CN220748293U - Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum - Google Patents

Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum Download PDF

Info

Publication number
CN220748293U
CN220748293U CN202322357762.4U CN202322357762U CN220748293U CN 220748293 U CN220748293 U CN 220748293U CN 202322357762 U CN202322357762 U CN 202322357762U CN 220748293 U CN220748293 U CN 220748293U
Authority
CN
China
Prior art keywords
water
tunnel
layer
permeable
waterproof system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322357762.4U
Other languages
Chinese (zh)
Inventor
陈彦丽
李亮
闫寒
司立国
倪守增
董勇男
金宝
付同华
梁丽娟
张庆学
樊佳昌
姚家恒
张国龙
韩德旺
杨欣
王成安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Huida New Building Materials Co ltd
Jinan Urban Construction Group Co Ltd
Shandong Quanjian Engineering Testing Co Ltd
Jinan Rail Transit Group Co Ltd
Jinan Municipal Engineering Construction Group Co Ltd
Shandong Huitong Construction Group Co Ltd
Shandong Huiyou Municipal Garden Group Co Ltd
Original Assignee
Shandong Huida New Building Materials Co ltd
Jinan Urban Construction Group Co Ltd
Shandong Quanjian Engineering Testing Co Ltd
Jinan Rail Transit Group Co Ltd
Jinan Municipal Engineering Construction Group Co Ltd
Shandong Huitong Construction Group Co Ltd
Shandong Huiyou Municipal Garden Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Huida New Building Materials Co ltd, Jinan Urban Construction Group Co Ltd, Shandong Quanjian Engineering Testing Co Ltd, Jinan Rail Transit Group Co Ltd, Jinan Municipal Engineering Construction Group Co Ltd, Shandong Huitong Construction Group Co Ltd, Shandong Huiyou Municipal Garden Group Co Ltd filed Critical Shandong Huida New Building Materials Co ltd
Priority to CN202322357762.4U priority Critical patent/CN220748293U/en
Application granted granted Critical
Publication of CN220748293U publication Critical patent/CN220748293U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to the technical field of underground tunnel, in particular to a double-layer waterproof system of an underground tunnel with a poor water-rich stratum, which is provided with two layers of quick-setting permeable concrete layers, wherein the quick-setting permeable concrete layers comprise an inner layer and an outer layer, and a plastic water stop plate is arranged between the inner layer and the outer layer; the center of the tunnel bottom plate is provided with a water permeable ditch penetrating through the bottom plate, and a water permeable pile is arranged at the bottom of the tunnel towards the water permeable ditch; longitudinal U-shaped water collecting grooves are reserved at arch feet on two sides of the tunnel. Solves the problem of water leakage of the underground structure of the stratum with poor water enrichment.

Description

Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum
Technical Field
The utility model relates to the technical field of underground tunnel construction, in particular to a waterproof system of an underground tunnel structure of a water-rich poor geological area.
Background
With the development of cities, the development forms and scales of underground spaces are more diversified, and the construction forms of underground tunnels, underground civil air defense, underground roads and the like are more and more. The common problem of underground engineering is leakage, and the influence of underground water on underground space engineering is long-term, and not only affects the structural safety, but also affects the use function of the underground space engineering. The problem of how to effectively solve the water leakage of the underground structure is a great difficulty in underground engineering and tunnel construction, especially in water-rich poor stratum.
Disclosure of Invention
The utility model aims to provide a double-layer waterproof system for a subsurface tunnel of a water-rich poor stratum, which solves the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
the double-layer waterproof system for the underground excavation tunnel of the water-rich poor stratum is provided with two layers of quick-setting permeable concrete layers, wherein the quick-setting permeable concrete layers comprise an inner layer and an outer layer, and a plastic water stop plate is arranged between the inner layer and the outer layer; the center of the tunnel bottom plate is provided with a water permeable ditch penetrating through the bottom plate, and a water permeable pile is arranged at the bottom of the tunnel towards the water permeable ditch; longitudinal U-shaped water collecting grooves are reserved at arch feet on two sides of the tunnel.
As a further scheme of the utility model: the thickness of the inner layer is 5 cm.
As still further aspects of the utility model: the outer layer has a thickness of 35 cm.
As still further aspects of the utility model: and a rainwater grid is arranged at the top end of the longitudinal U-shaped catchment ditch.
As still further aspects of the utility model: the number of the permeable piles is three, one is arranged in the middle line of the tunnel, and one is arranged on each side.
Compared with the prior art, the utility model has the beneficial effects that: the problems of underground water leakage and safety and stability of tunnel excavation face soil bodies can be effectively solved in water-rich poor stratum; the problem of traditional tunnel drainage facility bad condition, avoided the high cost that brings in the construction process of traditional tunnel drainage facility simultaneously is solved.
Drawings
Fig. 1 is a schematic structural view of the present utility model.
Fig. 2 is an enlarged partial schematic view of the tunnel bottom of the present utility model.
Fig. 3 is a schematic perspective view of the present utility model.
Wherein: 1 quick setting water permeable concrete layer, 2 plastic water stop plates, 3 longitudinal U-shaped water collecting grooves, 4 rain water grids, 5 water permeable grooves and 6 water permeable piles.
Detailed Description
The utility model will be described in detail below with reference to the drawings in connection with embodiments.
Referring to fig. 1-3, the utility model provides a double-layer waterproof system for a water-rich bad stratum undercut tunnel, which is provided with two quick-setting permeable concrete layers 1, wherein the quick-setting permeable concrete layers 1 comprise an inner layer and an outer layer, and a plastic water stop plate 2 is arranged between the inner layer and the outer layer; the center of the tunnel bottom plate is provided with a water permeable ditch 5 penetrating through the bottom plate, water permeable piles 6 are arranged at the bottom of the tunnel towards the water permeable ditch 5, the number of the water permeable piles 6 is three, the number of the water permeable piles is one in the middle line of the tunnel, and the number of the water permeable piles is one on both sides of the tunnel; the arch feet at two sides of the tunnel are respectively provided with a longitudinal U-shaped catchment ditch 3, and a rainwater grid 4 is arranged at the top end of the longitudinal U-shaped catchment ditch 3. Preferably, the inner layer has a thickness of 5 cm and the outer layer has a thickness of 35 cm.
The construction steps are as follows: 1. firstly hanging a single-layer net sheet rib after tunnel face excavation, and primarily spraying an inner layer to seal the tunnel face at time so as to ensure the stability of soil body of the tunnel face; 2. a plastic water stop plate 2 is hung outside the inner layer to form a first waterproof system, so that the water on the tunnel face is guaranteed to flow downwards to the arch bottom of the tunnel along the inner layer; 3. when the tunnel inverted arch is constructed, longitudinal U-shaped catchment ditches 3 are reserved at arch feet on two sides, broken stones are filled in the longitudinal U-shaped catchment ditches to form catchment channels along the tunnel direction, and water flowing downwards from the upper part of the tunnel through an inner layer is collected. The center of the tunnel bottom plate is provided with a water permeable ditch 5 penetrating through the bottom plate, three water permeable piles 6 are arranged at the bottom of the tunnel towards the water permeable ditch 5, one water permeable pile is arranged at the center line of the tunnel, and one water permeable pile is arranged at the two sides of the tunnel. So that the water of the tunnel face passes through the first waterproof system, most of the water is discharged to the bottom of the tunnel as main flow, and then permeates into the bottom of the tunnel through the water permeable piles 6, so that the pressure on primary support and structural water prevention of the tunnel is reduced; 4. the primary support steel arch is erected outside the plastic water stop plate 2, an outer layer is sprayed, primary support of the tunnel is completed, and water on the tunnel face is converged to the bottom of the tunnel along the primary sprayed inner layer under the protection of the plastic water stop plate 2, so that large-area water leakage of the primary support outer layer cannot be caused by convergence at the upper part of the tunnel; 5. a waterproof plate is applied to the primary support surface of the tunnel; 6. and (5) performing two layers of lining of the tunnel structure to finish the structure construction.
While the preferred embodiments of the present application have been described in detail, the present application is not limited to the above embodiments, and various changes may be made within the knowledge of those skilled in the art without departing from the spirit of the present application.

Claims (5)

1. The utility model provides a poor stratum undercut tunnel bilayer waterproof system of rich water which characterized in that: the rapid hardening water permeable concrete layer comprises an inner layer and an outer layer, and a plastic water stop plate is arranged between the inner layer and the outer layer; the center of the tunnel bottom plate is provided with a water permeable ditch penetrating through the bottom plate, and a water permeable pile is arranged at the bottom of the tunnel towards the water permeable ditch; longitudinal U-shaped water collecting grooves are reserved at arch feet on two sides of the tunnel.
2. The water-rich poor-formation undercut tunnel double-layer waterproof system according to claim 1, wherein: the thickness of the inner layer is 5 cm.
3. The water-rich poor-formation undercut tunnel double-layer waterproof system according to claim 2, wherein: the outer layer has a thickness of 35 cm.
4. A water-rich poor formation undercut tunnel bilayer waterproofing system according to claim 3, wherein: and a rainwater grid is arranged at the top end of the longitudinal U-shaped catchment ditch.
5. The water-rich poor-formation undercut tunnel double-layer waterproof system according to claim 4, wherein: the number of the permeable piles is three, one is arranged in the middle line of the tunnel, and one is arranged on each side.
CN202322357762.4U 2023-08-31 2023-08-31 Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum Active CN220748293U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322357762.4U CN220748293U (en) 2023-08-31 2023-08-31 Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322357762.4U CN220748293U (en) 2023-08-31 2023-08-31 Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum

Publications (1)

Publication Number Publication Date
CN220748293U true CN220748293U (en) 2024-04-09

Family

ID=90567762

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322357762.4U Active CN220748293U (en) 2023-08-31 2023-08-31 Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum

Country Status (1)

Country Link
CN (1) CN220748293U (en)

Similar Documents

Publication Publication Date Title
CN103741714B (en) Underground engineering full sheltered reverse excavation construction method
CN206722878U (en) A kind of mining light-duty filling counterfort
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN206512723U (en) A kind of multiple-layer horizontal coupling beam double-row pile and underground pipe gallery monolithic construction
CN101914925A (en) Basement by using optimized composite prefabricated arch wall as external wall
CN101418569B (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN208023593U (en) A kind of foundation pit fertilizer slot backfill structure in sponge city
CN109403332B (en) Method for combined excavation of layered bench sections of deep foundation pit of sandy cobble thick covering layer wide shallow valley
CN201321616Y (en) Deep foundation pit supporting, reinforcing, anti-seepage and waterproof structure
CN109024458A (en) A kind of coal mine subsidence land landscape revetment and the construction method of water-bed antiseepage
CN203161244U (en) Existing subway underground excavation running tunnel protection structure
CN105756100B (en) Basement post-pouring zone system and preparation method thereof
CN111425250B (en) Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system
CN220748293U (en) Double-layer waterproof system for underground excavation tunnel of poor water-rich stratum
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN206035045U (en) Prefabricated assembled underground granary of endocyst plastics
US20230349291A1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN111636483A (en) Waterproof device for reverse construction concrete structure gap and construction method
CN207987672U (en) A kind of permeable pavement structure
CN114233340B (en) Water spraying prevention construction method for coal mine underground roadway roof
CN216040465U (en) Ecological roadbed structure in sponge city based on original road
CN212772394U (en) Underground building supporting system
CN211547830U (en) Structure for preventing ground from being wetted
CN208009393U (en) A kind of non-dankly base manure slot backfill structure based on sponge city
CN111962632A (en) Rainwater sewer and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant