Auxiliary construction installation structure for dry-hanging ceramic veneer Download PDF

Info

Publication number
CN220666778U
CN220666778U CN202321093835.7U CN202321093835U CN220666778U CN 220666778 U CN220666778 U CN 220666778U CN 202321093835 U CN202321093835 U CN 202321093835U CN 220666778 U CN220666778 U CN 220666778U
Authority
CN
China
Prior art keywords
ceramic veneer
hanging
fixing
dry
fixed frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321093835.7U
Other languages
Chinese (zh)
Inventor
郑定浩
骆国华
蓝宇阳
黄婷婷
林凯希
王德福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou Construction Engineering Co ltd
Huizhou Construction Group Construction Engineering Co ltd
Original Assignee
Huizhou Construction Engineering Co ltd
Huizhou Construction Group Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou Construction Engineering Co ltd, Huizhou Construction Group Construction Engineering Co ltd filed Critical Huizhou Construction Engineering Co ltd
Priority to CN202321093835.7U priority Critical patent/CN220666778U/en
Application granted granted Critical
Publication of CN220666778U publication Critical patent/CN220666778U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model relates to a field of super large specification ceramic veneer installation especially relates to a dry-hanging ceramic veneer auxiliary construction mounting structure, and it includes coupling assembling, dead lever and fixed frame, coupling assembling is provided with a plurality of, and is a plurality of coupling assembling all includes mounting and first connecting piece, a plurality of the equal bolt fastening of mounting is in the wall, and is a plurality of first connecting piece bolt fastening respectively in each mounting, the dead lever is provided with a plurality of, a plurality of the dead lever bolt fastening respectively in each first connecting piece, a plurality of the dead lever is all fixed to be provided with a plurality of couples, a plurality of hanging holes with each couple one-to-one are seted up to the fixed frame, a plurality of couple peg graft the cooperation with each hanging hole respectively, fixed frame bond the cooperation and have ceramic veneer. This application has the manpower and materials that reduce consumption when setting up ceramic decorative panel in the wall, improves the effect of efficiency of construction.

Description

Auxiliary construction installation structure for dry-hanging ceramic veneer
Technical Field
The application relates to the field of ultra-large ceramic veneer installation, in particular to a dry-hanging ceramic veneer auxiliary construction installation structure.
Background
Along with the progress of science and technology, the ultra-conventional material is continuously applied to indoor fine-finishing construction. The ultra-large ceramic facing plate is an innovative and upgraded product of ceramic polished tiles, has the texture of natural stone, has color and texture more similar to those of stone, and is often applied to large-scale decoration engineering.
At present, the construction of the ultra-large ceramic veneer has no operation regulations and technical standards, and the common installation mode is as follows: firstly, a plurality of fixing rods are vertically fixed on a wall surface at intervals, then a base layer plate is welded and fixed on one side, far away from the wall surface, of each fixing rod, finally an adhesive is coated on the base layer plate, and a ceramic veneer is bonded and matched with the base layer plate, so that the ceramic veneer is arranged on the wall surface. After the ceramic veneer is arranged on the wall surface, a supporting frame is additionally erected to support the ceramic veneer, so that the occurrence of the condition that the ceramic veneer falls off from the base layer board due to the fact that the adhesive does not reach the specified bonding strength is reduced. And after the adhesive reaches the specified bonding strength, the support frame is removed and transferred.
Aiming at the related technology, the erection, dismantling and transferring of the support frame consume more manpower and material resources, and the construction efficiency is reduced.
Disclosure of Invention
In order to reduce the manpower and materials that consume when setting up ceramic veneer in the wall, improve the efficiency of construction, this application provides a hang ceramic veneer futilely and assist construction mounting structure.
The application provides a hang ceramic veneer futilely auxiliary construction mounting structure adopts following technical scheme:
the utility model provides a hang ceramic veneer futilely and assist construction mounting structure, includes coupling assembling, dead lever and fixed frame, coupling assembling is provided with a plurality ofly, a plurality of coupling assembling all includes mounting and first connecting piece, a plurality of equal bolt fastening of mounting is in the wall, a plurality of first connecting piece bolt fastening respectively in each mounting, the dead lever is provided with a plurality of, a plurality of the dead lever bolt cooperation respectively in each first connecting piece, a plurality of the dead lever is all fixed to be provided with a plurality of couples, a plurality of hanging holes with each couple one-to-one are seted up to the fixed frame, a plurality of the couple is pegged graft the cooperation with each hanging hole respectively, fixed frame bonding cooperation has ceramic veneer.
Through adopting above-mentioned technical scheme, before setting up ceramic veneer in the wall, earlier with the gluing agent with ceramic veneer bonding fit in fixed frame, after the gluing agent between ceramic veneer and the fixed frame reaches enough intensity, hang fixed frame and ceramic veneer futilely in each dead lever again, and then avoided the condition of direct bonding ceramic veneer and wall after the basic unit board is painted gluing agent, when having ensured ceramic veneer futilely hanging in the wall, the gluing agent between ceramic veneer and the fixed frame has reached appointed bonding strength, thereby promoted the stability of junction between ceramic veneer and the wall, reduced the emergence of the condition that ceramic veneer drops. And the condition that the support frame is required to be erected to support the ceramic veneer is avoided, the manpower and material resources consumed when the ceramic veneer is arranged on the wall surface are reduced, and the construction efficiency is improved.
Optionally, the plurality of fixing pieces are all provided with first adjusting grooves extending along the X-axis direction in a penetrating manner, the plurality of first connecting pieces are all provided with second adjusting grooves extending along the Y-axis direction in a penetrating manner, and the plurality of first connecting pieces and the fixing pieces are fixed through first adjusting bolts penetrating through the first adjusting grooves and the second adjusting grooves; the first connecting pieces are also provided with third adjusting grooves extending along the Z-axis direction in a penetrating mode, and the first connecting pieces and the fixing rods are fixed through second adjusting bolts penetrating through the third adjusting grooves.
By adopting the technical scheme, the positions of the fixing rods and the first connecting pieces are adjusted, so that the positions and angles of the fixing frames are changed, and the ceramic veneer is more accurately arranged at the appointed position.
Optionally, a plurality of grooves extending along the length direction of the fixing frame are formed in one side edge of the fixing frame, which is adhered to the ceramic veneer.
Through adopting above-mentioned technical scheme, a plurality of recesses have increased the frictional force of junction between gluing agent and the fixed frame to be favorable to fixedly bonding the ceramic veneer in fixed frame.
Optionally, a plurality of one side of dead lever is provided with the stiffening rod, and a plurality of the dead lever is all fixed to be set up in the stiffening rod.
Through adopting above-mentioned technical scheme, the reinforcing rod links to each other each dead lever to the stability of junction between the adjacent dead lever has been increased.
Optionally, the fixed frame includes horizontal pole and montant, the horizontal pole is provided with two, just the montant is provided with a plurality of, a plurality of the both ends of montant are fixed connection respectively in two horizontal poles.
Through adopting above-mentioned technical scheme, a plurality of montants have increased the stability of junction between two horizontal poles to be favorable to making the more firm bonding cooperation of ceramic decorative board in fixed frame.
Optionally, the connection part of a plurality of montants and each lateral rod is all fixed and is provided with the second connecting piece, and a plurality of the second connecting piece all is "L".
Through adopting above-mentioned technical scheme, the stability of junction between second connecting piece messenger montant and the horizontal pole increases to further be favorable to making the more firm bonding of ceramic decorative board cooperate in fixed frame.
Optionally, a plurality of couple all sets up in each stiffener, a plurality of couple divide into two sets of couple, and two sets of couple respectively along the length direction evenly distributed of two stiffeners, a plurality of the hanging hole all sets up in each horizontal pole, a plurality of the hanging hole divide into two sets of, two sets of the hanging hole respectively with two sets of couple one-to-one.
Through adopting above-mentioned technical scheme, when ceramic veneer hung and locates the wall, evenly distributed's couple is with the even transmission of load to stiffener and horizontal pole to be favorable to reducing the emergence of stiffener and the circumstances of horizontal pole damage.
Optionally, the external dimension of the fixed frame is the same as the external dimension of the ceramic veneer.
Through adopting above-mentioned technical scheme, when transporting ceramic decorative board, fixed frame provides extra support for the edge of ceramic decorative board to be favorable to reducing the emergence of the circumstances that ceramic decorative board damaged because of colliding with.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the ceramic veneer is arranged in front of the wall surface, the ceramic veneer is bonded and matched with the fixing frame by using the adhesive, after the adhesive between the ceramic veneer and the fixing frame reaches enough strength, the fixing frame and the ceramic veneer are dried and hung on each fixing rod, and then the situation that the ceramic veneer is directly bonded with the wall surface after the base plate is coated with the adhesive is avoided, when the ceramic veneer is dried and hung on the wall surface, the adhesive between the ceramic veneer and the fixing frame reaches the appointed bonding strength, so that the stability of the joint between the ceramic veneer and the wall surface is improved, and the falling situation of the ceramic veneer is reduced. And the condition that the support frame is required to be erected to support the ceramic veneer is avoided, the manpower and material resources consumed when the ceramic veneer is arranged on the wall surface are reduced, and the construction efficiency is improved.
2. The positions of the fixing rods and the first connecting pieces are adjusted, so that the positions and angles of the fixing frames are changed, and the ceramic veneer can be accurately arranged at the designated position.
3. The grooves increase the friction force at the joint between the adhesive and the fixed frame, thereby being beneficial to fixedly adhering the ceramic veneer to the fixed frame.
Drawings
Fig. 1 is a schematic diagram of the overall structure of an embodiment of the present application.
Fig. 2 is a schematic diagram of a connection relationship between a ceramic veneer and a fixed frame according to an embodiment of the present application.
Fig. 3 is an enlarged schematic view of the portion a in fig. 2.
Fig. 4 is an exploded view of a connection assembly according to an embodiment of the present application.
Fig. 5 is an exploded schematic view of the overall structure of an embodiment of the present application.
Fig. 6 is a bottom view of a stationary frame according to an embodiment of the present application.
Fig. 7 is an enlarged schematic view of a portion B in fig. 5.
Reference numerals illustrate: 1. a fixed rod; 2. a fixed frame; 3. a fixing member; 4. a first connector; 5. a reinforcing rod; 6. a second connector; 7. ceramic veneer; 21. a cross bar; 22. a vertical rod; 31. a first fixing plate; 32. a second fixing plate; 41. a second regulating groove; 42. a first adjusting bolt; 43. a first gasket; 44. a third regulating groove; 45. a second adjusting bolt; 46. a second gasket; 51. a hook; 211. a hanging hole; 212. a groove; 321. a first adjustment tank.
Detailed Description
The present application is described in further detail below in conjunction with figures 1-7.
The embodiment of the application discloses a dry-hanging ceramic veneer auxiliary construction mounting structure. Referring to fig. 1, the dry-hanging ceramic veneer auxiliary construction installation structure includes a connection assembly, a fixing rod 1 and a fixing frame 2. In the embodiment, the thickness direction of the wall surface is set as the X-axis direction, the length direction of the wall surface is set as the Y-axis direction, and the height direction of the wall surface is set as the Z-axis direction.
Referring to fig. 1 and 2, in the embodiment of the present application, the number of fixing bars 1 is set to six. Each fixing rod 1 is arranged along the Z-axis direction, and each fixing rod 1 is uniformly distributed on the wall surface along the Y-axis direction. The connecting assembly is provided with a plurality of, and a plurality of connecting assembly divide into six groups, and every group connecting assembly's quantity sets up to three, and three connecting assembly all along the length direction evenly distributed of dead lever 1.
Referring to fig. 3, the connection assembly includes a fixing member 3 and a first connection member 4, and the fixing member 3 includes a first fixing plate 31 and a second fixing plate 32. The first fixing plate 31 is rectangular, and four corners of the first fixing plate 31 are fixed on the wall surface through bolts. In the embodiment of the present application, the number of the second fixing plates 32 is two, the two second fixing plates 32 are horizontally welded and fixed on the first fixing plate 31, and the two second fixing plates 32 are respectively disposed near two sides of the first fixing plate 31.
Referring to fig. 3 and 4, the second fixing plate 32 is penetratively provided with a first adjustment groove 321 extending in the X-axis direction. In the embodiment of the present application, the number of the first connecting pieces 4 is set to two. The two first connecting pieces 4 are respectively arranged on the two second fixing plates 32, and the two first connecting pieces 4 are opposite to each other. The first connecting piece 4 is in an L shape, and one end of the first connecting piece 4 is provided with a second adjusting groove 41 extending along the Y-axis direction in a penetrating way. The first adjusting groove 321 and the second adjusting groove 41 are penetrated with a first adjusting bolt 42, the first adjusting bolt 42 is in threaded fit with a nut, and the nut abuts against the bottom of the second fixing plate. When the position of the fixing lever 1 needs to be adjusted, the first adjusting bolt 42 is rotated to loosen the connection between the first connecting piece 4 and the second fixing plate 32 and move the first connecting piece 4 along the first adjusting groove 321 and the second adjusting groove 41. In addition, a first spacer 43 is interposed between the first adjusting bolt 42 and the first and second fixing plates 4 and 32 so as to increase the stress area between the first adjusting bolt 42 and the first connecting member 4, thereby increasing the stability of the connection between the first connecting member 4 and the second fixing plate 32.
Referring to fig. 3 and 4, the other end of the first connecting member 4 is provided with a third adjustment groove 44 extending in the Z-axis direction therethrough. The third fixing groove is penetrated with a second adjusting bolt 45, and the fixing rod 1 is arranged on the first connecting piece 4 through the second adjusting bolt 45. When the position of the fixing lever 1 needs to be adjusted, the second adjusting bolt 45 is rotated to loosen the connection between the fixing lever 1 and the first connecting member 4 and move the fixing lever 1 along the third adjusting groove 44. A second spacer 46 is arranged between the second adjusting bolt 45 and the first connecting piece 4 in a cushioning manner so as to increase the stress area between the second adjusting bolt 45 and the first connecting piece 4, thereby increasing the stability of the joint between the first connecting piece 4 and the fixed rod 1.
Referring to fig. 5, two ends of each fixing rod 1 are provided with reinforcing rods 5, in this embodiment, the reinforcing rods 5 are made of equilateral angle steel, one sides of the two reinforcing rods 5 are welded and fixed on the top and bottom of each fixing rod 1 respectively, and the other sides of the two reinforcing rods 5 are far away from each other.
Referring to fig. 5 and 6, a plurality of hooks 51 are bolted to the side of the reinforcing rod 5 remote from the fixing rod 1. In the embodiment of the present application, the number of hooks 51 is set to three, and the three hooks 51 are uniformly distributed along the length direction of the reinforcing rod 5. The fixed frame 2 includes the cross bars 21 and the vertical bars 22, and in the present embodiment, the number of the cross bars 21 is set to two, and the number of the vertical bars 22 is set to six. Three hanging holes 211 corresponding to the hooks 51 one by one are formed in the bottoms of the two cross bars 21, so that the cross bars 21 can be conveniently hung on the reinforcing rods 5. The two cross bars 21 are all arranged along the Y-axis direction, the vertical bars 22 are all arranged between the two cross bars 21 along the Z-axis direction, and the vertical bars 22 are uniformly distributed along the length direction of the cross bars. The second connecting piece 6 is arranged at the joint between each vertical rod 22 and the two transverse rods 21, the second connecting piece 6 is L-shaped, and two ends of the second connecting piece 6 are respectively fixed on the transverse rods 21 and the vertical rods 22 by bolts so as to increase the stability of the joint between the transverse rods 21 and the vertical rods 22.
Referring to fig. 5 and 7, a ceramic veneer 7 is adhesively fitted to a side of the fixed frame 2 remote from the wall surface, and the shape and size of the ceramic veneer 7 are the same as those of the fixed frame 2. The two cross bars 21 are all offered recess 212 on the side that keeps away from the wall, and recess 212 extends along Y axle direction, and the lateral wall of recess 212 is close to the both ends setting of cross bar 21 respectively. The grooves 212 increase the friction between the cross bar 21 and the adhesive so that the adhesive can be firmly adhered to the cross bar 21, thereby reducing the occurrence of the situation that the ceramic veneer 7 falls off from the fixed frame 2.
The implementation principle of the auxiliary construction installation structure of the dry-hanging ceramic veneer is as follows: firstly, four corner bolts of a plurality of first fixing plates 31 are fixed on a wall surface, and a plurality of second adjusting bolts 45 penetrate through the third adjusting grooves 44, so that the first connecting pieces 4 are fixedly arranged on the fixing rods 1; next, the first adjusting grooves 321 are communicated with the second adjusting grooves 41, a plurality of first adjusting bolts 42 are penetrated through the first adjusting grooves 321 and the second adjusting grooves 41, and the first connecting pieces 4 are fixedly arranged on the second fixing plates 32 through nuts, so that the fixing rods 1 are fixedly arranged on the wall surface; then, each first adjusting bolt 42 is rotated to move each first connecting member 4 in the X-axis direction and the Y-axis direction, and each second adjusting bolt 45 is rotated to move each fixing rod 1 in the Z-axis direction, so that the sides of the fixing rods 1 away from the wall surface are flush.
Then, respectively welding and fixing an angle steel at the top and the bottom of each fixing rod 1, dividing six hooks 51 into two groups of three hooks 51, and respectively fixing each group of hooks 51 to each angle steel by bolts; finally, the adhesive is coated on the fixed frame 2, the ceramic veneer 7 is adhered and matched on the fixed frame 2, and when the adhesive is solidified and reaches a specified strength index, the ceramic veneer 7 and the fixed frame 2 are hung on the hooks 51. Thereby avoided directly with the emergence of the condition of ceramic veneer 7 bonding with the wall after the basic unit board is painted the gluing agent, promoted the stability of junction between ceramic veneer 7 and the wall, reduced the emergence of the condition that ceramic veneer 7 drops. And avoided the emergence that needs erect the condition that the support frame supported ceramic veneer 7, reduced the manpower and materials that consume when setting up ceramic veneer 7 in the wall, improved the efficiency of construction.
The foregoing are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in any way, therefore: all equivalent changes in structure, shape and principle of this application should be covered in the protection scope of this application.

Claims (8)

1. The utility model provides a hang supplementary construction mounting structure of ceramic decorative board futilely which characterized in that: including coupling assembling, dead lever (1) and fixed frame (2), coupling assembling is provided with a plurality of, a plurality of coupling assembling all includes mounting (3) and first connecting piece (4), a plurality of mounting (3) all bolt fastening in the wall, a plurality of first connecting piece (4) bolt fastening in each mounting (3) respectively, dead lever (1) is provided with a plurality of, a plurality of dead lever (1) bolt fastening in each first connecting piece (4) respectively, a plurality of dead lever (1) all are fixed be provided with a plurality of couples (51), a plurality of hanging holes (211) with each couple (51) one-to-one are seted up to fixed frame (2), a plurality of couple (51) are pegged graft respectively with each hanging hole (211), fixed frame (2) bonding cooperation has ceramic veneer (7).
2. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 1, wherein: a plurality of fixing pieces (3) are respectively provided with a first adjusting groove (321) extending along the X-axis direction in a penetrating way, a plurality of first connecting pieces (4) are respectively provided with a second adjusting groove (41) extending along the Y-axis direction in a penetrating way, and the first connecting pieces (4) and the fixing pieces (3) are fixed through first adjusting bolts (42) penetrating through the first adjusting grooves (321) and the second adjusting grooves (41); a plurality of first connecting pieces (4) are also provided with third adjusting grooves (44) extending along the Z-axis direction in a penetrating way, and a plurality of first connecting pieces (4) and each fixing rod (1) are fixed through second adjusting bolts (45) penetrating through the third adjusting grooves (44).
3. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 1, wherein: a plurality of grooves (212) extending along the length direction of the fixing frame (2) are formed in one side edge of the fixing frame, which is adhered to the ceramic veneer (7).
4. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 1, wherein: one side of a plurality of the fixing rods (1) is provided with a reinforcing rod (5), and a plurality of the fixing rods (1) are fixedly arranged on the reinforcing rod (5).
5. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 1, wherein: the fixed frame (2) comprises two cross bars (21) and two vertical bars (22), wherein the two cross bars (21) are arranged, the plurality of vertical bars (22) are arranged, and two ends of the plurality of vertical bars (22) are respectively and fixedly connected with the two cross bars (21).
6. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 5, wherein: a plurality of second connecting pieces (6) are fixedly arranged at the joints of the vertical rods (22) and the cross rods (21), and the second connecting pieces (6) are L-shaped.
7. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 5, wherein: a plurality of couple (51) all set up in each stiffening rod (5), a plurality of couple (51) divide into two sets of, and two sets of couple (51) are respectively along the length direction evenly distributed of two stiffening rods (5), and a plurality of hanging hole (211) all open and are located each horizontal pole (21), and a plurality of hanging hole (211) divide into two sets of, two sets of hanging hole (211) respectively with two sets of couple (51) one-to-one.
8. The dry-hanging ceramic veneer auxiliary construction mounting structure according to claim 1, wherein: the external dimension of the fixed frame (2) is the same as the external dimension of the ceramic veneer (7).
CN202321093835.7U 2023-05-08 2023-05-08 Auxiliary construction installation structure for dry-hanging ceramic veneer Active CN220666778U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321093835.7U CN220666778U (en) 2023-05-08 2023-05-08 Auxiliary construction installation structure for dry-hanging ceramic veneer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321093835.7U CN220666778U (en) 2023-05-08 2023-05-08 Auxiliary construction installation structure for dry-hanging ceramic veneer

Publications (1)

Publication Number Publication Date
CN220666778U true CN220666778U (en) 2024-03-26

Family

ID=90337256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321093835.7U Active CN220666778U (en) 2023-05-08 2023-05-08 Auxiliary construction installation structure for dry-hanging ceramic veneer

Country Status (1)

Country Link
CN (1) CN220666778U (en)

Similar Documents

Publication Publication Date Title
CN109736504B (en) Detachable suspended ceiling edge keel system and construction method thereof
CN107327111A (en) A kind of dried hanging hang structure and finishing systems
CN216195894U (en) Light trough structure and suspended ceiling
CN220666778U (en) Auxiliary construction installation structure for dry-hanging ceramic veneer
CN207122081U (en) A kind of dried hanging hang structure and finishing systems
CN102146703A (en) Installation and fixing method for wallboards and special positioning fixer for method
CN111809823A (en) Indoor wall surface stone decorative plate semi-unit type dry hanging system and installation method thereof
CN216076076U (en) Hang installation component and use its architectural decoration structure
CN212656419U (en) Novel peripheral revetment structure of assembled
CN216476073U (en) Hyperboloid stair decorative board mounting structure
CN212427897U (en) Dry-hanging stone system
CN212427881U (en) Wall surface hanging integral external corner system
CN212613203U (en) Reinforced concrete wall structure
CN113833196A (en) Light trough structure and suspended ceiling
CN213742082U (en) Assembled floor mounting structure
CN214833746U (en) Energy-conserving assembled light steel wall connection structure of building
CN216552577U (en) Hang stone material curtain futilely
CN214154391U (en) Novel fishing light complementary support
CN215290765U (en) Decorative structure of stone wall expansion joint
CN221168339U (en) Assembled suspended ceiling
CN217326236U (en) Dismantle convenient building interior decoration board
CN220504245U (en) Stone plate connecting device of stone curtain wall
CN219365044U (en) Prefabricated steel structure integrated assembled green building component
CN221095548U (en) Hanging framework and stone curtain wall mounting system
CN208650447U (en) A kind of curved decorative plate mounting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant