DE10005959C2 - Method and device for stacking bridges - Google Patents

Method and device for stacking bridges

Info

Publication number
DE10005959C2
DE10005959C2 DE2000105959 DE10005959A DE10005959C2 DE 10005959 C2 DE10005959 C2 DE 10005959C2 DE 2000105959 DE2000105959 DE 2000105959 DE 10005959 A DE10005959 A DE 10005959A DE 10005959 C2 DE10005959 C2 DE 10005959C2
Authority
DE
Germany
Prior art keywords
load
moved
presses
press
stack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
DE2000105959
Other languages
German (de)
Other versions
DE10005959A1 (en
Inventor
Reinhard Mueller
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DB Bahnbau Gruppe GmbH
Original Assignee
IBB INGENIEUR- BRUECKEN- und TIEFBAU GmbH
IBB INGENIEUR BRUECKEN und TIE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IBB INGENIEUR- BRUECKEN- und TIEFBAU GmbH, IBB INGENIEUR BRUECKEN und TIE filed Critical IBB INGENIEUR- BRUECKEN- und TIEFBAU GmbH
Priority to DE2000105959 priority Critical patent/DE10005959C2/en
Publication of DE10005959A1 publication Critical patent/DE10005959A1/en
Application granted granted Critical
Publication of DE10005959C2 publication Critical patent/DE10005959C2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Description

Die Erfindung betrifft ein Verfahren zum Abstapeln von Brücken sowie die da­ zu benötigte Vorrichtung. Das Verfahren und die Vorrichtung sind grundsätz­ lich auch zum Anheben von Brücken geeignet.The invention relates to a method for stacking bridges and there device required. The method and the device are basic also suitable for lifting bridges.

Im Brückenbau wird zum Absenken oder Anheben von Brücken üblicherweise folgendes Verfahren eingesetzt: Unter dem Endquerträger des Brückenkörpers, der auf Lagerstapeln ruht, werden Pressen auf Pressenstapel aufgebracht, so daß ihr Oberteil die Unterseite des Endquerträgers berührt. Die Lagerstapel und Pressenstapel werden aus Stapellagen gebildet. Das Verfahren umfaßt fol­ gende Schritte, die mehrmals in dieser Reihenfolge wiederholt werden, bis der Endquerträger seine Endlage erreicht hat. Die Pressen werden ausgefahren, so daß die Last nicht mehr auf den Lagerstapeln, sondern auf den Pressen ruht. Aus den Lagerstapeln kann dann jeweils eine Lage der Stapelhölzer entfernt werden. Die Pressen werden anschließend eingefahren, so daß die Last erneut auf den Lagerstapeln ruht. Dann werden die Pressen von den Pressenstapeln entfernt, indem sie beispielsweise auf seitlich neben den Pressenstapeln ange­ ordnete Hilfsstapel gerutscht oder weggehoben werden, so daß eine Lage der Stapelhölzer aus den Pressenstapeln entfernt werden kann. Anschließend wer­ den die Pressen erneut auf die Pressenstapel gestellt und die Pressen ausgefah­ ren, so daß die Last erneut auf den Pressen lagert. Sodann werden die übrigen Verfahrensschritte wiederholt, bis die Brücke von der Ausgangslage in die Endlage überführt ist.In bridge building, lowering or lifting bridges is common the following procedure is used: under the end cross member of the bridge body, that rests on stock piles, presses are placed on press piles, so that its upper part touches the underside of the end cross member. The stock piles and press stacks are formed from stack layers. The procedure includes fol steps that are repeated several times in this order until the End cross member has reached its end position. The presses are extended, so that the load no longer rests on the stockpiles, but on the presses. One layer of the stacking timber can then be removed from the storage stacks become. The presses are then retracted so that the load again rests on the stockpiles. Then the presses from the press stacks removed, for example, on the side next to the press stacks ordered auxiliary stacks are slipped or lifted away, so that a layer of Stacking sticks can be removed from the press stacks. Then who which the presses placed on the press stack again and the presses extended ren, so that the load rests on the presses. Then the rest Process steps repeated until the bridge from the starting position in the End position is transferred.

Nachteil dieses Verfahrens ist insbesondere, daß zum Wegheben der naturge­ mäß sehr schweren Pressen bzw. zum Verrutschen dieser Pressen auf Hilfssta­ pel erhebliche Kräfte aufgewendet werden müssen. Da diese Tätigkeit zumeist manuell erfolgen muß, sind dazu große körperliche Anstrengungen notwendig. Überdies ist dieser Verfahrensschritt zeitaufwendig und damit kostenintensiv.The disadvantage of this method is in particular that to remove the naturge very heavy presses or for slipping these presses on auxiliary sta pel considerable forces have to be applied. Since this activity mostly  manual exercise requires great physical exertion. Furthermore, this process step is time-consuming and therefore costly.

Es ist daher Ziel der vorliegenden Erfindung, den oben beschriebenen Nachteil des Standes der Technik zu überwinden. Dabei steht die Aufgabe, eine Lösung zu finden, die das Bewegen der Pressen auf Hilfsstapel oder das Wegheben der Pressen vermeidet und somit weniger große körperliche Anstrengungen erfor­ dert.It is therefore an object of the present invention to overcome the disadvantage described above to overcome the state of the art. The task is a solution to find the moving the presses on auxiliary piles or lifting the Avoids pressing and thus requires less physical exertion changed.

Erfindungsgemäß wird dies durch eine Vorrichtung gelöst, die aus einer Platt­ form besteht, auf der sich die Presse befindet, wobei die Plattform mittels Fe­ dern an die zu bewegende Last angehängt ist. Sowohl die Plattform als auch die Federn sind aus Stahl ausgeführt. Die Plattform wird mittels zwei oder mehr Federn an die zu bewegende Last angehängt. Die Federn sind so bemessen, daß sie einerseits die Presse an die zu bewegende Last stetig andrücken und ande­ rerseits die Last der Pressen tragen können. Die Federn sind vorzugsweise Spi­ ralfedern.According to the invention, this is achieved by a device which consists of a plate form exists on which the press is located, whereby the platform by means of Fe which is attached to the load to be moved. Both the platform and the Springs are made of steel. The platform is built using two or more Springs attached to the load to be moved. The springs are dimensioned so that they constantly press the press against the load to be moved, and others on the one hand can bear the load of the presses. The springs are preferably spi Ralf edern.

Bei Verwendung der erfindungsgemäßen Vorrichtung befindet sich somit die Presse nicht mehr direkt auf der obersten Stapellage, sondern auf einer darauf befindlichen Plattform. Diese Plattform, auf der sich die Presse befindet, wird an die Unterseite der zu bewegenden Last stetig angedrückt. Lagert die zu be­ wegende Last auf den Lagerstapeln kann somit eine Stapellage in den Pressen­ stapel eingeführt oder aus diesem entfernt werden, da zwischen der Plattform und der obersten Stapellage der Pressenstapel ausreichend Raum verbleibt. Es ist daher nicht erforderlich, die Presse von dem Pressenstapel auf einen Hilfs­ stapel zu verschieben oder sie hinwegzuheben. Auf diese Weise wird dieser körperlich sehr anstrengende Arbeitsschritt beim Abstapeln oder Anheben von Brücken eingespart. When using the device according to the invention, the Press no longer directly on the top stack, but on one on top of it located platform. This platform, on which the press is located, will constantly pressed on the underside of the load to be moved. Store the be moving load on the storage stacks can thus be a stack position in the presses stack inserted or removed from it, because between the platform and the top stack layer of the press stack has sufficient space. It is therefore not necessary to move the press from the press stack to an auxiliary move the stack or lift it away. In this way it becomes very physically demanding work step when stacking or lifting Saved bridges.  

Somit ergibt sich folgendes Verfahren zum Abstapeln von Brücken; wenn die erfindungsgemäße Vorrichtung eingesetzt wird: (a) Zunächst werden die Platt­ formen, die die Pressen tragen, an die zu bewegende Last angehängt. Dabei lagert die zu bewegende Last, die sich in ihrer Ausgangslage befindet, auf La­ gerstapeln. Unter den Plattformen befinden sich Pressenstapel, die ebenso wie die Lagerstapel aus übereinanderliegenden Stapelhölzern bestehen. Dabei wer­ den die Pressen stetig an die zu bewegende Last über die Federn und die Platt­ form angedrückt. (b) Anschließend werden die Pressen so ausgefahren, daß Plattformen auf die Pressenstapel gedrückt werden und dann die zu bewegen­ de Last auf den Presse ruht. (c) Daraufhin kann jeweils eine Lage der Stapelhöl­ zer aus den Lagerstapeln entfernt werden. (d) Im Anschluß daran werden die Pressen eingefahren, so daß die zu bewegende Last auf den Lagerstapeln ruht. Da die Pressen über die Plattformen mit den Spiralfedern an die Unterseite der zu bewegenden Last angedrückt werden, entsteht zwischen den Unterseiten der Plattformen und den Pressenstapeln ein Zwischenraum. (e) Aufgrund des­ sen kann eine Lage der Stapelhölzer aus den Pressenstapeln entfernt werden. Die Schritte (b) bis einschließlich (e) werden in dieser Reihenfolge wiederholt, bis die zu bewegende Last die Endlage erreicht hat.This results in the following procedure for stacking bridges; if the device according to the invention is used: (a) First, the plates shapes that carry the presses attached to the load to be moved. there stores the load to be moved, which is in its starting position, on La gerst stacking. Under the platforms are press stacks, which as well the storage stacks consist of stacked timber. Here who which the presses continuously to the load to be moved via the springs and the flat pressed on. (b) The presses are then extended so that Platforms are pressed onto the press stack and then the move the load rests on the press. (c) There can then be one layer of the stacking wood zer be removed from the stock piles. (d) Subsequently, the Presses retracted so that the load to be moved rests on the bearing stacks. As the presses over the platforms with the coil springs to the bottom of the the load to be moved is created between the undersides a space between the platforms and the press stacks. (e) Due to the A layer of the stacking timber can be removed from the press stacks. Steps (b) through (e) are repeated in this order, until the load to be moved has reached the end position.

Das Verfahren zum Anheben von Brücken unter Einsatz der erfindungsgemä­ ßen Vorrichtung unterscheidet sich von dem erläuterten Verfahren zum Ab­ stapeln von Brücken dahingehend, daß anstelle des Entfernens von Stapellagen aus den Lager- und Pressenstapeln jeweils Stapellagen in diese Stapel einge­ führt werden.The method for lifting bridges using the invention ß device differs from the explained method for Ab stacking bridges in that instead of removing stack layers from the storage and press stacks stacked into these stacks leads.

Die erfindungsgemäßen Verfahren zum Abstapeln oder Anheben von Brücken hat gegenüber dem Verfahren des Standes der Technik den erheblichen Vorteil, daß auf das körperlich sehr anstrengende Verschieben der Pressen auf einen Hilfsstapel, um eine Stapellage aus den Pressenstapeln entfernen zu können, verzichtet werden kann. Damit wird das Verfahren insgesamt weniger zeitauf­ wendig und folglich kostengünstiger.The method according to the invention for stacking or lifting bridges has the considerable advantage over the prior art method that that the physically very strenuous shifting of the presses onto you Auxiliary stacks in order to be able to remove a stack layer from the press stacks, can be dispensed with. This means that the process is less time-consuming overall agile and therefore cheaper.

Im folgenden wird die Erfindung anhand eines Ausführungsbeispiels mit Be­ zug auf die beiliegende Zeichnung näher erläutert.In the following the invention using an exemplary embodiment with Be train explained in more detail on the accompanying drawing.

Fig. 1 zeigt schematisch den Querschnitt eines Brückenüberbaues vor dem Ab­ stapeln. Der Endquerträger 2 des Brückenüberbaus 1, die zu bewegende Last, ruht auf Lagerstapeln 4, so daß sich die Lager in Höhe der Ausgangslage befin­ den. Die Pressen 5, die sich auf Plattformen 6 befinden, werden über Spriralfe­ dern 7 an die Unterseite des Endquerträgers 2 angedrückt. Dazu sind die Spiral­ federn sowohl mit der Plattform 6, auf der sich die Presse befindet, und der Un­ terseite des Endquerträgers 2 verbunden. Unter den Plattformen 6 befinden sich Pressenstapel 8, auf denen die Plattformen 6 bei ausgefahrenen Pressen 5 auf­ liegen. Sowohl die Lagerstapel 3 als auch die Pressenstapel 8 bestehen aus Sta­ pellagen 9, wobei sich die unterste Stapellage in Höhe der Endlage befindet. Fig. 1 shows schematically the cross section of a bridge superstructure before stacking. The end cross member 2 of the bridge superstructure 1 , the load to be moved, rests on bearing stacks 4 , so that the bearings are at the level of the starting position. The presses 5 , which are located on platforms 6 , 7 are pressed onto the underside of the end cross member 2 via spiral springs 7 . For this purpose, the spiral springs are connected to both the platform 6 , on which the press is located, and the underside of the end cross member 2 . Under the platforms 6 there are press stacks 8 on which the platforms 6 lie when the presses 5 are extended. Both the bearing stack 3 and the press stack 8 consist of stacking layers 9 , the lowest stacking layer being at the level of the end position.

Die erfindungsgemäße Vorrichtung wird in Fig. 2 detaillierter dargestellt. Die Presse 5 befindet sich auf der Plattform 6, die aus Stahl bestehen kann. Über Spiralfedern 7 aus Stahl ist die Plattform 6 an die zu bewegende Last, den Brüc­ kenüberbau 1, angehängt.The device according to the invention is shown in more detail in FIG. 2. The press 5 is located on the platform 6 , which can be made of steel. About coil springs 7 made of steel, the platform 6 is attached to the load to be moved, the bridge superstructure 1 .

Werden die Pressen 5 ausgefahren, so werden die Plattformen 6 auf die Pres­ senstapel 8 und gegen die Unterseite des Endquerträgers 2 gedrückt. Die zu bewegende Last, der Brückenüberbau 1, ruht dann nicht mehr auf den Lager­ stapeln 3, sondern auf den Pressenstapeln 8, so daß jeweils eine Stapellage 9 aus den Lagerstapeln 3 entfernt werden kann. Anschließend werden die Pressen 5 eingefahren, so daß die zu bewegende Last erneut auf den Lagerstapeln 3 ruht. Die Spiralfedern 7 drücken die Pressen 5 weiterhin an die zu bewegende Last an. Dadurch entsteht zwischen der Unterseite der Plattformen 6 und der ober­ sten Stapellage der Pressenstapel 8 ein Zwischenraum, so daß aus den Pressen­ stapeln 8 Stapellagen entfernt werden können. Diese Verfahrensschritte werden solange wiederholt, bis die Lager des Brückenüberbaus 1 ihre Endlage erreicht haben.If the presses 5 are extended, the platforms 6 are pressed onto the press stack 8 and against the underside of the end cross member 2 . The load to be moved, the bridge superstructure 1, then does not rest on the more storage stacks 3, but so that in each case a stack layer 9 can be removed from the storage stacks 3 on the press packs 8. The presses 5 are then retracted so that the load to be moved rests on the bearing stacks 3 again. The coil springs 7 continue to press the presses 5 against the load to be moved. This produces between the underside of the platforms 6 and the upper-most position of the stack press stack 8, a gap, so that the pressing can be made of stacked 8 stack layers are removed. These process steps are repeated until the bearings of the bridge superstructure 1 have reached their end position.

Claims (9)

1. Vorrichtung zum Einsatz beim Abstapeln oder Anheben von Brüc­ ken mittels Pressen, dadurch gekennzeichnet, daß sie aus einer Platt­ form (6) besteht, auf der sich die Presse (5) befindet, wobei die Platt­ form (6) mittels Federn (7) an die zu bewegende Last (1) angehängt ist.1. Device for use in stacking or lifting of bridges by means of presses, characterized in that it consists of a platform ( 6 ) on which the press ( 5 ) is located, the platform ( 6 ) by means of springs ( 7 ) is attached to the load to be moved ( 1 ). 2. Vorrichtung nach Anspruch 1, dadurch gekennzeichnet, daß die Fe­ dern (7) aus Stahl ausgeführt sind.2. Device according to claim 1, characterized in that the Fe countries ( 7 ) are made of steel. 3. Vorrichtung nach Anspruch 1, dadurch gekennzeichnet, daß die Plattform (6) aus Stahl ausgeführt ist.3. Device according to claim 1, characterized in that the platform ( 6 ) is made of steel. 4. Vorrichtung nach einem der vorstehenden Ansprüche, dadurch ge­ kennzeichnet, daß die Plattform (6) mittels zwei oder mehr Fe­ dern (7) an die zu bewegende Last (1) angehängt ist.4. Device according to one of the preceding claims, characterized in that the platform ( 6 ) by means of two or more feet ( 7 ) is attached to the load to be moved ( 1 ). 5. Vorrichtung nach einem der vorstehenden Ansprüche, dadurch ge­ kennzeichnet, daß die Federn (7) so bemessen sind, daß sie die Pres­ sen (5) stetig an die zu bewegende Last (1) andrücken.5. Device according to one of the preceding claims, characterized in that the springs ( 7 ) are dimensioned such that they press the pres sen ( 5 ) continuously against the load to be moved ( 1 ). 6. Vorrichtung nach einem der vorstehenden Ansprüche, dadurch ge­ kennzeichnet, daß die Federn (7) so bemessen sind, daß sie die auf der Plattform (6) befindliche Presse (5) tragen.6. Device according to one of the preceding claims, characterized in that the springs ( 7 ) are dimensioned such that they carry the press ( 5 ) located on the platform ( 6 ). 7. Vorrichtung nach einem der vorstehenden Ansprüche, dadurch ge­ kennzeichnet, daß die Federn (7) Spiralfedern sind. 7. Device according to one of the preceding claims, characterized in that the springs ( 7 ) are spiral springs. 8. Verfahren zum Abstapeln von Brücken unter Einsatz einer Vorrich­ tung nach einem der Ansprüche 1 bis 7, dadurch gekennzeichnet, daß es die Schritte:
  • a) Anhängen von Plattformen (6), die die Pressen (5) tra­ gen, an die zu bewegende Last (1), die sich in der Ausgangslage befindet, wobei sich unterhalb der Plattformen (6) Pressenstapel (8) befinden, die aus übereinanderliegenden Stapelhölzern (9) bestehen, während die zu bewegende Last (1) auf Lagersta­ peln (3) ruht, die ebenfalls aus übereinanderliegenden Stapelhöl­ zern (9) bestehen;
  • b) Ausfahren der Pressen (5), so daß die zu bewegende Last (1) auf den Pressen (5) ruht;
  • c) Entfernen einer Lage der Stapelhölzer (9) aus den La­ gerstapeln (8);
  • d) Einfahren der Pressen (5), so daß die zu bewegende Last (1) auf den Lagerstapeln ruht;
  • e) Entfernen einer Lage der Stapelhölzer (9) aus den Pressenstapeln (8);
umfaßt, wobei die Schritte (b) bis einschließlich (e) in dieser Reihen­ folge wiederholt werden, bis die zu bewegende Last (10) die Endlage erreicht hat.
8. A method for stacking bridges using a device according to one of claims 1 to 7, characterized in that it comprises the steps:
  • a) Attaching platforms ( 6 ), which the presses ( 5 ) carry, to the load to be moved ( 1 ), which is in the starting position, with below the platforms ( 6 ) press stack ( 8 ), which are made of stacked wood ( 9 ), while the load to be moved ( 1 ) on Lagersta peln ( 3 ) rests, which also consist of stacked wood ( 9 );
  • b) extending the presses ( 5 ) so that the load ( 1 ) to be moved rests on the presses ( 5 );
  • c) removing a layer of the stacking timbers ( 9 ) from the stack ( 8 );
  • d) retracting the presses ( 5 ) so that the load ( 1 ) to be moved rests on the bearing stacks;
  • e) removing a layer of the stacking timbers ( 9 ) from the press stacks ( 8 );
comprises, steps (b) through (e) being repeated in this sequence until the load ( 10 ) to be moved has reached the end position.
9. Verfahren zum Anheben von Brücken unter Einsatz einer Vorrich­ tung nach einem der Ansprüche 1 bis 7, dadurch gekennzeichnet, daß es die Schritte:
  • a) Anhängen von Plattformen (6), die die Pressen (5) tra­ gen, an die zu bewegende Last (1), die sich in der Ausgangslage befindet, wobei sich unterhalb der Plattformen (6) Pressensta­ pel (8) befinden, die aus übereinanderliegenden Stapelhölzern (9) bestehen, während die zu bewegende Last (1) auf Lagerstapeln (3) ruht, die ebenfalls aus übereinanderliegenden Stapelhöl­ zern (9) bestehen;
  • b) Ausfahren der Pressen (5), so daß die zu bewegende Last (1) auf den Pressen (5) ruht;
  • c) Einbringen einer Lage der Stapelhölzer (9) in die La­ gerstapel (3);
  • d) Einfahren der Pressen (5), so daß die zu bewegende Last (1) auf den Lagerstapeln (3) ruht;
  • e) Einbringen einer Lage der Stapelhölzer (9) in die Pres­ senstapel (8);
umfaßt, wobei die Schritte (b) bis einschließlich (e) in dieser Reihenfolge wie­ derholt werden, bis die zu bewegende Last (1) die Endlage erreicht hat.
9. A method for lifting bridges using a device according to one of claims 1 to 7, characterized in that it comprises the steps:
  • a) Attaching platforms ( 6 ), which the presses ( 5 ) carry, to the load to be moved ( 1 ), which is in the starting position, being below the platforms ( 6 ) press stack ( 8 ), the consist of superposed stack of timber (9), whereas the rests to move the load (1) in storage stacks (3) the Zern also superposed Stapelhöl (9) are made;
  • b) extending the presses ( 5 ) so that the load ( 1 ) to be moved rests on the presses ( 5 );
  • c) introducing a layer of the stacking timber ( 9 ) into the storage stack ( 3 );
  • d) retracting the presses ( 5 ) so that the load ( 1 ) to be moved rests on the bearing stacks ( 3 );
  • e) introducing a layer of the stacking timber ( 9 ) into the press stack ( 8 );
comprises, steps (b) through (e) being repeated in this order until the load ( 1 ) to be moved has reached the end position.
DE2000105959 2000-02-09 2000-02-09 Method and device for stacking bridges Expired - Fee Related DE10005959C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE2000105959 DE10005959C2 (en) 2000-02-09 2000-02-09 Method and device for stacking bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE2000105959 DE10005959C2 (en) 2000-02-09 2000-02-09 Method and device for stacking bridges

Publications (2)

Publication Number Publication Date
DE10005959A1 DE10005959A1 (en) 2001-08-30
DE10005959C2 true DE10005959C2 (en) 2002-04-18

Family

ID=7630494

Family Applications (1)

Application Number Title Priority Date Filing Date
DE2000105959 Expired - Fee Related DE10005959C2 (en) 2000-02-09 2000-02-09 Method and device for stacking bridges

Country Status (1)

Country Link
DE (1) DE10005959C2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20221894U1 (en) 2002-07-06 2009-03-19 Amphenol-Tuchel Electronics Gmbh Electrical connector

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH684103A5 (en) * 1991-12-09 1994-07-15 Robert Warthmann Bridge pillar unloading system
DE19634570C1 (en) * 1996-08-26 1997-12-18 Walter Dipl Ing Komm Device for raising and lowering multi-field components, particularly bridge superstructures

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH684103A5 (en) * 1991-12-09 1994-07-15 Robert Warthmann Bridge pillar unloading system
DE19634570C1 (en) * 1996-08-26 1997-12-18 Walter Dipl Ing Komm Device for raising and lowering multi-field components, particularly bridge superstructures

Also Published As

Publication number Publication date
DE10005959A1 (en) 2001-08-30

Similar Documents

Publication Publication Date Title
DE10392503T5 (en) palette
CH635045A5 (en) Stack change device.
DE10005959C2 (en) Method and device for stacking bridges
DE2629515A1 (en) MOLDING DEVICE WITH RIGID CORE
DE2936216A1 (en) MOBILE CRANE
DE2819295A1 (en) REEL STAND FOR MULTIPLE TRACK ROLLS
DE102004053931A1 (en) Pit drilling device has climbing assembly deck and work carrying deck arranged on peripheral side which can be brought into rest position with the help of lifting device
DE10210315B4 (en) Pallet stacker and pallet truck for use with such a device
DE8335816U1 (en) DEVICE FOR INTERMEDIATE STACKING OF CUT PRODUCTS
DE2805480A1 (en) DEVICE FOR GRIPPING AND HANDLING LOADS ARRANGED ON PALLETS
DE3808754C2 (en) Process for the introduction of press piles and sheet piles
DE102017108898A1 (en) Apparatus and method for raising or lowering a support bearing
DE3337126A1 (en) DEVICE FOR DELIVERING AND / OR RECEIVING PANELS, ESPECIALLY CIRCUIT BOARDS, FROM OR IN A PACK OF DISKS
AT37432B (en) Method and device for loading hydraulic plate presses for textile fabrics.
DE3015443C2 (en) Stone forming machine
DE1683809C3 (en) Compression press for making panels
DE2254519A1 (en) DEVICE FOR SUPPLYING PARTIAL STACKS OF PAPER SHEETS TO A COMPLETE STACK
DE2852868C2 (en) Machine for laying slabs composed of shaped stones
DE1995989U (en) DEVICE FOR UNSTACKING STACKS MADE FROM PANELS
DE3616109C1 (en) Method of constructing a superstructure supported on an arched supporting framework
DE4127053C2 (en) Plate press
DE4427472C2 (en) Process for joining sheet metal lying on top of one another by forming together, in particular deep drawing
DE3538096A1 (en) Device for setting shaped blocks formed from concrete
DE2925357A1 (en) Raising existing road bridge superstructure - involves staged elevation on retracting and extending hydraulic presses, and support insertion
AT4342U1 (en) DEVICE FOR PRODUCING LARGE AREA CONCRETE PARTS

Legal Events

Date Code Title Description
OM8 Search report available as to paragraph 43 lit. 1 sentence 1 patent law
OP8 Request for examination as to paragraph 44 patent law
D2 Grant after examination
8364 No opposition during term of opposition
8327 Change in the person/name/address of the patent owner

Owner name: DB BAHNBAU GRUPPE GMBH, 10179 BERLIN, DE

R081 Change of applicant/patentee

Owner name: DB BAHNBAU GRUPPE GMBH, DE

Free format text: FORMER OWNER: IBB INGENIEUR-, BRUECKEN- UND TIEFBAU GMBH, 01159 DRESDEN, DE

Effective date: 20110330

R119 Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee
R119 Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee

Effective date: 20140902