CN220246814U - Combined ecological frame - Google Patents

Combined ecological frame Download PDF

Info

Publication number
CN220246814U
CN220246814U CN202321975243.8U CN202321975243U CN220246814U CN 220246814 U CN220246814 U CN 220246814U CN 202321975243 U CN202321975243 U CN 202321975243U CN 220246814 U CN220246814 U CN 220246814U
Authority
CN
China
Prior art keywords
prefabricated
frame
ecological
frames
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321975243.8U
Other languages
Chinese (zh)
Inventor
张永喜
张玉涛
朱喜瑞
张启智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tangshan Zhongzhu New Building Materials Co ltd
Original Assignee
Tianjin Tianzhuang Building Materials Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Tianzhuang Building Materials Technology Co ltd filed Critical Tianjin Tianzhuang Building Materials Technology Co ltd
Priority to CN202321975243.8U priority Critical patent/CN220246814U/en
Application granted granted Critical
Publication of CN220246814U publication Critical patent/CN220246814U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a combined ecological frame, which relates to the technical field of ecological bank protection and comprises a plurality of prefabricated frames which are sequentially arranged, wherein a containing groove is formed in each prefabricated frame, and a fixing structure is arranged between two adjacent prefabricated frames and is used for forming a group of ecological frames from the sequentially arranged prefabricated frames; the fixing structure is detachably connected with a sealing plate positioned in the holding groove, and the bottom of the holding groove is provided with a lifting structure for lifting the ecological frame. The ecological frame is used for solving the problems that due to the fact that the number of the ecological frames is too large, workers need to frequently carry to corresponding positions and assemble the ecological frames, the labor required by the site is more, time and labor are consumed, the cost is high, and the construction progress is affected.

Description

Combined ecological frame
Technical Field
The disclosure relates to the technical field of ecological bank protection, in particular to a combined ecological frame.
Background
Along with the enhancement of environmental awareness, the construction of river course revetment also transits from traditional stereoplasm revetment to ecological type revetment, and ecological frame revetment is a common ecological type of revetment, is favorable to the water and soil exchange of revetment, has ecological, environmental protection, many-sided comprehensive advantages such as pleasing to the eye. The ecological frame retaining wall not only meets the use function of the retaining wall, but also prevents water and soil loss of the river bank and erosion of the river bank by coordination of planted plants and surrounding environment, adopts modular design, standardized production and field assembly, and has good product consistency. The ecological frame retaining wall adopts assembly type construction, and the speed is faster than traditional mode, guarantees the construction progress, reduces construction cost.
However, the ecological frame shore protection still has some problems, and because the number of the ecological frames is too large, workers need to frequently carry the ecological frames to corresponding positions and assemble the ecological frames, more labor is needed on site, time and labor are consumed, the cost is high, and the construction progress is influenced.
Disclosure of Invention
The purpose of this disclosure is to provide a combination formula ecological frame, and it has solved current ecological frame numerous, and the manual handling is consuming time and is spent the problem.
In order to achieve the above purpose, the present disclosure provides a combined ecological frame, which includes a plurality of prefabricated frames arranged in sequence, wherein a containing groove is formed on each prefabricated frame, and a fixing structure is arranged between two adjacent prefabricated frames, so that the plurality of prefabricated frames arranged in sequence form a group of ecological frames;
the fixing structure is detachably connected with a sealing plate positioned in the holding groove, and a lifting structure is arranged at the bottom of the holding groove and used for lifting the ecological frame.
In some embodiments, the fixing structure comprises split bolts, fixing blocks and screw holes, each of the fixing blocks is provided with four fixing blocks on the side wall of the containing groove, one surface, far away from the containing groove, of the fixing block is provided with screw holes and penetrates through the side wall of the prefabricated frame, the split bolts are arranged on the screw holes, and the split bolts penetrate through the screw holes to connect two adjacent prefabricated frames.
In some embodiments, the lifting structure comprises two lifting rings, one of the lifting rings is arranged in the containing groove at the head end, and the other lifting ring is arranged in the containing groove at the tail end.
In some embodiments, the upper surface of the fixed block is provided with a supporting groove, and a supporting block is arranged below the sealing plate and is fit with the supporting groove.
In some embodiments, two side walls of the prefabricated frame are provided with material exchange holes, and a filter screen is arranged in each material exchange hole.
In some embodiments, a groove is formed in the top of the prefabricated frame, and a bump is formed at a position, corresponding to the groove, of the bottom of the prefabricated frame.
In some embodiments, a plurality of screws are disposed between the filter screen and the substance exchange aperture.
Before installation, the sealing plate is taken out, a plurality of prefabricated frames are placed in parallel, the prefabricated frames are connected into a group of ecological frames through the fixing structure, the ecological frames are transported to corresponding positions through the lifting structure, the sealing plate is installed, the prefabricated frames are swung into a first layer according to requirements, the prefabricated frames of a second layer are hung above the prefabricated frames of the first layer, and soil is irrigated onto the sealing plate.
The effect that can be reached through the above-mentioned setting:
1. through setting up fixed knot constructs, connect a plurality of prefabricated frames together in proper order, will install in advance, carry again to a set of ecological frame of constitution, both save time and laborsaving.
2. Through setting up detachable closing plate, be convenient for hang ecological frame when taking down the closing plate, when installing the closing plate for hold soil.
3. The lifting structure is arranged at the bottom of the containing tank, so that the ecological frame is convenient to lift and transport to the corresponding position, manual carrying is reduced, and the burden of workers is lightened.
Additional features and advantages of the present disclosure will be set forth in the detailed description which follows.
Drawings
The accompanying drawings are included to provide a further understanding of the disclosure, and are incorporated in and constitute a part of this specification, illustrate the disclosure and together with the description serve to explain, but do not limit the disclosure.
In the drawings:
FIG. 1 is an isometric schematic of the overall structure of the present utility model;
FIG. 2 is a schematic illustration of the seal plate of the present utility model removed from the seal plate;
FIG. 3 is an enlarged view at A in FIG. 2;
FIG. 4 is an isometric view of the bottom of the present utility model;
fig. 5 is an enlarged view at B in fig. 4;
fig. 6 is an isometric view of a seal plate.
Reference numerals illustrate:
1. prefabricating a frame; 2. a holding groove; 3. a fixed structure; 31. a split bolt; 32. a fixed block; 33. a screw hole; 4. a sealing plate; 5. a lifting structure; 51. a hanging ring; 6. a support groove; 7. a support block; 8. a substance exchange well; 9. a filter screen; 10. a groove; 11. a bump; 12. and (5) a screw.
Detailed Description
Specific embodiments of the present disclosure are described in detail below with reference to the accompanying drawings. It should be understood that the detailed description and specific examples, while indicating and illustrating the disclosure, are not intended to limit the disclosure.
The disclosure provides a combination formula ecological frame, as shown in fig. 1, fig. 2 and fig. 3, ecological frame includes a plurality of prefabricated frames 1 of arranging in proper order, has seted up on the prefabricated frame 1 and has held groove 2, is equipped with fixed knot constructs 3 between two adjacent prefabricated frames 1 for a set of ecological frame is constituteed with a plurality of prefabricated frames 1 of arranging in proper order, can dismantle on the fixed knot constructs 3 and is connected with the closing plate 4 that is located and holds inslot 2, holds inslot 2 bottom and is equipped with lifting structure 5 for lifting ecological frame.
Through the setting of above-mentioned structure, utilize fixed knot between the adjacent prefabricated frame 1 constructs 3, connect together a plurality of prefabricated frames 1 in proper order, install it in advance, both save time and laborsaving. Through setting up detachable closing plate 4, be convenient for hang ecological frame when taking down closing plate 4, when installing closing plate 4 for hold soil, can prevent soil loss. The lifting structure 5 is arranged at the bottom of the containing groove 2, so that the ecological frame is convenient to lift and transport to the corresponding position, manual carrying is reduced, and the burden is lightened for staff.
In some embodiments, as shown in fig. 1, 2 and 3, the fixing structure 3 includes split bolts 31, fixing blocks 32 and screw holes 33, four fixing blocks 32 are disposed on the side wall of each holding groove 2, one surface of each fixing block 32 away from the holding groove 2 is provided with a screw hole 33 and penetrates through the side wall of the prefabricated frame 1, the split bolts 31 are disposed on the screw holes 33, and the split bolts 31 penetrate through the screw holes 33 to connect two adjacent prefabricated frames 1.
Through the arrangement of the structure, the stability of the fixed structure 3 is enhanced by the arrangement of the plurality of fixed blocks 32, and the screw holes 33 penetrating through the side walls are correspondingly arranged, so that the two adjacent prefabricated frames 1 are conveniently connected by the split bolts 31.
In some embodiments, as shown in fig. 1, 2 and 3, the lifting structure 5 includes two lifting rings 51, one of the lifting rings 51 being disposed in the receiving slot 2 at the head end and the other lifting ring 51 being disposed in the receiving slot 2 at the tail end.
The arrangement of the hanging ring 51 is convenient for transporting the assembled ecological frame to the corresponding position, and the hanging ring 51 is arranged at the bottom of the containing groove 2, so that the attractiveness is not affected.
In some embodiments, as shown in fig. 2, 3 and 6, the upper surface of the fixing block 32 is provided with a support groove 6, and the lower surface of the sealing plate 4 is provided with a support block 7, and the support block 7 should be fitted with the support groove 6.
In this arrangement, the support groove 6 is bonded to the support block 7, and the seal plate 4 is mounted on the fixing block 32, so that the shaking of the seal plate from left to right is avoided.
In some embodiments, as shown in fig. 1, two side walls of the prefabricated frame 1 are provided with a substance exchange hole 8, and a filter screen 9 is arranged in the substance exchange hole.
By the arrangement, air can be introduced into the accommodating groove 2, so that certain content of oxygen is ensured in the accommodating groove 2, and redundant water in the accommodating groove 2 can be discharged, so that the soil can keep proper humidity, and plants in the accommodating groove 2 can grow healthily. No matter exchange holes 8 are accumulated in the containing groove 2, so that the roots of plants can be rotten after being soaked in the water for a long time.
Through setting up filter screen 9, prevent that soil and water from losing from object exchange hole 8, but filter screen 9 still has the gap, put into the stone in filter screen 9 and block up filter screen 9's space, prevent that soil from losing from the gap.
In some embodiments, as shown in fig. 1 and 4, a groove 10 is formed at the top of the prefabricated frame 1, and a bump 11 is formed at the bottom of the prefabricated frame 1 at a position corresponding to the groove 10.
By the arrangement, when the ecological frames are placed, the convex blocks 11 of one group are matched with the grooves 10 of the other group, so that the arrangement of the ecological frames of each group is facilitated.
In some embodiments, as shown in fig. 1, 2 and 3, a plurality of screws 12 are provided between the filter mesh 9 and the substance exchange well 8
Through the arrangement, the filter screen is fixed in the material exchange hole, so that the phenomenon that the filter screen is deviated when the stone is put into the material exchange hole to enable the stone to fall out of the material exchange hole is avoided.
In summary, before installation, the sealing plate 4 is taken out, several prefabricated frames 1 are placed in parallel, the prefabricated frames 1 are connected into a group by using split bolts 31 to pass through screw holes 33 on the side walls of two adjacent prefabricated frames 1, then the prefabricated frames 1 are transported to corresponding positions by hanging rings 51 at the front end and the rear end through 4, then the sealing plate 4 is installed, the supporting blocks 7 under the sealing plate 4 are installed in the supporting grooves 6 on the fixing blocks 32, stone blocks are placed in the filter screen 9, gaps on the filter screen 9 are blocked, the stone blocks and the filter screen 9 are blocked in the material exchange holes 8, and the filter screen 9 is fixed in the material exchange holes 8 through screws 12. After the prefabricated frame 1 is fully arranged on the first layer according to the requirements, the prefabricated frame 1 on the second layer is hung above the prefabricated frame 1 on the first layer, wherein the sealing plate 4 is not arranged at the bottom of the second layer and the bottom of the containing groove 2 above, the inside of the containing groove 2 is communicated with the inside of the containing groove 2 on the lower layer, the boss at the bottom of the prefabricated frame 1 on the upper layer is matched with the groove 10 at the top of the prefabricated frame 1 on the lower layer, so that the bosses cannot move mutually, and finally the soil is placed in the containing groove 2.
The preferred embodiments of the present disclosure have been described in detail above with reference to the accompanying drawings, but the present disclosure is not limited to the specific details of the above embodiments, and various simple modifications may be made to the technical solutions of the present disclosure within the scope of the technical concept of the present disclosure, and all the simple modifications belong to the protection scope of the present disclosure.
In addition, the specific features described in the foregoing embodiments may be combined in any suitable manner, and in order to avoid unnecessary repetition, the present disclosure does not further describe various possible combinations.
Moreover, any combination between the various embodiments of the present disclosure is possible as long as it does not depart from the spirit of the present disclosure, which should also be construed as the disclosure of the present disclosure.

Claims (7)

1. The combined ecological frame is characterized by comprising a plurality of prefabricated frames (1) which are sequentially arranged, wherein a containing groove (2) is formed in each prefabricated frame (1), and a fixing structure (3) is arranged between every two adjacent prefabricated frames (1) and used for forming a group of ecological frames from the plurality of prefabricated frames (1) which are sequentially arranged;
the ecological frame is characterized in that the fixing structure (3) is detachably connected with a sealing plate (4) positioned in the accommodating groove (2), and a lifting structure (5) is arranged at the bottom of the accommodating groove (2) and used for lifting the ecological frame.
2. The combined ecological frame according to claim 1, wherein the fixing structure (3) comprises split bolts (31), fixing blocks (32) and screw holes (33), four fixing blocks (32) are arranged on the side wall of each containing groove (2), the screw holes (33) are formed in the side, far away from the containing grooves (2), of each fixing block (32) and penetrate through the side wall of the prefabricated frame (1), split bolts (31) are arranged on the screw holes (33), and the split bolts (31) penetrate through the screw holes (33) to connect two adjacent prefabricated frames (1).
3. A combined ecological frame according to claim 1, characterized in that the lifting structure (5) comprises two lifting rings (51), wherein one lifting ring (51) is arranged in the containing groove (2) at the head end, and the other lifting ring (51) is arranged in the containing groove (2) at the tail end.
4. A combined ecological frame according to claim 2, characterized in that the upper surface of the fixed block (32) is provided with a supporting groove (6), the lower surface of the sealing plate (4) is provided with a supporting block (7), and the supporting block (7) is attached to the supporting groove (6).
5. A combined ecological frame according to claim 1, characterized in that the two side walls of the prefabricated frame (1) are provided with substance exchange holes (8), and a filter screen (9) is arranged in the substance exchange holes.
6. The combined ecological frame according to claim 1, wherein a groove (10) is formed in the top of the prefabricated frame (1), and a protruding block (11) is arranged at a position corresponding to the groove (10) in the bottom of the prefabricated frame (1).
7. A combined ecological frame according to claim 5, characterized in that a plurality of screws (12) are arranged between the filter screen (9) and the substance exchange holes (8).
CN202321975243.8U 2023-07-26 2023-07-26 Combined ecological frame Active CN220246814U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321975243.8U CN220246814U (en) 2023-07-26 2023-07-26 Combined ecological frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321975243.8U CN220246814U (en) 2023-07-26 2023-07-26 Combined ecological frame

Publications (1)

Publication Number Publication Date
CN220246814U true CN220246814U (en) 2023-12-26

Family

ID=89235485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321975243.8U Active CN220246814U (en) 2023-07-26 2023-07-26 Combined ecological frame

Country Status (1)

Country Link
CN (1) CN220246814U (en)

Similar Documents

Publication Publication Date Title
CN206821413U (en) Chinese garden planting case
CN204104528U (en) Multiple field cycle water fish cultivating system
CN220246814U (en) Combined ecological frame
US20220022383A1 (en) Combined vertical greening device
CN215122424U (en) Potted landscape cultivation device for landscaping engineering
CN109247159A (en) A kind of spliced plant wall structure
CN212414003U (en) Portable submerged plant planting device for water ecological restoration
CN209390739U (en) A kind of two-sided green plant wall for gardens decoration
CN201042164Y (en) Floatable net cage for keeping scallop
CN206024608U (en) Container is planted to hydrocone type that can be used to factory farming
CN205865616U (en) Can arrange snorkeling formula aquaculture net case of silt automatically
CN216074965U (en) Multifunctional composite spur dike facility
CN215257190U (en) Connecting piece for water storage device
CN211322178U (en) Gabion flowerpot
CN113136833A (en) Ecological assembled spur dike and construction method thereof
JPH07115861A (en) Planter
CN215122944U (en) Industrial hemp circulation water planting groove
CN214801117U (en) Municipal garden afforestation seed germination box
CN215210866U (en) Ecological frame of prefabricated pin-connected panel and ecological slope protection structure of constituteing thereof
CN221029945U (en) Assembled landscape revetment for urban river
CN214126172U (en) High-position flower bed for sponge city
CN218622274U (en) Water and soil conservation side slope nursing plant growth board
CN212876869U (en) Novel landscape plant plants case
CN220157266U (en) Fungus grass intergrowth device
CN218218457U (en) Sand prevention planting frame with water conservation effect

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240511

Address after: 063000 Linjin Industrial Park, Hangu Management District, Tangshan City, Hebei Province (No. 3 Factory Building of Kunyue Metal Company)

Patentee after: Tangshan Zhongzhu New Building Materials Co.,Ltd.

Country or region after: China

Address before: Room 1102, Floor 11, R&D Building, Ecological Science Park, No. 1620, Zhongtian Avenue, Zhongxin Tianjin Ecological City, Binhai New Area, Tianjin, 300450

Patentee before: Tianjin Tianzhuang Building Materials Technology Co.,Ltd.

Country or region before: China