CN2761847Y - Reduced mining area water sump pump room - Google Patents
Reduced mining area water sump pump room Download PDFInfo
- Publication number
- CN2761847Y CN2761847Y CN 200420099476 CN200420099476U CN2761847Y CN 2761847 Y CN2761847 Y CN 2761847Y CN 200420099476 CN200420099476 CN 200420099476 CN 200420099476 U CN200420099476 U CN 200420099476U CN 2761847 Y CN2761847 Y CN 2761847Y
- Authority
- CN
- China
- Prior art keywords
- sump
- water
- well
- mining area
- storehouse
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model relates to a coal mine drainage system, particularly a reduced mining area water sump pump room. The utility model is composed of a left sump (1), a right sump (3), a pump room (4), water absorption wells (2), cleaning inclined drifts (12), a precipitation tank (14), a pipe way (5), etc., wherein the left sump (1) and the right sump (3) are respectively arranged on the left and the right sections of the same drift, the water absorption wells (2) are arranged between the two sections, a water blocking wall is arranged between the two sections and the water absorption wells (2), the bottom part of the water-blocking wall is provided with a water guide pipe (11) and a water valve (13) thereof, the pump room (4) is connected between the water absorption wells (2) and a drift (8) of a mining area vehicle station, the outer ends of the left sump (1) and the right sump (3) are respectively connected with the drift (8) of the mining area vehicle station through the cleaning inclined drifts (12), and the upper end of each of the cleaning inclined drifts (12) is provided with the precipitation tank (14). The mining area water sump pump room carries out intensive placement, omits a guide matching water drift and a water guide hole of the traditional water sump, reduces the numbers of the cleaning inclined drifts and the water absorption wells, reduces two intersections, reduces engineering work load and whole rock engineering work load, avoids the inflected lifting of the cleaning inclined drifts and saves engineering expense.
Description
Affiliated technical field
The utility model relates to Mine Drainage System, particularly a kind ofly is suitable for going down the hill that the exploiting field draining uses is simple, the reduced form mining area sump pump house of saving, centralized arrangement.
Background technology
Traditional mining area sump arrangement form is: inside and outside storehouse arranges that the water guide of joining lane, water guide cave, four cleaning inclined gallery and a plurality of absorbing well, absorption well are arranged.Have that engineering quantity is big, constructional difficulties, long in time limit, dig shortcoming such as inconvenience clearly.Nei Cang, Wai Cang are called again and pay sump, main sump.
Summary of the invention
Existing mining area sump pump house engineering quantity is big in order to overcome, constructional difficulties, dig inconvenient deficiency clearly, the utility model provides a kind of reduced form mining area sump pump house, it changes traditional sump arrangement form, realizes simple, saving, the centralized arrangement of pump house, saves engineering quantity and engineering cost.
The technical scheme that its technical problem that solves the utility model adopts is:
Reduced form mining area sump pump house is made up of Zuo Cang, You Cang, pump house, absorbing well, absorption well, cleaning inclined gallery, sedimentation basin, pipe way etc.Zuo Cang, right storehouse are left and right two sections of same gallery, are absorbing well, absorption wells between two sections; Between the two and the absorbing well, absorption well waterwall is set and separates, aqueduct through walls is installed in the bottom of waterwall, and water valve is installed on the aqueduct.Pump house is connected between absorbing well, absorption well and the tunnel, parking lot, bottom, exploiting field.The suction water pipe of the water pump in the pump house is arranged in absorbing well, absorption well, and the gutter of water pump is through pipe way, the supreme level of district dip.The outer end in Zuo Cang, right storehouse is connected with tunnel, parking lot, bottom, exploiting field through cleaning inclined gallery separately respectively.The cleaning inclined gallery the upper end, promptly with parking lot crossover point place, be provided with sedimentation basin.
The technical scheme that its technical problem that solves the utility model adopts can also be:
The gallery in Qi Zuocang and right storehouse is a straight tunnel or is straight tunnel substantially that it is parallel or substantially parallel with tunnel, parking lot, bottom, exploiting field; Pump house and Zuo Cang, right storehouse are vertical, or vertical substantially.
The utility model compared with prior art has following advantage:
This reduced form mining area sump pump house, the layout that intensifies, that removes traditional sump joins water guide lane, water guide cave, reduced the quantity of cleaning inclined gallery and absorbing well, absorption well, reduced by two crossover points, reduced engineering quantity and total rock engineering quantity, avoided clearing up the inclined gallery lifting of turning round.Under the constant situation of standage, saved engineering cost, have remarkable economic efficiency.
Description of drawings
Fig. 1: the schematic diagram that the utility model reduced form mining area sump pump house is arranged
Fig. 2: the A-A sectional view among Fig. 1
Among the figure: storehouse, a 1-left side, 2-absorbing well, absorption well, the right storehouse of 3-, 4-pump house, 5-pipe way, 6-exploiting field fortune coal are gone down the hill, go down the hill on the track of 7-exploiting field, tunnel, parking lot, bottom, 8-exploiting field, 9-water pump, 10-suction water pipe, 11-aqueduct, 12-cleaning inclined gallery, 13-water valve, 14-sedimentation basin
The specific embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is described in further detail:
Composition and arrangement form at the mining area sump of the utility model reduced form shown in Fig. 1,2 pump house.Mainly form by left storehouse (1), right storehouse (3), pump house (4), absorbing well, absorption well (2), cleaning inclined gallery (12), sedimentation basin (14) and pipe way (5) etc.
Change traditional inside and outside storehouse layout into left storehouse (1), right storehouse (3) layout.Only need tunnel of construction as sump.Along tunnel of construction, coal seam, sump is made for gallery in its middle part, two ends are that inclined gallery are as cleaning inclined gallery (12), sedimentation basin (14) is arranged with crossover point place, parking lot in cleaning inclined gallery (12), arrange pump house (4) in tunnel, parking lot (8) between the absorbing well, absorption well (2), arrange absorbing well, absorption well (2) at gallery and pump house (4) crossover point, absorbing well, absorption well (2) is divided into two sump, become left storehouse (1), (3) two sump in right storehouse, between absorbing well, absorption well (2) and sump waterwall being set separates, waterwall bottom is installed aqueduct through walls (11) and is communicated with, and aqueduct (11) is installed water valve (13), is used for water guide.Go down the hill to arrange pipe way (5) between (6) at pump house (4) and exploiting field fortune coal.The trend of storehouse (1), a left side, right storehouse (3) is straight line substantially, with tunnel, parking lot (8) almost parallel.The direction of pump house (4) and two sump, tunnel, parking lot (8) approximate vertical.
Drainage flow path: mine water enters sump through sedimentation basin (14), cleaning inclined gallery (12), the aqueduct (11) of water between sump and absorbing well, absorption well (2) in the sump enters absorbing well, absorption well (2), water in the absorbing well, absorption well (2) sucks water pump (9) by suction water pipe (10), enter gutter by water pump (9), again by gutter through pump house (4), pipe way (5), exploiting field fortune coal go down the hill (6) sump water is drained into a last level.
Close the water valve (13) of the aqueduct (11) that need not clear up the storehouse during cleaning sump, the water of need being cleared up the storehouse drains, by cleaning inclined gallery (12) mine car cleaning down.
Claims (2)
1. a reduced form mining area sump pump house comprises main sump, pays sump, pump house, absorbing well, absorption well, cleaning inclined gallery, sedimentation basin, pipe way; Main, a pair sump is communicated with absorbing well, absorption well, and main, as to pay sump one or both ends are connected with tunnel, parking lot, bottom, exploiting field through the cleaning inclined gallery; There is sedimentation basin upper end, cleaning inclined gallery; The suction water pipe of the water pump in the pump house is arranged in absorbing well, absorption well, and the gutter of water pump is through pipe way, the supreme level of district dip; It is characterized in that: said main sump, a pair sump are left storehouse (1), right storehouse (3), the two is left and right two sections of same gallery, be absorbing well, absorption well (2) between two sections, between the two and the absorbing well, absorption well (2) waterwall arranged, aqueduct (11) and water valve (13) thereof are arranged at the bottom of waterwall; Pump house (4) is connected between absorbing well, absorption well (2) and the tunnel, parking lot, bottom, exploiting field (8); The outer end of a left side storehouse (1), right storehouse (3) is connected with separately cleaning inclined gallery (12) respectively.
2. reduced form mining area sump pump house according to claim 1 is characterized in that: the gallery of said left storehouse (1), right storehouse (3) is a straight tunnel parallel with tunnel, parking lot, bottom, exploiting field (8); Pump house (4) and left storehouse (1), right storehouse (3) are vertical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200420099476 CN2761847Y (en) | 2004-12-30 | 2004-12-30 | Reduced mining area water sump pump room |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200420099476 CN2761847Y (en) | 2004-12-30 | 2004-12-30 | Reduced mining area water sump pump room |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2761847Y true CN2761847Y (en) | 2006-03-01 |
Family
ID=36094975
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200420099476 Expired - Fee Related CN2761847Y (en) | 2004-12-30 | 2004-12-30 | Reduced mining area water sump pump room |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2761847Y (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102168582A (en) * | 2011-05-12 | 2011-08-31 | 太原钢铁(集团)有限公司 | Drainage method for groundwater in construction of deviated well |
CN104196545A (en) * | 2014-08-08 | 2014-12-10 | 安徽理工大学 | Coal mine auxiliary shaft pipe way structure and construction method thereof |
CN104481586A (en) * | 2014-11-28 | 2015-04-01 | 贵州晨辉达矿业工程设计有限公司 | Press-in type pump room |
CN107448233A (en) * | 2017-09-22 | 2017-12-08 | 淮南矿业(集团)有限责任公司 | A kind of mine water disaster eliminates system and its method for eliminating water damage |
CN107701231A (en) * | 2017-11-17 | 2018-02-16 | 安徽马钢罗河矿业有限责任公司 | A kind of intensive overall structure shaft sump system and its construction method |
CN110939481A (en) * | 2019-12-18 | 2020-03-31 | 临沂矿业集团菏泽煤电有限公司 | Coal mine underground shared water absorption system |
-
2004
- 2004-12-30 CN CN 200420099476 patent/CN2761847Y/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102168582A (en) * | 2011-05-12 | 2011-08-31 | 太原钢铁(集团)有限公司 | Drainage method for groundwater in construction of deviated well |
CN104196545A (en) * | 2014-08-08 | 2014-12-10 | 安徽理工大学 | Coal mine auxiliary shaft pipe way structure and construction method thereof |
CN104196545B (en) * | 2014-08-08 | 2016-04-06 | 安徽理工大学 | A kind of colliery auxiliary shaft pipe way structure and construction method thereof |
CN104481586A (en) * | 2014-11-28 | 2015-04-01 | 贵州晨辉达矿业工程设计有限公司 | Press-in type pump room |
CN107448233A (en) * | 2017-09-22 | 2017-12-08 | 淮南矿业(集团)有限责任公司 | A kind of mine water disaster eliminates system and its method for eliminating water damage |
CN107701231A (en) * | 2017-11-17 | 2018-02-16 | 安徽马钢罗河矿业有限责任公司 | A kind of intensive overall structure shaft sump system and its construction method |
CN107701231B (en) * | 2017-11-17 | 2024-01-19 | 安徽马钢罗河矿业有限责任公司 | Underground sump system with intensive integral structure and construction method thereof |
CN110939481A (en) * | 2019-12-18 | 2020-03-31 | 临沂矿业集团菏泽煤电有限公司 | Coal mine underground shared water absorption system |
CN110939481B (en) * | 2019-12-18 | 2022-02-25 | 临沂矿业集团菏泽煤电有限公司 | Coal mine underground shared water absorption system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202402076U (en) | Drainage pump station for underground line intervals of rail traffic | |
CN2761847Y (en) | Reduced mining area water sump pump room | |
CN102383373B (en) | Be applied to elevated bridge invisible rainwater collecting system and the method to set up thereof of flat slope | |
CN206368389U (en) | One kind backwash and sewage sucking system | |
CN206070586U (en) | Inspection well structure for sewage access comprehensive pipe rack | |
CN108571013A (en) | A kind of underground pipe gallery structure that band rain sewage becomes a mandarin | |
CN204940015U (en) | Draining of rail device and rail system | |
CN109024673A (en) | A kind of sponge road surface-underground pipe gallery system and construction technology | |
CN102261125B (en) | Motorless multifunctional rain and flood control and utilization device | |
CN111472837A (en) | Mixed drainage facility of strip mine | |
CN203383853U (en) | Buffering system for solving problem of insufficient drainage ability of tunnel central ditch | |
CN205443854U (en) | Notch cuttype curb | |
CN215442013U (en) | Cross joint structure of comprehensive pipe gallery and drain pipe | |
CN202202393U (en) | Comprehensive road surface drainage system | |
CN107701231A (en) | A kind of intensive overall structure shaft sump system and its construction method | |
CN212387837U (en) | Mine circulating water treatment system | |
CN108532711B (en) | Building system based on sponge city construction | |
CN210977592U (en) | Novel panel small-sized water sump for underground coal mine | |
CN207420624U (en) | A kind of intensive overall structure shaft sump system | |
CN111535417A (en) | Road drainage structure and drainage method thereof | |
CN106049651A (en) | Urban water-logging prevention and control method | |
CN110714443A (en) | Comprehensive corridor arrangement structure for urban flood diversion | |
CN201981463U (en) | Drainage flat stone for road paving | |
CN108187372A (en) | A kind of High-efficient Water dirt piece-rate system for underground mine | |
CN205188808U (en) | Bridge rainwater collecting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |