DE102009008627A1 - Securing method for sloped and inclined buildings - Google Patents
Securing method for sloped and inclined buildings Download PDFInfo
- Publication number
- DE102009008627A1 DE102009008627A1 DE200910008627 DE102009008627A DE102009008627A1 DE 102009008627 A1 DE102009008627 A1 DE 102009008627A1 DE 200910008627 DE200910008627 DE 200910008627 DE 102009008627 A DE102009008627 A DE 102009008627A DE 102009008627 A1 DE102009008627 A1 DE 102009008627A1
- Authority
- DE
- Germany
- Prior art keywords
- anchor
- mat
- anchors
- delay
- procedure according
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/006—Lining anchored in the rock
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0086—Bearing plates
Abstract
Ein besonders wirtschaftliches und zugleich eine hahren für söhlige und geneigte Baue im untertägigen Berg- und Tunnelbau sieht vor, dass ein oder mehrere Anker aus dem bereits ausgebauten und gesicherten Streckenbereich heraus mit Hilfe einer vorkragenden Lafette in einem festgelegten Arbeitsgang und Schema abgebohrt, eingebracht und gesetzt werden, ohne dass weitere Manipulationen notwendig sind. Anschließend werden reihen- oder abschlagweise die Ankerköpfe aus dem mit Ankern vollständig gesicherten Bereich mit einem flexiblen Verzug versehen und mit Hilfselementen dort fixiert, sodass er bereits dicht am Gebirge anliegt und das Herabfallen kleinerer Gesteinsbrocken unterbindet. Erst im Anschluss daran werden die Verzughalte- oder Kalottenplatten aufgebracht und mit Befestigungs- und Spannelementen versehen.A particularly economical and at the same time a driving force for sloped and inclined construction in underground mining and tunneling provides that one or more anchors are drilled, inserted and set from the already developed and secured track area with the aid of a cantilevered carriage in a defined operation and scheme without further manipulation. Then the rows of anchor heads from the area completely secured with anchors are provided with a flexible delay and fixed there with auxiliary elements, so that it already rests close to the mountains and prevents the falling of smaller rocks. Only then are the distortion retaining or dome plates applied and provided with fastening and clamping elements.
Description
Die Erfindung betrifft ein Sicherungsverfahren für söhlige und geneigte Baue im untertägigen Berg- und Tunnelbau, bei dem nach dem Lösen des Gesteins die Streckenstöße und die Streckenfirste durch Einbringen von Gebirgsankern und eines Verzuges gesichert werden.The The invention relates to a safety method for sloped and inclined structures in the underground mining and tunneling, in which after the release of the rock the track joints and the Distances by introducing rock anchors and a delay be secured.
Die so genannte Ankertechnik umfasst alle Arbeitsteilvorgänge und maschinellen Einrichtungen für das Bohren und das Einbringen von Gebirgsankern. Sowohl in reinen Ankerstrecken wie auch in Strecken mit Kombiausbau aus Ankern und später eingebautem Unterstützungsausbau mit oder ohne Baustoffhinterfüllung werden bisher nicht durchgängig Ankerbohr- und Setzgeräte eingesetzt, die es ermöglichen, den Ankerausbau aus dem gesicherten Bereich einzubringen. Deshalb versucht man durch Vorpfänden von Verzugselementen aus Stahlblech oder Stahlmatten wenigstens einen vorläufigen Schutz zu ermöglichen. Diese Verfahrensweise erfordert aber eine erhebliche Aufenthaltszeit in einem zu diesem Zeitpunkt noch nicht ausgebauten Bereich, ist zeitraubend, leistungshemmend und behindert den Einsatz mechanisierter bzw. automatisierter Anker-, Bohr- und Setztechnologien erheblich.The so-called anchor technology includes all working sub-operations and mechanical facilities for the drilling and the introduction of mountain anchors. Both in pure Anchoring distances as well as in lines with combined expansion of anchors and later built-in support expansion with or without building material backfilling are not yet consistent Anchor drilling and setting tools used, which make it possible to bring in the armature removal from the secured area. Therefore you try by Vorpfänden of distortion elements of sheet steel or steel mats at least a temporary protection to enable. However, this procedure requires a significant residence time in an area not yet developed at this time, is Time-consuming, performance-inhibiting and hinders the use of mechanized or automated anchor, drilling and placement technologies significantly.
Der Erfindung liegt daher die Aufgabe zu Grunde, das Sicherungsverfahren für Ankerstrecken so vorzugeben, dass jegliche Arbeiten im unausgebauten Streckenabschnitt entfallen.Of the The invention is therefore based on the object of the safety method for anchor lines like that pretend that any work is in the undeveloped stretch of track omitted.
Die Aufgabe wird gemäß der Erfindung dadurch gelöst, dass die Anker reihen- oder abschlagsweise nach vorgegebenem Schema aus dem bereits ausgebauten und gesicherten Streckenbereich mit Hilfe einer vorkragenden Lafette ankerweise gebohrt und sofort mit einem Anker versehen und gesichert werden, worauf in dem dann ausgebauten Bereich auf die Ankerköpfe eine annähernd flexible Verzugmatte in Bahnen angepasster Form aufgeschoben und mit Hilfselementen fixiert wird und dass erst im Nachhinein die Kalotten- oder Verzughalteplatten aufgebracht sowie mit Befestigungs- und Spannelementen versehen werden.The Task is according to the invention solved by that the anchors in rows or abruptly according to a predetermined scheme from the already developed and secured route area with help a cantilever mounted gun anchorage and immediately with a Anchor be provided and secured, whereupon in the then developed Area on the anchor heads an approximate flexible delay mat pushed into tracks adapted form and is fixed with auxiliary elements and that only afterwards the Dome or arresting holding plates are applied as well as with fastening and clamping elements are provided.
Mit Hilfe eines derartigen Verfahrens werden die Arbeitsschritte Ankerloch bohren und Anker einbringen und setzen untrennbar miteinander verbunden. Es ermöglicht je nach eingesetzter Ankerbohr- und Setztechnik das Setzen eines oder mehrerer Anker nacheinander ohne Manipulationen im Gefahrenbereich der Maschine und des freigelegten, unausgebauten Gebirges. Ist dann die vollständige Ankerreihe fertig gesetzt oder der gesamte freigelegte Gebirgsabschnitt mit Ankern ausgebaut, wird nachträglich der Verzug in Form der flexiblen Verzugmatten im Schutz des Ankerausbaus vorgenommen. Dabei wird die Verzugmatte auf den Anker bzw. auf den Ankerkopf aufgeschoben und über ein einfaches Hilfselement zunächst fixiert und erst nach Fertigstellung des Verzuges mit Verzughalte- oder Kalottenplatten und Befestigungs- und Verspannelementen versehen. Die Hilfselemente bleiben unter den Kalottenplatten, brauchen also nicht gesondert entfernt und entsorgt zu werden, sondern bleiben Teil des kompletten Ankers. Mit diesem Verfahren ist es möglich, die Anker vollständig mechanisiert einzubringen, wobei die Arbeitsschritte im Einzelnen einfach aufeinander abzustimmen und insgesamt zu verkürzen sind, sodass die entsprechende Ausbauarbeit aufgrund des geringeren Zeitaufwandes preiswerter wird, ganz davon abgesehen, dass eben diese Arbeiten jeweils aus dem bereits abgesicherten Arbeitsbereich heraus vorgenommen werden können, sodass die Unfallgefahr entscheidend verringert ist.With Help of such a method become the steps anchor hole drill and anchor and put inseparable. Allows depending on the anchor drilling and setting technique used, setting a or several anchors one after the other without manipulation in the danger zone the machine and the exposed, undeveloped mountains. Is then the complete Anchor row finished or the entire exposed mountain section expanded with anchors, the delay in the form of flexible delay mats in the protection of the anchor construction made. there The delay mat is pushed onto the anchor or on the anchor head and over a simple auxiliary element first fixed and only after completion of the delay with delay hold- or dome plates and fastening and Verspannelementen provided. The Auxiliary elements remain under the dome plates, so do not need separately removed and disposed of, but remain part of the complete anchor. With this method it is possible to use the Anchor complete Mechanized to bring in, with the work steps in detail just to match and shorten in total, so that the corresponding expansion work due to the lower time required cheaper is, quite apart from that just these works each made from the already secured work area out can be so that the risk of accidents is significantly reduced.
Nach einer zweckmäßigen Ausführungsform ist vorgesehen, dass das Ankerschema ins Profil mit Hilfe bekannter Projektionsverfahren wie z. B. Licht- oder Laserpunkte auf das Gebirge projiziert und an diesen Punkten dann die Bohrlöcher und Anker platziert werden. Dadurch ist genau und einfach vorzugeben, wo die entsprechenden Anker später die Gebirgsschichten halten sollen.To an expedient embodiment provided that the anchor scheme into the profile using known Projection methods such. B. light or laser points on the mountains projected and then placed at these points the holes and anchors. This makes it easy to specify where the appropriate Anchor later should hold the mountain layers.
Es kann vorgesehen werden, dass das Ankerschema bei IPC-gesteuerten Maschinen rechnergeschützt programmiert wird und die einzelnen Positionen automatisch angefahren und die Bohrlöcher abgebohrt werden.It can be provided that the anchor scheme in IPC controlled Machines computer-protected is programmed and the individual positions approached automatically and the drilled holes drilled become.
Eine weitere zweckmäßige Ausführungsform sieht vor, dass die Ankerlöcher mit Hilfe der vorkragenden Bohrlafette aus dem bereits ausgebauten Streckenbereich heraus ins Gebirge gestoßen werden und dass dann ein Anker eingeschoben und als Anker mit integrierter Klebesäule darin voll- oder teilverklebt wird, wobei es sich hierbei um in zwei Schritten setzbare Anker, wie Reibrohranker, Spreizhülsenanker u. Ä. oder um Einschrittanker handelt. Nach diesem Verfahren erfolgt das Bohren und das Setzen der Anker in zwei Arbeitsschritten. Es ist aber auch möglich mit einer kombinierten Bohr- und Ankerstange zu arbeiten und damit in einem Arbeitsschritt. Nach dem neuen Verfahren kann vorteilhaft ein Anker unabhängig ob im Einschritt- oder im Zweischrittverfahren verwendet werden, der für den jeweiligen Einsatzfall optimiert ist. Es können also preisoptimierte Anker zum Einsatz gebracht werden. Unabhängig von der Ausbildung der Arbeitsschritte Ankerloch bohren und Anker setzen, bleibt es bei dem großen Vorteil, dass diese Arbeiten mechanisiert aus dem bereits ausgebauten und geschützten Streckenbereich heraus und ohne Manipulationen im Gefahrenbereich der Maschinen erfolgen können.A sees further expedient embodiment before that the anchor holes with the help of the projecting drill carriage from the already developed track area out into the mountains and then that an anchor is inserted and anchored as an anchor adhesive column is fully or partially glued therein, this being in two-step settable anchor, such as friction tube anchor, expansion sleeve anchor u. Ä. or is a one-step anchor. After this process, the drilling is done and setting the anchors in two steps. But it is also possible with a combined drill and anchor rod to work and thus in a step. After the new procedure can be beneficial an anchor independent whether used in one-step or two-step procedures, the for the particular application is optimized. So it can be price optimized anchor be put to use. Regardless of the training of the Steps to drill anchor hole and anchor, it remains the big one Advantage that this work mechanized from the already developed and protected Track area out and without manipulation in the danger area the machines can be done.
Bekannt sind dafür spezielle mechanisierte Anker-, Bohr- und Setzlafetten, die durch einfaches Drehen, Schwenken oder Verschieben der Bohr- und Setzeinrichtungen das Bohren der Ankerlöcher und das Einbringen und Setzen von einzelnen oder mehreren (bei vorhandener Magazinierung) Anker zu ermöglichen. Dies hat erhebliche technische und verfahrensmäßige Vorteile. Besondere Vorteile ergeben sich beim Einsatz von Hohlankern mit integrierter Klebesäule.Are known for this purpose special mechanized anchor, drilling and Setzlafetten, by simple Turning, pivoting or moving the drilling and setting facilities to allow the drilling of the anchor holes and the introduction and setting of one or more (in the presence of magazining) anchor. This has significant technical and procedural benefits. Special advantages arise when using hollow anchors with integrated adhesive column.
Nach einer weiteren zweckmäßigen Ausführung ist vorgesehen, dass die Lafette einem Bohrwagen, einer Bohrbühne oder einer Teil- oder Vollschnittmaschine oder einem eigenen Fahrwerk zugeordnet wird, um auf diese Weise Ankerbohr- und Setzarbeiten so zu mechanisieren, dass sie in kürzesten Zeitabschnitten zu bewältigen sind.To another expedient embodiment provided that the carriage to a Bohrwagen, a Bohrbühne or a partial or full cutting machine or a separate chassis is assigned to anchor drilling and setting work in this way to mechanize them in the shortest time increments deal with are.
Weiter vorne ist darauf hingewiesen worden, dass eine besondere, annähernd flexible Verzugmatte zum Einsatz kommt, nämlich eine solche, die auf die Ankerköpfe aufgeschoben und daran mit Hilfe von Hilfselementen festgelegt werden kann. Dies erreicht man besonders vorteilhaft dann, wenn man wie erfindungsgemäß vorgeschlagen die annähernd flexible Verzugmatte erst nach vollständiger Sicherung einer Ankerreihe oder des Gesamtstreckenabschnittes durch Anker auf die Ankerköpfe aufschiebt. Es soll verfahrensgemäß also der Gesamtstreckenabschnitt, egal ob es sich um eine bogenförmige Strecke oder um eine Strecke mit rechtwinkligem Querschnitt handelt, zunächst einmal gänzlich abgesichert, d. h. geankert werden, bevor dann die weiteren Arbeiten vorgenommen werden. Dies hat den sicherheitlichen großen Vorteil, dass alle Arbeiten im geschützten und gesicherten Bereich erfolgen, nämlich die Bohr- und Ankersetzarbeiten von der vollständig ausgebauten Strecke heraus und die Sicherung über die flexible Matte dann aus dem mit Ankern ausgebauten Bereich heraus. Es kann somit praktisch zu den bisher immer wieder auftretenden Unfällen durch herabfallendes Gestein oder durch lockere Gebirgsabschnitte nicht mehr kommen.Further the front has been pointed out that a special, almost flexible Arrears mat is used, namely one that is on the anchor heads deferred and fixed by means of auxiliary elements can. This is achieved particularly advantageous when proposed as in the invention the approximate flexible delay mat only after complete securing of an anchor row or of the total distance section by anchors on the anchor heads. It should be procedurally so the Total distance section, no matter if it is a curved track or is a section of rectangular cross-section, first of all completely secured, d. H. be anchored before then the further work be made. This has the safety advantage that all work is protected and secured area, namely the drilling and anchoring networks from the fully developed Then stretch out and secure over the flexible mat out of the anchored area out. It can be practical to the ever recurring accidents caused by falling rocks or not come through loose mountain sections.
Das Einbringen der flexiblen Verzugmatte wird dadurch erleichtert und beschleunigt, dass die annähernd flexible Verzugmatte aus zwei oder mehr Teilmatten besteht, die einander überlappend im Streckenprofil eingebracht werden. Während die beschriebenen, annähernd flexiblen Verzugmatten problemlos auf den Ankerkopf bzw. die Ankerköpfe aufgeschoben werden können, wäre dies bei Drahtverzugmatten oder ähnlichen Verzugelementen nicht möglich. Eine solche flexible Verzugmatte kann vorteilhaft geradezu eingespannt werden, wenn die vorläufige Fixierung über die Hilfselemente vorgenommen wird. Damit ist insgesamt nicht nur eine Beschleunigung der Arbeiten erreichbar, sondern gleichzeitig auch eine wesentlich höhere Sicherheit. Bei der zweiteiligen Ausbildung wird die erste Teilmatte oben an der Firste entsprechend festgelegt und dann abschnittweise gespannt oder verspannt auf die Ankerköpfe aufgeschoben und dort gesichert, bevor dann die andere Teilmatte von der Firste über den anderen Stoß verspannt wird. Schon die Beschreibung verdeutlicht, dass ein derartiges Arbeitsverfahren wesentlich einfacher und sicherer ist, als die bisherigen Verfahren mit entsprechend vorgepfändeten Verzugelementen und Ähnlichem. Vor allem sind diese flexiblen Verzugmatten an beiden Längsseiten an den Ankerköpfen festgelegt, sodass es zu Überlastungen, Einbrüchen und Ähnlichem nicht kommen kann.The Introducing the flexible arresting mat is thereby facilitated and that accelerates that approximate flexible delay mat consists of two or more partial mats, the overlapping each other be introduced in the route profile. While the described, almost flexible Defective mats easily pushed onto the anchor head or the anchor heads can be would this in wire delay mats or the like Delay elements not possible. Such a flexible delay mat can advantageously clamped downright if the provisional Fixation over the auxiliary elements is made. This is not just a total an acceleration of work achievable, but at the same time also a much higher one Safety. In the two-part training, the first mat part fixed at the top of the ridge and then in sections cocked or strained on the anchor heads and deferred there before then the other part mat from the ridge over the other push braced becomes. Even the description makes it clear that such a working method much easier and safer than the previous methods with correspondingly pledged Delay elements and the like. Above all, these flexible delay mats on both sides at the anchor heads set, causing overloads, burglaries and the like can come.
Um die Verlegung der zweiten Teilmatte zu vereinfachen kann es zweckmäßig sein, die Teilmatten im Überlappungsbereich mit Kupplungselementen auszurüsten, um so gleichzeitig auch noch zu verhindern, dass im Überlappungsbereich durch Herabfallen und Herabhängen einer Seite der Teilmatte sich Öffnungen für herabfallendes Gestein ergeben.Around To simplify the laying of the second mat, it may be expedient the sub-mats in the overlap area equip with coupling elements, at the same time also to prevent that in the overlap area by falling down and hanging down one side of the mat partitions for falling down Yielded rock.
Die Verzugmatte muss an mehreren Stellen über den Ankerkopf geschoben werden, was problemlos möglich ist, wenn wie erfindungsgemäß vorgesehen eine Verzugmatte aus einem Kunststofffadengewebe und in bergbauzugelassener Zusammensetzung eingesetzt wird. Eine solche Verzugmatte, die beispielsweise schwer entflammbar ist, kann auch im untertägigen Bergbau eingesetzt werden und ermöglicht ein Aufstecken auf das Ankerkopf, ohne dass die Verzugmatte selbst dabei beschädigt wird. Vielmehr legen sich die einzelnen Kunststofffäden um den Ankerkopf herum und die Tragfähigkeit der Verzugmatte bleibt voll erhalten.The Defective mat must be pushed over the anchor head in several places be that, easily possible is if as provided by the invention a delay mat made of a plastic thread and in mining approved Composition is used. Such a delay mat, for example is hardly flammable, can also be used in underground mining and allows an attachment to the anchor head without the default mat itself it is damaged. Rather, the individual plastic threads wrap around the anchor head and the carrying capacity of the Delay mat remains fully preserved.
Nach einer weiteren zweckmäßigen Ausführung ist vorgesehen, dass eine Verzugmatte aus einer Abroll-Kunststofffolie oder aufspritzbarem Material und in bergbauzugelassener Zusammensetzung eingesetzt wird. Die abrollbare Kunststofffolie kann ebenfalls auf den Ankerkopf aufgeschoben werden, ohne dass die Kunststofffolie selbst dabei einreißt. Sie wird durch den Ankerkopf nur gelocht. Gegebenenfalls besteht die Möglichkeit, die Kunststofffolie in dem vorgesehenen Bereich leicht einzuschneiden, um das Überschieben zu erleichtern. Bei Verwendung von aufspritzbaren Folien werden die Ankerköpfe mit eingespritzt. Hier kann auf Verzughalte- und Kalottenplatten sowie Verspannelemente bei den Ausbauankern verzichtet werden.To another expedient embodiment provided that a delay mat from a roll-off plastic film or sprayable material and mining-approved composition becomes. The unrollable plastic film can also be applied to the anchor head be deferred without the plastic film itself tears. she is only punched by the anchor head. If necessary, there is the Possibility, slightly cut the plastic film in the intended area to the sliding over to facilitate. When using sprayable foils the anchor heads injected with. Here can on delay holding and dome plates and Verspannelemente be dispensed with the expansion anchors.
Weiter vorne ist darauf hingewiesen worden, dass die Kalotten- oder Verzug halteplatte erst nach vollständiger Absicherung des Streckenabschnittes dem jeweiligen Anker bzw. dem Ankerkopf zugeordnet wird. Dazu sieht die Erfindung weiter vor, dass die Kalotten- oder Verzughalteplatte und die zugehörigen Spann- und Befestigungselemente nach dem Einbringen des Verzugmaterials mechanisch mit dem Anker verbunden werden.Further front has been noted that the dome or draft holding plate only after complete Securing the section of the route to the respective anchor or the Anchor head is assigned. For this purpose, the invention further provides that the dome or default holding plate and the associated clamping and fasteners after the introduction of the drafting material mechanically connected to the anchor.
Zur Fixierung oder besser gesagt zur vorläufigen Fixierung der Verzugmatte auf dem jeweiligen Ankerkopf dient ein Hilfselement, wobei es besonders vorteilhaft ist, wenn zur Fixierung der Verzugmatte auf den Ankerköpfen ein Hilfselement in Form einer Kunststoff-, Gummi- oder Blechplatte eingesetzt wird, deren mittige Gestaltung zahnförmige oder ähnliche, den Querschnitt verengende Keilelemente aufweist. Ein solches Hilfselement kann ohne großen Kraftaufwand auf den Ankerkopf aufgeschoben werden, sodass die Verzugmatte in kürzester Zeit am Gebirge so festgelegt ist, dass er so lange hält, bis die Kalottenplatte mit den Befestigungs- und Verspannelementen unter gleichzeitiger Fixierung der Verzugmatte verspannt oder sonst wie angebracht wird.to Fixation or rather for temporary fixation of the delay mat on the respective anchor head is an auxiliary element, and it is particularly is advantageous if for fixing the default mat on the anchor heads Auxiliary element in the form of a plastic, rubber or sheet metal plate is used, the central design tooth-shaped or similar, narrowing the cross-section Has wedge elements. Such an auxiliary element can be used without much effort be pushed onto the anchor head, so that the delay mat in shortest time is set on the mountains so that it holds until the dome plate with the fastening and clamping elements under simultaneous Fixing the default mat is clamped or otherwise attached.
Die Erfindung zeichnet sich insbesondere dadurch aus, dass ein Verfahren geschaffen worden ist, das unter wesentlicher Erhöhung der Produktivität und der Betriebssicherheit gleichzeitig die Möglichkeit gibt, das Einbringen der Anker vollständig zu mechanisieren, zumindest aber können alle wesentlichen Arbeiten im gesicherten Streckenbereich bzw. aus dem entsprechend sicheren Streckenbereich heraus vorgenommen werden.The Invention is characterized in particular by the fact that a method has been created, which substantially increases the productivity and the reliability at the same time gives the possibility of introducing the anchor completely to mechanize, at least but all essential work in the secured route area or from the corresponding safe Track area be made out.
Weitere Einzelheiten und Vorteile des Erfindungsgegenstandes ergeben sich aus der nachfolgenden Beschreibung der zugehörigen Zeichnung, in der ein bevorzugtes Ausführungsbeispiel mit den dazu notwendigen Einzelheiten und Einzelteilen dargestellt ist. Es zeigen:Further Details and advantages of the subject invention arise from the following description of the accompanying drawings, in which preferred embodiment presented with the necessary details and individual parts is. Show it:
Bei
Während die
in
Während die
Die
vorläufige
Fixierung der Verzugsmatte
Bezüglich
Alle genannten Merkmale, auch die den Zeichnungen allein zu entnehmenden, werden allein und in Kombination als erfindungswesentlich angesehen.All mentioned features, including the drawings to be taken alone, are considered alone and in combination as essential to the invention.
Claims (13)
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE200910008627 DE102009008627A1 (en) | 2009-02-12 | 2009-02-12 | Securing method for sloped and inclined buildings |
EP10709262A EP2396512A2 (en) | 2009-02-12 | 2010-02-12 | Securing method for horizontal and inclined workings |
PCT/GB2010/050240 WO2010092405A2 (en) | 2009-02-12 | 2010-02-12 | Securing method for horizontal and inclined workings |
AU2010212624A AU2010212624A1 (en) | 2009-02-12 | 2010-02-12 | Securing method for horizontal and inclined workings |
ZA2011/06046A ZA201106046B (en) | 2009-02-12 | 2011-08-17 | Securing method for horizontal and inclined workings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE200910008627 DE102009008627A1 (en) | 2009-02-12 | 2009-02-12 | Securing method for sloped and inclined buildings |
Publications (1)
Publication Number | Publication Date |
---|---|
DE102009008627A1 true DE102009008627A1 (en) | 2010-08-19 |
Family
ID=42338640
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE200910008627 Withdrawn DE102009008627A1 (en) | 2009-02-12 | 2009-02-12 | Securing method for sloped and inclined buildings |
Country Status (5)
Country | Link |
---|---|
EP (1) | EP2396512A2 (en) |
AU (1) | AU2010212624A1 (en) |
DE (1) | DE102009008627A1 (en) |
WO (1) | WO2010092405A2 (en) |
ZA (1) | ZA201106046B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010099777A3 (en) * | 2009-03-06 | 2011-04-14 | Dr. Klaus Schulte Gmbh Chemisch Technische Fabrikation | Lagging mat for underground mining and tunneling |
CN102102526A (en) * | 2010-12-30 | 2011-06-22 | 枣庄矿业集团新安煤业有限公司 | Coal mine roadway supporting method and working face hole-cutting anchor mesh ladder and individual supporting device used by same |
CN102536282A (en) * | 2012-02-27 | 2012-07-04 | 西安科技大学 | Method for preventing and controlling bottom heaving disaster of mine stoping tunnel |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587944B (en) * | 2012-03-22 | 2014-04-16 | 山东华联矿业股份有限公司 | Soft rock-stratum small-section tunneling advance supporting technology |
CN102839981B (en) * | 2012-09-25 | 2014-12-10 | 山东大学 | Backfilling stand shoring system of three-dimensional prestress wire of deep soft rock roadway |
CN103016033A (en) * | 2012-12-31 | 2013-04-03 | 枣庄矿业集团新安煤业有限公司 | Working face crossheading belt plate supporting device |
CN104141496B (en) * | 2014-06-21 | 2016-06-01 | 西安科技大学 | A kind of rectangular shaped roadways failure and deformation of surrounding rocks control method |
CN104790981B (en) * | 2015-04-03 | 2017-04-19 | 山东大学 | Structure and method for improving connection performance between concrete spray layer and arch frames |
CN104790972A (en) * | 2015-04-03 | 2015-07-22 | 山东大学 | Construction method and structure for underground construction confined concrete shoring prestressed steel strands |
CN107060806A (en) * | 2017-03-29 | 2017-08-18 | 安徽理工大学 | It is a kind of can active firm wall U-shaped steel bracket |
CN112554912A (en) * | 2020-12-11 | 2021-03-26 | 天长市飞龙金属制品有限公司 | Steel grating combined support for tunnel initial construction support |
CN113653514A (en) * | 2021-09-16 | 2021-11-16 | 河海大学 | Soft rock tunnel drainable yielding support structure and construction method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2557200A1 (en) * | 1983-12-27 | 1985-06-28 | Somafer Sa | DEVICE FOR THE SOFT SUPPORT OF WALLS OF UNDERGROUND GALLERIES |
CA1244270A (en) * | 1985-08-01 | 1988-11-08 | Donald Gagnon | Friction washer for securing a wire mesh screening onto the protruding end of rock bolts |
US5207535A (en) * | 1991-10-30 | 1993-05-04 | Saab Thomas L | Push-on gripper plate for use with rock bolts |
DE29703416U1 (en) * | 1997-02-26 | 1997-04-24 | Radtke Johannes | Anchor plate |
-
2009
- 2009-02-12 DE DE200910008627 patent/DE102009008627A1/en not_active Withdrawn
-
2010
- 2010-02-12 AU AU2010212624A patent/AU2010212624A1/en not_active Abandoned
- 2010-02-12 EP EP10709262A patent/EP2396512A2/en not_active Withdrawn
- 2010-02-12 WO PCT/GB2010/050240 patent/WO2010092405A2/en active Application Filing
-
2011
- 2011-08-17 ZA ZA2011/06046A patent/ZA201106046B/en unknown
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010099777A3 (en) * | 2009-03-06 | 2011-04-14 | Dr. Klaus Schulte Gmbh Chemisch Technische Fabrikation | Lagging mat for underground mining and tunneling |
CN102102526A (en) * | 2010-12-30 | 2011-06-22 | 枣庄矿业集团新安煤业有限公司 | Coal mine roadway supporting method and working face hole-cutting anchor mesh ladder and individual supporting device used by same |
CN102536282A (en) * | 2012-02-27 | 2012-07-04 | 西安科技大学 | Method for preventing and controlling bottom heaving disaster of mine stoping tunnel |
CN102536282B (en) * | 2012-02-27 | 2013-10-16 | 西安科技大学 | Method for preventing and controlling bottom heaving disaster of mine stoping tunnel |
Also Published As
Publication number | Publication date |
---|---|
AU2010212624A1 (en) | 2011-09-22 |
WO2010092405A2 (en) | 2010-08-19 |
EP2396512A2 (en) | 2011-12-21 |
WO2010092405A3 (en) | 2011-05-12 |
ZA201106046B (en) | 2012-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE102009008627A1 (en) | Securing method for sloped and inclined buildings | |
EP2836680B1 (en) | Method for drilling holes in soil or rock material and for fixing an anchor in a borehole and apparatus therefor | |
DE102008024365A1 (en) | Automated drilling and tying device with separate carriages | |
EP1727967B1 (en) | Method and device for producing pre-tensioned anchorings | |
EP2487374B1 (en) | Method and system for setting a self-tapping undercut anchor | |
DE102010014612A1 (en) | Hollow rod shear connector e.g. two-phase anchor, for use in e.g. inclined roadway construction, has armature tube coated with addition mixed filling material, where clamping path is affiliated with anchor member through clamping sleeve | |
AT505959B1 (en) | METHOD AND DEVICE FOR DRILLING, IN PARTICULAR BUTTING OR TORQUE DRILLING OF A HOLE IN GROUND OR ROCK MATERIAL AND FOR FORMING AN ANCHORAGE | |
DE3902727C2 (en) | ||
DE102009012570A1 (en) | Method for securing long-roadway building element in underground mine, involves reinforcing and/or stabilizing roof in transition area in front of roof support with back-filling building material by support system | |
EP1119687B1 (en) | Jacket tube for a drilling and anchoring device | |
DE112013003397B4 (en) | Method and apparatus for forming boreholes and anchoring them in the borehole | |
AT12444U1 (en) | METHOD FOR HITCHING BZW. DRILLING HOLES IN FLOOR OR ROCK MATERIALS AND FIXING AN ANCHORAGE | |
AT402534B (en) | METHOD FOR DRIVING A TUNNEL OR THE LIKE AND REMOVAL REINFORCEMENT FOR IMPLEMENTING THE METHOD | |
DE102009016153A1 (en) | Lining for constructing e.g. tunnel, has anchor secured in mountain, sealing foil arranged at tunnel outbreak, and outer side fastener comprising nozzle, where clamping connection is provided between nozzle and anchor end | |
DE102009012085A1 (en) | Anchor mat for underground mining and tunneling | |
DE2118034B2 (en) | Mine prefabricated concrete supports - has round hole with bows protruding in to take interposed locking bush with wedges | |
DE4400644A1 (en) | Tensionable GfK mountain anchor | |
CH374819A (en) | Process for the production of prestressed anchors for structures such as retaining walls, excavation securing devices and the like and prestressing anchors produced according to this process | |
DE3922906A1 (en) | Flexible rock anchors for cramped conditions in a mine - consists of cone shaped links on cable core | |
DE3906150A1 (en) | Temporary support for underground roadways | |
CH606770A5 (en) | Mine gallery anchorage rod | |
DE3309381C1 (en) | Method and device for securing the wall of gate roads in mining by means of an accompanying dam of hydraulically setting dam construction material | |
DE4009632A1 (en) | Support for long term securing mining areas | |
EP3094787A1 (en) | Ground anchor | |
DE4130161C1 (en) | Roadway arch support reinforcement - uses endless reinforcing cables, extending in roadway longitudinal direction, distributed over arch periphery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R119 | Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee | ||
R119 | Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee |
Effective date: 20140902 |