Czech (cs)
Inventor
Pavel ULRICH
Original Assignee
ALMEVA EAST EUROPE s.r.o.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ALMEVA EAST EUROPE s.r.o. filed Critical ALMEVA EAST EUROPE s.r.o.
Priority to CZ2020-37863U priority Critical patent/CZ34402U1/en
Publication of CZ34402U1 publication Critical patent/CZ34402U1/en
Priority to PCT/CZ2021/000038 priority patent/WO2022033613A1/en
Priority to SK50004-2023U priority patent/SK9807Y1/en
Priority to PL131250U priority patent/PL131250U1/en
Priority to DE212021000439.3U priority patent/DE212021000439U1/en
Priority to HUU2300046U priority patent/HU5676U/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L41/00Branching pipes; Joining pipes to walls
    • F16L41/004Joining to walls at other than 90 degrees
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L21/00Joints with sleeve or socket
    • F16L21/02Joints with sleeve or socket with elastic sealing rings between pipe and sleeve or between pipe and socket, e.g. with rolling or other prefabricated profiled rings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L41/00Branching pipes; Joining pipes to walls
    • F16L41/02Branch units, e.g. made in one piece, welded, riveted
    • F16L41/021T- or cross-pieces
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L41/00Branching pipes; Joining pipes to walls
    • F16L41/08Joining pipes to walls or pipes, the joined pipe axis being perpendicular to the plane of the wall or to the axis of another pipe
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L41/00Branching pipes; Joining pipes to walls
    • F16L41/08Joining pipes to walls or pipes, the joined pipe axis being perpendicular to the plane of the wall or to the axis of another pipe
    • F16L41/10Joining pipes to walls or pipes, the joined pipe axis being perpendicular to the plane of the wall or to the axis of another pipe the extremity of the pipe being screwed into the wall
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J13/00Fittings for chimneys or flues 
    • F23J13/04Joints; Connections
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J2213/00Chimneys or flues
    • F23J2213/20Joints; Connections

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Incineration Of Waste (AREA)
  • Pipe Accessories (AREA)
  • Rigid Pipes And Flexible Pipes (AREA)
  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)

Description

Trubková sestava pro vložkování spalinových cestPipe assembly for flue gas lining

Oblast technikyField of technology

Technické řešení se týká trubkové sestavy pro vložkování spalinových cest, která slouží zvláště ke zjednodušení postupu a zvýšení spolehlivosti vložkování spalinové cesty, potažmo komínové šachty.The technical solution relates to a pipe assembly for the lining of flue gas ducts, which serves in particular to simplify the process and increase the reliability of the lining of the flue gas path, and thus the chimney shaft.

Dosavadní stav technikyPrior art

Při vložkování spalinové cesty se zpravidla problém přechodu z větší průměrové dimenze vložky na menší průměr řeší vkládáním redukcí až na požadovaný průměr, a to napojováním jednotlivých trubkových dílů postupně za sebou, například v sestavě: rovný díl s následující redukcí s konkrétním zmenšeným průměrem a potom s dílem náležitého menšího průměru apod.When inserting the flue gas path, the problem of transition from a larger diameter dimension of the insert to a smaller diameter is usually solved by inserting reductions to the desired diameter by connecting individual pipe parts one after the other, for example in an assembly: straight part with subsequent reduction with specific reduced diameter and then with part of a corresponding smaller diameter, etc.

Nezřídka vyvstávají situace, kdy je potřeba uspořádat spalinovou cestu jejím vedením z vertikálního směru na směr horizontální a zároveň změnit průřezovou dimenzi v této části spalinové cesty s ohledem na systém odvodu spalin z příslušného spotřebiče.It often arises when it is necessary to arrange the flue gas path by guiding it from a vertical direction to a horizontal direction and at the same time change the cross-sectional dimension in this part of the flue gas path with respect to the flue gas discharge system from the respective appliance.

Až dosud se takové situace řešily postupným napojováním trubkových dílů v sérii za sebou. Například na vertikální rovný trubkový díl většího průměru se napojuje trubková redukce, na níž v liniovém napojení následuje trubkové koleno menšího průměru, kterým se změní poloha daného úseku spalinové cesty do horizontálního směru a s přechodem na menší průměr. Nevýhodou tohoto řešení je samozřejmě prodloužení vložkované spalinové cesty, ale i bezpečnost těsnění. Čím víc prvků trubkových dílů je napojeno na sebe, tím vzniká více spojů a je větší pravděpodobnost výskytu chyby ve vzájemném těsnění.Until now, such situations have been solved by gradually connecting the tubular parts in series. For example, a pipe reducer is connected to a vertical straight pipe section of larger diameter, on which a pipe connection of a smaller diameter follows in a linear connection, which changes the position of a given section of the flue in the horizontal direction and with a transition to a smaller diameter. The disadvantage of this solution is, of course, the extension of the inserted flue gas path, but also the safety of the seal. The more elements of the tubular parts are connected to each other, the more connections are made and the greater the probability of an error in the mutual sealing.

Výše uvedené problémy částečně odstraňuje řešení dle užitného vzoru CZ 29629 Ul.The above problems are partially eliminated by the solution according to the utility model CZ 29629 Ul.

K odstranění uvedených stávajících nevýhod systémů vložkování spalinových cest trubkovými díly, je zvláště pro kritický kolenový úsek navrženo nové technické řešení, jehož podstata spočívá vtom, že sestává z jednodílného kompaktního prvku úseku spalinové cesty pro vedení spalin zvláště z horizontálního směru do vertikálního směru nebo naopak, ve formě sestavy tvořené závitovou přírubou na straně jedné a nasouvacího hrdla na straně druhé, vzájemně propojených kolonovým úsekem, vybaveného nejméně jednou přechodovou redukcí k přechodu kolonového úseku do spodku nasouvacího hrdla s větším příčným průřezem. Hlavní nevýhody dosavadních řešení spočívají v nutné poměrně velké redukci průřezu vkládané vložky vůči původnímu průřezu spalinové cesty nebo v potřebě bouracích a stavebních prací při vložkování spalinové cesty.In order to overcome the above-mentioned disadvantages of flue gas lining systems, a new technical solution is proposed, especially for the critical knee section, in which it consists of a one-piece compact flue gas section element for conducting flue gas ducts in particular from horizontal to vertical or vice versa. in the form of an assembly formed by a threaded flange on the one hand and a plug-in neck on the other hand, interconnected by a column section, provided with at least one transition reduction for the transition of the column section to the bottom of the plug-in neck with a larger cross section. The main disadvantages of the existing solutions are the necessary relatively large reduction in the cross-section of the inserted liner relative to the original cross-section of the flue gas path or in the need for demolition and construction work in the insertion of the flue gas path.

Podstata technického řešeníThe essence of the technical solution

Nevýhody dosavadních technických řešení pro vložkování spalinových cest odstraňuje řešení, jehož podstata spočívá v trubkové sestavě, která je tvořena základní vložkovací trubkou, sestávající z rovného trubkového úseku jednostranně zakončeného nasouvacím hrdlem, do něhož se nasune další vložkovací díl pro vložkování spalinové cesty, přičemž rovný trubkový úsek je opatřen nejméně jedním bočním otvorem olemovaným boční přírubou s vnitřním závitem, do níž je, prostřednictvím vnějšího závitu, našroubována redukční přípojní trubice, napojená na zdroj spalin. Výhoda tohoto řešení je především v tom, že boční příruba jez větší části zapuštěna do stěny rovného trubkového úseku, a tudíž v půdorysném pohledu na základní vložkovací trubku přesahuje vnější rozměr nasouvacího hrdla maximálně o 10 mm. Základní vložkovací trubka tedy může mít ve vztahu k původnímu průřezu spalinové cesty podstatně větší průřez. Jednotlivé základní vložkovací trubky lze tedy bez problému spouštět do vložkované spalinové cesty a prostřednictvímThe disadvantages of the prior art solutions for flue gas lining are eliminated by the solution, the essence of which consists in a tubular assembly consisting of a basic lining tube consisting of a straight pipe section terminated on one side by a plug-in neck into which another flue gas lining insert is inserted. the section is provided with at least one side opening bordered by a side flange with an internal thread, into which, by means of an external thread, a reduction connecting pipe connected to a flue gas source is screwed. The advantage of this solution is in particular that the side flange of the weir is largely embedded in the wall of the straight pipe section, and thus, in plan view of the base liner, exceeds the outer dimension of the push-in neck by a maximum of 10 mm. Thus, the base liner can have a substantially larger cross-section relative to the original cross-section of the flue gas path. The individual base liners can thus be lowered into the inserted flue gas path and via without any problems

-1 CZ 34402 UI zasunutí do nasouvacího hrdla napojovat na sebe. Vnitřek nasouvacího hrdla je opatřen kruhovým těsněním, které zamezuje úniku spalin mimo spalinovou cestu. Vhodnou úpravou délky rovných trubkových úseků je možno přesně definovat polohu bočního otvoru, respektive boční příruby vůči existujícímu otvoru pro napojení tak, aby nebyly potřebné stavební zásahy. Vlastní připojení na zdroj spalin se realizuje redukční přípojní trubicí, která je k rovnému trubkovému úseku základní vložkovací trubky napojena našroubováním do boční příruby, a to pod úhlem v rozmezí 85 až 95°. Mezi boční přírubu a redukční přípojní trubici je vložen těsnící kroužek. Technické řešení výrazně zvětšuje možný a použitelný průřez trubek pro vložkování, usnadňuje montáž nové vložkované spalinové cesty a umožňuje bezproblémové napojení více zdrojů spalin na jednu vertikální spalinovou cestu, představovanou základními vložkovacími trubkami s napojenými redukčními přípojnými trubicemi.-1 GB 34402 Connect the UI plug-in into the plug-in socket. The inside of the plug-in neck is provided with a circular seal, which prevents the escape of flue gases outside the flue gas path. By suitable adjustment of the length of the straight pipe sections, it is possible to precisely define the position of the side opening or the side flange relative to the existing connection opening so that no construction work is required. The actual connection to the flue gas source is realized by a reducing connection pipe, which is connected to the straight pipe section of the basic liner pipe by screwing it into the side flange, at an angle in the range of 85 to 95 °. A sealing ring is inserted between the side flange and the reducing connection tube. The technical solution significantly increases the possible and usable cross-section of the pipes for lining, facilitates the installation of a new lined flue gas path and enables seamless connection of multiple flue gas sources to one vertical flue gas path, represented by basic lining pipes with connected reduction connecting pipes.

Objasnění výkresůExplanation of drawings

Další výhody a účinky předloženého technického řešení jsou dále patrné z připojených výkresů, kde značí:Other advantages and effects of the presented technical solution are further evident from the attached drawings, where they indicate:

Obr. 1 - Boční pohled na trubkovou sestavu s detailním osovým řezem,Giant. 1 - Side view of a pipe assembly with a detailed axial section,

Obr. 2 - Prostorový pohled na trubkovou sestavu složenou ze základní vložkovací trubky a z boční příruby s napojenou redukční přípojní trubicí.Giant. 2 - Spatial view of a pipe assembly consisting of a basic liner pipe and a side flange with a connected reduction connection pipe.

Příklad uskutečnění technického řešeníExample of implementing a technical solution

Popisovaný příklad provedení technického řešení představuje jednu z možností realizace trubkové sestavy pro vložkování spalinových cest, tak jak je znázorněna na obr. 1 až 2.The described exemplary embodiment of the technical solution represents one of the possibilities of realizing a pipe assembly for lining flue gas paths, as shown in Figs. 1 to 2.

Trubková sestava 1 pro vložkování spalinových cest s možností napojení na spalinový vývod kotle je tvořena základní vložkovací trubkou 2, která sestává z rovného trubkového úseku 3, jednostranně zakončeného nasouvacím hrdlem 4 a z rovného trubkového úseku 3, který je opatřen nejméně jedním bočním otvorem 5 olemovaným boční přírubou 6, která má vnitřní závit 7, do něhož je, prostřednictvím vnějšího závitu 8, nacházejícím se na konci redukční přípojní trubice 9, tato našroubována do boční příruby 6. Redukční přípojní trubice 9 je napojená na zdroj spalin. Redukční přípojní trubice 9 je k rovnému trubkovému úseku 3 základní vložkovací trubky 2 napojena pod úhlem B v rozmezí 85 až 95°. Vnitřek nasouvacího hrdla 4 základní vložkovací trubky 2 je opatřen kruhovým těsněním 10. Mezi boční přírubu 6 a redukční přípojní trubici 9 je vložen těsnící kroužek 11.The pipe assembly 1 for lining the flue gas ducts with the possibility of connection to the flue gas outlet of the boiler is formed by a basic lining pipe 2, which consists of a straight pipe section 3 terminated on one side by a plug-in neck 4 and a straight pipe section 3 provided with at least one side opening 5 a flange 6 having an internal thread 7 into which, by means of an external thread 8 located at the end of the reduction connecting tube 9, it is screwed into the side flange 6. The reduction connecting tube 9 is connected to a flue gas source. The reducing connection tube 9 is connected to the straight pipe section 3 of the base liner 2 at an angle B in the range of 85 to 95 °. The inside of the plug-in neck 4 of the base liner 2 is provided with an annular seal 10. A sealing ring 11 is inserted between the side flange 6 and the reduction connecting tube 9.

Jednotlivé základní vložkovací trubky 2 se, při vložkování spalinové cesty, spouštějí do stávající spalinové cesty a prostřednictvím zasunutí do nasouvacího hrdla 4 napojují na sebe. Vnitřek nasouvacího hrdla 4 je opatřen kruhovým těsněním 10. které zamezuje úniku spalin mimo spalinovou cestu. Vhodnou úpravou délky rovných trubkových úseků 3 je možno přesně definovat polohu bočního otvoru 5, respektive boční příruby 6 vůči existujícímu otvoru pro napojení tak, aby nebyly potřebné stavební zásahy. Vlastní připojení na zdroj spalin se realizuje redukční přípojní trubicí 9, která jek rovnému trubkovému úseku 3 základní vložkovací trubky 2 napojena našroubováním do boční příruby 6, a to pod úhlem B v rozmezí 85 až 95°, což umožňuje optimální proudění spalin. Mezi boční přírubu 6 a redukční přípojní trubici 9 je vložen těsnící kroužek 11. Toto technické řešení umožňuje bezproblémové napojení více zdrojů spalin na jednu vertikální spalinovou cestu představovanou základními vložkovacími trubkami 2 s napojenými redukčními přípojnými trubicemi 9.The individual basic insertion pipes 2, when inserting the flue gas path, are lowered into the existing flue gas path and connected to one another by being inserted into the plug-in neck 4. The inside of the plug-in neck 4 is provided with a circular seal 10, which prevents the escape of flue gases outside the flue gas path. By suitable adjustment of the length of the straight pipe sections 3, it is possible to precisely define the position of the side opening 5 or the side flange 6 relative to the existing connection opening so that no construction work is required. The actual connection to the flue gas source is realized by a reducing connection pipe 9, which is connected to the straight pipe section 3 of the base liner 2 by screwing into the side flange 6 at an angle B in the range of 85 to 95 °, which allows optimal flue gas flow. A sealing ring 11 is inserted between the side flange 6 and the reduction connection tube 9. This technical solution enables the seamless connection of several flue gas sources to one vertical flue gas path represented by the basic insertion pipes 2 with the reduction connection pipes 9 connected.

-2 CZ 34402 UI-2 CZ 34402 UI

Průmyslová využitelnostIndustrial applicability

Trubková sestava pro vložkování spalinových cest s možností napojení na spalinový vývod kotle, je vhodná pro renovaci prakticky všech druhů spalinových cest a komínů.Pipe assembly for lining flue gas ducts with the possibility of connection to the flue gas outlet of the boiler, is suitable for the renovation of practically all types of flue gas ducts and chimneys.

Claims (4)

NÁROKY NA OCHRANUCLAIMS FOR PROTECTION 1. Trubková sestava (1) pro vložkování spalinových cest s možností napojení na spalinový vývod kotle, vyznačující se tím, že je tvořena základní vložkovací trubkou (2), sestávající z rovného trubkového úseku (3) jednostranně zakončeného nasouvacím hrdlem (4), přičemž rovný trubkový úsek (3) je opatřen nejméně jedním bočním otvorem (5) olemovaným boční přírubou (6) s vnitřním závitem (7), do níž je, prostřednictvím vnějšího závitu (8), našroubována redukční přípojní trubice (9), napojená na zdroj spalin.A pipe assembly (1) for lining flue gas ducts with the possibility of connection to the flue gas outlet of a boiler, characterized in that it is formed by a basic lining pipe (2) consisting of a straight pipe section (3) terminated on one side by a plug-in neck (4), the straight pipe section (3) is provided with at least one side opening (5) bordered by a side flange (6) with an internal thread (7), into which, by means of an external thread (8), a reduction connecting pipe (9) is screwed, connected to the source flue. 2. 2. Trubková sestava (1) pro vložkování spalinových cest podle nároku 1, vyznačující se tím, že redukční přípojní trubice (9) je k rovnému trubkovému úseku (3) základní vložkovací trubky (2) napojena pod úhlem napojení (B) v rozmezí 85 až 95°.Pipe assembly (1) for lining flue gas ducts according to Claim 1, characterized in that the reducing connection pipe (9) is connected to the straight pipe section (3) of the base lining pipe (2) at a connection angle (B) of range 85 to 95 °. 3. Trubková sestava (1) pro vložkování spalinových cest podle nároku 1, vyznačující se tím, že vnitřek nasouvacího hrdla (4) základní vložkovací trubky (2) je opatřen kruhovým těsněním (10).Pipe assembly (1) for lining flue gas ducts according to Claim 1, characterized in that the interior of the plug-in neck (4) of the base lining pipe (2) is provided with an annular seal (10). 4. Trubková sestava (1) pro vložkování spalinových cest podle nároku 1 a 2, vyznačující se tím, že mezi boční přírubu (6) a redukční přípojní trubici (9) je vložen těsnící kroužek (11).Pipe assembly (1) for lining flue gas ducts according to Claims 1 and 2, characterized in that a sealing ring (11) is inserted between the side flange (6) and the reduction connecting tube (9).
CZ2020-37863U 2020-08-10 2020-08-10 Pipe assembly for flue gas lining CZ34402U1 (en)

Priority Applications (6)

Application Number Priority Date Filing Date Title
CZ2020-37863U CZ34402U1 (en) 2020-08-10 2020-08-10 Pipe assembly for flue gas lining
PCT/CZ2021/000038 WO2022033613A1 (en) 2020-08-10 2021-08-04 Pipe assembly for lining flue gas paths
SK50004-2023U SK9807Y1 (en) 2020-08-10 2021-08-04 Pipe assembly for lining flue gas paths
PL131250U PL131250U1 (en) 2020-08-10 2021-08-04 Pipe assembly for laying the flue gas path
DE212021000439.3U DE212021000439U1 (en) 2020-08-10 2021-08-04 Pipe assembly for lining the flue gas duct
HUU2300046U HU5676U (en) 2020-08-10 2021-08-04 Pipe assembly for lining flue gas paths

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CZ2020-37863U CZ34402U1 (en) 2020-08-10 2020-08-10 Pipe assembly for flue gas lining

Publications (1)

Publication Number Publication Date
CZ34402U1 true CZ34402U1 (en) 2020-09-22

Family

ID=72614767

Family Applications (1)

Application Number Title Priority Date Filing Date
CZ2020-37863U CZ34402U1 (en) 2020-08-10 2020-08-10 Pipe assembly for flue gas lining

Country Status (6)

Country Link
CZ (1) CZ34402U1 (en)
DE (1) DE212021000439U1 (en)
HU (1) HU5676U (en)
PL (1) PL131250U1 (en)
SK (1) SK9807Y1 (en)
WO (1) WO2022033613A1 (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU3619378A (en) * 1977-04-22 1979-11-22 Kemp & Co Pty Ltd Side branch insertion in pipes
NL1016246C2 (en) * 2000-09-22 2002-03-25 Interactive Bouwprodukten B V Tubing system for passing flue gases.
US7055865B2 (en) * 2003-10-23 2006-06-06 The Harrington Corporation Lateral connection system
US20160327190A1 (en) * 2015-05-06 2016-11-10 Mei-Pin Hsing Oxygen sensor seat structure
CN107401648A (en) * 2017-07-21 2017-11-28 江苏易元新材料科技有限公司 A kind of easy-to-maintain threeway

Also Published As

Publication number Publication date
PL131250U1 (en) 2023-07-17
HU5676U (en) 2023-11-28
SK9807Y1 (en) 2023-07-26
SK500042023U1 (en) 2023-03-29
DE212021000439U1 (en) 2023-04-13
WO2022033613A1 (en) 2022-02-17

Similar Documents

Publication Publication Date Title
BRPI0416425A (en) fixing of well casings
US6976712B2 (en) Corrosion-resistant coupling means and methods for using same
BRPI0509112A (en) angled locking connector
CZ34402U1 (en) Pipe assembly for flue gas lining
JP2022055366A (en) Pipe liner end termination
PT2083203E (en) Screwed fitting for metal corrugated pipes
US9022429B2 (en) Pipe reduction piece made from plastic material
PL202243B1 (en) Impervious connection system for chimneys and pre-fabricated modular conduits
CZ281099A3 (en) Device for tight connection of a pipe with sewer pipe, particularly with thin-walled sewer pipe
ITUD940195A1 (en) COMBINATION OF A FLEXIBLE HOSE FOR AIR AND A CONNECTION NOZZLE AND CONNECTION NOZZLE FOR THIS
CZ29629U1 (en) Angle pipe especially for lined flue gas conduits
EP2054658B1 (en) Composable pipework having a plurality of modular tubular ducts
EP2682660B1 (en) Conical fitting for metal sheet pipes
EP1969276B1 (en) Modular tubular element
RU2008121825A (en) SECTION RADIATOR
CA3088799A1 (en) Plug connection between two tubular workpieces made of concrete, each workpiece having an inner liner made of plastic
JP7147474B2 (en) conversion plug
ITMI970430A1 (en) FITTING FOR FLUID SHUT-OFF VALVES WITH INTERNAL ROTATING DIVERTER ELEMENT FOR MAINTAINING THE DIRECTION OF THE
KR200216870Y1 (en) ball valve for pipe with different diameter
CZ123098A3 (en) T-shaped part of a pipeline
US20150369481A1 (en) Chimney pipe, exhaust gas system and method for producing an exhaust gas system having such a chimney pipe
ITBO20010689A1 (en) CONNECTION MODULE FOR SMOKE RODS
JP7022382B2 (en) Resin cheese fittings
ITBS20030054U1 (en) JUNCTION JOINT FOR MULTILAYER PIPES
JP2020173016A (en) Pipe joint with loose flange

Legal Events

Date Code Title Description
FG1K Utility model registered

Effective date: 20200922