CN87105991A - 高炉 - Google Patents

高炉 Download PDF

Info

Publication number
CN87105991A
CN87105991A CN87105991.6A CN87105991A CN87105991A CN 87105991 A CN87105991 A CN 87105991A CN 87105991 A CN87105991 A CN 87105991A CN 87105991 A CN87105991 A CN 87105991A
Authority
CN
China
Prior art keywords
blast furnace
gas
preheating gas
preheating
import
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN87105991.6A
Other languages
English (en)
Other versions
CN1007161B (zh
Inventor
大野阳太郎
堀田裕久
胁元一致
川田仁
辻本一彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP30913386A external-priority patent/JPH0619090B2/ja
Priority claimed from JP62000222A external-priority patent/JPS63169312A/ja
Priority claimed from JP62001853A external-priority patent/JPS63171815A/ja
Application filed by NKK Corp filed Critical NKK Corp
Publication of CN87105991A publication Critical patent/CN87105991A/zh
Publication of CN1007161B publication Critical patent/CN1007161B/zh
Expired legal-status Critical Current

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B5/00Making pig-iron in the blast furnace

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)
  • Manufacture Of Iron (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
  • Furnace Details (AREA)

Abstract

一高炉包括:一高炉炉体:位于高炉炉体下部的风口,通过这些风口向炉内鼓送氧气体积占40%或者更多的气体:以及位于高炉炉体料线之下0.15至0.60范围内的预热气体进口,而料线和风口端高度之间的距离为1。预热气体进口设置在高炉炉体的一个或若干高度上,其与水平线之间的向下斜角为20°至50°以便向炉内鼓送预热气体。预热气体进口装有燃烧器,燃烧器上装有燃气源导管,氧气源导管和控制预热气体温度的气体导管。

Description

本发明涉及炼铁高炉,更具体来说,涉及预热加入高炉中的炉料的预热气体的鼓风。
在用铁矿冶炼生铁的传统高炉作业中,热空气流几乎无例外地靠从风口鼓风。占鼓风气流成分79%的氮气虽然不参与还原,但是有助于向高炉平面和料线之间堆积的炉料提供大量热量以加速气体的还原。换言之,氮气对作为还原剂和热源的焦碳具有补充供热的作用。因此,它对预热高炉炉身上部中的炉料特别有效,所以不再需要预热炉料的热源。
最近,为了提高高炉的生产率,或者为了利用炉顶煤气原料合成化工产品,已有人提出了各种高炉作业的方法,其中通过风口鼓风的气流都主要由氧气组成。例如,已公开的日本专利申请159104/85号中公开的一种方法,包括以下步骤:
1.把主要由铁矿和焦碳组成的炉料通过高炉炉顶装入高炉;
2.通过高炉风口鼓入纯氧气,粉煤以及控温的气体以防止在风口端上升至火焰温度;
3.通过高炉的一中间层鼓入基本不含氮气的预热气体以预热炉料;以及
4.借助鼓入的纯氧气,炉料中含有的焦碳燃烧以便使铁矿石熔化和还原,并且从炉顶产生基本不含氮气的高炉煤气。
但是,这种方法难于长期维持低燃料比的高炉作业。
本发明的目的是提供一种高炉,它能够长期维持低燃料比的高炉作业。
为了实现这一目的,按照本发明的高炉包括:
一高炉炉体;
在高炉炉体下部的风口,通过这些风口鼓入氧气体积占40%或者更高的气体;以及
在料线之下0.15至0.60的预热气体进口,料线和风口端的距离等于1.0。
本发明的此目的和其它目的和优点将结合以下附图作更为详细的说明。
图1是本发明高炉的垂直剖视图;
图2是沿图1Ⅱ-Ⅱ线的本发明高炉的水平端视图;
图3是表明本发明高炉的预热气体进口的相对位置与燃料比的关系的图表;
图4是表明预热气体进口的相对位置与熔融铁中含硅量的关系的图表;以及
图5是本发明的燃烧器的剖视图。
现在对照图1说明按照本发明的高炉的一个实施例。
图1是本发明高炉的一垂直剖视图。把含有铁矿石、焦碳和助熔剂的炉料装入高炉,堆到预定的料线14的高度。风口12位于高炉炉体11上。通过风口12,向高炉中鼓送氧气体积占40%或更高的气体,粉煤和火焰温度控制剂。预热气体进口13位于料线之下0.50的高度,料线至风口高度的距离为1.0。16个预热气体进口构成同一高度上的预热气体进口组,预热气体进口具有一个与水平线成25°角的向下的斜度,通过这些进口13,向高炉中鼓送预热气体以便预热炉料。因此,鼓入的氧气体积占40%或更高的气体使焦碳和粉煤很好地燃烧,由于产生高温的还原气体,铁矿石被熔化并还原成生铁和炉渣。图2是沿图1剖面线Ⅱ-Ⅱ的水平端视图。16个进口13在圆周上等距布置。
在此实施例中,预热气体进口的位置在料线之下0.50的高度上,料线和风口端之间的距离为1.0。但是,这个位置也可以设在料线之下0.15至0.60的范围内。这一位置范围最好是在料线之下0.30至0.55。
现在说明限制这一位置范围的原因。
图3是表明本发明的预热气体进口13的相对位置与燃料比的关系的图表。图中横坐标表示当料线和风口端之间的距离为1.0时,从料线到预热气体进口的位置为某一距离时的燃料比。图4是表明预热气体进口13的相对位置与熔融铁中含硅量的关系的图表。与图3相似,图4的横坐标表示当料线和风口端之间的距离为1.0时,从料线到预热气体进口的位置为某一距离时的熔融铁中的含硅量。
如图3所示,当料线和风口端之间的距离为1.0时,在从料线之下0.15至0.60的范围内,燃料比较低,在每吨熔融生铁500至600公斤的范围内(500-600Kg/ton),另外,生产故障也少。如果预热气体进口设在离料线少于0.15的位置上,当高炉在燃料比为每吨熔融铁650公斤或更低时作业,就会发生熔融铁温度降低或损坏磨耗板(Wearing    plate)的问题。如果预热气体进口离料线的距离超过0.60,会产生熔融铁温度降低或挂料现象。当预热气体进口离料线的距离小于0.15或大于0.60时,除非高炉在燃料比为每吨熔融铁700吨以上时,就不可能长期维持稳定的高炉作业。
如图4所示,当预热气体进口设在料线之下0.15至0.60的范围时,熔融铁中含硅量几乎下降到0.30(重量)%或者更少。这对高炉作业是十分有利的,因为这样就不需要在出铁后进行脱硅了。
预热空气进口的位置最好在料线之下0.33至0.55的范围内。在这一范围内,不仅燃料比而且熔融铁中含硅量都会进一步下降。
如上所述,由于对预热气体进口位置的范围进行了限制,就可以降低燃料比,防止生产故障,并可生产低硅熔融生铁。
利用位于高炉炉身中部的探针测量炉料或者气体的温度,在此基础上鼓入预热气体。预热气体是通过处在同一高度上的进口,或者是通过处在不同高度上的进口鼓送的。在通过若干高度上的进口鼓风时,设置在炉壁圆周的每一高度上的预热气体进口划分为若干区组,因此,如果在同一区中上下分布的上组和下组间气体量、气体温度同时变化,那么就比单一高度上的进口鼓风预热效果要好得多。在采用若干高度上的进口鼓送预热气体时,进口布置的设计最好使每一高度的气量或气温可以改变,或者使同一高度相邻进口之间的气量或气温可以改变。有了这样的设计,就可以实施最佳控制。另外,在采用若干高度上的进口鼓送预热气体时,上下层上的每一进口最好平行交错布置以便气体沿着炉壁圆周均匀向上吹送。
当鼓送相同量气体而不变其温度时,高温预热气体最好通过从一环形管分支的若干支管鼓送。各高度的预热气体进口并不专门限制其数量,但是最好为8至18个,以便在料线高度附近使气体成分及靠近炉壁处温度接近均匀一致。而且,不同高度的预热气体进口最好分成1至4层。
高炉炉体中的预热气体进口的下斜角度最好大于炉料堆放角度。这是因为要防止炉料的粉粒堵塞预热气体进口。在炉体中的预热气体进口的下斜相对于水平线的角度最好在20°至50°的范围。如果这个下斜角度小于20°,炉料的粉粒就会堵塞预热气体进口。另一方面,考虑到炉料的堆放角最多在45°至50°之间,这个下斜角度大于50°也没有用处。另外,由于下斜角度加大,预热气体进口的孔也变大,鉴于炉体的保护,大于50°的下斜角度也是不符合要求的。
预热气体制备方法有两种要加以考虑。
一种方法是利用高炉的炉顶煤气加氧气在高炉附近的燃烧炉中产生。在实施这种方法时,为了向高炉中均匀地鼓送预热气体,建议把热风导管向上通到炉身的高度,然后与耐火的重型环形管相接,环形管通过许多支管与每个预热气体进口相接。
另一种方法是,在向高炉鼓送预热气体的进口处设置气体燃烧器,气体燃烧器带有一燃气源导管,一氧气源导管和一气体温度控制气源导管。通过控制燃气量和氧气量的方法使每个气体燃烧器都可实现温度和预热风量的独立控制。通往燃烧器的那些导管不必是耐火的。这种方法与从大型燃烧炉传送预热气体的第一种方法的不同之处在于:在每个预热气体进口都设置一燃烧器,因而在每个预热气体进口都可自由方便地控制风温和风量。而且,在高炉炉身上无需铺设重型的环形热风管。在冶炼中可根据高炉状况迅速进行控制。
图5是本发明使用的燃烧器的粗略剖视图。燃气源导管21和氧气源导管22都与燃烧器本体28相连接,其连接方式使得气流量可以自由地控制。导燃器29设置在氧气喷出的部位。燃烧器本体外包有铁板壳。气体源导管25也与燃烧器本体28相接以便自由控制燃烧器产生的气体的温度。冷却水管由进水管23和排水管24组成。

Claims (6)

1、一高炉包括:
一高炉炉体;
位于高炉炉体下部一组风口,通过这些风口向炉内鼓送氧气体积占40%或更高的气体;以及
位于高炉炉体料线之下0.15至0.60范围内的若干预热气体进口,而料线和风口端高度之间的距离等于1。
2、按照权利要求1所述的高炉,其特征在于:该预热气体进口设置在料线之下0.30至0.55的范围内。
3、按照权利要求1所述的高炉,其特征在于:该预热气体进口设置在高炉炉体的同一高度上。
4、按照权利要求1所述的高炉,其特征在于:该预热气体进口设置在高炉炉体的二个或二个以上的不同高度。
5、按照权利要求1所述的高炉,其特征在于:该预热气体进口在垂直面内与水平线之间形成的斜角为20°至50°。
6、按照权利要求1所述的高炉,其特征在于:该预热气体进口上装有气体燃烧器,该燃烧器上装有燃气源导管,氧气源导管和控制预热气体温度的气体导管。
CN87105991A 1986-12-27 1987-12-26 高炉 Expired CN1007161B (zh)

Applications Claiming Priority (6)

Application Number Priority Date Filing Date Title
JP309133/86 1986-12-27
JP30913386A JPH0619090B2 (ja) 1986-12-27 1986-12-27 酸素高炉
JP62000222A JPS63169312A (ja) 1987-01-06 1987-01-06 酸素高炉の構造
JP222/87 1987-01-06
JP1853/87 1987-01-09
JP62001853A JPS63171815A (ja) 1987-01-09 1987-01-09 酸素高炉

Publications (2)

Publication Number Publication Date
CN87105991A true CN87105991A (zh) 1988-07-27
CN1007161B CN1007161B (zh) 1990-03-14

Family

ID=27274356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN87105991A Expired CN1007161B (zh) 1986-12-27 1987-12-26 高炉

Country Status (5)

Country Link
EP (1) EP0273420B1 (zh)
KR (1) KR930004473B1 (zh)
CN (1) CN1007161B (zh)
AU (1) AU596253B2 (zh)
DE (1) DE3787518T2 (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102414328A (zh) * 2009-04-30 2012-04-11 杰富意钢铁株式会社 高炉操作方法
CN102449173A (zh) * 2009-05-29 2012-05-09 杰富意钢铁株式会社 高炉操作方法

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4844737A (en) * 1986-12-27 1989-07-04 Nippon Kokan Kabushiki Kaisha Method for operating a blast furnance by blowing pulverized coal
KR100826963B1 (ko) * 2001-11-13 2008-05-02 주식회사 포스코 고로 노심온도 관리 방법
CN114134271B (zh) * 2021-12-03 2022-12-06 昌黎县兴国精密机件有限公司 一种高炉低碳冶炼的喷吹调控装置及方法

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE763817C (de) * 1939-03-21 1954-07-12 Thyssen Sche Gas U Wasserwerke Verfahren zum Verhuetten von mit festem Brennstoff und Zuschlaegen vermischten Eisenerzen im Hochofen
DE743376C (de) * 1939-05-20 1944-01-11 Roechlingsche Eisen & Stahl Verfahren zur Verhuettung von Eisenerzen
FR869065A (fr) * 1940-01-13 1942-01-23 Lindes Eismaschinen Ag Procédé de traitement de minerai
CH254586A (de) * 1947-01-17 1948-05-15 Von Roll Ag Verfahren und Ofen zum Verhütten von Eisenerz mit einem an Sauerstoff angereicherten Wind.
US2593257A (en) * 1948-08-26 1952-04-15 Standard Oil Dev Co Blast furnace operation
GB668218A (en) * 1948-12-14 1952-03-12 Bleloch William Improvements in the smelting of metallic oxides in a blast furnace
GB674546A (en) * 1949-05-19 1952-06-25 Ruhrgas Ag Process for the simultaneous production of metals and rich gas
US3423080A (en) * 1963-11-06 1969-01-21 Interlake Steel Corp Electric arc furnace
US3364009A (en) * 1964-03-12 1968-01-16 Kemmetmuller Roland Method for the production of iron and steel
FR2156456A1 (en) * 1971-10-20 1973-06-01 Nippon Kokan Kk Blast furnace combined operation - by blowing a reducing gas and an oxygen enriched flux
BE817647R (fr) * 1974-07-15 1974-11-04 Bruleur reducteur de haut fourneau ou toutes autres utilisations calorifiques reductrices
US4844737A (en) * 1986-12-27 1989-07-04 Nippon Kokan Kabushiki Kaisha Method for operating a blast furnance by blowing pulverized coal

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102414328A (zh) * 2009-04-30 2012-04-11 杰富意钢铁株式会社 高炉操作方法
CN102414328B (zh) * 2009-04-30 2014-03-05 杰富意钢铁株式会社 高炉操作方法
CN102449173A (zh) * 2009-05-29 2012-05-09 杰富意钢铁株式会社 高炉操作方法
CN104878140A (zh) * 2009-05-29 2015-09-02 杰富意钢铁株式会社 高炉操作方法

Also Published As

Publication number Publication date
KR930004473B1 (ko) 1993-05-27
EP0273420B1 (en) 1993-09-22
DE3787518D1 (de) 1993-10-28
CN1007161B (zh) 1990-03-14
DE3787518T2 (de) 1994-03-10
EP0273420A3 (en) 1988-08-03
AU596253B2 (en) 1990-04-26
EP0273420A2 (en) 1988-07-06
AU8294687A (en) 1988-06-30
KR880007746A (ko) 1988-08-29

Similar Documents

Publication Publication Date Title
CN1037528C (zh) 转炉炼铁法
CN1317398C (zh) 直接熔炼工艺的启动方法
CN102433450A (zh) 富氧侧吹还原熔池熔炼炉及其富锡复杂物料炼锡方法
CN87105991A (zh) 高炉
CN1231601C (zh) 制造液态生铁的工艺方法
CN104630411A (zh) 一种qdf电炉炼钢工艺
CN204752780U (zh) 熔融还原炼铁装置
CN100336915C (zh) 含碳铁团块生产铁水的熔融还原炼铁法
CN106766971B (zh) 能处理含铅二次物料的富氧侧吹强化熔炼炉
CN1017628B (zh) 用煤粉和铁矿粉直接冶炼铁水的方法及装置
JP2881840B2 (ja) 高炉羽口粉体吹き込み方法
CN206572975U (zh) 能高效处理含铅二次物料的富氧侧吹强化熔炼炉
US6235080B1 (en) Charging device for directly charging reduced fine iron ore into melter-gasifier
CN1435500A (zh) 一种用粉矿冷固结球团冶炼含铬铁水的方法
CN115323101B (zh) 一种转炉氧枪快速打火的方法
RU2151197C1 (ru) Способ выплавки чугуна и агрегат для его осуществления
CN1014432B (zh) 熔融还原铁矿石生产生铁的方法
JPH0130888B2 (zh)
JPS6043403B2 (ja) 微粉炭吹込みによる高炉操炉方法
SU1235897A1 (ru) Способ ведени доменной плавки
US2832681A (en) Blast furnace and heater combination
CN1353201A (zh) 铁矿还原熔融电弧炼钢炉及其工艺
CN2173380Y (zh) 烧结机用纯高炉煤气点火器
CN116904674A (zh) 一种高铝渣条件下高炉快速复风的方法
KR20040056092A (ko) 유동환원공정의 부원료 소성장치 및 방법

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C13 Decision
C14 Grant of patent or utility model
C15 Extension of patent right duration from 15 to 20 years for appl. with date before 31.12.1992 and still valid on 11.12.2001 (patent law change 1993)
C19 Lapse of patent right due to non-payment of the annual fee