CN2703075Y - Lead and taper type multifunction scaffold - Google Patents

Lead and taper type multifunction scaffold Download PDF

Info

Publication number
CN2703075Y
CN2703075Y CN 200420026923 CN200420026923U CN2703075Y CN 2703075 Y CN2703075 Y CN 2703075Y CN 200420026923 CN200420026923 CN 200420026923 CN 200420026923 U CN200420026923 U CN 200420026923U CN 2703075 Y CN2703075 Y CN 2703075Y
Authority
CN
China
Prior art keywords
scaffold
bowl
joint
brace
vertical rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200420026923
Other languages
Chinese (zh)
Inventor
张树荣
成军
朱兵
任友义
朱汉彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200420026923 priority Critical patent/CN2703075Y/en
Application granted granted Critical
Publication of CN2703075Y publication Critical patent/CN2703075Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a multifunction scaffold comprising steel tubes. Rod pieces are connected by adopting a bowl fastening type. The multifunction scaffold is characterized in that the tooth fasteners engaged with each other are provided between the joints of the transversal rod pieces and the lower bowl fasteners of the vertical rods, and the joints are pressed by upper bowl fasteners lifted on top pins, the multifunction scaffold not only makes the three-dimensional space of the structure be firmly and reliably stressed, but also the multifunction scaffold has quick installation and labor saving. The joints are not limited by directions, and the loading capacity of the scaffold also can be regulated through regulating the density degree of the vertical rods. The length of the scaffold has multiple sizes, and the scaffold has auxiliary components, so the scaffold is not limited by the height of the land and the shape of the structure object, and due to the connecting piece with tooth fasteners can be once formed, the multifunction scaffold has low cost.

Description

Tooth button-type multifunction scaffold
The present invention relates to the scaffold that a kind of building operations is used, particularly a kind of scaffold of multi-functional one-tenth series.
The scaffold that uses in the present civil works, the scaffold that useful galvanized wire colligation mao bamboon or round log are assembled into, useful bolted fastener type steel pipe scaffold, Sterling at grade intersection scaffold as Britain, the door-type scaffold that useful door shape stationary frame structure is assembled into, door-type scaffold as the production of Japanese Wako Trading Co., Ltd, also useful steel pipe is welded into triangle, quadrangle, integral frame-type scaffold that form such as trapezoidal is interconnected to then etc., but all there is certain shortcoming in all these scaffolds, what have will expend a large amount of bamboo and wood materials, can not form series of products; The fastener that has will carry installation by the workman, both loses easily, wastes time and energy again during assembly unit; The complex structure that has, the cost height, function is few, and bearing capacity can not change; What have is then too heavy, transports constantly, can only use in major works; The major accident that scaffold integral body is decayed also took place because of assembly unit rear stability difference in what have.
The bowl button-type tubular scaffolding that Britain SGB company produces is a kind of scaffold of multi-functional one-tenth series.In a vertical rod, establish a joint, utilize a cover bowl fastening type connector, can connect four cross bars simultaneously, install rapidly every 50cm, easy to use.But, the connector of this scaffold, being connected of upper and lower bowl button and cross bar joint, can not accomplish precision continuously, so many cross bars are when connecting on a joint, the cross bar joint can not be all compacted in the bowl button, thus this joint design resist such as wind-force, eccentric force and at random laterally intensity of force a little less than, be difficult to guarantee when setting up high-rise scaffold, problem can not take place.
The objective of the invention is to provide a kind of scaffold of improved multi-functional one-tenth series, it is not only installed and removes conveniently, is suitable for multiple use, and can increases the three dimensions stability of scaffold greatly.
Invention is to realize like this, on the basis of the bowl button-type tubular scaffolding that Britain SGB company produces, improve its connection device, promptly recessed tooth is set being fixed in the vertical rod following bowl button top inner edge, the plush copper armpit place of the joint of installing at cross bar or brace two ends is provided with double wedge, when vertical rod is connected with cross bar or brace, the recessed tooth of the double wedge on the joint and following bowl button is meshed, and after will going up the bowl button again and falling fastening joint top, connection i.e. announcement is finished.Adopt this connected mode, be equipped with other accessory again, promptly can be assembled into multi-purpose scaffold, Stability Analysis of Structures, solid and reliable.
The present invention mainly contains following advantage:
1, structural strength is good, and is reliable and stable in three dimensions, uses tooth button-type joint, makes the whole local pressure of participating in of scaffold, compares with anodontia button person, improves more than 20% of structural strength approximately.In addition, according to circumstances, can the company's of setting up wall device and brace, increased the strength and stiffness of scaffold.
2, construction is laborsaving rapidly, and accessory is difficult for losing, and reduces labor intensity: because of this joint, only knock with hand hammer, promptly dismantled and assembled, in case of necessity, vertical rod can be installed connecting pin additional, with the scaffold integral hoisting that assembles, so dismounting is laborsaving rapidly.Because of the main member that connects scaffold is attached on the rod member, compare again, both can prevent that accessory from losing the heavy burden that need carry a large amount of bolts in the time of can removing workman's assembly unit, dismounting scaffold again from bolt fastener.
3, applied widely, highly versatile adds auxiliary bar, form seriation after, multiple use can be provided: the present invention not only can be by straight line but also can be by arrangement of curves; Both can on the level land, use, can on the ground of any discrepancy in elevation, use again; Both can make scaffold, bracing frame, support column can be made climbing scaffold again, material hoisting frame, safety net support bar.When making scaffold and bracing frame and using, can adjust set spacing flexibly, thereby, adjust the grade of load according to the density degree of vertical rod according to load request.Therefore, the present invention can be widely used in multiple building, as crane span structure, tunnel, room build, engineerings such as bridge, water tower, chimney.
4, the rod member syndeton is simple, and is easy to maintenance, durable in use, and during transportation, entrucking and stacking keeping occupy little space.
5, for high-lager building, as adopt climbing scaffold of the present invention, then can reduce the scaffold consumption in a large number, and can rise step by step along the building main body.
6, because of the following bowl button that has the tooth button and the joint of cross bar or brace, all can with following bowl of button and joint one-shot forming so cost of production of the present invention, compare with the scaffold of production Britain SGB company, be more or less the same, but than the producer of SGB company, its structural performance is reliable and stable far.
Below in conjunction with accompanying drawing, the present invention is described in further detail.
Fig. 1 tooth snapping head structure
1-vertical rod 5-go up bowl to detain
2-cross bar, 6-ejector pin
3-following bowl button 7-fastening blocks (detaining with last bowl is an integral body)
4-cross bar joint
Fig. 2 tooth snapping head
Following bowl of button of Fig. 3
24-recessed tooth
Bowl button on Fig. 4
Fig. 5 cross bar joint
Fig. 6 brace and brace joint
8-brace, 22-bolt
9-brace joint, 23-pin
25-double wedge
Fig. 7 double-pole scaffold arrangement diagram (brace is not drawn in the plan view)
10-connect wall to support
11-safety net and support bar
12-vertical rod base
13-vertical rod adjustable seats
The single scaffold arrangement diagram of Fig. 8 (brace is not drawn in the plan view)
Fig. 9 bracing frame arrangement diagram
Figure 10 support post construction figure
14-adjustable supports column base
15-support column base
Figure 11 climbing scaffold arrangement diagram
16-outrigger 26-pre embedded bolt climbs
17-widen outrigger
18-lifting tackle group
19-pre embedded bolt
Figure 12 outrigger constructional drawing that climbs
20-pulling force gripper shoe, 27-screw-jack
21-thrust support plate
During the assembly unit scaffold, as Fig. 1, shown in 2, set joint in vertical rod, rotation and on carry and can be on freely rotating in the vertical rod bowl detaining, make ejector pin (6) have the fastening block (7) of cotter way and will go up bowl button (5) and be stuck on the ejector pin (6) by it, the nose portion of transverse bar member joint is inserted in the following bowl of button (3), the part tooth button of bowl button (3) is meshed with the tooth button of joint, to go up bowl button (5) then falls, fasten joint top, and the clockwise direction rotation, because of last bowl button end face is the spiral ascending curve, the top is subjected to the extruding of ejector pin (6), more twist tightlier, beat 2-3 time with the hand hammer clockwise direction more at last, can reach the spacing purpose of self-locking, this structure can be installed 4 cross bars or brace simultaneously at a contact.
When brace (8) is gone up installation brace joint (9), as shown in Figure 6, be to pound the brace end flat, with bolt (22) itself and brace joint are fused, with pin (23) bolt (22) is fixed on the brace joint (9), and between brace (8) and the brace joint (9), can bolt (22) is pivot still, rotation relatively, the requirement of different angles when installing to satisfy.
Other are as the platform extension outrigger, safety net support bar and other various support members, and all available this joint connects.
For ease of construction, all vertical rods, brace, cross bar etc. all have plurality of specifications, and with auxiliary part, no matter set up double-pole scaffold, Fig. 7, single scaffold, Fig. 8, or bracing frame, Fig. 9, density degree that all can be by regulating vertical rod also is equipped with corresponding cross bar, forms the different scaffold of bearing capacity, simultaneously, its shape also can change with building shape.Vertical rod (1) has vertical rod base (12) to enlarge Area of bearing, and vertical rod adjustable seats (13) is to adjust the vertical rod height.In like manner, the support column of Figure 10 also is provided with support column base (15) and adjustable supports column base (14), plays same effect.
Because scaffolding structure of the present invention is stable, be connected firmly, so can be used as climbing scaffold, when assembling this scaffold, be to utilize pre embedded bolt (19) and (26) imbedded in the building to bear thrust and the pulling force that scaffold transmits, the outrigger that the wall-attachment tripod constitutes adopts the bottom to remove by frame as the carriage of scaffold, and the top connects high way by frame and realizes climbing.Earlier two adjustable seats on the joist are inserted in the scaffold upright rod (1) during assembling, open pore with pulling force gripper shoe (20) is inserted in pre embedded bolt (26) again, with the bolt hole of thrust support plate (21), be inserted in pre embedded bolt (19) and tighten all nuts at last and adjust screw-jack (27).During dismounting, stop operation earlier, unclamp the nut on screw-jack and thrust support plate and the pulling force gripper shoe then, pull down the outrigger that climbs on this frame scaffold top.
Below illustrate:
Adopt  48 * 3.5 steel pipe manufacturing vertical rods (1) and cross bar (2), with  48 * 2.2 steel pipe manufacturing braces (8), vertical rod length is divided into two kinds of specifications of 360cm, 240cm, cross bar length is pressed 30cm, 90cm, four kinds of specification settings of 120cm, 180cm, brace length is divided into three kinds of 169.7cm, 216.3cm, 254.6cm, with the A of thick 7mm 2Steel plate strikes out the following bowl of button that the top inner edge is provided with 48 recessed teeth (7.5 ° of per tooths), directly be welded in the vertical rod (1) by the 60cm spacing, weld  10 bar dowels on it in addition as ejector pin (6), be fixed on the joint of cross bar (2) or brace (8) end, be to forge by No. 35 punching blocks to form, each joint is the arcuation plush copper in two ends up and down, and 5 double wedges are arranged at plush copper armpit place, when the assembling scaffold, two plush coppers are inserted up and down in the bowl button respectively and are made its double wedge detain the interior recessed tooth of part and be meshed with following bowl up and down, then by rotation, knock, the bowl button is held out against by ejector pin.This syndeton is used in combination with other member again, can form the multifunction scaffold of reliable and stable one-tenth series.According to calculating the double-pole scaffold scaffolding height, can reach more than the 50m.
Double-pole scaffold various combination load capacity change list
The high cm load force of the wide cm frame of channel width cm frame kg/m
I 120 180 180 3000
II 120 120 180 4200
III 120 90 180 5600
During the assembling climbing scaffold, because of the longest 360cm of vertical rod, so every joint is climbed and is defined as 360cm, consider that work high above the ground must guarantee safety, more common adding is twice during the computationally secure coefficient, the sidewalk tolerance of climbing scaffold is decided to be 90cm, and its load force is defined as 1/2 of common scaffold, and its package size divides two kinds of concrete numerals as follows:
The high cm load force of the wide cm frame of the wide cm frame in sidewalk kg/m
I 90 180 180 1500
II 90 120 180 2100

Claims (1)

1, a kind of multifunction scaffold of dressing up by steel pipe, comprising: vertical rod (1), cross bar (2), brace (8), vertical rod base (12), vertical rod adjustable seats (13), connect wall support (10), safety net and support bar (11), utilize the bowl fastening type connector to connect between these rod members, following bowl of button (3) arranged in vertical rod (1), ejector pin (6), and also have one can rotation in the vertical rod move on bowl button (5), cross bar joint (4) is arranged on cross bar (2), brace joint (9) is arranged on brace (8), it is characterized in that: the following bowl of top inner edge of detaining (3) at all scaffold joint components is provided with recessed tooth (24), arc plush copper armpit place at cross bar joint (4) or brace joint (9) is provided with double wedge (25), when vertical rod (1) and cross bar (2) or brace (8) when being connected, the nose portion of joint, in bowl button (5) and the following bowl of button (3), the double wedge (25) that plush copper armpit place is provided with is meshed with the recessed tooth of part (24) of following bowl of button (3) in the insertion.
CN 200420026923 2004-05-10 2004-05-10 Lead and taper type multifunction scaffold Expired - Fee Related CN2703075Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200420026923 CN2703075Y (en) 2004-05-10 2004-05-10 Lead and taper type multifunction scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200420026923 CN2703075Y (en) 2004-05-10 2004-05-10 Lead and taper type multifunction scaffold

Publications (1)

Publication Number Publication Date
CN2703075Y true CN2703075Y (en) 2005-06-01

Family

ID=34771463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200420026923 Expired - Fee Related CN2703075Y (en) 2004-05-10 2004-05-10 Lead and taper type multifunction scaffold

Country Status (1)

Country Link
CN (1) CN2703075Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100368653C (en) * 2006-06-02 2008-02-13 丹阳市利普机械配件厂 Bowl fastening type up bowl of scaffold, and forging method
WO2011079616A1 (en) * 2009-12-28 2011-07-07 北京奥宇模板有限公司 Steel tube scaffold with combined bowl and plate buckles
CN102704670A (en) * 2012-06-24 2012-10-03 郑德春 Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof
CN104372941A (en) * 2014-10-27 2015-02-25 无锡市安捷脚手架有限公司 Scaffold connection part
CN104818842A (en) * 2015-05-07 2015-08-05 天津泰瑞达科技有限公司 Lower bowl-type buckle for bowl-type buckle scaffold and mounting method thereof
CN110700562A (en) * 2019-11-11 2020-01-17 金华市东山机械厂 Scaffold fastener and mounting tool thereof
CN110700563A (en) * 2019-11-11 2020-01-17 金华市东山机械厂 Scaffold fixing assembly

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100368653C (en) * 2006-06-02 2008-02-13 丹阳市利普机械配件厂 Bowl fastening type up bowl of scaffold, and forging method
WO2011079616A1 (en) * 2009-12-28 2011-07-07 北京奥宇模板有限公司 Steel tube scaffold with combined bowl and plate buckles
CN102704670A (en) * 2012-06-24 2012-10-03 郑德春 Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof
CN102704670B (en) * 2012-06-24 2014-05-07 郑德春 Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof
CN104372941A (en) * 2014-10-27 2015-02-25 无锡市安捷脚手架有限公司 Scaffold connection part
CN104818842A (en) * 2015-05-07 2015-08-05 天津泰瑞达科技有限公司 Lower bowl-type buckle for bowl-type buckle scaffold and mounting method thereof
CN110700562A (en) * 2019-11-11 2020-01-17 金华市东山机械厂 Scaffold fastener and mounting tool thereof
CN110700563A (en) * 2019-11-11 2020-01-17 金华市东山机械厂 Scaffold fixing assembly
CN110700563B (en) * 2019-11-11 2021-03-09 金华市东山机械厂 Scaffold fixing assembly
CN110700562B (en) * 2019-11-11 2021-04-02 金华市东山机械厂 Scaffold fastener and mounting tool thereof

Similar Documents

Publication Publication Date Title
CN2703075Y (en) Lead and taper type multifunction scaffold
CN2782837Y (en) Integral lifting form-climbing platform system
CN86201080U (en) Multi-functional scaffold with buckles
CN2787770Y (en) Communication tower
CN2799740Y (en) Assembling bis-adjustable multifunctional early-demolishment device
CN2832994Y (en) Dedicated protection frame for construction of main structure
CN109339436B (en) Special-shaped concrete hole body assembled formwork supporting device
CN2525161Y (en) Lift well mould
CN109577627B (en) Pole bench equipment platform is embraced to knot
CN210828286U (en) Overturn-preventing protection device for lifting scaffold
CN111305495B (en) Lightweight concrete combined stair
CN1258630C (en) Scaffolding
CN217759863U (en) Ladder operating frame for in-cabin combined working platform
CN1016880B (en) Process for manufacturing of lost casing and frames for use during said process
CN218090529U (en) Cast-in-place box girder external mold rapid prototyping bearing structure
CN211647378U (en) Prefabricated bench hoisting structure system
CN220747221U (en) Steel frame spliced structure
CN2186270Y (en) Desnity rib board with pile beam frame
CN218406483U (en) Reverse three-way stair running reinforcement device
CN216810965U (en) Adjustable top support for formwork
CN109594760B (en) Interior crowded pole bench equipment platform of embracing
CN210194434U (en) Cable saddle type steel lofting platform
CN213837016U (en) Supporting beam steel structure with high rigidity
CN2795346Y (en) Protective frame special for building main body construction
CN217531269U (en) Construction platform frock is used in production of a burst formula tower section of thick bamboo

Legal Events

Date Code Title Description