DE102011014614A1 - scaffolding and procedures for creating a scaffolding - Google Patents
scaffolding and procedures for creating a scaffolding Download PDFInfo
- Publication number
- DE102011014614A1 DE102011014614A1 DE102011014614A DE102011014614A DE102011014614A1 DE 102011014614 A1 DE102011014614 A1 DE 102011014614A1 DE 102011014614 A DE102011014614 A DE 102011014614A DE 102011014614 A DE102011014614 A DE 102011014614A DE 102011014614 A1 DE102011014614 A1 DE 102011014614A1
- Authority
- DE
- Germany
- Prior art keywords
- scaffolding
- tubes
- vertical frame
- guide element
- fall protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/14—Railings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/14—Railings
- E04G5/144—Railings specific for the lateral, i.e. short side of a scaffold
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mutual Connection Of Rods And Tubes (AREA)
- Ladders (AREA)
Abstract
Die Erfindung betrifft ein Baugerüst, das mindestens zwei Vertikalrahmen (1) umfasst. Jeder Vertikalrahmen (1) besteht aus mindestens zwei Rohren (2, 3), die durch mindestens eine Traverse (4) miteinander verbunden sind und die im mittleren Drittel der Länge der Rohre (2, 3) angeordnet ist. Der Vertikalrahmen (1) weist mindestens eine Befestigungseinrichtung (5) auf. Es ist eine Querstrebe (7) vorgesehen, die entlang der Rohre (2, 3) verschiebbar ist. Die Erfindung betrifft weiterhin ein Verfahren zur Erstellung eines Baugerüstes, bei dem in der obersten Gerüstebene die die Absturzsicherung bildenden Stangen (6) über die im Bereich der freien Enden der Rohre (2, 3) angeordnete Querstrebe (7) hinweg an den Befestigungseinrichtungen (5) der benachbarten Vertikalrahmen (1) eingehängt werden. Nach dem Einhängen der Stangen (6) wird die Querstrebe (7) entlang der Rohre (2, 3) in Richtung der Belagbohlen (8) verschoben.The invention relates to a scaffolding comprising at least two vertical frames (1). Each vertical frame (1) consists of at least two tubes (2, 3) which are connected to each other by at least one cross member (4) and which is arranged in the middle third of the length of the tubes (2, 3). The vertical frame (1) has at least one fastening device (5). A cross strut (7) is provided which can be moved along the tubes (2, 3). The invention further relates to a method for the construction of a scaffolding, in which the rods (6) forming the fall protection in the uppermost scaffolding level over the cross strut (7) arranged in the region of the free ends of the tubes (2, 3) on the fastening devices (5 ) of the adjacent vertical frame (1). After the rods (6) have been hung in, the cross strut (7) is displaced along the tubes (2, 3) in the direction of the facing planks (8).
Description
Die Erfindung betrifft ein Baugerüst, umfassend mindestens zwei Vertikalrahmen, wobei jeder Vertikalrahmen aus mindestens zwei Rohren besteht, die durch mindestens eine Traverse miteinander verbunden sind, welche im mittleren Drittel der Länge der Rohre angeordnet ist, und der mindestens eine Befestigungseinrichtung für eine eine Absturzsicherung bildende Stange aufweist. Die Erfindung betrifft außerdem ein Verfahren zur Erstellung eines Baugerüstes.The invention relates to a scaffolding, comprising at least two vertical frames, wherein each vertical frame consists of at least two tubes which are interconnected by at least one cross member, which is arranged in the middle third of the length of the tubes, and the at least one fastening device for a fall protection forming Rod has. The invention also relates to a method for creating a scaffolding.
Baugerüste der eingangs genannten Art sind an sich bekannt. Sie finden Anwendung, um an der Fassade von Bauwerken Arbeiten vornehmen zu können. Die Baugerüste weisen dabei in Abhängigkeit von der Höhe des Gebäudes beziehungsweise des Baugerüstes mehrere übereinander liegende Ebenen auf.Scaffolding of the type mentioned are known per se. They are used to make work on the facade of buildings. The scaffolds have, depending on the height of the building or the scaffolding on several superposed planes.
Bei der Erstellung der Baugerüste werden zunächst zwischen zwei benachbarten Vertikalrahmen Belagbohlen an den Traversen befestigt. Durch Aneinanderreihung mehrerer Vertikalrahmen mit dazwischen liegenden Belagbohlen sind die Baugerüste in der Länge variabel erstellbar. Bei der Erstellung der jeweils darüber liegenden Ebene wird ein Vertikalrahmen auf den darunter liegenden Vertikalrahmen aufgesetzt. Sodann werden von der unteren Ebene Belagbohlen an den Traversen des darüber angeordneten Vertikalrahmens befestigt, wodurch die darüber liegende Ebene begehbar ist. Es besteht jedoch in der darüber liegenden Ebene zu diesem Zeitpunkt noch keine Absturzsicherung. Die Absturzsicherung ist bei den Baugerüsten von Stangen gebildet, die zwischen benachbarten Vertikalrahmen an den Rohren des Rahmens vorgesehenen Befestigungseinrichtungen eingehängt sind.In the construction of the scaffolds first planks are attached to the trusses between two adjacent vertical frame. By juxtaposing several vertical frames with planks lying therebetween, the scaffolding can be variably set in length. When creating the level above, a vertical frame is placed on the underlying vertical frame. Then, from the lower level planks are attached to the trusses of the above vertical frame, whereby the overlying level is accessible. However, there is still no fall protection in the higher level at this time. The fall protection is formed in the scaffolding of rods which are suspended between adjacent vertical frame provided on the tubes of the frame fasteners.
Durch die Erstellung der oberen Ebene ohne Absturzsicherung ist die Unfallgefahr bei den bekannten Baugerüsten erhöht. Die Berufsgenossenschaften fordern daher, dass ein Begehen der Belagbohlen nur erfolgen darf, wenn bereits ein Geländer montiert ist. Zur Erfüllung dieser Bedingung ist aus der
Der bekannte Vertikalrahmen erfüllt die an ihn gestellten Bedingungen. Allerdings ist der Vertikalrahmen nicht in der Lage zu verhindern, dass der Gerüstbauer die Belagbohle eines noch nicht mit einer Absturzsicherung versehenen Abschnitts betritt. Somit ist zwar theoretisch durch den bekannten Vertikalrahmen die Möglichkeit geschaffen, die Absturzsicherung aus einer gesicherten Position heraus zu installieren und erst im Anschluss daran den jeweiligen Abschnitt zu betreten; in der Praxis lässt es sich jedoch aufgrund der Barrierefreiheit mit dem bekannten Vertikalrahmen nicht verhindern, dass die Belagbohlen in einem ungesicherten Bereich betreten werden.The well-known vertical frame meets the conditions imposed on him. However, the vertical frame is unable to prevent the scaffolder from entering the plank of a section not yet provided with a fall arrest device. Thus, although theoretically created by the known vertical frame, the possibility to install the fall protection from a secure position out and only then to enter the respective section; in practice, however, due to the accessibility with the known vertical frame, it can not be prevented that the decking planks are entered in an unsecured area.
Hier will die Erfindung Abhilfe schaffen. Der Erfindung liegt die Aufgabe zugrunde, ein Baugerüst zu schaffen, bei dem während des Auf- beziehungsweise Abbaus des Gerüstes die Unfallgefahr reduziert ist. Gemäß der Erfindung wird diese Aufgabe dadurch gelöst, dass eine Querstrebe vorgesehen ist, die entlang der Rohre verschiebbar ist.The invention aims to remedy this situation. The invention has for its object to provide a scaffolding, in which during the construction or dismantling of the scaffold, the risk of accidents is reduced. According to the invention, this object is achieved in that a transverse strut is provided, which is displaceable along the tubes.
Mit der Erfindung ist ein Baugerüst geschaffen, welches die Unfallgefahr beim Auf- beziehungsweise Abbau reduziert. Dies ist dadurch gewährleistet, dass durch die entlang der Rohre verschiebbare Querstrebe während des Aufbauens eine Barriere zum Begehen des benachbarten Abschnitts des Baugerüstes gebildet ist. Dadurch ist der Gerüstbauer beim Erstellen des Gerüstes unmittelbar daran gehindert, den Bereich des Baugerüstes zu betreten, in dem noch keine Absturzsicherungen montiert sind. Vielmehr ist es bei dem erfindungsgemäßen Baugerüst möglich, aus der gesicherten Position heraus die Absturzsicherung an den Befestigungsvorrichtungen anzubringen und im Anschluss daran die Barriere entlang der Rohre in den Bodenbereich zu verschieben, sodass der dann ebenfalls gesicherte Bereich begehbar ist.With the invention, a scaffolding is created, which reduces the risk of accidents during construction or dismantling. This is ensured by the fact that is formed by the slidable along the tubes crossbar during construction, a barrier for committing the adjacent portion of the scaffolding. As a result, the scaffolder is prevented immediately when creating the scaffolding, to enter the area of the scaffolding, in which no fall arresters are mounted. Rather, with the scaffolding according to the invention, it is possible to attach the fall protection to the fastening devices from the secured position and subsequently to move the barrier along the tubes into the floor area, so that the area which is likewise secured can be walked on.
Um das erfindungsgemäße Gerüst zu demontieren ist es zwingend erforderlich, die Querstrebe aus dem Bodenbereich, in der sie zusätzlich die Funktion als Belagsicherung inne hat, zu lösen und stattdessen in die Position als Durchlaufbarriere, in der sie zusätzlich die Funktion als Transportsicherung einnimmt, zu verschieben. Erst dann ist es möglich, die Belagbohlen zu demontieren und somit das ganze Gerüst abzubauen. Dadurch bedingt, dass sich die Querstrebe in der Position als Transportsicherung befindet, können die Vertikalrahmen transportgerecht gestapelt, gebündelt und verladen werden. Dies wiederum hat zur Folge, dass sich bei der nächsten Montage des Gerüstes, die Querstrebe unmittelbar in der Position befindet, in der sie als Durchlaufbarriere für die Gerüstbauer fungiert. Der Gerüstbauer wird durch die Querstrebe daran gehindert, in den noch ungesicherten Bereich zu laufen. Erst wenn er aus gesicherter Position den Seitenschutz montiert hat, öffnet er die Querstrebe und verschiebt sie in Richtung der Belagbohlen, in der sie als Belagsicherung fungiert. Erst danach ist der Durchgang in das bereits gesicherte nächste Gerüstfeld frei. Diese Zwangs-Montagefolge erhöht die Sicherheit im Gerüstbau.In order to disassemble the scaffold according to the invention, it is absolutely necessary to disengage the cross strut from the floor area in which it additionally has the function of covering protection and instead to move it into the position as a passage barrier in which it additionally assumes the function of securing the transport , Only then it is possible to disassemble the planks and thus reduce the entire scaffold. Due to the fact that the cross strut is in the position as a transport lock, the vertical frame can be stacked suitable for transport, bundled and loaded. This in turn means that at the next assembly of the scaffold, the cross strut is directly in the position in which it acts as a passage barrier for the scaffolders. The scaffolder is prevented by the cross strut from running into the still unsecured area. Only when he has mounted the side guard from a secured position, he opens the crossbar and moves it in the direction of the planks, in which it acts as a covering protection. Only then is the passage into the already secured next scaffolding field free. This forced installation sequence increases safety in scaffolding.
In Ausgestaltung der Erfindung weist die Querstrebe an ihren Enden Führungselemente auf, die die Rohre mindestens bereichsweise umgreifen. Mit Hilfe der Führungselemente ist eine zuverlässige Anbringung der Querstrebe an den Vertikalrahmen möglich. Das mindestens bereichsweise Umgreifen der Rohre durch die Führungselemente ermöglicht zudem im Bedarfsfall eine Demontage der Querstrebe.In an embodiment of the invention, the cross member at its ends on guide elements, which surround the tubes at least partially. With the help of the guide elements a reliable attachment of the cross member to the vertical frame is possible. The at least partially encompassing the tubes by the guide elements also allows, if necessary, a disassembly of the crossbar.
Vorteilhaft ist im Bereich des Führungselementes ein federbelastetes Sicherungselement vorgesehen. Die Verwendung eines federbelasteten Sicherungselementes ermöglicht zwar eine Demontage der Querstrebe, soweit dies gewünscht ist. Sie verhindert jedoch zuverlässig die unbeabsichtigte Entfernung des Führungselementes von dem jeweiligen Rohr des Vertikalrahmens.Advantageously, a spring-loaded securing element is provided in the region of the guide element. Although the use of a spring-loaded securing element allows disassembly of the crossbar, if desired. However, it reliably prevents inadvertent removal of the guide member from the respective tube of the vertical frame.
In Weiterbildung der Erfindung ist das Führungselement als geschlossener Haltebügel ausgebildet. Das Vorsehen eines geschlossenen Haltebügels verhindert, dass bei der Betätigung der Querstrebe diese nicht unbeabsichtigt vollständig von dem Vertikalrahmen lösbar ist. Auf diese Weise ist ein Herabfallen der Querstrebe bei ihrer Betätigung verhindert, wodurch die Unfallgefahr zusätzlich reduziert ist.In a further development of the invention, the guide element is designed as a closed headband. The provision of a closed retaining clip prevents that upon actuation of the crossbar this is not inadvertently completely detached from the vertical frame. In this way, a drop of the cross member is prevented during their operation, whereby the risk of accidents is additionally reduced.
Bevorzugt sind an den Rohren Einhängenocken angeordnet. Die Einhängenocken dienen zum Arretieren der Querstrebe in den verschieden Positionen. Sie gewährleisten zudem eine positionsgenaue und zuverlässige Anordnung der Querstrebe in den einzelnen während der Montage beziehungsweise Demontage des Gerüsts oder dem Transport und Lagerung der Rahmen.Preferably, hook-in cams are arranged on the tubes. The suspension cams serve to lock the crossbar in different positions. They also ensure a positionally accurate and reliable arrangement of the cross member in the individual during assembly or disassembly of the framework or the transport and storage of the frame.
Die Aufgabe wird darüber hinaus durch ein Verfahren zur Erstellung eines Baugerüstes gelöst, bei dem in der obersten Gerüstebene die die Absturzsicherung bildenden Stangen über die im Bereich der freien Enden der Rohre angeordnete Querstrebe hinweg an den Befestigungseinrichtungen der benachbarten Vertikalrahmen eingehängt werden und nach dem Einhängen der Stangen die Querstrebe entlang der Rohre in Richtung der Belagbohlen verschoben wird.The object is also achieved by a method for creating a scaffolding, in which in the uppermost scaffold level, the fall protection rods forming are mounted on the fastening means of the adjacent vertical frame over the arranged in the free ends of the tubes cross strut and after hanging the Rods, the crossbar along the tubes in the direction of the planks is moved.
Andere Weiterbildungen und Ausgestaltungen der Erfindung sind in den übrigen Unteransprüchen angegeben. Ein Ausführungsbeispiel der Erfindung ist in der Zeichnung dargestellt und wird nachfolgend im Einzelnen beschrieben. Es zeigen:Other developments and refinements of the invention are specified in the remaining subclaims. An embodiment of the invention is illustrated in the drawing and will be described in detail below. Show it:
Das als Ausführungsbeispiel gewählte Baugerüst umfasst eine Vielzahl von Vertikalrahmen
An den bodenseitigen Enden der Rohre
Die Traverse
Die Befestigungseinrichtung
Die Befestigungseinrichtung
Im Ausführungsbeispiel ist an jedem Vertikalrahmen
Bei dem Sicherungselement
Das Führungselement
Wie in
Bei der Erstellung eines Baugerüstes werden zunächst zwischen zwei benachbarten Vertikalrahmen
Die jeweils oberste Ebene ist zwischen den jeweiligen Vertikalrahmen nach Einhängen der Belagbohlen noch nicht mit einer Absturzsicherung versehen. Da das Anbringen der Absturzsicherung aus einer gesicherten Position heraus erfolgen muss, werden die die Absturzsicherung bildenden Stangen
Zur weiteren Erstellung der Absturzsicherung an dem Baugerüst ist die Anbringung der Stangen
Die Montage der Stangen
Bei der Demontage des erfindungsgemäßen Baugerüstes erfolgt die vorstehend beschriebene Vorgehensweise in umgekehrter Reihenfolge. Zur Demontage der jeweiligen Absturzsicherung wird die Querstrebe
Mit der Erfindung ist ein Baugerüst geschaffen, welches die Sicherheit beim Auf- und Abbau der Baugerüste wesentlich erhöht. Die Querstrebe
ZITATE ENTHALTEN IN DER BESCHREIBUNG QUOTES INCLUDE IN THE DESCRIPTION
Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list of the documents listed by the applicant has been generated automatically and is included solely for the better information of the reader. The list is not part of the German patent or utility model application. The DPMA assumes no liability for any errors or omissions.
Zitierte PatentliteraturCited patent literature
- DE 102008005813 A1 [0004] DE 102008005813 A1 [0004]
Claims (7)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102011014614.8A DE102011014614B4 (en) | 2011-03-21 | 2011-03-21 | Scaffolding and procedures for creating a scaffolding |
EP12160591A EP2503075A1 (en) | 2011-03-21 | 2012-03-21 | Construction scaffold and method to erect a construction scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102011014614.8A DE102011014614B4 (en) | 2011-03-21 | 2011-03-21 | Scaffolding and procedures for creating a scaffolding |
Publications (2)
Publication Number | Publication Date |
---|---|
DE102011014614A1 true DE102011014614A1 (en) | 2012-09-27 |
DE102011014614B4 DE102011014614B4 (en) | 2014-12-24 |
Family
ID=45939141
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE102011014614.8A Active DE102011014614B4 (en) | 2011-03-21 | 2011-03-21 | Scaffolding and procedures for creating a scaffolding |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP2503075A1 (en) |
DE (1) | DE102011014614B4 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102014224002A1 (en) | 2014-11-25 | 2016-05-25 | Peri Gmbh | Railing rail and scaffolding with a railing rail |
WO2019057957A1 (en) | 2017-09-25 | 2019-03-28 | Peri Gmbh | Pole-shaped scaffolding element, scaffolding part having a scaffolding element of this kind and method for mounting a scaffolding element of this kind |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102018114244A1 (en) | 2018-06-14 | 2019-12-19 | Wilhelm Layher Verwaltungs-Gmbh | Single scaffold arm |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD123540A1 (en) * | 1975-12-18 | 1977-01-05 | ||
ATE7723T1 (en) * | 1980-12-04 | 1984-06-15 | Cenclark B.V. | RAILING FOR SCAFFOLDING. |
US6976557B2 (en) * | 2004-02-27 | 2005-12-20 | Aluma Enterprises Inc. | Toeboard system for scaffolding |
GB2432874A (en) * | 2005-12-03 | 2007-06-06 | Znd Uk Ltd | Handrail support |
DE102008005813A1 (en) | 2008-01-24 | 2009-08-27 | Rux Gmbh | Vertical frame, particularly for pipe rack, has two supports, which are connected with each other by cross beam and fastening unit, where cross beam is arranged in middle third of length of pipes |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT7723B (en) | 1901-04-04 | 1902-05-26 | Jagd Und Fischereischutz Ver F | |
DE3642846A1 (en) * | 1986-12-16 | 1988-07-07 | Aluminium Walzwerke Singen | FRAME ELEMENT |
DE19633092A1 (en) * | 1996-08-16 | 1998-02-19 | Peri Gmbh | Removable facade scaffolding |
FR2922238A1 (en) * | 2007-10-12 | 2009-04-17 | Herve Remy | Modular collective protection element i.e. multi-level ladder, for use during e.g. renovation of edifice, has horizontal bars integrated to vertical tubes, and plates supported on horizontal bars based on work to be realized |
BE1018056A5 (en) * | 2008-03-20 | 2010-04-06 | Vcs Man Consult Bvba | DEVICE AND METHOD FOR THE SAFE CONSTRUCTION AND DEMOLITION OF A SCAFFOLDING. |
DE202009002249U1 (en) * | 2009-02-17 | 2009-06-18 | Moser, Reinhold | feed handrails |
-
2011
- 2011-03-21 DE DE102011014614.8A patent/DE102011014614B4/en active Active
-
2012
- 2012-03-21 EP EP12160591A patent/EP2503075A1/en not_active Withdrawn
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD123540A1 (en) * | 1975-12-18 | 1977-01-05 | ||
ATE7723T1 (en) * | 1980-12-04 | 1984-06-15 | Cenclark B.V. | RAILING FOR SCAFFOLDING. |
US6976557B2 (en) * | 2004-02-27 | 2005-12-20 | Aluma Enterprises Inc. | Toeboard system for scaffolding |
GB2432874A (en) * | 2005-12-03 | 2007-06-06 | Znd Uk Ltd | Handrail support |
DE102008005813A1 (en) | 2008-01-24 | 2009-08-27 | Rux Gmbh | Vertical frame, particularly for pipe rack, has two supports, which are connected with each other by cross beam and fastening unit, where cross beam is arranged in middle third of length of pipes |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102014224002A1 (en) | 2014-11-25 | 2016-05-25 | Peri Gmbh | Railing rail and scaffolding with a railing rail |
WO2016083215A1 (en) | 2014-11-25 | 2016-06-02 | Peri Gmbh | Railing bar and scaffolding having a railing bar |
WO2019057957A1 (en) | 2017-09-25 | 2019-03-28 | Peri Gmbh | Pole-shaped scaffolding element, scaffolding part having a scaffolding element of this kind and method for mounting a scaffolding element of this kind |
DE102017216889A1 (en) | 2017-09-25 | 2019-03-28 | Peri Gmbh | Bar-shaped scaffolding element, scaffolding part with such a scaffolding element and method for mounting such a scaffolding element |
Also Published As
Publication number | Publication date |
---|---|
EP2503075A1 (en) | 2012-09-26 |
DE102011014614B4 (en) | 2014-12-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1571275B1 (en) | Device for the assembling of a temporary railing of a scaffold | |
EP3896240A1 (en) | Scaffolding | |
WO2002103136A2 (en) | Dismountable scaffolding | |
EP3679206A1 (en) | Anti-fall safeguard with supporting base | |
DE202022105308U1 (en) | Device for preventing people from falling | |
EP1338723A2 (en) | Mounting device for a temporary scaffolding safety rail | |
DE102011014614B4 (en) | Scaffolding and procedures for creating a scaffolding | |
DE3108020C2 (en) | ||
DE4027754C2 (en) | Support training for scaffolding floors or the like with at least one recess in the accessible area | |
DE102008005814B4 (en) | stand column | |
EP2557252B1 (en) | Work platform and method for securely setting up a support frame tower | |
DE102008005813B4 (en) | vertical frame | |
DE102019204713A1 (en) | Formwork system for the production of concrete walls | |
DE202022104065U1 (en) | stair stringer | |
DE202020103951U1 (en) | Safety railing | |
DE102009024857A1 (en) | Stair stringer for stair towers utilized as e.g. emergency stairs during renovation work on public buildings, has retainers arranged in step form, and supporting units, which are independent of height of points and distance of supports | |
DE202008001019U1 (en) | Device for arranging struts on scaffolding uprights | |
DE10128039B4 (en) | Railing rail for scaffold railing | |
DE102015101788B4 (en) | Security system for building construction and its use | |
DE202021102273U1 (en) | Attachment device for the frame of a scaffolding | |
DE202020103145U1 (en) | Console for mounting on the frame of a scaffolding | |
DE3616838A1 (en) | DEVICE FOR APPLYING RAILING BOARDS OD. DGL. | |
DE202022105807U1 (en) | stair stringer | |
DE202023105830U1 (en) | Device for attaching fall protection to scaffolding | |
DE202023100314U1 (en) | scaffolding |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R012 | Request for examination validly filed | ||
R016 | Response to examination communication | ||
R016 | Response to examination communication | ||
R018 | Grant decision by examination section/examining division | ||
R020 | Patent grant now final | ||
R081 | Change of applicant/patentee |
Owner name: SCAFOM-RUX GMBH, DE Free format text: FORMER OWNER: RUX GMBH, 58135 HAGEN, DE |