that are processed hot or cold are suitable. Thus, the trained undercut / groove leads to a particularly good seal between the manhole cover and the existing road construction. This permanently and reliably prevents the ingress of moisture or water between the road structure and manhole cover so that rinsing or frost damage, such as, for example, chipping off of asphalt due to frost, can be reliably prevented.

Vorteilhafterweise ist die Nut oder der Hinterschnitt als Ringnut auf der schachtabgewandten Seitenfläche der Verschlussaufnahme angeordnet. Die Ausführung als Ringnut sorgt für eine noch bessere Lagesicherung des Fugenmaterials und somit durch die geringere Gefahr von Frost- oder Belastungsschäden für eine größere Dauerhaftigkeit des Schachtbauwerks. Advantageously, the groove or the undercut is arranged as an annular groove on the shaft side facing away from the closure receptacle. The design as an annular groove ensures even better securing of the joints material and thus by the lower risk of frost or load damage for greater durability of the shaft structure.

Ein weiterer Vorteil kann zudem bei einer Variante der Erfindung in der Anordnung einer Vorrichtung zur Aufnahme einer Einstieghilfe in der Verschlussaufnahme liegen. Dadurch dass eine Einstieghilfe einfach und direkt in den Schachtrahmen gesteckt werden kann, findet diese in aller Regel bei den, den Schacht betretenden Personen, in der Anwendung eine größere Akzeptanz. Die Sicherheit der Personen wird damit im Sinne der Unfallverhütungsvorschriften auf einfache Weise gewährleistet. A further advantage may also lie in a variant of the invention in the arrangement of a device for receiving an entry aid in the closure receptacle. The fact that an entry aid can be easily and directly inserted into the manhole frame, this is usually in the, the man entering the shaft, in the application a greater acceptance. The safety of persons is thus ensured in the sense of accident prevention regulations in a simple manner.

Zudem kann bei einer Alternative eine am Betonstützkörper an der schachtabgewandten Seitenfläche angeordnete Ringnut vorhanden sein. Diese schafft mit Ihrer konturierten Ausprägung an der sich verjüngenden Seitenfläche des Betonstützkörpers eine besonders gute Verkrallung mit dem Vergussmörtel, was einen dauerhaft optimalen Lastabtrag sicherstellt. In addition, in one alternative, an annular groove arranged on the concrete support body at the side facing away from the shaft may be present. This creates with its contoured expression of the tapered side surface of the concrete support a particularly good claw with the grout, which ensures a durable optimal load transfer.

Eine gegenüber dem vorgenannten verbesserte Weiterbildung sieht vor, dass am Betonstützkörper an der schachtabgewandten Seitenfläche drei gleichmäßig voneinander beabstandete Ringnuten angeordnet sind, die für eine sehr homogene und noch bessere Verzahnung des Vergussmörtels mit der Schachtabdeckungsanordnung sorgen. Damit wird eine haftungsoptimierte Oberfläche an der Schachtabdeckung im Bereich der Lastabtragungsflächen generiert. A comparison with the aforementioned improved embodiment provides that three evenly spaced annular grooves are arranged on the concrete support body on the lateral side facing away from the shaft, which ensure a very homogeneous and even better toothing of the grouting mortar with the manhole cover arrangement. This generates an adhesion-optimized surface on the manhole cover in the area of the load transfer surfaces.

Vorteilhafterweise beginnt die sich nach unten verjüngende schachtabgewandte Seitenfläche des Betonstützkörpers am unteren Ende des Schenkels der Verschlussaufnahme. Dabei erfolgt insbesondere ein bündiger Übergang. Damit wird eine klare Trennung der Randbereiche zwischen der Tragfunktion des Betonstützkörpers in der Binderschicht mit tragender Funktion und der Dichtungsfunktion der Verschlussaufnahme in der Deckschicht erreicht. Dies führt zu einer besonders dauerhaften Lösung. Advantageously, the downwardly tapering shaft facing away from side surface of the concrete support body begins at the lower end of the leg of the closure receptacle. In particular, a flush transition occurs. This achieves a clear separation of the edge regions between the support function of the concrete support body in the binder layer with a supporting function and the sealing function of the closure receptacle in the cover layer. This leads to a particularly durable solution.

Ein erfindungsgemäßes Verfahren zum Einbau eines Schachtabdeckungsrahmens gemäß einem der Ansprüche 1 bis 9 sieht vor, dass

  • – mittels eines Fräskopfes eine Einbauöffnung über einem Schachtbauwerk derart freigefräst wird, dass die ausgebildete Fräskante im oberen Bereich korrespondierend zu der einsetzbaren Verschlussaufnahme des Schachtabdeckungsrahmens und im unteren Bereich korrespondierend zu dem an der Verschlussaufnahme angeordnetem Betonstützkörper verläuft,
  • – danach der Schachtabdeckungsrahmen gemäß einem der Ansprüche 1 bis 8 über dem Schachtkopf ausgerichtet und provisorisch derart fixiert wird, dass ein zu verfüllender Ringraum ausgebildet ist,
  • – anschließend der Ringraum im Anlagebereich des Betonstützkörpers mit einem Vergussmörtel verfüllt wird,
  • – und abschließend der verbleibende Ringraum im Bereich der Verschlussaufnahme mit einem dauerhaft elastischen Kunststoffmörtel für statisch und dynamisch hochbelastete Fugen verfüllt wird.
An inventive method for installing a manhole cover frame according to one of claims 1 to 9 provides that
  • By means of a milling head, an installation opening is milled over a shaft structure in such a way that the formed milling edge runs in the upper area corresponding to the insertable closure receptacle of the manhole cover frame and in the lower area corresponds to the concrete support body arranged on the closure receptacle,
  • - Then the manhole cover frame according to one of claims 1 to 8 aligned above the shaft head and provisionally fixed such that an annular space to be filled is formed,
  • - Then the annulus is filled in the contact area of the concrete support with a grout,
  • - And finally the remaining annular space in the area of the closure receptacle is filled with a permanently elastic plastic mortar for statically and dynamically highly loaded joints.

Das erfindungsgemäße Verfahren stellt so auf einfache und kostengünstige Weise die Ausbildung eines maßgenauen Aushubs für die einzusetzende Schachtabdeckungsanordnung sicher. Die als Ringraum ausgebildete Fuge ist in ihrer Größe optimal gewählt und an allen Seiten der Schachtabdeckungsanordnung ideal verteilt. Der Fugenraum ist somit insgesamt gegenüber den Lösungen aus dem Stand der Technik sehr schmal und es wird nur wenig Fugenmaterial benötigt. The method according to the invention thus ensures, in a simple and cost-effective manner, the formation of a dimensionally accurate excavation for the manhole cover arrangement to be used. The gap formed as an annular space is optimally chosen in size and ideally distributed on all sides of the manhole cover arrangement. The joint space is thus very narrow overall compared to the solutions of the prior art and only a small amount of joint material is required.

Durch die Ausbildung der Fuge mittels Fräsvorgang kann der gleiche Fugenspalt sowohl zur Verankerung des Betonstützkörpers in der Binderschicht mit tragender Funktion als auch zur Abdichtung der Verschlussaufnahme gegenüber der Deckschicht verwendet werden. Dabei wird in den Fugenraum zuerst der Vergussmörtel und anschließend der elastische Kunststoffmörtel eingebracht. Die Einbauzeit zur Einbringung des Vergussmörtels und der Abdichtungsmasse wird somit reduziert. By forming the joint by means of milling, the same joint gap can be used both for anchoring the concrete support body in the binder layer with a supporting function and for sealing the closure receptacle relative to the cover layer. In the process, first the grouting mortar and then the elastic plastic mortar are introduced into the joint space. The installation time for the introduction of the grout and the sealing compound is thus reduced.

Da der Kunststoffmörtel auch geeignet ist, die Verschlussaufnahme gegenüber offenporigen Asphalt abzudichten, kann dieser nun mit einer erfindungsgemäßen Schachtabdeckung trotz Verwendung eines Schachtabdeckungsrahmens mit sich nach unten verjüngendem Betonstützkörper verwendet werden. Das aus dem Stand der Technik bekannte Verbindungsproblem und die damit verbundenen Rissbildungen zwischen Schachtabdeckungsanordnung und der Deckschicht werden somit wirksam und dauerhaft vermieden. Since the plastic mortar is also suitable for sealing the closure receptacle against open-pored asphalt, it can now be used with a manhole cover according to the invention despite the use of a manhole cover frame with downwardly tapering concrete support body. The known from the prior art connection problem and the associated cracking between manhole cover assembly and the cover layer are thus effectively and permanently avoided.

Besonders vorteilhaft wird das Verfahren durchgeführt, wenn der dauerhaft elastische Kunststoffmörtel die Nut im Schenkel ausfüllt. Dadurch ist die Lagesicherung der Abdichtungsmasse besonders wirksam. So eingebaute Schachtabdeckungsanordnungen sind damit sehr langlebig. Particularly advantageously, the method is carried out when the permanently elastic plastic mortar fills the groove in the leg. As a result, the position assurance of the sealing compound is particularly effective. Thus installed manhole cover arrangements are thus very durable.

Weitere Merkmale, Einzelheiten und Vorteile der Erfindung ergeben sich aus dem Wortlaut der Ansprüche sowie aus der folgenden Beschreibung von Ausführungsbeispielen anhand der Zeichnungen. Es zeigen: Further features, details and advantages of the invention will become apparent from the wording of the claims and from the following description of exemplary embodiments with reference to the drawings. Show it:

1 eine erfindungsgemäße Schachtabdeckungsanordnung; 1 a manhole cover assembly according to the invention;

2 einen Ausschnitt einer erfindungsgemäßen Schachtabdeckungsanordnung im Fugenbereich im eingebauten Zustand; 2 a detail of a manhole cover assembly according to the invention in the joint area in the installed state;

3 eine Schachtabdeckungsanordnung vor Einsatz in ein Straßenbauwerk; 3 a manhole cover assembly prior to use in a road construction;

4 obige Schachtabdeckungsanordnung im eingebauten Zustand im Schnitt; 4 above manhole cover arrangement in the installed state in section;

5 eine erfindungsgemäße Schachtabdeckungsanordnung im eingebauten Zustand in der Draufsicht. 5 a manhole cover assembly according to the invention in the installed state in plan view.

1 zeigt eine erfindungsgemäße Schachtabdeckungsanordnung 1 zur Verwendung im Straßenneubau und in Sanierungsverfahren, mit einem Verschlusselement 6 und einem Schachtabdeckungsrahmen 2, wobei der Schachtabdeckungsrahmen 2 zweiteilig aus einer Verschlussaufnahme 3 zur Aufnahme des Verschlusselements 6 und einem Betonstützkörper 4 ausgebildet ist, wobei der Betonstützkörper 4 und die Verschlussaufnahme 3 zumindest abschnittsweise form- und stoffschlüssig miteinander verbunden sind, die Verschlussaufnahme 3 den Betonstützkörper 4 in Richtung des Verschlusselements 6 überragt, und der Betonstützkörper 4 eine sich nach unten verjüngende schachtabgewandte Seitenfläche 5 aufweist, wobei die Verschlussaufnahme 3 an der schachtabgewandten Seite 7 der Schachtabdeckungsanordnung 1 einen nach unten abgewinkelten Schenkel 8 aufweist, der den Betonstützkörper 4 an dessen schachtabgewandter Seite 7 zumindest teilweise umfasst. 1 shows a manhole cover assembly according to the invention 1 for use in road construction and rehabilitation processes, with a closure element 6 and one Manhole cover frame 2 , wherein the manhole cover frame 2 two-part from a closure 3 for receiving the closure element 6 and a concrete support 4 is formed, wherein the concrete support body 4 and the lock receptacle 3 at least partially positively and materially connected to each other, the closure receptacle 3 the concrete support 4 in the direction of the closure element 6 surmounted, and the concrete support body 4 a downwardly tapering shaft facing away side surface 5 having, wherein the closure receptacle 3 on the side facing away from the shaft 7 the manhole cover arrangement 1 a downwardly angled leg 8th comprising the concrete support body 4 on the side facing away from the shaft 7 at least partially.

Dabei ist der Schenkel 8 L-förmig und in einem sich nicht verjüngenden Bereich 9 des Betonstützkörpers 4 angeordnet. Weiterhin ist erkennbar, dass der Schenkel 8 eine Nut 10 aufweist. Die Nut 10 ist dabei als Ringnut auf der schachtabgewandten Seitenfläche 7 der Verschlussaufnahme 3 angeordnet. Zudem ist in der Verschlussaufnahme 3 eine Vorrichtung zur Aufnahme einer Einstieghilfe 11 ausgebildet. Außerdem sind am Betonstützkörper 4 an dessen schachtabgewandten verjüngenden Seitenflächen 5 drei gleichmäßig voneinander beabstandete Ringnuten 12 angeordnet. Die sich nach unten verjüngende schachtabgewandte Seitenfläche 5 des Betonstützkörpers 4 beginnt dabei am unteren Ende 13 des Schenkels 8 der Verschlussaufnahme 3. Ferner ist eine Ringbewehrung 14 im Betonkörper 4 zu erkennen. This is the thigh 8th L-shaped and in a non-tapered area 9 of concrete support 4 arranged. Furthermore, it can be seen that the leg 8th a groove 10 having. The groove 10 is here as an annular groove on the shaft side facing away from the side 7 the lock receptacle 3 arranged. In addition, in the lock receptacle 3 a device for receiving a boarding aid 11 educated. In addition, the concrete support body 4 at the shaft facing away from tapered side surfaces 5 three equally spaced annular grooves 12 arranged. The downwardly tapering shaft facing away side surface 5 of concrete support 4 starts at the bottom 13 of the thigh 8th the lock receptacle 3 , Furthermore, a ring reinforcement 14 in the concrete body 4 to recognize.

2 beschreibt einen Ausschnitt im Bereich der Fugenausbildung einer erfindungsgemäßen Schachtabdeckungsanordnung 1 im eingebauten Zustand. Nach der Durchführung des erfindungsgemäßen Verfahrens zum Einbau eines Schachtabdeckungsrahmens gemäß einem der Ansprüche 1 bis 9 kann man erkennen, dass die an der Binderschicht mit tragender Funktion 15 ausgebildete Fräskante 19 im oberen Bereich 20 korrespondierend zu der eingesetzten Verschlussaufnahme 3 des Schachtabdeckungsrahmens 2 und im unteren Bereich 21 korrespondierend zu dem an der Verschlussaufnahme 3 angeordneten Betonstützkörper 4 verläuft. Der zu verfüllende Ringraum 22 ist dabei vollständig verfüllt. 2 describes a section in the region of the joint formation of a manhole cover arrangement according to the invention 1 in the installed state. After carrying out the method according to the invention for installing a manhole cover frame according to any one of claims 1 to 9, it can be seen that the at the binder layer with supporting function 15 trained milling edge 19 in the upper area 20 corresponding to the closure receptacle used 3 of the manhole cover frame 2 and at the bottom 21 corresponding to that on the closure receptacle 3 arranged concrete support body 4 runs. The annular space to be filled 22 is completely filled.

Im Anlagebereich des Betonstützkörpers 4 ist dies mit einem Vergussmörtel 18 geschehen, und im Bereich der Verschlussaufnahme 3 mit einem dauerhaft elastischen Kunststoffmörtel 17 für statisch und dynamisch hochbelastete Fugen. Der dauerhaft elastische Kunststoffmörtel 18 füllt dabei die Nut 10 im Schenkel 8 vollständig aus. In the contact area of the concrete support body 4 this is with a grout 18 done, and in the area of the closure shot 3 with a permanently elastic plastic mortar 17 for statically and dynamically heavily loaded joints. The permanently elastic plastic mortar 18 fills the groove 10 in the thigh 8th completely off.

Weiterhin ist dargestellt, dass der Kunststoffmörtel 17 mit der Deckschicht 16 in Kontakt steht, während der Vergussmörtel 18 den Ringraum 22 zur Binderschicht mit tragender Funktion 15 hin abgrenzt. Auf der schachtabgewandten sich verjüngenden Seitenfläche 5 sind die Ringnuten 12 zu erkennen, die eine Verzahnung des Betonstützkörpers 4 mit dem Vergussmörtel 18 gewährleisten. Furthermore, it is shown that the plastic mortar 17 with the topcoat 16 in contact while the grout 18 the annulus 22 to the binder course with a supporting function 15 delimited. On the bay facing away from the tapered side surface 5 are the ring grooves 12 to recognize the teeth of the concrete support body 4 with the grout 18 guarantee.

3 zeigt die erfindungsgemäße Schachtabdeckungsanordnung 1 vor der über einen Ausgleichsring 24 zu erfolgenden Montage auf dem Schachtkopf 23. Man erkennt die mittels eines Fräskopfes freigefräste Einbauöffnung 26, wobei die ausgebildete Fräskante 19 im oberen Bereich 20 korrespondierend zu der einsetzbaren Verschlussaufnahme 3 und im unteren Bereich 21 korrespondierend zu dem an der Verschlussaufnahme 3 angeordnetem Betonstützkörper 4 verläuft. Im dargestellten Beispiel ist unterhalb der Binderschicht mit tragender Funktion 15 noch eine Tragschicht 25 angeordnet. 3 shows the manhole cover assembly according to the invention 1 in front of over a balancing ring 24 to be mounted on the shaft head 23 , One recognizes the cut-free by means of a milling head mounting hole 26 , wherein the trained milling edge 19 in the upper area 20 corresponding to the insertable closure receptacle 3 and at the bottom 21 corresponding to that on the closure receptacle 3 arranged concrete support body 4 runs. In the example shown below is below the binder layer with supporting function 15 still a base course 25 arranged.

4 beschreibt die erfindungsgemäße Schachtabdeckungsanordnung 1 im eingebauten Zustand. Dabei ist gut gezeigt, dass die Oberseite der Verschlussaufnahme 3 mit der Oberseite der Deckschicht 16 ein Planum 27 bilden. Durch den eingebrachten Kunststoffmörtel 17 in die Nut 10 der Verschlussaufnahme 3 entsteht eine sehr ordentliche Fugensituation, welche eine gute Dichtigkeit sicherstellt, so dass kein Wasser in die Binderschicht mit tragender Funktion 15 gelangen kann. Der Vergussmörtel 18 verbindet sich über die Ringnuten 12 des Betonstützkörpers 4 in idealer Weise mit diesem und der angrenzenden Binderschicht mit tragender Funktion 15 sowie der Tragschicht 25. Zudem stellt der Vergussmörtel 18 sicher, dass der Betonstützkörper 4 gleichmäßig auf dem Ausgleichsring 24 aufliegt, was zu einer homogenen Spannungsverteilung im Bauteil und damit einhergehenden Langlebigkeit führt. Die Vorrichtung zur Aufnahme einer Einstieghilfe 11 befindet sich im Randbereich des Schachteinstiegs und ist somit praktisch positioniert. 4 describes the manhole cover assembly according to the invention 1 in the installed state. It is well shown that the top of the closure receptacle 3 with the top of the topcoat 16 a planum 27 form. Through the introduced plastic mortar 17 in the groove 10 the lock receptacle 3 creates a very neat joint situation, which ensures a good tightness, so that no water in the binder layer with bearing function 15 can get. The grout 18 connects via the ring grooves 12 of concrete support 4 ideally with this and the adjacent binder layer with bearing function 15 and the base layer 25 , In addition, the grout 18 sure that the concrete support body 4 evenly on the compensation ring 24 rests, which leads to a homogeneous stress distribution in the component and the associated longevity. The device for receiving a boarding aid 11 is located in the edge area of the shaft entrance and is thus practically positioned.

5 beschreibt die erfindungsgemäße Schachtabdeckungsanordnung 1 im eingebauten Zustand aus der Vogelperspektive jedoch ohne Verschlusselement. Dabei ist nur die Deckschicht 16 des Straßenbauwerks erkennbar. Der Schachtabdeckungsrahmen 2 grenzt dabei mit seiner Verschlussaufnahme 3 über nur eine Fuge aus Kunststoffmörtel 17 an die Deckschicht 16. Weiterhin ist die Vorrichtung zur Aufnahme einer Einstieghilfe 11 erkennbar. 5 describes the manhole cover assembly according to the invention 1 when installed from a bird's eye view, but without closure element. It is only the top layer 16 of the road structure recognizable. The manhole cover frame 2 borders with its closure 3 over only one joint of plastic mortar 17 to the topcoat 16 , Furthermore, the device for receiving a boarding aid 11 recognizable.

Die Erfindung ist nicht auf eine der vorbeschriebenen Ausführungsformen beschränkt, sondern in vielfältiger Weise abwandelbar. The invention is not limited to one of the above-described embodiments, but can be modified in many ways.

Sämtliche aus den Ansprüchen, der Beschreibung und der Zeichnung hervorgehenden Merkmale und Vorteile, einschließlich konstruktiver Einzelheiten, räumlicher Anordnungen und Verfahrensschritten, können sowohl für sich als auch in den verschiedensten Kombinationen erfindungswesentlich sein. All resulting from the claims, the description and the drawing features and advantages, including structural details, spatial arrangements and Process steps, can be essential to the invention, both for themselves and in various combinations.

BezugszeichenlisteLIST OF REFERENCE NUMBERS

1 1
Schachtabdeckungsanordnung Manhole cover assembly
2 2
Schachtabdeckungsrahmen Manhole cover frame
3 3
Verschlussaufnahme locking receiver
4 4
Betonstützkörper Concrete support body
5 5
verjüngende Seite rejuvenating side
6 6
Verschlusselement closure element
7 7
schachtabgewandte Seite bay side facing away
8 8th
Schenkel leg
9 9
nicht verjüngender Bereich non-rejuvenating area
1010
Nut  groove
1111
Vorrichtung zur Aufnahme einer Einstieghilfe  Device for receiving a boarding aid
1212
Ringnuten  ring grooves
1313
unteres Ende  lower end
1414
Ringbewehrung  ring reinforcement
1515
Binderschicht mit tragender Funktion  Binder layer with carrying function
1616
Deckschicht  topcoat
1717
Kunststoffmörtel  Plastic mortar
1818
Vergussmörtel  grout
1919
Fräskante  milling edge
2020
oberer Bereich der Fräskante  Upper area of the milling edge
2121
unterer Bereich der Fräskante  lower area of the milling edge
2222
Ringraum  annulus
2323
Schachtkopf  wellhead
2424
Ausgleichsring  compensation ring
2525
Tragschicht  base course
2626
Einbauöffnung  hole
2727
Planum  Planum

ZITATE ENTHALTEN IN DER BESCHREIBUNG QUOTES INCLUDE IN THE DESCRIPTION

Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list of the documents listed by the applicant has been generated automatically and is included solely for the better information of the reader. The list is not part of the German patent or utility model application. The DPMA assumes no liability for any errors or omissions.

Zitierte PatentliteraturCited patent literature

  • DE 102006056936 A1 [0005, 0007] DE 102006056936 A1 [0005, 0007]

Claims (11)

Schachtabdeckungsanordnung (1) zur Verwendung im Straßenneubau und in Sanierungsverfahren, mit einem Verschlusselement (6) und einem Schachtabdeckungsrahmen (2), wobei der Schachtabdeckungsrahmen (2) zweiteilig aus einer Verschlussaufnahme (3) zur Aufnahme des Verschlusselements (6) und einem Betonstützkörper (4) ausgebildet ist, wobei der Betonstützkörper (4) und die Verschlussaufnahme (3) zumindest abschnittsweise form- und stoffschlüssig miteinander verbunden sind, die Verschlussaufnahme (3) den Betonstützkörper (4) in Richtung des Verschlusselements (6) überragt, und der Betonstützkörper (4) eine sich nach unten verjüngende schachtabgewandte Seitenfläche (5) aufweist, dadurch gekennzeichnet, dass die Verschlussaufnahme (3) an der schachtabgewandten Seite (7) der Schachtabdeckungsanordnung (1) einen nach unten abgewinkelten Schenkel (8) aufweist, der den Betonstützkörper (4) an dessen schachtabgewandter Seite (7) zumindest teilweise umfasst. Manhole cover arrangement ( 1 ) for use in new road construction and rehabilitation processes, with a closure element ( 6 ) and a manhole cover frame ( 2 ), wherein the manhole cover frame ( 2 ) in two parts from a closure receptacle ( 3 ) for receiving the closure element ( 6 ) and a concrete support body ( 4 ), wherein the concrete support body ( 4 ) and the closure receptacle ( 3 ) are at least partially positively and materially connected to each other, the closure receptacle ( 3 ) the concrete support body ( 4 ) in the direction of the closure element ( 6 ) and the concrete support body ( 4 ) a downwardly tapering shaft facing away side surface ( 5 ), characterized in that the closure receptacle ( 3 ) on the side facing away from the shaft ( 7 ) of the manhole cover arrangement ( 1 ) a downwardly angled leg ( 8th ) comprising the concrete support body ( 4 ) on its side facing away from the shaft ( 7 ) at least partially. Schachtabdeckungsanordnung (1) nach Anspruch 1, dadurch gekennzeichnet, dass der Schenkel (8) L-förmig ist. Manhole cover arrangement ( 1 ) according to claim 1, characterized in that the leg ( 8th ) Is L-shaped. Schachtabdeckungsanordnung (1) nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass der Schenkel (8) in einem sich nicht verjüngenden Bereich (9) des Betonstützkörpers (4) angeordnet ist. Manhole cover arrangement ( 1 ) according to claim 1 or 2, characterized in that the leg ( 8th ) in a non-tapered area ( 9 ) of the concrete support body ( 4 ) is arranged. Schachtabdeckungsanordnung (1) nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass der Schenkel (8) eine Nut (10) aufweist. Manhole cover arrangement ( 1 ) according to one of the preceding claims, characterized in that the leg ( 8th ) a groove ( 10 ) having. Schachtabdeckungsanordnung (1) nach Anspruch 4, dadurch gekennzeichnet, dass die Nut (10) als Ringnut auf der schachtabgewandten Seitenfläche (7) der Verschlussaufnahme (3) angeordnet ist. Manhole cover arrangement ( 1 ) according to claim 4, characterized in that the groove ( 10 ) as an annular groove on the shaft side facing away from the side ( 7 ) of the closure receptacle ( 3 ) is arranged. Schachtabdeckungsanordnung (1) nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass in der Verschlussaufnahme (3) eine Vorrichtung (11) zur Aufnahme einer Einstieghilfe ausgebildet ist. Manhole cover arrangement ( 1 ) according to one of the preceding claims, characterized in that in the closure receptacle ( 3 ) a device ( 11 ) is designed to receive an entry aid. Schachtabdeckungsanordnung (1) nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass am Betonstützkörper (4) an der schachtabgewandten Seitenfläche mindestens eine Ringnut (12) angeordnet ist. Manhole cover arrangement ( 1 ) according to one of the preceding claims, characterized in that on the concrete support body ( 4 ) at the side facing away from the shaft at least one annular groove ( 12 ) is arranged. Schachtabdeckungsanordnung (1) nach Anspruch 7, dadurch gekennzeichnet, dass am Betonstützkörper (4) an der schachtabgewandten Seitenfläche drei gleichmäßig voneinander beabstandete Ringnuten (12) angeordnet sind. Manhole cover arrangement ( 1 ) according to claim 7, characterized in that on the concrete support body ( 4 ) on the lateral side facing away from the shaft three equally spaced annular grooves ( 12 ) are arranged. Schachtabdeckungsanordnung (1) nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass die sich nach unten verjüngende schachtabgewandte Seitenfläche (5) des Betonstützkörpers (4) am unteren Ende (13) des Schenkels (8) der Verschlussaufnahme (3) beginnt. Manhole cover arrangement ( 1 ) according to any one of the preceding claims, characterized in that the downwardly tapering side facing away from the shaft ( 5 ) of the concrete support body ( 4 ) at the lower end ( 13 ) of the thigh ( 8th ) of the closure receptacle ( 3 ) begins. Verfahren zum Einbau eines Schachtabdeckungsrahmens (2) gemäß einem der Ansprüche 1 bis 9 wobei – mittels eines Fräskopfes eine Einbauöffnung (26) über einem Schachtbauwerk derart freigefräst wird, dass die ausgebildete Fräskante (19) im oberen Bereich (20) korrespondierend zu der einsetzbaren Verschlussaufnahme (3) des Schachtabdeckungsrahmens (2) und im unteren Bereich (21) korrespondierend zu dem an der Verschlussaufnahme (3) angeordnetem Betonstützkörper (4) verläuft, – danach der Schachtabdeckungsrahmen (2) gemäß einem der Ansprüche 1 bis 8 über dem Schachtkopf ausgerichtet und provisorisch derart fixiert wird, dass ein zu verfüllender Ringraum (22) ausgebildet ist, – anschließend der Ringraum (22) im Anlagebereich des Betonstützkörpers (4) mit einem Vergussmörtel (18) verfüllt wird, – und abschließend der verbleibende Ringraum (22) im Bereich der Verschlussaufnahme (3) mit einem dauerhaft elastischen Kunststoffmörtel (17) für statisch und dynamisch hochbelastete Fugen verfüllt wird. Method for installing a manhole cover frame ( 2 ) according to one of claims 1 to 9 wherein - by means of a milling head an installation opening ( 26 ) is milled over a shaft structure such that the formed milling edge ( 19 ) in the upper area ( 20 ) corresponding to the insertable closure receptacle ( 3 ) of the manhole cover frame ( 2 ) and at the bottom ( 21 ) corresponding to that on the closure receptacle ( 3 ) arranged concrete support body ( 4 ), then the manhole cover frame ( 2 ) according to one of claims 1 to 8 aligned above the shaft head and provisionally fixed such that an annular space to be filled ( 22 ) is formed, - then the annulus ( 22 ) in the contact area of the concrete support body ( 4 ) with a grout ( 18 ), and finally the remaining annulus ( 22 ) in the area of the closure receptacle ( 3 ) with a permanently elastic plastic mortar ( 17 ) is filled for statically and dynamically highly loaded joints. Verfahren nach Anspruch 10, dadurch gekennzeichnet, dass der dauerhaft elastische Kunststoffmörtel (17) die Nut (10) im Schenkel (8) ausfüllt. A method according to claim 10, characterized in that the permanently elastic plastic mortar ( 17 ) the groove ( 10 ) in the thigh ( 8th ).
DE102015102803.4A 2015-02-26 2015-02-26 Manhole cover assembly and method of installation Withdrawn DE102015102803A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
DE102015102803.4A DE102015102803A1 (en) 2015-02-26 2015-02-26 Manhole cover assembly and method of installation
PL16151930T PL3064650T3 (en) 2015-02-26 2016-01-19 Shaft cover assembly and method for installing
EP16151930.1A EP3064650B1 (en) 2015-02-26 2016-01-19 Shaft cover assembly and method for installing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102015102803.4A DE102015102803A1 (en) 2015-02-26 2015-02-26 Manhole cover assembly and method of installation

Publications (1)

Publication Number Publication Date
DE102015102803A1 true DE102015102803A1 (en) 2016-09-01

Family

ID=55272224

Family Applications (1)

Application Number Title Priority Date Filing Date
DE102015102803.4A Withdrawn DE102015102803A1 (en) 2015-02-26 2015-02-26 Manhole cover assembly and method of installation

Country Status (3)

Country Link
EP (1) EP3064650B1 (en)
DE (1) DE102015102803A1 (en)
PL (1) PL3064650T3 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685203B (en) * 2019-09-19 2021-04-20 杭州南岳建设工程有限公司 Method for ensuring compactness of periphery of gully of inspection well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3400875A1 (en) * 1984-01-12 1985-07-18 Stanislaus Dipl.-Ing. 7340 Geislingen Malik Manhole cover
DE202008003124U1 (en) * 2008-03-05 2008-06-05 Heinrich Meier Eisengiesserei Gmbh & Co. Kg Frame of a manhole cover
DE102006056936A1 (en) 2006-11-30 2008-06-05 Buderus Kanalguss Gmbh Manhole covering mounting method, involves filling annular space between reinforcing elements and manhole covering frame with binding filling material, where elements are connected with frame in sections in force and/or form-fit manner
DE102013000709A1 (en) * 2012-01-20 2013-07-25 Schachtguss-Ht Gmbh Manhole frame and manhole cover with a replaceable receptacle for attaching an entry aid and system of manhole frame and boarding aid

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4031778C1 (en) * 1990-10-07 1991-10-17 Eci - European Chemical Industries Ltd., Monaghan, Ie Anti-pollution covering for soil - has stretchable supporting layer with fluid covering layer above it
DE29709676U1 (en) * 1997-06-04 1997-07-24 Postelt, Peter, 58710 Menden Manhole or street gully with manhole cover

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3400875A1 (en) * 1984-01-12 1985-07-18 Stanislaus Dipl.-Ing. 7340 Geislingen Malik Manhole cover
DE102006056936A1 (en) 2006-11-30 2008-06-05 Buderus Kanalguss Gmbh Manhole covering mounting method, involves filling annular space between reinforcing elements and manhole covering frame with binding filling material, where elements are connected with frame in sections in force and/or form-fit manner
DE202008003124U1 (en) * 2008-03-05 2008-06-05 Heinrich Meier Eisengiesserei Gmbh & Co. Kg Frame of a manhole cover
DE102013000709A1 (en) * 2012-01-20 2013-07-25 Schachtguss-Ht Gmbh Manhole frame and manhole cover with a replaceable receptacle for attaching an entry aid and system of manhole frame and boarding aid

Also Published As

Publication number Publication date
PL3064650T3 (en) 2018-05-30
EP3064650B1 (en) 2017-12-13
EP3064650A1 (en) 2016-09-07

Similar Documents

Publication Publication Date Title
EP0311884A2 (en) Manhole cover
EP3064650B1 (en) Shaft cover assembly and method for installing
DE69826650T2 (en) HYDROPHILIC SEAL FOR SLOTTED WALLS
DE102011001082A1 (en) Device for height compensation of manhole coverings, particularly for new construction and cleansing of manhole coverings, has pressure distribution plate, which has lead-through encased by annular bead
DE202020004474U1 (en) Light shaft with facility for assembly
EP2108739B1 (en) Road construction system for sealing joints
EP0003720B1 (en) Method of making a crack-proof, impervious joint between an asphaltic surfacing and part of a structure, set of shaped elements for carrying out the method and structure built according to the method
DE202005020089U1 (en) End section for e.g. balcony has opening on upper part of cover side, and into which edge of coating material is inserted
DE102019133026A1 (en) Attachment system, road drain, adapter element and method
AT520609B1 (en) Drainage device for draining a subsoil
EP4261357A1 (en) Device for a drain device arranged in the floor of a room and method for mounting the drain device
DE102005009727A1 (en) Method for sealing sewer inspection covers by applying a setting compound onto the lipped support to form a custom made seal
DE2703583A1 (en) Drain built flush into road or runway surface - has U=section gutter piece and cover plate joined together by adhesive layers or anchors
DE102006056146B4 (en) Cleaning pipe for installation in a pipeline under a base plate
DE29608961U1 (en) Day waterproof manhole cover
DE202015001561U1 (en) Sump pit
DE9117082U1 (en) Concrete tub
DE102015006095A1 (en) bathtub
DE19962392A1 (en) Filling method to plug wall holes/cracks uses an attachment fitted to the wall to form a pouring gutter to direct the filling material into the hole/crack with removal of the surplus when the attachment is dismantled
DE2031652A1 (en) Device for connecting a plate-shaped component to another component
DE202013004936U1 (en) Channel for transporting liquids and component for producing such a channel
DE102011018844A1 (en) Drainage channel for drainage of large areas, such as parking places, airport runways, roads, sidewalks, for guiding surface water of waste water treatment plant, has drainage surface provided with drainage recesses and two side walls
DE202019100789U1 (en) Sealing device for arrangement in a soffit of a building exterior wall below a floor-deep window or door
EP2133470A1 (en) Drainage element
DE102010017472A1 (en) Method of potting a manhole cover, potting compound and use of the potting compound in a method for potting a manhole cover

Legal Events

Date Code Title Description
R012 Request for examination validly filed
R016 Response to examination communication
R119 Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee