anchor cable
shed ding
ding support
joist
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200520074278
Other languages
English (en)
Inventor
谢文兵
荆升国
赵晨光
郑百生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200520074278 priority Critical patent/CN2839560Y/zh
Application granted granted Critical
Publication of CN2839560Y publication Critical patent/CN2839560Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型涉及采矿工程、岩土工程施工中巷道岩面支护的装置,具体说是将现有的锚索支护和棚式支护相互不干涉的两种支护通过一根锚索托梁连接在一起形成耦合一体化支护。其优点是提高棚式支护的承载能力和护表能力。

Description

锚索支护与棚式支护耦合一体化装置
                        技术领域
本实用新型涉及一种采矿工程中岩土工程巷道岩石壁支护装置,具体讲是将原有相互不干涉的棚护支护与锚索支护相耦合为一体化支护的装置。
                        背景技术
目前采矿工程,岩土工程施工中采用的锚索支护和棚式支护都是单体使用,互不干涉。其中锚索支护的每一只锚索所支护的岩壁面积很有限,由于岩石的结构和施工成本的因素,决定锚索又不可能加的过密;棚护支护由于棚护梁的长度较长,梁的抗弯力与梁的长度平方数成反比,故其支护承载能力差。棚式支护中的拱形支护,如U型钢支护,现有施工工艺决定了棚式支护的实际承载结构模型为可动绞支座二绞拱模型,其支架稳定性较差。为了提高支架的稳定性,对现有梁支护拱形支护进行结构补偿,一般采用补打锚索,但由于锚索与棚式支护没有耦合为一体,故锚索对棚式支护的结构补偿能力差,难以共同承载岩壁的作用力而有效地阻挡巷道壁岩石的位移和脱落。
                        发明内容
本实用新型的目的是提供一种锚索支护与棚式支护耦合一体化装置,它将锚索支护和棚式支护两者相互连接而成耦合一体化支护。
为了解决上述技术问题,本实用新型的技术方案是:一种锚索支护与棚式支护耦合一体化装置,包括棚体梁,其特征是在棚式支护两根相邻的棚体梁靠岩石的一面与棚体梁相垂直安装一根锚索托梁,锚索托梁的内侧孔中安装锚索锁头及锚索,使锚索与棚体梁耦合成一体。
本实用新型的积极效果是,利用锚索托梁将锚索支护和棚式支护耦合一体共同承载,由于锚索的主动支护作用力发挥在岩石深部稳定体上,通过耦合作用大大提高棚式支护的承载能力,有效发挥棚式支护的护表能力。锚索托梁由高强度钢带制成,长度短,不仅成本低,装卸运输、安装方便,而且其惯性矩和抗弯能力强,因而对棚式支柱的耦合力很大,支护补偿能力强。由于锚索托梁安装在棚体梁的外侧,不占用巷道的净断面;同时棚体梁有一定的厚度,又解决了锚索锁头外露带来的巷道施工的安全稳患。
                        附图说明
下面结合附图及实施例对本实用新型进一步详细说明。
图1为锚索支护与棚式支护耦合一体化装置的结构示意图;
图2为图1的俯视图。
图中:1、棚体梁,2、锚索托梁,3、夹板,4、螺钉螺母,5、锚索锁头,6、锚索。
                        具体实施方式
图1、图2所示的锚索托梁2垂直安装在棚式支护两只相邻的棚体梁1的外侧,即靠近岩壁的一侧,用夹板3将锚索托梁与棚体梁夹住,并用螺钉螺母4将二者固定牢固。锚索托梁2内侧即靠近巷道的一侧,中部孔中安装锚索锁头5和锚索6,这样就将锚索与棚体梁耦合成一体,其同承载。由于锚索的主动支护作用力发挥在岩石深部稳定体上,作用力极大,通过锚索托梁将作用力传递给棚体梁,从而大大提高了棚式支护的承载能力,同时扩大了两单体支护的护表面积。
锚索托梁一般使用16M高程度钢带式型钢制作,长度一般在一米左右,故其惯性矩和抗弯能力较高,耦合力和补偿力比目前使用的槽钢梁长度短,体积小,成本低,便于装卸、运输,安装拆卸。
锚索锁头6安装在锚索托梁2的内侧,锚索托梁2安装在棚体梁1的外侧,这样的结构,锚索托梁2不占用巷道面积,又避免了锚索锁头外露过多造成巷道施工带来的安全隐患。

Claims (2)

1、一种锚索支护与棚式支护耦合一体化装置,包括棚体梁(1),其特征是在棚式支护两根相邻的棚体梁(1)靠岩石的一面与棚体梁(1)相垂直固定安装一根锚索托梁(2),锚索托梁的内侧孔中安装锚索锁头(5)及锚索(6),使锚索(6)与棚体梁耦合成一体。
2、根据权利要求1所述的一种锚索支护与棚式支护耦合一体化装置,其特征是棚体梁(1)与托梁(2)用V形夹板(3)和螺钉螺母(4)固定连接。
CN 200520074278 2005-08-03 2005-08-03 锚索支护与棚式支护耦合一体化装置 Expired - Fee Related CN2839560Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520074278 CN2839560Y (zh) 2005-08-03 2005-08-03 锚索支护与棚式支护耦合一体化装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520074278 CN2839560Y (zh) 2005-08-03 2005-08-03 锚索支护与棚式支护耦合一体化装置

Publications (1)

Publication Number Publication Date
CN2839560Y true CN2839560Y (zh) 2006-11-22

Family

ID=37427544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520074278 Expired - Fee Related CN2839560Y (zh) 2005-08-03 2005-08-03 锚索支护与棚式支护耦合一体化装置

Country Status (1)

Country Link
CN (1) CN2839560Y (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182484A (zh) * 2011-05-06 2011-09-14 中钢集团马鞍山矿山研究院有限公司 地下矿山开采的锚竹联合支护方法
CN102226407A (zh) * 2011-05-23 2011-10-26 中铁二院工程集团有限责任公司 四线大跨隧道索拱联合初期支护构造
CN102345463A (zh) * 2011-10-19 2012-02-08 中交第一公路工程局有限公司 一种城市敏感区大跨浅埋暗挖隧道支护结构
CN102518459A (zh) * 2011-12-15 2012-06-27 湖南科技大学 一种深井煤巷用高强度可自动让压的锚索槽钢梁

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182484A (zh) * 2011-05-06 2011-09-14 中钢集团马鞍山矿山研究院有限公司 地下矿山开采的锚竹联合支护方法
CN102182484B (zh) * 2011-05-06 2013-10-09 中钢集团马鞍山矿山研究院有限公司 地下矿山开采的锚竹联合支护方法
CN102226407A (zh) * 2011-05-23 2011-10-26 中铁二院工程集团有限责任公司 四线大跨隧道索拱联合初期支护构造
CN102345463A (zh) * 2011-10-19 2012-02-08 中交第一公路工程局有限公司 一种城市敏感区大跨浅埋暗挖隧道支护结构
CN102518459A (zh) * 2011-12-15 2012-06-27 湖南科技大学 一种深井煤巷用高强度可自动让压的锚索槽钢梁
CN102518459B (zh) * 2011-12-15 2014-04-30 湖南科技大学 一种深井煤巷用高强度可自动让压的锚索槽钢梁

Similar Documents

Publication Publication Date Title
CN2839560Y (zh) 锚索支护与棚式支护耦合一体化装置
CN104563578A (zh) 用于500kV变电站的组合式构架柱及其安装方法
CN101812845A (zh) 高陡坡中小型水电站混凝土垂直输送系统
CN207260727U (zh) 一种组合式输电钢管塔
CN209413342U (zh) 一种具有稳定连接结构的电梯框架
CN208827813U (zh) 一种索道托力装置
CN200943505Y (zh) 一种防松复合托盘
CN215925647U (zh) 一种用于塔扣合一的拱肋扣索锚固梁
CN214116253U (zh) 一种傍山渠道的加固装置
CN213015701U (zh) 一种气膜连接钢索滑轮组件
CN101439827B (zh) 弧形可转向索鞍
CN209723244U (zh) 一种门梁与抗风柱的连接结构
CN201125534Y (zh) 预应力束拉板式弯起器
CN204402097U (zh) 用于500kV变电站出线、进线、过渡的集成式构架
CN209618732U (zh) 轻重塔吊转换节
CN102654059A (zh) 连体式让压锚杆体系
CN2731106Y (zh) 锚壳喷支护体系
CN104563554A (zh) 用于500kV变电站集成式构架的组合式格构梁
CN217712631U (zh) 一种矿用球形锚索锚具
CN219802189U (zh) 一种配重式柔性光伏支架
CN104533115A (zh) 用于500kV变电站出线、进线、过渡的集成式构架
CN219860084U (zh) 一种预制弧形构件的脱模吊架
CN220067316U (zh) 高适用性柔性光伏支架
CN200961484Y (zh) 一种外置式锚索与棚式支护耦合装置
CN216379730U (zh) 挖掘机行走架及挖掘机

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA MINING UNIV.

Free format text: FORMER OWNER: XIE WENBING; PATENTEE

Effective date: 20070413

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20070413

Address after: 221000 Zhai mountain, southern suburbs of Jiangsu City, Xuzhou Province

Patentee after: China University of Mining & Technology

Address before: 221000 School of energy and safety engineering, China University of Mining and Technology, Xuzhou, Jiangsu Province

Co-patentee before: Jing Shengguo

Patentee before: Xie Wenbing

Co-patentee before: Zhao Chenguang

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee