CN219772721U - Temporary support for hoisting steel box girder - Google Patents

Temporary support for hoisting steel box girder Download PDF

Info

Publication number
CN219772721U
CN219772721U CN202321049740.5U CN202321049740U CN219772721U CN 219772721 U CN219772721 U CN 219772721U CN 202321049740 U CN202321049740 U CN 202321049740U CN 219772721 U CN219772721 U CN 219772721U
Authority
CN
China
Prior art keywords
steel box
temporary support
hoisting
upright
jacks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321049740.5U
Other languages
Chinese (zh)
Inventor
易佳飞
李军
吴远见
胡兴亚
叶木水
孙志贤
曾招丞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202321049740.5U priority Critical patent/CN219772721U/en
Application granted granted Critical
Publication of CN219772721U publication Critical patent/CN219772721U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to the technical field of temporary supports, and particularly relates to a temporary support for hoisting a steel box girder, which comprises a concrete foundation, wherein a plurality of stand columns are arranged on the concrete foundation at intervals, a distribution beam is arranged on the stand columns, a plurality of sandboxes are arranged on the distribution beam, a plurality of jacks are arranged on two sides of each sandbox, the jacks are arranged on the distribution beam, push rods of the jacks are upwards arranged, and tooth plates are arranged on the push rods of the jacks.

Description

Temporary support for hoisting steel box girder
Technical Field
The utility model belongs to the technical field of temporary supports, and particularly relates to a temporary support for hoisting a steel box girder.
Background
The steel box girder needs the temporary support as the basis when hoisting, has safe construction operation platform on the temporary support, therefore, the temporary support's demand lies in stable in structure, convenient to detach and installation, especially during steel box girder hoist and mount, need bear the steel box girder earlier by the temporary support, then make the steel box girder descend gradually, finally bear the steel box girder completely by the temporary support, under this requirement, the applicant is to improve the structural stability of current steel box girder and the cooperation of temporary support and steel box girder.
Disclosure of Invention
The utility model provides a temporary bracket for hoisting a steel box girder.
The utility model aims to provide a temporary support for hoisting a steel box girder, which consists of structures such as a pre-buried steel plate, an upright post, a distribution beam, a jack and the like.
In order to achieve the purpose of the utility model, the technical scheme of the utility model is as follows:
the temporary support for hoisting the steel box girder comprises a concrete foundation, wherein a plurality of stand columns are arranged at intervals on the concrete foundation, a distribution beam is arranged on the stand columns, a plurality of sandboxes are arranged on the distribution beam, a plurality of jacks are arranged on two sides of each sandbox, the jacks are arranged on the distribution beam, push rods of the jacks are upwards arranged, and tooth plates are arranged on the push rods of the jacks.
Further, an embedded steel plate is arranged in the concrete foundation, and the upright post is connected with the embedded steel plate.
Further, a supporting beam is arranged between the upright posts.
Further, the supporting beam comprises inclined struts which are obliquely arranged and transverse struts which are horizontally arranged, one end of each inclined strut is connected with one upright post, the other end of each inclined strut is connected with the other upright post, one end of each transverse strut is connected with one upright post, and the other end of each transverse strut is connected with the other upright post.
Further, a connecting plate is arranged on the upright post, and the diagonal bracing and the transverse bracing are fixedly connected with the connecting plate.
Further, the distribution beam is made of I-shaped steel.
Further, a plurality of reinforcing rib plates are arranged at the joint of the upright post and the embedded steel plate.
Further, a plurality of reinforcing rib plates are arranged at the joint of the upright post and the distribution beam.
Further, the reinforced net is arranged inside the concrete foundation, and the reinforced net is arranged at the top, the bottom and the side parts of the concrete foundation.
Compared with the prior art, the utility model has the beneficial effects that:
1. according to the utility model, the concrete foundation is taken as a bearing foundation of the temporary support, the embedded steel plate in the concrete foundation is utilized to be fixed with the upright post, I-steel is arranged at the upper end of the upright post to be used as a distribution beam to distribute the weight of the steel box girder, the sandbox supports the bottom of the steel box girder, the jack is matched with the pressing plate to support the side wing of the steel box girder, the steel box girder stably falls on the supporting point of the upright post foundation and the supporting surface of the distribution beam as the foundation under the continuous descending of the push rod of the jack and the continuous sand releasing of the sandbox, the upright post, the distribution beam and the jack are assembled to form the temporary support, and after the steel box girder is fixed, the upright post, the distribution beam and the jack are disassembled, so that the temporary support is convenient to install and disassemble and has a stable structure.
2. The utility model installs the supporting beam between the upright posts, the supporting beam is based on the cross braces and the diagonal braces, the stability between the upright posts is increased, and the supporting beam and the upright posts are convenient to detach after the steel box girder is hoisted and fixed.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the utility model.
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
fig. 2 is a schematic diagram of the front view structure of the present utility model.
In the figure:
1. the concrete foundation comprises pre-buried steel plates, 2, upright posts, 3, connecting plates, 4, diagonal braces, 5, transverse braces, 6, distribution beams, 7, sandboxes, 8, jacks, 9, dental plates, 10, steel box beams, 11 and concrete foundations.
Detailed Description
The utility model will be further described with reference to the drawings and examples.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of exemplary embodiments according to the present utility model. As used herein, the singular is also intended to include the plural unless the context clearly indicates otherwise, and furthermore, it is to be understood that the terms "comprises" and/or "comprising" when used in this specification are taken to specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof.
In the present utility model, terms such as "upper", "lower", "left", "right", "front", "rear", "vertical", "horizontal", "side", "bottom", etc. refer to an orientation or a positional relationship based on that shown in the drawings, and are merely relational terms, which are used for convenience in describing structural relationships of various components or elements of the present utility model, and do not denote any one of the components or elements of the present utility model, and are not to be construed as limiting the present utility model.
Example 1
The embodiment is a temporary bracket for hoisting a steel box girder, which is used for temporarily supporting the steel box girder 10, and has the main technical requirements that the temporary bracket is convenient to install and detach and has a stable structure, and comprises a concrete foundation 11, wherein an embedded steel plate 1 is embedded in the concrete foundation 11, C25 concrete is adopted as concrete, in the embodiment, the width and the height of the concrete foundation 11 are 3500mm and 500mm, the length is determined according to the length of the temporary bracket, the range is 6000-17000mm, reinforcing steel meshes are arranged at the positions, which are 50mm away from the top surface, the bottom and the side surface, inside the concrete foundation 11, of the embedded steel plate 1 are embedded in the top surface of the concrete foundation 11, the steel plates are 500mm long and 500mm wide and 16mm high, a plurality of stand columns 2 are arranged at intervals are arranged on the concrete foundation 11, the stand columns 2 are connected with the embedded steel plate 1 in a bolt connection mode, the upright post 2 of the embodiment adopts more than 6 cylindrical hollow columns with the diameter of 325mm, the distance between the upright posts 2 is 2m in the longitudinal bridge direction, the distance between the transverse bridge and the upright posts 2 is 2.3-2.5m, the upright posts 2 are connected with the distribution beam 6 through bolts, in the embodiment, the connection part of the upright posts 2 and the embedded steel plate 1 is provided with a plurality of reinforcing rib plates, the connection part of the upright posts 2 and the distribution beam 6 is provided with a plurality of reinforcing rib plates, the stability of the connection part of the reinforcing upright posts 2, the embedded steel plate 1 and the distribution beam 6 is enhanced, the distribution beam 6 is I-shaped steel, the I-shaped steel structure of the distribution beam 6 also mainly plays the role of distributing the weight of the steel box beam 10, a plurality of sand boxes 7 are arranged on the distribution beam 6, a plurality of jacks 8 are arranged on two sides of the sand boxes 7, the jacks 8 are fixedly arranged on the distribution beam 6 through bolts, the push rods of the jacks 8 are upwards arranged, the tooth plate 9 is installed on the push rod of the jack 8, and elevation is adjusted through the jack 8 in the embodiment.
This embodiment is for guaranteeing the stable structure of stand 2, install a supporting beam between stand 2, a supporting beam includes inclined stay 4 and horizontal bracing 5 of arranging of slope, the one end and a stand 2 of inclined stay 4 are connected, the other end and another stand 2 of inclined stay 4 are connected, the one end and a stand 2 of horizontal bracing 5 are connected, the other end and another stand 2 of horizontal bracing 5 are connected, specifically, the welding has connecting plate 3 on the stand 2, inclined stay 4, the fixed connection of horizontal bracing 5 and connecting plate 3, fixed connection mode includes welding and bolted connection, a supporting beam adopts channel-section steel structure, the material is Q235B, in addition, this embodiment erects safety construction operation platform on distributing beam 6, the railing of platform is formed by the angle steel welding, establish green mesh net in the railing outside, the plank or steel sheet are laid to the platform bottom, the cat ladder adopts GB 4053.1-2009's fixed steel straight ladder, the welding is in the stand 2 outside.
The above is only a preferred embodiment of the present utility model, and is not intended to limit the present utility model, but various modifications and variations can be made to the present utility model by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model should be included in the protection scope of the present utility model.
While the foregoing description of the embodiments of the present utility model has been presented in conjunction with the drawings, it should be understood that it is not intended to limit the scope of the utility model, but rather, it is intended to cover all modifications or variations within the scope of the utility model as defined by the claims of the present utility model.

Claims (9)

1. The temporary support for hoisting the steel box girder is characterized by comprising a concrete foundation (11), wherein a plurality of stand columns (2) which are arranged at intervals are arranged on the concrete foundation (11), distribution girders (6) are arranged on the stand columns (2), a plurality of sandboxes (7) are arranged on the distribution girders (6), a plurality of jacks (8) are arranged on two sides of each sandbox (7), the jacks (8) are arranged on the distribution girders (6), push rods of the jacks (8) are upwards arranged, and tooth plates (9) are arranged on the push rods of the jacks (8).
2. Temporary support for hoisting steel box girders according to claim 1, characterized in that the concrete foundation (11) is provided with pre-buried steel plates (1), and the upright posts (2) are connected with the pre-buried steel plates (1).
3. Temporary support for hoisting steel box girders according to claim 1, characterized in that support beams are arranged between the uprights (2).
4. A temporary support for hoisting a steel box girder according to claim 3, characterized in that the support beam comprises inclined struts (4) which are arranged obliquely and horizontal struts (5) which are arranged horizontally, one end of each inclined strut (4) is connected with one upright (2), the other end of each inclined strut (4) is connected with the other upright (2), one end of each horizontal strut (5) is connected with one upright (2), and the other end of each horizontal strut (5) is connected with the other upright (2).
5. The temporary support for hoisting steel box girders according to claim 4, wherein the upright posts (2) are provided with connecting plates (3), and the diagonal braces (4) and the transverse braces (5) are fixedly connected with the connecting plates (3).
6. Temporary support for hoisting steel box girders according to claim 1, characterized in that the distribution girders (6) are "i" steel.
7. Temporary support for hoisting steel box girders according to claim 2, characterized in that the connection of the upright (2) and the pre-buried steel plate (1) is provided with a plurality of reinforcing ribs.
8. Temporary support for hoisting steel box girders according to claim 1, characterized in that the connection of the upright (2) to the distribution girder (6) is provided with a number of reinforcing ribs.
9. Temporary support for hoisting steel box girders according to claim 1, characterized in that the concrete foundation (11) is internally provided with a reinforcement mesh arranged at the top, bottom and sides of the concrete foundation (11).
CN202321049740.5U 2023-05-05 2023-05-05 Temporary support for hoisting steel box girder Active CN219772721U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321049740.5U CN219772721U (en) 2023-05-05 2023-05-05 Temporary support for hoisting steel box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321049740.5U CN219772721U (en) 2023-05-05 2023-05-05 Temporary support for hoisting steel box girder

Publications (1)

Publication Number Publication Date
CN219772721U true CN219772721U (en) 2023-09-29

Family

ID=88135785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321049740.5U Active CN219772721U (en) 2023-05-05 2023-05-05 Temporary support for hoisting steel box girder

Country Status (1)

Country Link
CN (1) CN219772721U (en)

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
WO2022252829A1 (en) Liftable scaffold, lifting and installation methods thereof, and construction method for prefabricated building
CN114059758A (en) Assembled double-layer integral elevator shaft platform
CN210002931U (en) tool type protection system for telescopic adjustment of construction of super high-rise outer frame column
CN113265950A (en) Support for large cantilever bent cap construction and construction method thereof
CN219772721U (en) Temporary support for hoisting steel box girder
CN217378583U (en) Crossbeam support structure with main tower column stull function
CN215482366U (en) Double-line continuous beam bracket structure
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN212926984U (en) Movable suspension operating platform
CN112502475B (en) Supporting bearing capacity conversion device and using method thereof
CN213204913U (en) Modular prefabricated staircase operation platform
CN114876209A (en) Steel reinforced beam sectional construction method for limited hoisting
CN115045505A (en) Device for pouring concrete platform on steel structure frame and construction method
CN219387254U (en) Pushing bracket for steel box girder
CN220014395U (en) Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping
CN111827090A (en) Large-size quick assembling steel pipe support
CN216864857U (en) Quick support bracket convenient to cast-in-place roof beam construction
CN221589272U (en) Cast-in-situ bent cap support
CN219080936U (en) Lifting adjustable all-steel climbing frame
CN211923517U (en) A auxiliary stay frame for installing platform in hydraulic pressure creeping formwork
CN220319075U (en) Guy rope hanging basket assembling platform
CN211286560U (en) Spherical node suspension adjustable operation platform
CN212897484U (en) High-altitude operation platform for constructional engineering
CN214168805U (en) Novel movable lifting formwork support system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant