hanger plate
chain block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322629679.8U
Other languages
Chinese (zh)
Inventor
李旭
韦伟
万一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Ruiyong Construction Engineering Technology Co ltd
Nanjing Ruiyong Urban Renewal Research Institute Co ltd
Original Assignee
Jiangsu Ruiyong Construction Engineering Technology Co ltd
Nanjing Ruiyong Urban Renewal Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Ruiyong Construction Engineering Technology Co ltd, Nanjing Ruiyong Urban Renewal Research Institute Co ltd filed Critical Jiangsu Ruiyong Construction Engineering Technology Co ltd
Priority to CN202322629679.8U priority Critical patent/CN221191235U/en
Application granted granted Critical
Publication of CN221191235U publication Critical patent/CN221191235U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model discloses a combined lifting appliance for installing an elevator prefabricated assembly type stairway, relates to the technical field of assembly type building lifting, and aims to solve the problems that mechanical damage is easy to occur between a lifting rope and a lifting ring of an existing prefabricated stairway lifting appliance, construction safety is threatened, and meanwhile a crane lifting arm cannot enter a building to operate. The combined lifting appliance for installing the prefabricated elevator in the elevator shaft comprises a steel support and a lifting beam, wherein the lifting beam is connected with the steel support through a fixed bolt, a movable sliding block is arranged on the lifting beam, an electric winch is hung below the movable sliding block, the movable sliding block is connected with the electric winch through a sling, and an iron shoulder pole is arranged below the electric winch; the lifting device is characterized in that a rolling lifting ring is arranged on the lower lifting plate, a level device is arranged in the middle of the lower lifting plate, a limiting part is arranged on the lower lifting plate, and opposite perforations are formed in the limiting part at equal intervals.

Description

Combined lifting appliance for installing prefabricated elevator in elevator lane
Technical Field
The utility model relates to the technical field of assembly type building hoisting, in particular to a combined lifting appliance for installing an elevator prefabricated assembly type stairway.
Background
With the aggravation of the aging population, a significant part of the elderly people in China still live in the multi-storey houses without elevators, which affects the quality of life of the elderly people to a certain extent. With the advance of the barrier-free urban work, the practical requirement of adding elevators to multi-layer houses in each city becomes an increasingly prominent problem.
In the old district elevator transformation project, the elevator additionally installed in the old building is required to face the problem of entering a house, and some buildings are not suitable for the elevator to directly reach a user gate, but a reinforced concrete corridor or a reinforced concrete corridor is required to be additionally installed, so that the transformation requirement can be met. In the old district elevator transformation project, generally adopt assembled stair in order to satisfy elevator income family demand, assembled stair is generally prefabricated in the mill, adopts the mode of hoist and mount assembly to accomplish the installation after transporting to scene, and this in-process, the use of hoist is indispensable.
For example, chinese issued patent number CN209583387U, an adjustable spreader for assembled stairway lifting: comprises a cross beam, a support rod, a sling and an iron shoulder pole; the cross beam comprises a first cross beam and a second cross beam; a plurality of perforations are respectively arranged on the first cross beam and the second cross beam along the horizontal direction; the perforations on the first cross beam correspond to the perforations on the second cross beam respectively, so that the support rod can pass through the perforations to form a hoisting support structure; the support rods comprise a first support rod and a second support rod; the first support rod passes through the perforations on the left sides of the first cross beam and the second cross beam to form a left side hoisting support structure; the second supporting rod passes through the first cross beam and the through holes on the right side of the second cross beam to form a right side hoisting supporting structure; one end of the sling is connected with the left hoisting supporting structure and the right hoisting supporting structure, and the other end of the sling is connected with the iron shoulder pole; by adopting the scheme, the hoisting size can be conveniently adjusted, the stress state of the hoisting ring and the member is improved, and the installation of the prefabricated staircase is more accurate.
However, most of the hoisting prefabricated stair slings at present directly adopt sling connecting components and electric winches, because the weight of the prefabricated stair is large, the pressure generated by the sling is large, the sling directly penetrates through the bearing hanging ring in a slender manner, the pressure born by the sling is extremely large, when the sling starts to lift the prefabricated stair and moves the prefabricated stair, the sling and the hanging ring slide, because the pressure between the sling and the hanging ring is large, a great amount of heat is generated by friction force, mechanical structural damage is easily generated to the sling and the hanging ring, the sling is used in high strength during construction, hidden damage of the sling and the hanging ring is not easy to perceive, and accidents are easy to occur; meanwhile, prefabricated stairways generated by additionally installing elevators in old communities are installed in a building in general construction operation, and a common crane cannot extend a suspension arm into the building for operation. Therefore, the existing requirements are not met, and for this reason we propose a combined sling for installing prefabricated assembled stairway of an elevator.
Disclosure of utility model
The utility model aims to provide a combined sling for installing an elevator prefabricated assembly type stairway, which solves the problems that the existing prefabricated stairway sling slings and hanging rings in the prior art are easy to cause mechanical damage, threat is caused to construction safety, and meanwhile, a crane boom cannot enter a building to operate.
In order to achieve the above purpose, the present utility model provides the following technical solutions: a modular spreader for add-on elevator prefabricated bench installations, comprising: the steel support and the hoisting beam are connected through a fixed bolt, a movable sliding block is arranged on the hoisting beam, an electric hoist is hoisted below the movable sliding block, the movable sliding block is connected with the electric hoist through a sling, an iron shoulder pole is arranged below the electric hoist, the iron shoulder pole is divided into an upper hanging plate and a lower hanging plate, the upper hanging plate is connected with the lower hanging plate through a sling, and two chain blocks are arranged on the lower hanging plate;
Further comprises: the lifting device is characterized in that two rolling lifting rings are arranged on the lower lifting plate, the two rolling lifting rings are symmetrically arranged on the lower lifting plate, a level device is arranged in the middle of the lower lifting plate, limiting parts are arranged on the lower lifting plate, and opposite perforations are formed in the limiting parts at equal intervals.
Preferably, the rolling hanging ring is provided with a manual locking bearing, the manual locking bearing is provided with an outer ring and an inner ring, and countersunk screws are arranged between the outer ring and the inner ring.
Preferably, the manual locking bearing is provided with metal rolling balls and a retainer, wherein the metal rolling balls are positioned on the retainer, and the retainer is provided with the metal rolling balls which are annularly arranged at equal intervals.
Preferably, the steel support bottom is provided with universal wheels.
Preferably, one end, far away from the steel support, of the lifting beam is provided with a supporting structure, and the supporting structure is provided with riding wheels and moving wheels.
Preferably, one end, far away from the steel support, of the lifting beam is provided with a turnover type protruding structure.
Preferably, the chain block upside is provided with the chain block and goes up the lifting hook, and the downside is provided with the chain block and goes down the lifting hook, the chain block goes up the lifting hook and passes down the perforation of hanger plate and connect down the hanger plate, the chain block is gone down the lifting hook and is passed through the hoist cable and connect the pre-buried rings of prefabricated stair.
Compared with the prior art, the utility model has the beneficial effects that:
1. When the existing lifting appliance works, great friction heat is generated between the lifting rope and the lifting ring; meanwhile, during construction, the lifting appliance works in a high strength mode, workers are difficult to withdraw the time to check the integrity of the device, and once misoperation occurs during lifting of prefabricated stairs and galleries, safety hazards are prone to occurring.
2. According to the utility model, the lifting appliance in the building is adjusted, the universal wheels are arranged under the steel support, and the riding wheels and the movable wheels are arranged on the lifting beam support structure, so that the movable angle of the lifting appliance in the building is increased, the multi-angle multi-azimuth complex construction is facilitated, and the installation of prefabricated stairs and galleries is ensured.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is an enlarged view of a portion of the utility model at A;
FIG. 3 is an enlarged view of a portion of the utility model at B;
FIG. 4 is a schematic view of the manual locking bearing structure of the present utility model;
In the figure: 100. a steel support; 101. a fixing bolt; 105. a universal wheel; 200. hoisting the beam; 201. moving the slide block; 202. an electric hoist; 210. an iron shoulder pole; 211. a hanging plate is arranged; 212. a lower hanger plate; 300. a rolling hanging ring; 301. a level device; 302. chain block; 308. a limiting member; 309. perforating; 310. manually locking the bearing; 311. an outer ring; 312. an inner ring; 313. countersunk head screws; 314. a metal ball; 315. a retainer; 400. embedding a hanging ring; 401. the chain block is hung down; 402. and a lifting hook is arranged on the chain block.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments.
Referring to fig. 1-4, an embodiment of the present utility model is provided: the utility model provides a combination hoist for installing prefabricated assembled ladder of elevator additional, including steel support 100, hoist and mount roof beam 200 and steel support 100 are through fixing bolt 101 connection, be provided with the removal slider 201 on hoist and mount roof beam 200, the removal slider 201 below hangs and is had electric hoist 202, be used for receiving and releasing the hoist cable, the removal slider 201 passes through the hoist cable to be connected with electric hoist 202, electric hoist 202 below is provided with iron shoulder pole 210, keep the balance of being hung equipment, iron shoulder pole 210 divide into upper hanger plate 211 and lower hanger plate 212, upper hanger plate 211 and lower hanger plate 212 pass through the hoist cable to be connected, be provided with two chain block 302 on the lower hanger plate 212, be used for adjusting the fore-and-aft atress of being hung equipment;
further comprises: the lower hanging plate 212 is provided with two rolling hanging rings 300, the two rolling hanging rings 300 are symmetrically arranged on the lower hanging plate 212, the middle part of the lower hanging plate 212 is provided with a level device 301, the lower hanging plate 212 is provided with a limiting part 308, the limiting part 308 is provided with opposite perforations 309 at equal distance, the level device 301 is observed, and the moment is adjusted through the hand hoist 302, so that the suspended equipment is kept horizontal as much as possible.
Referring to fig. 2 and 4, the scrollable hanging ring 300 is provided with a manual locking bearing 310, the manual locking bearing 310 is provided with an outer ring 311 and an inner ring 312, a countersunk screw 313 is arranged between the outer ring 311 and the inner ring 312, the manual locking bearing 310 is used for avoiding severe friction between a sling and the hanging ring, and after adjustment, the countersunk screw 313 is screwed in to lock the manual locking bearing 310.
Referring to fig. 4, the manual locking bearing 310 is provided with metal balls 314 and a cage 315, the metal balls 314 are located on the cage 315, and the metal balls 314 are annularly arranged at equal intervals on the cage 315.
Referring to fig. 1, a universal wheel 105 is provided at the bottom of the steel support 100, and the position of the lifting tool can be adjusted by the universal wheel 105.
Referring to fig. 1, a supporting structure is disposed at one end of the lifting beam 200 far away from the steel support 100, and is provided with riding wheels and moving wheels, so that the lifting beam 200 can move at a large angle through the riding wheels and the moving wheels.
Referring to fig. 1 and 3, the end of the lifting beam 200, which is far away from the steel support 100, is provided with a turnover type protrusion structure.
Referring to fig. 2, a chain block upper hook 402 is provided on the upper side of the chain block 302, a chain block lower hook 401 is provided on the lower side of the chain block upper hook 402, the chain block lower hook 402 passes through a pair of holes 309 of the lower hanging plate 212 to connect the lower hanging plate 212, the chain block lower hook 401 is connected with a pre-buried hanging ring 400 of a pre-buried stair through a sling, the connection between the sling and the pre-buried stair is realized through the chain block upper hook 402, the chain block lower hook 401, the sling and the pre-buried ring 400 of the pre-buried stair, the pre-buried stair is lifted by the sling is satisfied, and the stress condition of the pre-buried stair is adjusted by the chain block 302.
Working principle: when the lifting device is used, the lifting device steel support 100 is moved to a construction position through the universal wheels 105, the lifting beam 200 and the steel support 100 are fixedly connected through the fixing bolts 101, a supporting structure is arranged at the other end of the lifting beam 200, the lifting beam 200 enters the supporting structure through the riding wheels, the position of the lifting beam 200 is adjusted through the riding wheels and the moving wheels of the supporting structure, the turnover type protruding structure on the lifting beam 200 is turned up, and the positions of the lifting beam 200 and the supporting structure are blocked. The movable sliding block 201 on the movable hanging beam is moved to one side of the prefabricated staircase and gallery, the sling is lowered through the electric hoist 202, the iron shoulder pole 210 is connected, the upper lifting hook 402 of the chain block penetrates through the opposite through hole 309 of the lower lifting plate 212 to be connected with the lower lifting plate 212, the lower lifting hook 401 of the chain block is connected with the pre-buried lifting ring 400 of the prefabricated staircase and gallery through the sling, the prefabricated staircase and gallery are slowly pulled up through the electric hoist 202, the level gauge device 301 is observed, the level gauge device 302 is adjusted until the level gauge device 301 is approximately horizontal, the countersunk screw 313 on the manual locking bearing 310 is screwed into the inner ring 312, the manual locking bearing 310 is locked, the prefabricated staircase and gallery are moved to the installation position through the movable sliding block 201, and the electric hoist 202 is lowered to the sling, so that the lifting of the prefabricated staircase and the gallery is completed.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present utility model may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a combination hoist for installing prefabricated assembled ladder of elevator additional, includes steel support (100), hoist and mount roof beam (200) are connected through fixing bolt (101) with steel support (100), are provided with on hoist and mount roof beam (200) and remove slider (201), it has electric hoist (202) to hang below removing slider (201), and remove slider (201) and electric hoist (202) are connected through the hoist cable, electric hoist (202) below is provided with iron shoulder pole (210), iron shoulder pole (210) divide into upper hanger plate (211) and lower hanger plate (212), upper hanger plate (211) and lower hanger plate (212) are connected through the hoist cable, be provided with two chain block (302) on lower hanger plate (212);
The method is characterized in that: further comprises: the utility model discloses a lifting device for a car, including lower hanger plate (212), but be provided with on lower hanger plate (212) and roll rings (300), but roll rings (300) are two altogether, and the symmetry is located lower hanger plate (212), lower hanger plate (212) middle part sets up spirit level device (301), set up spacing part (308) on lower hanger plate (212), equidistance is provided with on spacing part (308) and to perforation (309).
2. A modular spreader for add-on elevator prefabricated bench installations according to claim 1, characterized in that: the rolling lifting ring (300) is provided with a manual locking bearing (310), the manual locking bearing (310) is provided with an outer ring (311) and an inner ring (312), and countersunk screws (313) are arranged between the outer ring (311) and the inner ring (312).
3. A modular spreader for installing prefabricated elevator walkways as set forth in claim 2 wherein: the manual locking bearing (310) is provided with a metal rolling ball (314) and a retainer (315), the metal rolling ball (314) is positioned on the retainer (315), and the metal rolling balls (314) are annularly arranged at equal intervals on the retainer (315).
4. A modular spreader for installing prefabricated elevator walkways as set forth in claim 3 wherein: and universal wheels (105) are arranged at the bottom of the steel support (100).
5. A modular spreader for add-on elevator prefabricated bench installations according to claim 4, characterized in that: one end of the lifting beam (200) far away from the steel support (100) is provided with a support structure, and the support structure is provided with riding wheels and moving wheels.
6. A modular spreader for add-on elevator prefabricated bench installations according to claim 5, characterized in that: one end of the lifting beam (200) far away from the steel support (100) is provided with a turnover type protruding structure.
7. A modular spreader for add-on elevator prefabricated bench installations according to claim 6, characterized in that: the chain block is characterized in that a chain block upper lifting hook (402) is arranged on the upper side of the chain block (302), a chain block lower lifting hook (401) is arranged on the lower side of the chain block upper lifting hook (402) penetrates through a pair of holes (309) of the lower lifting plate (212) to be connected with the lower lifting plate (212), and the chain block lower lifting hook (401) is connected with a pre-buried lifting ring (400) of a prefabricated stair through a sling.
CN202322629679.8U 2023-09-27 2023-09-27 Combined lifting appliance for installing prefabricated elevator in elevator lane Active CN221191235U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322629679.8U CN221191235U (en) 2023-09-27 2023-09-27 Combined lifting appliance for installing prefabricated elevator in elevator lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322629679.8U CN221191235U (en) 2023-09-27 2023-09-27 Combined lifting appliance for installing prefabricated elevator in elevator lane

Publications (1)

Publication Number Publication Date
CN221191235U true CN221191235U (en) 2024-06-21

Family

ID=91514059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322629679.8U Active CN221191235U (en) 2023-09-27 2023-09-27 Combined lifting appliance for installing prefabricated elevator in elevator lane

Country Status (1)

Country Link
CN (1) CN221191235U (en)

Similar Documents

Publication Publication Date Title
CN111456395B (en) Mounting, fixing and construction method for prefabricated member of prefabricated building
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN111021749A (en) Simple hoisting mechanism for bare concrete exterior wall cladding and construction method thereof
CN113250434A (en) Multifunctional composite scaffold system
CN112177309A (en) Assembled protection platform used in building elevator shaft
CN206767425U (en) A kind of integral hoisting device for rapid for ground-connecting-wall steel reinforcement cage
CN221191235U (en) Combined lifting appliance for installing prefabricated elevator in elevator lane
CN210289116U (en) Safe self-locking device for external wall template
CN114961054B (en) Resource-saving type assembled green curtain wall structure and construction method thereof
CN212769534U (en) Rotatable simple and easy hoist device
AU2021102633A4 (en) Method for carrying objects by girder crane lifting device arranged in light well
CN206693641U (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building
CN211691536U (en) Simple lifting mechanism for bare concrete exterior wall cladding
CN114412192A (en) Interlayer complex special-shaped aluminum veneer curtain wall and construction method thereof
CN210825249U (en) Novel self-lifting material platform
CN113636467A (en) Rolling mill frame hoisting device
CN112878656B (en) Electric lifting climbing frame device for building engineering
CN110606434A (en) Super-large crane for building
CN218467178U (en) Safety tool for hoisting concrete precast column
CN218371306U (en) Mine hydraulic support dismouting mechanism
CN219448895U (en) Emergency rescue device for rapid personnel lifting in ultra-deep vertical shaft
CN216276806U (en) Novel integral lifting type operation platform for elevator shaft construction
CN221031587U (en) Aluminum mould operation floor elevator mouth edge protection device capable of being hoisted for multiple times
CN216446535U (en) Construction structure of overhead vestibule bottom furred ceiling of superelevation layer
CN221073407U (en) Movable simple hanging basket structure for building outer elevation construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant