CN221001294U - Assembled formwork-free channel structure - Google Patents
Assembled formwork-free channel structure Download PDFInfo
- Publication number
- CN221001294U CN221001294U CN202322586572.XU CN202322586572U CN221001294U CN 221001294 U CN221001294 U CN 221001294U CN 202322586572 U CN202322586572 U CN 202322586572U CN 221001294 U CN221001294 U CN 221001294U
- Authority
- CN
- China
- Prior art keywords
- channel
- poured
- bottom die
- channel bottom
- water distribution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 claims abstract description 42
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 claims description 31
- 239000010959 steel Substances 0.000 claims description 31
- 210000002421 cell wall Anatomy 0.000 claims description 10
- 239000004540 pour-on Substances 0.000 claims description 4
- 239000011150 reinforced concrete Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 16
- 238000000034 method Methods 0.000 abstract description 9
- 238000007796 conventional method Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses an assembled formwork-free channel structure, belongs to the field of water distribution channel construction, and solves the problems that the existing water distribution channel construction method is complex in working procedures and has secondary structure quality risks. The method comprises the steps of pouring concrete pool walls firstly, pouring concrete pool walls later, connecting two opposite surfaces of the concrete pool walls which are poured firstly by the channel bottom die, and pouring water distribution channels and channel bottom dies, wherein the water distribution channels are poured on the channel bottom dies, and the concrete pool walls which are poured later are poured on the concrete pool walls which are poured earlier. According to the utility model, the prefabricated channel bottom die is adopted, a supporting scaffold is not required to be arranged during construction, a template is not required to be reserved for taking out an opening, the first poured concrete pool wall is poured to the water distribution channel bottom elevation, then the prefabricated channel bottom die is installed, the water distribution channel is poured and the later poured concrete pool wall is poured, the channel bottom die is reserved, and the workload of removing the supporting scaffold and plugging the opening is avoided.
Description
Technical Field
The utility model belongs to the field of water distribution channel construction, and particularly relates to an assembled formwork-free channel structure.
Background
Various water distribution channels are common components of water treatment structures. According to the characteristics of various water treatment process flows, the water distribution channel is often arranged at the upper part or the middle part of the tank body, so that the working condition that a closed space is formed at the lower part of the channel is often caused. In the construction of the conventional method, in order to take out the templates and the scaffolds for supporting the channels, holes with proper sizes (usually not less than 1.0x1.80m) are reserved at the positions of the side walls, which do not affect the main structure, and after the channel strength reaches the design strength, the templates and the scaffolds in the closed space are taken out; and finally, blocking the hole by adopting bricks, and then performing construction of plastering, waterproofing and other procedures. It can be seen that the conventional method is complicated in procedure and has a secondary structure quality risk.
Disclosure of utility model
The utility model aims to provide an assembled formwork-free channel structure, which solves the problems that the existing water distribution channel construction method is complex in working procedures and has secondary structure quality risks.
The technical scheme of the utility model is as follows: the utility model provides an assembled formwork-free channel structure, includes pouring concrete cell wall earlier, later pouring concrete cell wall, water distribution channel and channel die block, and the channel die block is connected two opposite faces of pouring concrete cell wall earlier, and the water distribution channel is pour on the channel die block, and later pouring concrete cell wall is pour on pouring concrete cell wall earlier.
As a further improvement of the utility model, the post-pouring concrete pool wall and the channel are integrally poured and formed.
As a further improvement of the utility model, the channel bottom die is a precast reinforced concrete slab, and is provided with criss-cross distributed steel bars and stressed steel bars, and the stressed steel bars extend out of two ends of the channel bottom die and are connected with horizontal steel bars of the wall of the poured concrete pool.
As a further improvement of the utility model, the bottom die of the channel is provided with a hanging ring.
As a further improvement of the utility model, the cross section of the channel bottom die is trapezoid with narrow upper part and wide lower part.
As a further improvement of the utility model, a vertical water stop steel plate is arranged between the pouring concrete pool wall and the pouring concrete pool wall, and the water stop steel plates are positioned at two ends of the channel bottom die.
The beneficial effects of the utility model are as follows: according to the utility model, the prefabricated channel bottom die is adopted, a supporting scaffold is not required to be arranged during construction, a template is not required to be reserved for taking out an opening, the first poured concrete pool wall is poured to the water distribution channel bottom elevation, then the prefabricated channel bottom die is installed, the water distribution channel is poured and the later poured concrete pool wall is poured, the channel bottom die is reserved, and the workload of removing the supporting scaffold and plugging the opening is avoided. The utility model can greatly simplify the construction process, reduce the use of templates and scaffolds, save the construction period, and is scientific, reasonable, green, economical, safe and reliable.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic diagram of the connection of a stressed steel bar to a horizontal steel bar in the present utility model;
FIG. 3 is a plan view of a channel bottom die of the present utility model;
FIG. 4 is an elevation view of a channel form of the present utility model;
fig. 5 is a side view of fig. 4.
In the figure: 1, pouring concrete pool walls; 2-pouring concrete pool walls; 3-a bolt with a water stop wing plate; 4-closing the space; 5-a channel bottom die; 51-distributing steel bars; 52-stressed steel bars; 6-water stopping steel plates; 7-templates; 8-horizontal steel bars; 9-vertical steel bars; 10-a water distribution channel; 11-hanging rings.
Detailed Description
The present utility model will be described in detail with reference to the accompanying drawings.
As shown in fig. 1-5, an assembled formwork-free channel structure comprises a concrete pool wall 1, a concrete pool wall 2, a water distribution channel 10 and a channel bottom die 5, wherein the channel bottom die 5 is connected with two opposite surfaces of the concrete pool wall 1, the water distribution channel 10 is cast on the channel bottom die 5, and the concrete pool wall 2 is cast on the concrete pool wall 1.
The post-cast concrete pool wall 2 and the channel 10 are integrally cast.
The channel bottom die 5 is a precast reinforced concrete slab, the channel bottom die 5 is provided with distributed steel bars 51 and stressed steel bars 52 which are criss-cross, and the stressed steel bars 52 extend out of two ends of the channel bottom die 5 and are connected with the horizontal steel bars 8 of the first poured concrete pool wall 1. And the bottom die 5 of the channel is provided with a hanging ring 11, so that the hanging is convenient.
When the assembly type channel bottom die 5 is prefabricated, the distribution steel bars 51, the stress steel bars 52 and the hanging rings 11 can be configured according to working conditions.
The cross section of the channel bottom die 5 is trapezoid with narrow upper part and wide lower part, so that the later-stage cement paste is convenient to joint, and the construction quality is improved.
A vertical water stop steel plate 6 is arranged between the first pouring concrete pool wall 1 and the second pouring concrete pool wall 2, and the water stop steel plates 6 are positioned at two ends of the channel bottom die 5.
Example 1,
The thickness of the channel bottom die 5 is 70-100mm, the width of the top surface of the channel bottom die 5 is 470mm, the width of the ground of the channel bottom die 5 is 500mm, and the length of the two ends of the stressed steel bars 52 extending out of the channel bottom die 5 is 150mm.
The construction method comprises the following steps:
After the construction of the pouring concrete pool wall 1 is finished, the prefabricated bottom die 5 is installed in place to the horizontal steel bars 8, the vertical steel bars 9 of the pool body are constructed normally, water stop steel plates 6 are arranged at two ends of a construction joint of the water distribution channel 10, then the water distribution channel 10 and the templates 7 of the pouring concrete pool wall 2 are erected, bolts 3 with water stop wing plates are adopted for erection, and then concrete pouring can be carried out.
After the pouring of the water distribution channel 10 and the post-pouring concrete pool wall 2 is completed, a closed space 4 is formed below the water distribution channel 10, other follow-up demolding work is not needed in the closed space 4, and the channel bottom die 5 is reserved in the channel structure. According to the utility model, a template taking-out hole is not required to be reserved, a supporting scaffold is not required to be arranged, the construction procedure can be greatly simplified, the use of the template and the scaffold is reduced, the construction period is saved, and the method is scientific, reasonable, green, economical, safe and reliable.
Claims (6)
1. A modular form supporting-free channel structure is characterized in that: including pouring concrete cell wall (1) earlier, pouring concrete cell wall (2) later, water distribution channel (10) and channel die block (5), two opposite faces of pouring concrete cell wall (1) earlier are connected in channel die block (5), water distribution channel (10) pour on channel die block (5), concrete cell wall (2) pour on pouring concrete cell wall (1) earlier later.
2. The fabricated formwork-free channel structure as claimed in claim 1, wherein: and the rear pouring concrete pool wall (2) and the channel (10) are integrally poured and formed.
3. A fabricated formwork-free channel structure as claimed in claim 1 or 2, wherein: the channel bottom die (5) is a precast reinforced concrete slab, the channel bottom die (5) is provided with criss-cross distributed steel bars (51) and stressed steel bars (52), and the stressed steel bars (52) extend out of two ends of the channel bottom die (5) and are connected with horizontal steel bars (8) of the poured concrete pool wall (1).
4. A fabricated formwork-free channel structure as claimed in claim 3, wherein: and a hanging ring (11) is arranged on the channel bottom die (5).
5. The fabricated formwork-free channel structure as claimed in claim 4, wherein: the cross section of the channel bottom die (5) is trapezoid with narrow upper part and wide lower part.
6. The fabricated formwork-free channel structure as claimed in claim 4, wherein: vertical water-stopping steel plates (6) are arranged between the pouring concrete pool wall (1) and the pouring concrete pool wall (2), and the water-stopping steel plates (6) are positioned at two ends of the channel bottom die (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322586572.XU CN221001294U (en) | 2023-09-22 | 2023-09-22 | Assembled formwork-free channel structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322586572.XU CN221001294U (en) | 2023-09-22 | 2023-09-22 | Assembled formwork-free channel structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN221001294U true CN221001294U (en) | 2024-05-24 |
Family
ID=91088638
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322586572.XU Active CN221001294U (en) | 2023-09-22 | 2023-09-22 | Assembled formwork-free channel structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN221001294U (en) |
-
2023
- 2023-09-22 CN CN202322586572.XU patent/CN221001294U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110005200B (en) | Construction process for concrete pouring compaction of horizontal hidden beam | |
CN113481944B (en) | Construction method of dam surface hole connection girder supporting structure | |
CN111472324A (en) | Butt-pull-bolt-free rectangular aqueduct body integral pouring construction template and method | |
CN221001294U (en) | Assembled formwork-free channel structure | |
CN216689076U (en) | A prefabricated apron that is used for hollow mound top to pour construction | |
CN111173270A (en) | Prefabricated balcony aluminum mold structure and construction method | |
CN212103921U (en) | No split bolt formula rectangle aqueduct body monolithic casting construction template | |
CN214993106U (en) | Pier pouring die | |
CN112012473B (en) | Integrated steel formwork for wall body of cantilever rib type of sewage pool | |
CN215165197U (en) | A typical forms for concreting retaining wall | |
CN213412368U (en) | Horizontal adjustable prefabricated building body mould | |
CN209798958U (en) | Pouring system for drainage ditch of bottom plate post-cast strip and shaping hanging die for drainage ditch | |
CN110118014B (en) | Exterior wall template system free of exterior scaffold and construction method thereof | |
CN111236624A (en) | Construction method of PCF structure cast-in-place node template reinforcing system | |
CN215405915U (en) | Dam surface hole connection girder supporting structure | |
CN204728698U (en) | The closed formwork structure of a kind of concrete suspension bridging piece | |
CN111005558A (en) | Mould for manufacturing basic cavity concrete mould and using method thereof | |
CN217268355U (en) | Constructional column non-disassembly pouring mold | |
CN219365408U (en) | Pouring forming positioning device for counter sill and constructional column base of caisson | |
CN220746932U (en) | Prefabricated and cast-in-situ dual-purpose mould for independent foundation of form slope | |
CN215670050U (en) | Assembled balcony prefabricated part | |
CN212478530U (en) | Construction hydraulic pressure template climbing device | |
CN209799361U (en) | Construction mold device for flanging of toilet | |
CN214739360U (en) | Novel gutter beam body | |
CN220450787U (en) | Non-dismantling modularized lining board |