CN220414857U - Prefabricated member for air conditioner opening - Google Patents
Prefabricated member for air conditioner opening Download PDFInfo
- Publication number
- CN220414857U CN220414857U CN202321744962.9U CN202321744962U CN220414857U CN 220414857 U CN220414857 U CN 220414857U CN 202321744962 U CN202321744962 U CN 202321744962U CN 220414857 U CN220414857 U CN 220414857U
- Authority
- CN
- China
- Prior art keywords
- baffle
- sleeve
- air conditioner
- prefabricated member
- air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004378 air conditioning Methods 0.000 claims abstract description 10
- 238000009413 insulation Methods 0.000 claims description 5
- 239000011159 matrix material Substances 0.000 abstract description 13
- 238000010276 construction Methods 0.000 abstract description 7
- 238000004080 punching Methods 0.000 abstract description 4
- 238000009434 installation Methods 0.000 abstract description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 238000005553 drilling Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 4
- 241001074085 Scophthalmus aquosus Species 0.000 description 3
- 238000004321 preservation Methods 0.000 description 3
- 238000009417 prefabrication Methods 0.000 description 2
- 230000006978 adaptation Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Duct Arrangements (AREA)
Abstract
The utility model belongs to the field of air-conditioning hole installation, and particularly relates to an air-conditioning hole prefabricated member, which comprises a concrete matrix, wherein the thickness of the concrete matrix is the same as that of a wall body, a sleeve is pre-arranged in the middle of the concrete matrix, the air-conditioning hole prefabricated member pouring mold comprises a pouring box body formed by a front baffle, a rear baffle, a left baffle, a right baffle and a bottom plate, the left baffle and the right baffle are connected with the front baffle and the rear baffle through sockets and slots, the size of the pouring box body is matched with that of the concrete matrix, through holes are pre-arranged on the left baffle and the right baffle, the diameter of each through hole is matched with that of the sleeve, and the air-conditioning hole prefabricated member is directly installed in masonry, so that the secondary punching time is saved, and the construction efficiency is improved.
Description
Technical Field
The utility model belongs to the field of air conditioner opening installation, and particularly relates to an air conditioner opening prefabricated member.
Background
At present, an air-conditioning sleeve is reserved on an external wall for secondary masonry, and the air-conditioning sleeve is mainly reserved in two modes, wherein after the masonry is completed, a water drill is used for forming holes in the masonry, and the reserved holes are easy to be blocked during plastering and external wall heat preservation construction; in addition, the inner wall is plastered, the outer wall is perforated by a water drill after the heat insulation construction is completed, and the method is easy to pollute the inner wall and the outer wall during the water drill drilling construction and is inconvenient to clean.
Above-mentioned two modes all need utilize the water brill to carry out the secondary drilling, and the water brill drilling all needs to set up the support body, increases workman's intensity of labour, and water brill drilling efficiency is also lower moreover, has reduced the efficiency of construction, influences the construction progress.
Disclosure of Invention
In order to solve the problem that secondary drilling needs to be carried out by adopting a water drill on a secondary masonry outer wall, the air conditioner opening prefabricated member is provided. The prefabricated member for the air conditioner opening is directly installed during masonry, so that the time of secondary punching is saved, and the construction efficiency is improved.
In order to solve the technical problems, the utility model adopts the technical scheme that: the utility model provides an air conditioner entrance to a cave prefabrication, includes the concrete base member, and the thickness of concrete base member is the same with the thickness of wall body, and the sleeve pipe has been preset at the middle part of concrete base member, and sheathed tube both ends extend to the outside of concrete base member, and outside sheathed tube length is the same with the outer wall heat preservation layer thickness, and the length of inboard sheathed tube is the same with the thickness of interior wall plastering.
Further, the sleeve is made of PVC.
Further, the inner diameter of the sleeve is the same as the diameter of the air conditioner hole.
The other technical scheme of the utility model is as follows: the utility model provides an air conditioner entrance to a cave prefab pouring die, includes the bottom plate, and the four sides of bottom plate are provided with preceding baffle, backplate, left baffle and right baffle, and preceding baffle, backplate and bottom plate integrated into one piece set up, are provided with a plurality of sockets on preceding baffle and the backplate, and left baffle and right baffle are provided with socket assorted slot, and left baffle, right baffle pass through socket and slot and preceding baffle and backplate are connected, and preceding baffle, backplate, left baffle, right baffle form jointly with the bottom plate and pour the box body, pour box body size and concrete matrix phase adaptation, preset the through-hole on left baffle and the right baffle, the through-hole diameter suits with the sleeve pipe diameter.
Further, a plurality of left studs are arranged on the left baffle, a left locating plate is sleeved on the plurality of left studs, and the left locating plate is fixedly connected with the left studs through bolts.
Further, a plurality of right studs are arranged on the right baffle, a right locating plate is sleeved on the plurality of right studs, and the right locating plate is fixedly connected with the right studs through bolts.
Compared with the prior art, the utility model has the following beneficial effects: according to the utility model, the sleeve is prefabricated into the concrete matrix according to the masonry wall thickness, plastering thickness and heat preservation thickness, and then the prefabricated air conditioner opening is directly built into the wall body when the wall body is built, so that secondary punching is not required by using a water drill, and the labor and mechanical cost for secondary punching are saved. Meanwhile, the problem that the gap filling of the secondary hole-opening sleeve is not tight and leakage risk exists at the outer wall is avoided.
In addition, the utility model also provides a pouring die for the prefabricated member of the air conditioner opening, and the prefabricated member of the air conditioner opening can be formed by one-time pouring by using the die. The pouring die is suitable for walls with different plastering thicknesses and heat insulation thicknesses.
Drawings
The utility model is further described below with reference to the accompanying drawings.
FIG. 1 is a schematic structural view of an air conditioning tunnel portal preform of the present utility model.
Fig. 2 is a schematic structural view of an air conditioner opening prefabricated member pouring mold.
Fig. 3 is a schematic view of the casting mold with the right baffle removed.
In the figure, 1 is a concrete matrix, 2 is a sleeve, 3 is a front baffle, 4 is a rear baffle, 5 is a left baffle, 6 is a right baffle, 7 is a bottom plate, 8 is a socket, 9 is a slot, 10 is a through hole, 11 is a left stud, 12 is a left locating plate, 13 is a right stud, and 14 is a right locating plate.
Detailed Description
As shown in FIG. 1, the prefabricated member for the air conditioner hole comprises a concrete matrix 1, wherein the thickness of the concrete matrix 1 is the same as that of a wall body, a sleeve 2 is preset in the middle of the concrete matrix 1, two ends of the sleeve 2 extend to the outer side of the concrete matrix 1, the length of the outer sleeve 2 is the same as that of an outer wall insulation layer, and the length of the inner sleeve 2 is the same as that of an inner wall plastering surface. The material of the sleeve 2 is usually PVC. In addition, the inner diameter of the sleeve 2 is the same as the diameter of the air conditioning hole.
The utility model uses the prefabricated member of the air conditioner opening to avoid the problems of wall pollution and building rubbish increase caused by opening holes after the opening omission of masonry and plastering is completed. The labor and mechanical cost of secondary hole opening are saved; compared with the situation that the gap filling of the secondary hole opening sleeve 2 is not tight, leakage exists at the outer wall part, no gap exists between the prefabricated part sleeve 2 of the air conditioner hole and the concrete matrix 1, and leakage cannot occur.
As shown in fig. 2-3, another technical scheme of the protection of the present utility model is as follows: the utility model provides an air conditioner entrance to a cave prefabrication mould, includes that preceding baffle 3, backplate 4, left baffle 5, right baffle 6 and bottom plate 7 form jointly and pour the box body, preceding baffle 3, backplate 4 and bottom plate 7 integrated into one piece set up, wholly are the door font structure of putting. The left baffle 5, the left baffle 5 are designed as a detachable structure in view of the need for demolding.
Be provided with a plurality of sockets 8 on preceding baffle 3 and backplate 4, left baffle 5 and right baffle 6 are provided with socket 8 assorted slot 9, and left baffle 5, right baffle 6 are connected with preceding baffle 3 and backplate 4 through socket 8 and slot 9, pour box body size and concrete matrix 1 and adapt to, have preset through-hole 10 on left baffle 5 and the right baffle 6 simultaneously, and through-hole 10 diameter suits with sleeve pipe 2 diameter.
When pouring is needed, the cut PVC sleeve 2 is placed in the pouring box body, and the sizes of the PVC pipes on the left and right sides of the pouring box body are adjusted so that the thickness of the PVC pipes is consistent with the thickness of plastering and heat insulation. And then pouring is started, after the concrete is solidified, the left baffle plate 5 and the right baffle plate 6 are disassembled, and the prefabricated member of the air conditioner opening is taken out.
In the pouring process, the position of the PVC sleeve 2 in the pouring box body needs to be adjusted, the adjusting process needs to be adjusted by a ruler, in addition, in the pouring process, the position of the PVC sleeve 2 can be moved due to impact force during pouring, and the positioning speed and the positioning accuracy of the PVC sleeve 2 are improved. A plurality of left studs 11 are arranged on the left baffle 5, a left positioning plate 12 is sleeved on the plurality of left studs 11, and the left positioning plate 12 is fixedly connected with the left studs 11 through bolts. A plurality of right studs 13 are arranged on the right baffle 6, a right positioning plate 14 is sleeved on the plurality of right studs 13, and the right positioning plate 14 is fixedly connected with the right studs 13 through bolts.
Through left baffle 5 and right baffle 6, carry out quick location to the left and right ends of PVC sleeve pipe 2, do not need to carry out dimensional measurement, left baffle 5 and right baffle 6 also carry out spacingly to PVC sleeve pipe 2 moreover, produce the displacement when preventing that it from pouring, promote PVC sleeve pipe 2's installation accuracy.
The embodiments of the present utility model have been described in detail with reference to the accompanying drawings, but the present utility model is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the spirit of the present utility model.
Claims (3)
1. An air conditioner entrance to a cave prefab, its characterized in that: the concrete base (1) is included, the thickness of the concrete base (1) is the same as that of a wall body, a sleeve (2) is preset in the middle of the concrete base (1), two ends of the sleeve (2) extend to the outer side of the concrete base (1), the length of the outer sleeve (2) is the same as that of an outer wall insulation layer, and the length of the inner sleeve (2) is the same as that of an inner wall plastering surface.
2. An air conditioning tunnel portal preform as claimed in claim 1, wherein: the sleeve (2) is made of PVC.
3. An air conditioning tunnel portal preform as claimed in claim 2, wherein: the inner diameter of the sleeve (2) is the same as the diameter of the air conditioner hole.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321744962.9U CN220414857U (en) | 2023-07-05 | 2023-07-05 | Prefabricated member for air conditioner opening |
CN202323587704.7U CN220945889U (en) | 2023-07-05 | 2023-07-05 | Air conditioner entrance to a cave prefab pouring mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321744962.9U CN220414857U (en) | 2023-07-05 | 2023-07-05 | Prefabricated member for air conditioner opening |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202323587704.7U Division CN220945889U (en) | 2023-07-05 | 2023-07-05 | Air conditioner entrance to a cave prefab pouring mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220414857U true CN220414857U (en) | 2024-01-30 |
Family
ID=89640978
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202323587704.7U Active CN220945889U (en) | 2023-07-05 | 2023-07-05 | Air conditioner entrance to a cave prefab pouring mould |
CN202321744962.9U Active CN220414857U (en) | 2023-07-05 | 2023-07-05 | Prefabricated member for air conditioner opening |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202323587704.7U Active CN220945889U (en) | 2023-07-05 | 2023-07-05 | Air conditioner entrance to a cave prefab pouring mould |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN220945889U (en) |
-
2023
- 2023-07-05 CN CN202323587704.7U patent/CN220945889U/en active Active
- 2023-07-05 CN CN202321744962.9U patent/CN220414857U/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN220945889U (en) | 2024-05-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN220414857U (en) | Prefabricated member for air conditioner opening | |
CN109016089B (en) | Mold, manufacturing process and installation method of small door jamb | |
CN107859332B (en) | Construction method for embedding wire pipe of prefabricated distribution box | |
CN215150318U (en) | Gypsum shield constructs section of jurisdiction model and pours mould | |
CN210950229U (en) | Embedded device for gas inlet pipe sleeve in indoor shear wall | |
CN108265854B (en) | On-site foaming polyurethane external wall external heat insulation system and construction method thereof | |
CN211597350U (en) | Pipeline wall-penetrating prefabricated unit and manufacturing tool | |
CN211312927U (en) | Prefabricated part for wall bushing of secondary structure refrigerant pipeline of subway station | |
CN110616848A (en) | Pipeline wall-penetrating prefabricated unit and manufacturing tool | |
CN215368736U (en) | Horizontal hole die reserved for structural slab | |
CN110656644A (en) | Reinforcement cage erecting structure and method for breaking pile head of cast-in-place pile through static blasting by reverse construction method | |
CN210211032U (en) | Air duct prefabricating die with length capable of being customized | |
CN215054110U (en) | Heat-insulation external wall panel | |
CN201009342Y (en) | One-shot forming wallboard mold for supplying flowline production arranged with vertical and horizontal through hole | |
CN220565702U (en) | Wall body water pipe indent structure | |
CN221031441U (en) | Device for improving die supporting efficiency of paying-off hole | |
CN221912491U (en) | Visual modularization air conditioner hole building block preparation mould | |
CN211492096U (en) | Concrete prefabricated part mould and formed concrete prefabricated part thereof | |
CN211523740U (en) | Air conditioner hole pre-buried pipe prefabricated building block pouring die | |
CN212826009U (en) | Aerated concrete block mould box | |
CN207919868U (en) | Pipeline through-wall structure Prefabricated block | |
CN110230926B (en) | Masonry structure and process for air inlet and conical section of suspension furnace combustion chamber | |
CN203449433U (en) | Wall block making machine of honeycomb structure | |
CN219292694U (en) | Pipe fitting mould with exhaust needle | |
CN219411827U (en) | Paying-off hole die |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |