CN219365044U - Prefabricated steel structure integrated assembled green building component - Google Patents

Prefabricated steel structure integrated assembled green building component Download PDF

Info

Publication number
CN219365044U
CN219365044U CN202320394814.2U CN202320394814U CN219365044U CN 219365044 U CN219365044 U CN 219365044U CN 202320394814 U CN202320394814 U CN 202320394814U CN 219365044 U CN219365044 U CN 219365044U
Authority
CN
China
Prior art keywords
building structure
wall
building
prefabricated steel
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202320394814.2U
Other languages
Chinese (zh)
Inventor
孙皓田
吕冠军
刁涣玺
夏政华
朱飞
刘亚丹
李政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Beiyang Architectural Design Co ltd
Original Assignee
Qingdao Beiyang Architectural Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Beiyang Architectural Design Co ltd filed Critical Qingdao Beiyang Architectural Design Co ltd
Priority to CN202320394814.2U priority Critical patent/CN219365044U/en
Application granted granted Critical
Publication of CN219365044U publication Critical patent/CN219365044U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

本实用新型提供一种预制钢结构一体化装配式绿色建筑构件,涉及建筑构件技术领域,包括建筑结构墙,所述建筑结构墙的侧面均匀贯穿设置有多个紧固件,所述建筑结构墙的一侧设置有建筑结构件,所述建筑结构墙的底部设置有底撑机构,所述紧固件的一端安装有螺帽,所述紧固件的一端外壁设置有卡扣件,所述卡扣件的侧面连接有支撑块,所述建筑结构墙的侧面固定安装有支撑杆。本实用新型通过将紧固件利用螺帽卡装在建筑结构墙的侧面,且通过支撑块挤压在支撑杆上进行装配连接,从而有利于通过将紧固件连接在墙体上,进而实现了有效地实现了侧面支撑作用,即可提升了侧面强度,提高了与墙体连接之间的刚性,进而保证了进一步提升了整体的稳定性。

The utility model provides a prefabricated steel structure integrated assembly type green building component, which relates to the technical field of building components, including a building structure wall, the side of the building structure wall is uniformly provided with a plurality of fasteners, the building structure wall One side of the building structure is provided with a building structure, the bottom of the building structure wall is provided with a bottom support mechanism, one end of the fastener is installed with a nut, and the outer wall of one end of the fastener is provided with a buckle. A support block is connected to the side of the buckle, and a support bar is fixedly installed on the side of the building structure wall. The utility model clamps the fastener on the side of the building structure wall by using a nut, and squeezes the support block on the support rod for assembly and connection, thereby facilitating the connection of the fastener to the wall, thereby realizing In order to effectively realize the side support function, the side strength can be improved, the rigidity between the connection with the wall can be improved, and the overall stability can be further improved.

Description

一种预制钢结构一体化装配式绿色建筑构件A prefabricated steel structure integrated assembly type green building component

技术领域technical field

本实用新型涉及建筑构件技术领域,尤其涉及一种预制钢结构一体化装配式绿色建筑构件。The utility model relates to the technical field of building components, in particular to a prefabricated steel structure integrated assembly type green building component.

背景技术Background technique

随着建筑市场创新的需求,施工建设朝着高效、快速、质量等方向发展,装配式建筑作为一种新的建筑形式,它在保证现场施工有序管理的基础上,提高施工效率,缩短施工周期,并且对施工质量的控制起到了非常重要的作用。装配式建筑是指把传统建造方式中的大量现场作业工作转移到工厂进行,在工厂加工制作好建筑用构件和配件(如楼板、墙板、楼梯、阳台等),运输到建筑施工现场,通过可靠的连接方式在现场装配安装而成的建筑。With the demand for innovation in the construction market, construction is developing in the direction of high efficiency, speed, and quality. As a new form of construction, prefabricated buildings improve construction efficiency and shorten construction time on the basis of ensuring orderly management of on-site construction. cycle, and played a very important role in the control of construction quality. Prefabricated building refers to the transfer of a large number of on-site operations in the traditional construction method to the factory, where the building components and accessories (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in the factory, and transported to the construction site. Reliable connections are assembled and installed on site.

现有技术中,如中国专利号为:CN217480614U的“装配式建筑构件”,包括:主板和位于主板两端并垂直于主板设置的端板,至少一个所述端板的两侧边缘处各具有一向远离主板方向延伸的折弯板,2个面对面间隔设置的折弯板之间围成一可供外部构件嵌入的槽形安装区。本实用新型可以用作横梁或者立柱或者其他连接结构,在提高自身结构强度的同时,可以实现与外部构件的快速安装且具有良好的结构稳定性。In the prior art, as the Chinese patent number is: CN217480614U "fabricated building components", comprising: a main board and end plates positioned at both ends of the main board and perpendicular to the main board, at least one of the two side edges of the end board has a A bent plate extending away from the main board, and a groove-shaped mounting area for external components to be embedded is enclosed between two face-to-face bent plates arranged at intervals. The utility model can be used as a beam or a column or other connecting structures, and can realize fast installation with external components while improving its own structural strength and has good structural stability.

但是现有的预制钢结构的装配构件虽然实现了有效的装配效果,但是在安装与腔体连接部分缺乏紧固连接件,以至于造成了该建筑构件的强度存在不足的情况,以至于即使提升了自身强度后还是存在结构件与墙体之间会出现松动进而造成稳定性不足发生倒塌危险的问题。However, although the assembly components of the existing prefabricated steel structures have achieved effective assembly effects, there is a lack of fastening connectors in the connection between the installation and the cavity, so that the strength of the building components is insufficient, so that even if the lifting After improving its own strength, there is still the problem that there will be looseness between the structural parts and the wall, resulting in insufficient stability and the risk of collapse.

实用新型内容Utility model content

本实用新型的目的是为了解决现有技术中存在预制钢结构的装配构件虽然实现了有效的装配效果,但是在安装与腔体连接部分缺乏紧固连接件,以至于造成了该建筑构件的强度存在不足的情况,以至于即使提升了自身强度后还是存在结构件与墙体之间会出现松动进而造成稳定性不足发生倒塌危险的问题,而提出的一种预制钢结构一体化装配式绿色建筑构件。The purpose of this utility model is to solve the problem that the assembly components of the prefabricated steel structure in the prior art have achieved an effective assembly effect, but there is a lack of fastening connectors in the connection between the installation and the cavity, so that the strength of the building components is caused. There are insufficient conditions, so that even after improving its own strength, there will still be looseness between the structural parts and the wall, resulting in insufficient stability and the risk of collapse. A prefabricated steel structure integrated prefabricated green building is proposed member.

为了实现上述目的,本实用新型采用了如下技术方案:一种预制钢结构一体化装配式绿色建筑构件,包括建筑结构墙,所述建筑结构墙的侧面均匀贯穿设置有多个紧固件,所述建筑结构墙的一侧设置有建筑结构件,所述建筑结构墙的底部设置有底撑机构,所述紧固件的一端安装有螺帽,所述紧固件的一端外壁设置有卡扣件,所述卡扣件的侧面连接有支撑块,所述建筑结构墙的侧面固定安装有支撑杆,所述支撑块的一端卡装在支撑杆的外壁。In order to achieve the above purpose, the utility model adopts the following technical scheme: a prefabricated steel structure integrated assembly type green building component, including a building structure wall, the side of the building structure wall is uniformly provided with a plurality of fasteners, so One side of the building structure wall is provided with a building structure, the bottom of the building structure wall is provided with a bottom support mechanism, one end of the fastener is installed with a nut, and the outer wall of one end of the fastener is provided with a buckle A support block is connected to the side of the buckle, a support bar is fixedly installed on the side of the building structure wall, and one end of the support block is clamped on the outer wall of the support bar.

优选的,所述建筑结构件的顶部均匀分布有多个网格架,所述网格架的两端设置有装配连接件,所述网格架的顶部设置有箱体。Preferably, a plurality of grid frames are evenly distributed on the top of the building structure, assembly connectors are provided at both ends of the grid frame, and boxes are provided on the top of the grid frame.

优选的,所述底撑机构的底部固定安装有底撑座,所述底撑座的底部连接有连接座。Preferably, a bottom support seat is fixedly installed on the bottom of the bottom support mechanism, and a connecting seat is connected to the bottom of the bottom support seat.

优选的,所述底撑座的内侧设置有卡装板,所述连接座的内侧开设有卡装槽,所述卡装板与卡装槽之间卡装连接。Preferably, a clamping plate is provided on the inner side of the bottom support, and a clamping groove is opened on the inner side of the connecting seat, and the clamping plate and the clamping groove are clamped and connected.

优选的,所述建筑结构墙的一侧两端设置有主体架,所述主体架的侧面贯穿开设有第一安装孔,所述建筑结构墙的侧面两端贯穿开设有第二安装孔,所述第一安装孔与第二安装孔之间相连通。Preferably, a main frame is provided at both ends of one side of the building structure wall, a first mounting hole is opened through the side of the main frame, and a second mounting hole is opened through both ends of the side of the building structure wall, so The first installation hole communicates with the second installation hole.

优选的,所述紧固件的两端活动连接有垫片,所述垫片的一侧贴合在螺帽的侧面,所述垫片的另一侧贴合在建筑结构墙的侧面。Preferably, gaskets are movably connected to both ends of the fastener, one side of the gasket is attached to the side of the nut, and the other side of the gasket is attached to the side of the building structure wall.

优选的,所述支撑杆的侧面固定连接有多个支撑棒,所述支撑棒的一端均固定连接在建筑结构墙的一侧。Preferably, a plurality of support rods are fixedly connected to the side of the support rod, and one end of the support rods is fixedly connected to one side of the building structure wall.

优选的,所述建筑结构墙的侧面贯穿开设有穿孔,所述紧固件的两端活动贯穿于穿孔的内侧。Preferably, a perforation is formed on the side of the building structure wall, and the two ends of the fastener are movable through the inner side of the perforation.

优选的,所述建筑结构件的一端均匀分布有多个侧支架,所述建筑结构件的一侧均匀分布有多个防护架。Preferably, a plurality of side brackets are evenly distributed on one end of the building structure, and a plurality of protective frames are evenly distributed on one side of the building structure.

优选的,所述建筑结构件的底部设置有多个中部撑架,所述中部撑架的底部与底撑机构的顶部之间连接,所述底撑机构的侧面贯穿开设有多个侧装孔。Preferably, the bottom of the building structure is provided with a plurality of middle brackets, the bottom of the middle brackets is connected to the top of the bottom support mechanism, and the side of the bottom support mechanism is provided with a plurality of side mounting holes .

与现有技术相比,本实用新型的优点和积极效果在于,Compared with the prior art, the utility model has the advantages and positive effects that:

1、本实用新型中,通过设置有紧固件,通过将紧固件利用螺帽卡装在建筑结构墙的侧面,且通过支撑块挤压在支撑杆上进行装配连接,从而有利于通过将紧固件连接在墙体上,进而实现了有效地实现了侧面支撑作用,即可提升了侧面强度,提高了与墙体连接之间的刚性,进而保证了进一步提升了整体的稳定性,提升了安全性。1. In the present utility model, by providing fasteners, by clamping the fasteners on the side of the building structure wall with nuts, and extruding the support blocks on the support rods for assembly and connection, it is beneficial to pass the Fasteners are connected to the wall, thereby effectively realizing the side support function, which can improve the side strength, improve the rigidity between the connection with the wall, and further ensure the further improvement of the overall stability. security.

2、本实用新型中,通过有建筑结构件,通过将建筑结构件的顶部分布多个网格架并放置有箱体,且建筑结构件的两端通过装配连接件进行装配连接,从而方便了在使用的过程中,可通过装配连接件进行连接装配效果,实现了快速的连接装配效果,同时箱体放置在网格架上可培养一些绿色植物等,有利于提供了绿色环保的效果。2. In the utility model, through the building structural parts, a plurality of grid frames are distributed on the top of the building structural parts and a box is placed, and the two ends of the building structural parts are assembled and connected by assembly connectors, thereby facilitating In the process of use, the connection and assembly effect can be achieved by assembling the connecting parts, and the fast connection and assembly effect is realized. At the same time, some green plants can be cultivated when the cabinet is placed on the grid frame, which is beneficial to provide a green and environmental protection effect.

附图说明Description of drawings

图1为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的立体结构示意图;Fig. 1 is a three-dimensional structural schematic diagram of a prefabricated steel structure integrated assembly type green building component proposed by the utility model;

图2为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的另一角度结构示意图;Fig. 2 is another perspective structure diagram of a prefabricated steel structure integrated assembly type green building component proposed by the utility model;

图3为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的另一角度结构示意图;Fig. 3 is another perspective structure schematic diagram of a prefabricated steel structure integrated assembly type green building component proposed by the utility model;

图4为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的底撑构件结构示意图;Fig. 4 is a structural schematic diagram of the bottom support member of the prefabricated steel structure integrated assembly type green building member proposed by the utility model;

图5为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的侧撑构件的结构示意图;Fig. 5 is a structural schematic diagram of a side support component of a prefabricated steel structure integrated assembly type green building component proposed by the utility model;

图6为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的A处放大结构示意图;Fig. 6 is a schematic diagram of an enlarged structure at A of a prefabricated steel structure integrated assembly type green building component proposed by the utility model;

图7为本实用新型提出一种预制钢结构一体化装配式绿色建筑构件的B处放大结构示意图。Fig. 7 is a schematic diagram of an enlarged structure at B of a prefabricated steel structure integrated assembly type green building component proposed by the utility model.

图例说明:1、建筑结构墙;2、紧固件;3、建筑结构件;4、底撑机构;11、主体架;12、第一安装孔;13、第二安装孔;21、垫片;22、螺帽;23、卡扣件;24、支撑块;25、支撑杆;26、支撑棒;27、穿孔;31、网格架;32、装配连接件;33、侧支架;34、箱体;35、防护架;41、底撑座;42、侧装孔;43、卡装板;44、连接座;45、卡装槽。Legend: 1. Building structural wall; 2. Fasteners; 3. Building structural parts; 4. Bottom support mechanism; 11. Main frame; 12. First installation hole; 13. Second installation hole; 21. Gasket ; 22, nut; 23, buckle; 24, support block; 25, support rod; 26, support rod; 27, perforation; 31, grid frame; Box body; 35, protective frame; 41, bottom support seat; 42, side mounting hole; 43, clamping plate; 44, connecting seat; 45, clamping groove.

具体实施方式Detailed ways

为了能够更清楚地理解本实用新型的上述目的、特征和优点,下面结合附图和实施例对本实用新型做进一步说明。需要说明的是,在不冲突的情况下,本申请的实施例及实施例中的特征可以相互组合。In order to understand more clearly the above purpose, features and advantages of the utility model, the utility model will be further described below in conjunction with the accompanying drawings and embodiments. It should be noted that, in the case of no conflict, the embodiments of the present application and the features in the embodiments can be combined with each other.

在下面的描述中阐述了很多具体细节以便于充分理解本实用新型,但是,本实用新型还可以采用不同于在此描述的其他方式来实施,因此,本实用新型并不限于下面公开说明书的具体实施例的限制。In the following description, a lot of specific details have been set forth in order to fully understand the utility model, but the utility model can also be implemented in other ways that are different from those described here. Therefore, the utility model is not limited to the specific details of the following disclosure EXAMPLE LIMITATIONS.

实施例1Example 1

如图1-图7所示,本实用新型提供一种技术方案:一种预制钢结构一体化装配式绿色建筑构件,包括建筑结构墙1,建筑结构墙1的侧面均匀贯穿设置有多个紧固件2,建筑结构墙1的一侧设置有建筑结构件3,建筑结构墙1的底部设置有底撑机构4,紧固件2的一端安装有螺帽22,紧固件2的一端外壁设置有卡扣件23,卡扣件23的侧面连接有支撑块24,建筑结构墙1的侧面固定安装有支撑杆25,支撑块24的一端卡装在支撑杆25的外壁,建筑结构墙1的一侧两端设置有主体架11,主体架11的侧面贯穿开设有第一安装孔12,建筑结构墙1的侧面两端贯穿开设有第二安装孔13,第一安装孔12与第二安装孔13之间相连通,紧固件2的两端活动连接有垫片21,垫片21的一侧贴合在螺帽22的侧面,垫片21的另一侧贴合在建筑结构墙1的侧面,支撑杆25的侧面固定连接有多个支撑棒26,支撑棒26的一端均固定连接在建筑结构墙1的一侧,建筑结构墙1的侧面贯穿开设有穿孔27,紧固件2的两端活动贯穿于穿孔27的内侧。As shown in Figures 1 to 7, the utility model provides a technical solution: a prefabricated steel structure integrated assembly type green building component, including a building structure wall 1, the side of the building structure wall 1 is uniformly arranged with a plurality of tight Firmware 2, one side of the building structure wall 1 is provided with a building structure 3, the bottom of the building structure wall 1 is provided with a bottom support mechanism 4, one end of the fastener 2 is equipped with a nut 22, and one end of the fastener 2 is provided on the outer wall A buckle 23 is provided, the side of the buckle 23 is connected with a support block 24, the side of the building structure wall 1 is fixedly installed with a support rod 25, and one end of the support block 24 is clamped on the outer wall of the support rod 25, and the building structure wall 1 A main frame 11 is provided at both ends of one side of the main frame 11, and a first installation hole 12 is opened through the side of the main frame 11, and a second installation hole 13 is opened at both ends of the side of the building structure wall 1, and the first installation hole 12 is connected with the second The installation holes 13 are connected, and the two ends of the fastener 2 are movably connected with gaskets 21. One side of the gasket 21 is attached to the side of the nut 22, and the other side of the gasket 21 is attached to the building structure wall. 1, the side of the support rod 25 is fixedly connected with a plurality of support rods 26, and one end of the support rod 26 is fixedly connected to one side of the building structure wall 1, and the side of the building structure wall 1 is provided with a perforation 27, and the fastener The two ends of 2 move through the inner side of perforation 27.

在本实施例中,通过建筑结构墙1两端的主体架11实现了主体支撑,同时将第一安装孔12与第二安装孔13之间通过螺栓安装连接,实现主体安装的作用,随后通过紧固件2插装在建筑结构墙1的侧面,将垫片21与螺帽22均套设螺纹连接在紧固件2上,同时配合支撑块24与支撑杆25之间连接支撑,从而实现了侧面的强度,提升了墙体与结构件之间的稳定性,进而保证了安全性,通过支撑棒26可对支撑杆25提供了安装支撑的作用,穿孔27则可为紧固件2的贯穿安装提供了便捷。In this embodiment, the main body is supported by the main frame 11 at both ends of the building structure wall 1. At the same time, the first installation hole 12 and the second installation hole 13 are connected by bolts to realize the main body installation. The firmware 2 is inserted on the side of the building structure wall 1, and the gasket 21 and the nut 22 are threaded and connected to the fastener 2, and at the same time, the supporting block 24 and the supporting rod 25 are connected and supported, thereby realizing The strength of the side improves the stability between the wall and the structure, thereby ensuring safety. The support rod 26 can provide support for the installation of the support rod 25, and the perforation 27 can be used for the penetration of the fastener 2 Installation provides convenience.

实施例2Example 2

如图1-图7所示,建筑结构件3的顶部均匀分布有多个网格架31,网格架31的两端设置有装配连接件32,网格架31的顶部设置有箱体34,底撑机构4的底部固定安装有底撑座41,底撑座41的底部连接有连接座44,底撑座41的内侧设置有卡装板43,连接座44的内侧开设有卡装槽45,卡装板43与卡装槽45之间卡装连接,建筑结构件3的一端均匀分布有多个侧支架33,建筑结构件3的一侧均匀分布有多个防护架35,建筑结构件3的底部设置有多个中部撑架,中部撑架的底部与底撑机构4的顶部之间连接,底撑机构4的侧面贯穿开设有多个侧装孔42。As shown in Figures 1 to 7, a plurality of grid frames 31 are evenly distributed on the top of the building structure 3, the two ends of the grid frame 31 are provided with assembly connectors 32, and the top of the grid frame 31 is provided with a box body 34 , the bottom of the bottom support mechanism 4 is fixedly installed with a bottom support seat 41, the bottom of the bottom support seat 41 is connected with a connecting seat 44, the inner side of the bottom support seat 41 is provided with a clamping plate 43, and the inner side of the connecting seat 44 is provided with a clamping slot 45, the clamping connection between the clamping plate 43 and the clamping groove 45, a plurality of side brackets 33 are evenly distributed on one end of the building structure 3, and a plurality of protective frames 35 are evenly distributed on one side of the building structure 3, the building structure The bottom of the piece 3 is provided with a plurality of middle brackets, the bottom of the middle brackets is connected with the top of the bottom support mechanism 4 , and the side of the bottom support mechanism 4 is provided with a plurality of side mounting holes 42 .

在本实施例中,通过网格架31可便于站人和对箱体34提供放置空间的作用,通过装配连接件32则可为建筑结构件3提供了整体装配连接的作用,将两个装配连接件32之间对接同时利用螺栓进行紧固即可,安装便捷易操作,箱体34则可栽培一些植物有利于提升了绿色环保的效果,通过防护架35则可提供了防护放置人员站立时掉落的问题,底撑座41在底部对整体提供了支撑的效果,侧装孔42可在将底撑座41与卡装板43连接完成后进行限位固定,在此同时可先将卡装板43卡装入卡装槽45的内侧进而实现了便捷安装的作用,降低了安装难度,提升了安装效率。In this embodiment, the grid frame 31 can facilitate people standing and provide space for the box body 34, and the assembly connector 32 can provide the overall assembly and connection function of the building structure 3, and the two assemblies The connection between the connectors 32 can be fastened with bolts at the same time, and the installation is convenient and easy to operate. The box body 34 can cultivate some plants, which is conducive to improving the effect of environmental protection. The protective frame 35 can provide protection when placing people standing. For the problem of falling, the bottom support 41 provides support for the whole at the bottom. The side mounting hole 42 can be used to limit and fix the bottom support 41 and the clamping plate 43 after the connection is completed. At the same time, the clamp can be fixed first. The installation plate 43 is snapped into the inner side of the snap-in slot 45 so as to realize the function of convenient installation, reduce the difficulty of installation, and improve the installation efficiency.

本实施例的工作原理:在使用时,首先建筑结构墙1两端的主体架11实现了主体支撑,同时将第一安装孔12与第二安装孔13之间通过螺栓安装连接,实现主体安装的作用,随后通过紧固件2插装在建筑结构墙1的侧面,将垫片21与螺帽22均套设螺纹连接在紧固件2上,同时配合支撑块24与支撑杆25之间连接支撑,从而实现了侧面的强度,提升了墙体与结构件之间的稳定性,进而保证了安全性,通过支撑棒26可对支撑杆25提供了安装支撑的作用,穿孔27则可为紧固件2的贯穿安装提供了便捷,通过网格架31可便于站人和对箱体34提供放置空间的作用,通过装配连接件32则可为建筑结构件3提供了整体装配连接的作用,将两个装配连接件32之间对接同时利用螺栓进行紧固即可,安装便捷易操作,箱体34则可栽培一些植物有利于提升了绿色环保的效果,通过防护架35则可提供了防护放置人员站立时掉落的问题,底撑座41在底部对整体提供了支撑的效果,侧装孔42可在将底撑座41与卡装板43连接完成后进行限位固定,在此同时可先将卡装板43卡装入卡装槽45的内侧进而实现了便捷安装的作用,降低了安装难度,提升了安装效率。The working principle of this embodiment: when in use, firstly, the main body frame 11 at both ends of the building structure wall 1 realizes the main body support, and at the same time connects the first installation hole 12 and the second installation hole 13 by bolts to realize the installation of the main body function, and then the fastener 2 is inserted on the side of the building structure wall 1, the gasket 21 and the nut 22 are threaded on the fastener 2, and the connection between the support block 24 and the support rod 25 is matched. support, thereby realizing the strength of the side, improving the stability between the wall and the structural parts, thereby ensuring safety, the support rod 26 can provide the installation support for the support rod 25, and the perforation 27 can be used for tight The through-installation of the firmware 2 provides convenience. The grid frame 31 can facilitate the standing of people and provide space for the box body 34. The assembly connector 32 can provide the overall assembly and connection of the building structure 3. Just connect the two assembly connectors 32 and fasten them with bolts at the same time, the installation is convenient and easy to operate, and the box body 34 can cultivate some plants, which is conducive to improving the effect of environmental protection, and the protective frame 35 can provide protection. To solve the problem of people falling when standing, the bottom support 41 provides support for the whole at the bottom, and the side mounting holes 42 can be used to limit and fix the bottom support 41 and the clamping plate 43 after the connection is completed. At the same time The clamping plate 43 can be clamped into the inner side of the clamping groove 45 first, so as to realize the function of convenient installation, reduce the difficulty of installation, and improve the installation efficiency.

以上所述,仅是本实用新型的较佳实施例而已,并非是对本实用新型作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例应用于其它领域,但是凡是未脱离本实用新型技术方案内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本实用新型技术方案的保护范围。The above is only a preferred embodiment of the utility model, and is not intended to limit the utility model in other forms. Any skilled person who is familiar with this profession may use the technical content disclosed above to change or remodel it into an equivalent change. The equivalent embodiments are applied to other fields, but any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present utility model still belong to the technical solution of the present utility model scope of protection.

Claims (10)

1. The utility model provides a green building element of prefabricated steel construction integration assembled, includes building structure wall (1), its characterized in that: the side of building structure wall (1) evenly runs through and is provided with a plurality of fastener (2), one side of building structure wall (1) is provided with building structure (3), the bottom of building structure wall (1) is provided with bottom stay mechanism (4), nut (22) are installed to one end of fastener (2), one end outer wall of fastener (2) is provided with fastener (23), the side of fastener (23) is connected with supporting shoe (24), the side fixed mounting of building structure wall (1) has bracing piece (25), the one end cartridge of supporting shoe (24) is at the outer wall of bracing piece (25).
2. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the top evenly distributed of building structure spare (3) has a plurality of grid frames (31), the both ends of grid frame (31) are provided with assembly connecting piece (32), the top of grid frame (31) is provided with box (34).
3. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the bottom of the bottom support mechanism (4) is fixedly provided with a bottom support seat (41), and the bottom of the bottom support seat (41) is connected with a connecting seat (44).
4. A prefabricated steel structure integrated fabricated green building element according to claim 3, wherein: the inside of the bottom support seat (41) is provided with a clamping plate (43), the inside of the connecting seat (44) is provided with a clamping groove (45), and the clamping plate (43) is connected with the clamping groove (45) in a clamping way.
5. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the two ends of one side of the building structure wall (1) are provided with main body frames (11), first mounting holes (12) are formed in the side face of each main body frame (11) in a penetrating mode, second mounting holes (13) are formed in the two ends of the side face of the building structure wall (1) in a penetrating mode, and the first mounting holes (12) are communicated with the second mounting holes (13).
6. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: two ends of the fastener (2) are movably connected with gaskets (21), one side of each gasket (21) is attached to the side face of the nut (22), and the other side of each gasket (21) is attached to the side face of the building structure wall (1).
7. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the side of bracing piece (25) fixedly connected with a plurality of bracing pieces (26), the one end of bracing piece (26) all fixed connection is in one side of building structure wall (1).
8. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the side of the building structure wall (1) is provided with a through hole (27) in a penetrating mode, and two ends of the fastening piece (2) movably penetrate through the inner side of the through hole (27).
9. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: one end of the building structural member (3) is uniformly provided with a plurality of side brackets (33), and one side of the building structural member (3) is uniformly provided with a plurality of protection frames (35).
10. The prefabricated steel structure integrated fabricated green building element according to claim 1, wherein: the bottom of building structure (3) is provided with a plurality of middle supporting frames, be connected between the bottom of middle supporting frame and the top of bottom bracing mechanism (4), a plurality of side dress holes (42) have been run through to the side of bottom bracing mechanism (4).
CN202320394814.2U 2023-03-06 2023-03-06 Prefabricated steel structure integrated assembled green building component Expired - Fee Related CN219365044U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320394814.2U CN219365044U (en) 2023-03-06 2023-03-06 Prefabricated steel structure integrated assembled green building component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320394814.2U CN219365044U (en) 2023-03-06 2023-03-06 Prefabricated steel structure integrated assembled green building component

Publications (1)

Publication Number Publication Date
CN219365044U true CN219365044U (en) 2023-07-18

Family

ID=87114535

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320394814.2U Expired - Fee Related CN219365044U (en) 2023-03-06 2023-03-06 Prefabricated steel structure integrated assembled green building component

Country Status (1)

Country Link
CN (1) CN219365044U (en)

Similar Documents

Publication Publication Date Title
CN108560725B (en) Container house stand and wallboard system
KR20130045711A (en) Indoor decorative curtain wall construction unit
CN110145054B (en) Assembled building composite external wall panel structure
CN219365044U (en) Prefabricated steel structure integrated assembled green building component
CN207453256U (en) A kind of modularization prefabricated panel
CN210460334U (en) Combined door base sleeve
CN219773324U (en) Concrete beam plate structure
CN215670511U (en) Assembled inner partition plate
CN216379971U (en) Steel structural framework of simple house
CN215054839U (en) Lightweight external wallboard for prefabricated building
KR20200045266A (en) Roof structure of unit modular house
CN213297120U (en) Quick-release aluminum formwork for building construction
CN214711308U (en) Plug-type assembled finished product wardrobe structure
CN212405556U (en) Prefabricated wall for prefabricated building
CN211172654U (en) Assembled light gauge steel structure
CN202718252U (en) Wallboard connection structure of modulus method prefabricated plate-type house
JPH0649756Y2 (en) Panels for concrete formwork
CN114673428A (en) A prefabricated structure building door and window fixing mechanism
CN222253298U (en) A building construction support frame
CN111733967A (en) Low-cost structure energy-saving integrated engineering bamboo assembly type building system
CN211597225U (en) Assembled light steel wallboard
CN209053289U (en) Novel sound insulating building curtain wall
CN221590060U (en) Superimposed sheet
CN214245305U (en) Assembled highway steel bridge combination formula support frame
CN214738744U (en) Beam column structure connecting piece

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230718