CN218715059U - Large template attached to steel frame of high-rise building machine - Google Patents

Large template attached to steel frame of high-rise building machine Download PDF

Info

Publication number
CN218715059U
CN218715059U CN202221402709.0U CN202221402709U CN218715059U CN 218715059 U CN218715059 U CN 218715059U CN 202221402709 U CN202221402709 U CN 202221402709U CN 218715059 U CN218715059 U CN 218715059U
Authority
CN
China
Prior art keywords
formwork
frame
steel frame
template
building machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221402709.0U
Other languages
Chinese (zh)
Inventor
陈平霞
张明扬
王邦平
李志�
陈前广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Henggui Chuangke Construction Engineering Technology Co ltd
Shanghai Ouyue Construction And Installation Engineering Co ltd
Original Assignee
Jiangsu Henggui Chuangke Construction Engineering Technology Co ltd
Shanghai Ouyue Construction And Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Henggui Chuangke Construction Engineering Technology Co ltd, Shanghai Ouyue Construction And Installation Engineering Co ltd filed Critical Jiangsu Henggui Chuangke Construction Engineering Technology Co ltd
Priority to CN202221402709.0U priority Critical patent/CN218715059U/en
Application granted granted Critical
Publication of CN218715059U publication Critical patent/CN218715059U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses an adhere to high-rise building machine steel frame big template, steel frame big template includes steel frame, and steel frame includes frame, lower frame, goes up frame, through a plurality of back of the body muscle, horizontal muscle fixed connection between the lower frame, and the back of the body muscle includes the back of the body muscle of the relative both ends fixed connection with lower frame, last frame and lies in the middle back of the body muscle between the back of the body muscle of the limit, and the template is fixed on steel frame's leading flank. Holes with the interval of 100mm are punched on the rectangular pipe, the large template is used for splicing and connecting the mounting holes, and the rectangular pipe is also used for connecting, mounting and using the large template and the surrounding purlin. The large formwork can be freely assembled in construction, and the large formwork modules are connected by pins and pin pieces, so that the large formwork is fast and convenient to assemble and disassemble. The integral template is manufactured in the vertical direction, the integral structure strength of the large template steel frame is good, the installation is convenient, the integral large template is hoisted on a top platform of the building machine, and the large template climbs along with the whole building machine system.

Description

Large template attached to steel frame of high-rise building machine
Technical Field
The utility model relates to a template technical field is built in the room, concretely relates to adhere to high-rise building machine steel frame large formword.
Background
In the house building concrete casting, the workload of formwork supporting and formwork removing is large, particularly in the high-rise building, the workload of formwork supporting is performed by using wood formwork or scattered formwork and aluminum formwork, and corresponding formwork modules are different due to different structures, so that a large number of different formwork modules exist on site. In the template layer-transferring movement, the template-supporting time is wasted due to the reason that templates are randomly placed or lost and the like. The whole template is lifted or the template and the working frame body climb together, so that the rapid installation of the template is realized.
Disclosure of Invention
The utility model provides an adhere to high-rise building machine steel frame big template, the rectangle pipe is gone up and is gone up interval 100mm hole, assembles the connection mounting hole with big template, also is used as big template and encloses to connect between the purlin and install and use. The large formwork can be freely assembled in construction, and the large formwork modules are connected by pins and pin pieces, so that the large formwork is fast and convenient to assemble and disassemble. The integral formwork is manufactured in the vertical direction, the integral structural strength of the large formwork steel frame is good, the installation is convenient, the integral large formwork is hoisted on a top platform of the building machine, and the large formwork climbs along with the whole building machine system.
The utility model discloses a technical scheme as follows: the utility model provides an attached high-rise building machine steel frame big template, steel frame big template includes steel framework, and steel framework includes frame, lower frame, goes up between frame, the lower frame through a plurality of back of the body muscle, horizontal muscle fixed connection, and the back of the body muscle includes the back of the body muscle with lower frame, the relative both ends fixed connection of last frame and lies in the middle back of the body muscle between the back of the body muscle, and the template is fixed on steel framework's leading flank.
On the basis of the scheme, the upper frame, the lower frame, the back rib and the transverse rib are preferably galvanized steel pipes.
On the basis of the scheme, the upper frame, the lower frame, the back ribs and the transverse ribs are preferably rectangular tubes.
On the basis of the scheme, preferably, a plurality of holes with the spacing of 100mm are punched on the back rib.
On the basis of the scheme, preferably, the upper ends of at least two middle back ribs are fixedly provided with large template hanging rings.
On the basis of the scheme, the large formwork hanging ring preferably comprises a U-shaped connecting piece, the connecting piece is clamped on the middle back rib and fixedly connected through a bolt, the lower end of the inverted U-shaped rod is fixedly installed on the outer end face of the connecting piece, and the upper end of the inverted U-shaped rod protrudes out of the outer end face of the connecting piece in the up-down direction to form the large formwork hanging ring.
On the basis of the scheme, preferably, two adjacent edge back ribs of two adjacent steel frame large templates are fixedly connected through pins and pin pieces.
On the basis of the scheme, the steel frame large template preferably comprises an inner steel frame large template and an outer steel frame large template, large template enclosing purlins are fixedly mounted on the outer side surfaces of the inner steel frame large template and the outer steel frame large template, the screw rod penetrates through the large template enclosing purlins to fixedly connect the inner steel frame large template and the outer steel frame large template, and screw rod nuts are mounted at two ends of the screw rod.
On the basis of the scheme, the template is preferably a 4mm steel template.
Compared with the prior art, the utility model discloses following beneficial effect has:
the steel frame is formed by splicing and welding 80-40-3.5/Q235 galvanized steel pipes, holes with the interval of 100mm are punched on the rectangular pipes, and the rectangular pipes are spliced and connected with mounting holes by using large templates and are also used for connecting and mounting the large templates and the surrounding purlins. The large formwork can be freely assembled in construction, and the large formwork modules are connected by pins and pin pieces, so that the large formwork is fast and convenient to assemble and disassemble. The integral template is manufactured in the vertical direction, the integral structure strength of the large template steel frame is good, the installation is convenient, the integral large template is hoisted on a top platform of the building machine, and the large template climbs along with the whole building machine system.
Drawings
FIG. 1 is a schematic structural view of a steel frame;
FIG. 2 is a left side view of FIG. 1;
FIG. 3 is a schematic structural view of the present FIG. 1 and steel plate assembly;
FIG. 4 is a left side view of FIG. 3;
FIG. 5 is a schematic view of the present invention;
FIG. 6 is a left side view of FIG. 5;
fig. 7 is a perspective view of the present invention;
fig. 8 is a matching schematic diagram of two adjacent steel frame large templates assembled by using pins and pin sheets.
Detailed Description
In order to more clearly illustrate embodiments of the present invention or technical solutions in the prior art, specific embodiments of the present invention will be described below with reference to the accompanying drawings. It is obvious that the drawings in the following description are only examples of the invention, and that for a person skilled in the art, other drawings and embodiments can be obtained from these drawings without inventive effort.
As shown in figures 1-6, a big template of steel frame attached to a high-rise building machine comprises a steel frame, wherein the steel frame comprises an upper frame 1 and a lower frame 2, the upper frame and the lower frame are fixedly connected through a plurality of back ribs and transverse ribs, the back ribs comprise side back ribs 3 fixedly connected with the two opposite ends of the lower frame and the upper frame and middle back ribs 4 positioned between the side back ribs, and a template 5 is fixed on the front side surface of the steel frame.
Wherein the template is a 4mm steel template, and can also be a plywood and the like.
The upper frame, the lower frame, the back rib and the transverse rib are galvanized steel pipes, and the steel frame is formed by welding 80-40-3.5/Q235 galvanized steel pipes in a splicing mode.
The upper frame, the lower frame, the back rib and the transverse rib are rectangular tubes.
The back ribs are punched with a plurality of holes 6 with the spacing of 100 mm. The large formwork is used as a hole for assembling, connecting and installing two large formworks and also used for connecting, installing and using the large formworks and the surrounding purlin. The large formwork can be manufactured into various different moduli, can be freely assembled in construction, and is quickly and conveniently assembled and disassembled by adopting pins and pin sheets for connection. The integral template is manufactured in the vertical direction, the integral structure strength of the large template steel frame is good, the installation is convenient, the integral large template is hoisted on a top platform of the building machine, and the large template climbs along with the whole building machine system.
The upper ends of at least two middle back ribs are fixedly provided with large template hanging rings.
The large formwork lifting ring comprises a U-shaped connecting piece 7, the connecting piece is clamped on the middle back rib and is fixedly connected with the middle back rib through a bolt, the lower end of an inverted U-shaped rod 8 is fixedly installed on the outer end face of the connecting piece, and the upper end of the inverted U-shaped rod protrudes out of the outer end face of the connecting piece in the up-down direction to form the large formwork lifting ring. The hanging ring is convenient to install and replace.
Two adjacent edge back ribs of two adjacent steel frame large templates are fixedly connected through a pin 9 and a pin piece 10, and the disassembly and the assembly are convenient.
The large steel frame template comprises an inner large steel frame template and an outer large steel frame template, the outer side surfaces of the inner large steel frame template and the outer large steel frame template are fixedly provided with a large template surrounding purlin 11, a screw rod 12 penetrates through the large template surrounding purlin to fixedly connect the inner large steel frame template and the outer large steel frame template, and screw rod nuts 13 are installed at two ends of the screw rod.
It should be noted that the above embodiments can be freely combined as necessary. The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (9)

1. The utility model provides an attached high-rise building machine steel frame large formwork, its characterized in that, steel frame large formwork includes steel framework, and steel framework includes frame, lower frame, goes up through a plurality of back of the body muscle, horizontal muscle fixed connection between frame, the lower frame, and the back of the body muscle includes the back of the body muscle of the relative both ends fixed connection of frame, last frame and lies in the back of the body muscle of the centre between the back of the body muscle of the limit, and the template is fixed on steel framework's leading flank.
2. The large formwork attached to a steel frame of a high-rise building machine according to claim 1, wherein the upper frame, the lower frame, the back rib and the transverse rib are galvanized steel pipes.
3. The large formwork attached to a steel frame of a high-rise building machine according to claim 1, wherein the upper frame, the lower frame, the back rib and the transverse rib are rectangular pipes.
4. A large formwork attached to a steel frame of a high-rise building machine according to claim 1, wherein the back rib is punched with a plurality of holes with a distance of 100 mm.
5. The large formwork attached to the steel frame of the high-rise building machine according to claim 4, wherein the upper ends of at least two middle back ribs are fixedly provided with large formwork hanging rings.
6. The large formwork attached to the steel frame of the high-rise building machine according to claim 5, wherein the large formwork hanging ring comprises a U-shaped connecting member, the connecting member is clamped on the middle back rib and fixedly connected through a bolt, the lower end of the inverted U-shaped rod is fixedly installed on the outer end face of the connecting member, and the upper end of the inverted U-shaped rod protrudes out of the outer end face of the connecting member in the up-down direction to form the large formwork hanging ring.
7. The large steel frame formwork for attaching a high-rise building machine according to claim 4, wherein two adjacent edge back ribs of two adjacent large steel frame formworks are fixedly connected through a pin and a pin sheet.
8. The large steel frame formwork for the high-rise building machine according to claim 4, wherein the large steel frame formwork comprises an inner large steel frame formwork and an outer large steel frame formwork, large formwork enclosing purlins are fixedly arranged on the outer side surfaces of the inner large steel frame formwork and the outer large steel frame formwork, a screw rod penetrates through the large formwork enclosing purlins to fixedly connect the inner large steel frame formwork and the outer large steel frame formwork, and screw rod nuts are arranged at two ends of the screw rod.
9. The large formwork attached to the steel frame of the high-rise building machine according to claim 1, wherein the formwork is a 4mm steel formwork or plywood.
CN202221402709.0U 2022-06-07 2022-06-07 Large template attached to steel frame of high-rise building machine Active CN218715059U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221402709.0U CN218715059U (en) 2022-06-07 2022-06-07 Large template attached to steel frame of high-rise building machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221402709.0U CN218715059U (en) 2022-06-07 2022-06-07 Large template attached to steel frame of high-rise building machine

Publications (1)

Publication Number Publication Date
CN218715059U true CN218715059U (en) 2023-03-24

Family

ID=85607411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221402709.0U Active CN218715059U (en) 2022-06-07 2022-06-07 Large template attached to steel frame of high-rise building machine

Country Status (1)

Country Link
CN (1) CN218715059U (en)

Similar Documents

Publication Publication Date Title
CN103397728B (en) Formwork panel dismountable and thickness adjustable combined steel bar truss floor bearing plate
CN218715059U (en) Large template attached to steel frame of high-rise building machine
CN203403577U (en) Combined type steel bar truss floor support plate with demountable thickness-adjustable formwork panel
CN214834809U (en) Template drilling-free clamp
CN212984631U (en) Plate lowering hanging die
CN210050544U (en) Assembled finished product supporting and hanging frame
CN210867045U (en) Support frame for cable bridge
CN218715060U (en) Light steel frame plastic large formwork attached to high-rise building machine
CN218715070U (en) Upper frame body main frame structure of hydraulic creeping formwork
CN215211527U (en) Steel constructs component convenient to connect
CN210084734U (en) Detachable lifting appliance for square steel pipe column
CN217175203U (en) Reinforced steel member at energy-saving steel structure joint
CN219365044U (en) Prefabricated steel structure integrated assembled green building component
CN214497159U (en) Assembled pier convenient to install and connect
CN220599210U (en) Adjustable lifting plate hanging die assembly device
CN220058491U (en) Roof hanger
JP3604071B2 (en) Hundred-footed floor beams in wooden houses
CN213927840U (en) Assembled enclosure wall
CN216546634U (en) Engine room upside down hanging scaffold
CN221053295U (en) Convenient construction stair
CN220036183U (en) Clamp type code plate for steel beam installation
CN216196520U (en) I-steel positioning and clamping device
CN219826107U (en) Quick easy-to-install and-remove elevator shaft operation frame and template
CN219429514U (en) Climbing frame dismantling support
CN211736510U (en) Adjustable construction support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant