CN114876209A - Steel reinforced beam sectional construction method for limited hoisting - Google Patents

Steel reinforced beam sectional construction method for limited hoisting Download PDF

Info

Publication number
CN114876209A
CN114876209A CN202210735448.2A CN202210735448A CN114876209A CN 114876209 A CN114876209 A CN 114876209A CN 202210735448 A CN202210735448 A CN 202210735448A CN 114876209 A CN114876209 A CN 114876209A
Authority
CN
China
Prior art keywords
steel
scaffold
beams
hoisting
steel rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210735448.2A
Other languages
Chinese (zh)
Inventor
裴云龙
王春杨
史先觉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202210735448.2A priority Critical patent/CN114876209A/en
Publication of CN114876209A publication Critical patent/CN114876209A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/142Means in or on the elements for connecting same to handling apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/007Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/16Struts or stiffening rods, e.g. diagonal rods
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/12Clamps or clips for crossing members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0408Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section
    • E04C2003/0413Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section being built up from several parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0443Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by substantial shape of the cross-section
    • E04C2003/0452H- or I-shaped

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a steel rib beam segmented construction method for limited hoisting, and relates to the technical field of steel rib beam installation. The method comprises the following steps: the steel skeleton beam is made in sections, and the whole section of steel skeleton beam is divided into a side steel skeleton beam and a middle steel skeleton beam. Connect the scaffold frame horizontal pole in the scaffold frame pole setting, make the scaffold frame horizontal pole flush with the bottom surface that the position was preset to the reinforcing bar roof beam. And hoisting the side steel reinforced beam to the side mounting position, and connecting the side steel reinforced beam to the steel column by using a first mounting bolt. And hoisting the middle steel rib beam to the middle mounting position, and connecting the two ends of the middle steel rib beam with the end parts of the side steel rib beams at the two sides respectively by using second mounting bolts. And correcting the positions of the side steel rib beams and the middle steel rib beam. And respectively welding an upper flange plate and a lower flange plate on the side steel skeleton beam and the middle steel skeleton beam to finish the installation of the steel skeleton beams. By means of the method for installing the steel reinforced beams in sections, the problem that hoisting of the steel reinforced beams is limited is solved, construction efficiency is improved, and construction cost is reduced.

Description

Steel reinforced beam sectional construction method for limited hoisting
Technical Field
The invention relates to the technical field of steel reinforced beam installation, in particular to a steel reinforced beam sectional construction method for limited hoisting.
Background
At present, with the continuous development of national economy, infrastructure construction is vigorously developed in various places of China in recent years, steel structures gradually enter the visual field of people, various steel structures are generated at the same time, and the steel skeleton beam is one of the structural forms.
In the prior art, the traditional steel reinforced beam installation is generally carried out by directly hoisting machinery such as a truck crane, a crawler crane, a tower crane and the like with hoisting capacity to an installation position. The steel skeleton beam has the characteristics of large volume and heavy weight, so that the hoisting is difficult. Many lifting device hoist simultaneously probably need, but when the construction site was limited, can further increase the hoist and mount degree of difficulty, lead to some reinforcing bar roof beam can't use supporting hoist and mount machinery to install.
Disclosure of Invention
In view of the above, the present invention provides a steel reinforced beam segment construction method for limited hoisting, so as to solve the above problems.
Based on the purpose, the invention provides a steel reinforced beam segmented construction method for limited hoisting, which comprises the following steps:
s1, manufacturing the steel skeleton beam in sections, and manufacturing the whole section of steel skeleton beam into a side steel skeleton beam and a middle steel skeleton beam.
And S2, connecting the scaffold cross rod to the scaffold upright rod to enable the scaffold cross rod to be flush with the bottom surface of the preset position of the steel rib beam.
S3, hoisting the side steel rib beam to the side mounting position, and connecting the side steel rib beam to the steel column by using a first mounting bolt.
And S4, hoisting the middle steel rib beam to the middle mounting position, and connecting the two ends of the middle steel rib beam with the end parts of the side steel rib beams at the two sides respectively by using second mounting bolts.
And S5, correcting the positions of the side steel rib beams and the middle steel rib beam.
And S6, welding upper and lower flange plates on the side steel skeleton beams and the middle steel skeleton beam respectively to complete the installation of the steel skeleton beams.
Compared with the prior art, the invention has the beneficial effects that:
1. the whole section of steel rib beam is divided into the side steel rib beam and the middle steel rib beam, so that the weight of each section of steel rib beam is within the hoisting capacity range of the tower crane, the hoisting difficulty is reduced, the site construction condition is met, and the problem of hoisting limitation is solved.
2. Use the scaffold frame as the support, install each section reinforcing bar roof beam respectively, convenient operation, the installation degree of difficulty is low, can effectively improve the efficiency of construction, reduces construction cost, practices thrift the time limit for a project.
Further, the specific step of S2 includes: connecting the fasteners to the scaffold cross bars and the scaffold upright bars; lifting the cross rod of the scaffold through the fastener to enable the elevation of the cross rod of the scaffold to be flush with the bottom surface of the preset position of the steel reinforced beam; and tightening the fasteners to fix the cross rods of the scaffold on the vertical rods of the scaffold.
Further, the specific step of S5 includes: correcting the connecting center lines of the side steel rib beams, the middle steel rib beam and the steel columns; and correcting the elevation of the side steel rib beam and the middle steel rib beam.
Further, before S6, the method further includes: replacing the first mounting bolt with a first high-strength bolt; and replacing the second mounting bolt with a second high-strength bolt.
Further, after S6, the method further includes: and adjusting the position of the cross rod of the scaffold, and restoring the elevation of the cross rod of the scaffold to the set elevation of the formwork.
Drawings
Fig. 1 is a schematic mounting diagram of a scaffold for a segmented construction method of a hoisting-limited steel skeleton beam according to an embodiment of the present invention;
FIG. 2 is a schematic side steel-reinforced beam installation diagram for a steel-reinforced beam sectional construction method with limited hoisting according to an embodiment of the present invention;
FIG. 3 is a schematic view of the installation of the middle steel skeleton beam for the sectional construction method of the steel skeleton beam with limited hoisting provided by the embodiment of the invention;
FIG. 4 is a schematic elevation view of a section construction method for a steel reinforced beam with limited hoisting according to an embodiment of the present invention;
FIG. 5 is a schematic sectional view of the sectional construction method for steel reinforced beams with limited hoisting according to the embodiment of the present invention;
fig. 6 is a schematic elevation view of a scaffold cross bar elevation restoration for a hoisting-limited steel skeleton beam segmental construction method according to an embodiment of the present invention;
fig. 7 is a schematic view of a cross section of a scaffold cross bar for a hoisting-limited steel skeleton beam segmental construction method according to an embodiment of the present invention, which is restored to an elevation.
Labeled as: 1. a steel column; 2. a side steel skeleton beam; 3. an intermediate steel skeleton beam; 4. erecting a scaffold; 5. a scaffold rail; 6. a fastener; 7. stepping on the foot plate.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to specific embodiments below.
As shown in FIG. 1, the steel reinforced beam sectional construction method for limited hoisting provided by the invention comprises the following steps:
s1, manufacturing the steel skeleton beam in sections, and manufacturing the whole section of steel skeleton beam into the side steel skeleton beam 2 and the middle steel skeleton beam 3, so that the weight of each section of steel skeleton beam is within the hoisting capacity range of the tower crane. In the embodiment, the steel skeleton beam is divided into two side steel skeleton beams 2 and a middle steel skeleton beam 3.
S2, erecting steel columns 1 and scaffolds, symmetrically arranging the two steel columns 1, and respectively and fixedly installing the two steel columns 1 on the ground. The scaffold is by scaffold frame pole setting 4, scaffold frame horizontal pole 5 and step on sole 7 etc. and constitute, and scaffold frame pole setting 4 is installed between two steel columns 1, and scaffold frame stand fixed connection is subaerial, along the central line symmetric distribution of two steel columns 1. Scaffold cross-bar 5 perpendicular to scaffold pole setting 4 sets up, wears the dress respectively in fastener 6 with scaffold cross-bar 5 and scaffold pole setting 4, and scaffold cross-bar 5 and scaffold pole setting 4 all can slide in fastener 6 this moment. The scaffold cross rod 5 is lifted, so that the elevation of the scaffold cross rod 5 is flush with the bottom surface of the preset position of the steel rib beam. The fastener 6 is screwed up after the position of the scaffold cross rod 5 is adjusted, the scaffold cross rod 5 is fixed on the scaffold upright rod 4, and the foot treading plate 7 is installed above the scaffold cross rod 5.
S3, as shown in fig. 2, hoisting the side steel skeleton beam 2 to a side mounting position above the scaffold cross rod 5 and close to the steel column 1 by using a tower crane, connecting the side steel skeleton beam 2 to the steel column 1 by using a first mounting bolt, and connecting the two side steel skeleton beams 2 with the steel columns 1 at two sides respectively. During operation, the worker can perform an operation on the footstep plate 7.
And S4, as shown in figure 3, hoisting the middle steel rib beam 3 to the middle mounting position between the two side steel rib beams 2 by using a tower crane, and respectively connecting the two ends of the middle steel rib beam 3 with the end parts of the side steel rib beams 2 at the two sides by using second mounting bolts. The three sections of steel skeleton beams are connected together to form an integral steel skeleton beam.
And S5, correcting the connecting center lines of the side steel rib beams 2, the middle steel rib beam 3 and the steel column 1, and enabling the three steel rib beams to be located on the same horizontal line. And (3) correcting and correcting the elevations of the side steel rib beams 2 and the middle steel rib beam 3, and enabling the steel rib beams to be located at preset positions as shown in figures 4 and 5.
S6, the mounting bolts of each node are replaced from the center to the two ends in sequence, the first mounting bolts are replaced by the first high-strength bolts, the second mounting bolts are replaced by the second high-strength bolts, the high-strength bolts are used for guaranteeing the mounting stability of the steel reinforced beam, and the bearing capacity is enhanced. After the replacement of the bolts is finished, the upper flange plate and the lower flange plate are respectively welded on the side steel rib beams 2 and the middle steel rib beam 3, and the construction of the steel rib beams is finished.
As shown in fig. 6 and 7, the fastener 6 is loosened, the position of the scaffold cross bar 5 is adjusted, the elevation of the scaffold cross bar 5 is restored to the set elevation of the formwork, and after the position of the scaffold cross bar 5 is adjusted, the fastener 6 is screwed down, and the position of the scaffold cross bar 5 is fixed.
The embodiments of the invention are intended to embrace all such alternatives, modifications and variances that fall within the broad scope of the appended claims. Therefore, any omissions, modifications, substitutions, improvements and the like that may be made without departing from the spirit and principles of the invention are intended to be included within the scope of the invention.

Claims (5)

1. A steel reinforced beam sectional construction method for limited hoisting is characterized by comprising the following steps:
s1, manufacturing the steel skeleton beam in sections, and manufacturing the whole section of steel skeleton beam into a side steel skeleton beam and a middle steel skeleton beam;
s2, connecting the scaffold cross bar to the scaffold upright post to enable the scaffold cross bar to be flush with the bottom surface of the preset position of the steel rib beam;
s3, hoisting the side steel rib beam to a side mounting position, and connecting the side steel rib beam to the steel column by using a first mounting bolt;
s4, hoisting the middle steel rib beam to a middle mounting position, and connecting two ends of the middle steel rib beam with the end parts of the side steel rib beams at two sides respectively by using second mounting bolts;
s5, correcting the positions of the side steel rib beams and the middle steel rib beam;
and S6, welding upper and lower flange plates on the side steel skeleton beams and the middle steel skeleton beam respectively to complete the installation of the steel skeleton beams.
2. The segmented construction method for hoisting limited steel reinforced beams as claimed in claim 1, wherein the specific steps of S2 include:
connecting fasteners to the scaffold cross rods and the scaffold upright rods;
lifting the cross rod of the scaffold by a fastener to enable the elevation of the cross rod of the scaffold to be flush with the bottom surface of the preset position of the steel reinforced beam;
and tightening the fasteners to fix the cross rods of the scaffold on the vertical rods of the scaffold.
3. The segmented construction method for hoisting limited steel reinforced beams as claimed in claim 1, wherein the specific steps of S5 include:
correcting the central lines of the connection of the side steel rib beams, the middle steel rib beam and the steel columns;
and correcting the elevation of the side steel rib beam and the middle steel rib beam.
4. The method of claim 1, further comprising, before S6:
replacing the first mounting bolt with a first high-strength bolt;
and replacing the second mounting bolt with a second high-strength bolt.
5. The method of claim 1, further comprising, after S6: and adjusting the position of the cross rod of the scaffold, and restoring the elevation of the cross rod of the scaffold to the set elevation of the formwork.
CN202210735448.2A 2022-06-27 2022-06-27 Steel reinforced beam sectional construction method for limited hoisting Pending CN114876209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210735448.2A CN114876209A (en) 2022-06-27 2022-06-27 Steel reinforced beam sectional construction method for limited hoisting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210735448.2A CN114876209A (en) 2022-06-27 2022-06-27 Steel reinforced beam sectional construction method for limited hoisting

Publications (1)

Publication Number Publication Date
CN114876209A true CN114876209A (en) 2022-08-09

Family

ID=82682897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210735448.2A Pending CN114876209A (en) 2022-06-27 2022-06-27 Steel reinforced beam sectional construction method for limited hoisting

Country Status (1)

Country Link
CN (1) CN114876209A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115263000A (en) * 2022-08-29 2022-11-01 中建八局第一建设有限公司 Device for in-situ correction of super-long steel beam after high-position segmented hoisting and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905218A (en) * 2019-11-12 2020-03-24 江苏南通三建集团股份有限公司 Sectional hoisting process for super-large-span box-shaped steel beam
CN112324131A (en) * 2020-10-29 2021-02-05 杭州二建建设有限公司 One-frame dual-purpose large-span stiff beam construction structure and construction method thereof
CN114293783A (en) * 2021-12-22 2022-04-08 中国建筑第八工程局有限公司 High-altitude large-span steel beam mounting method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905218A (en) * 2019-11-12 2020-03-24 江苏南通三建集团股份有限公司 Sectional hoisting process for super-large-span box-shaped steel beam
CN112324131A (en) * 2020-10-29 2021-02-05 杭州二建建设有限公司 One-frame dual-purpose large-span stiff beam construction structure and construction method thereof
CN114293783A (en) * 2021-12-22 2022-04-08 中国建筑第八工程局有限公司 High-altitude large-span steel beam mounting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115263000A (en) * 2022-08-29 2022-11-01 中建八局第一建设有限公司 Device for in-situ correction of super-long steel beam after high-position segmented hoisting and construction method
CN115263000B (en) * 2022-08-29 2023-06-20 中建八局第一建设有限公司 Device for in-situ correction after high-level sectional hoisting of ultra-long steel beam and construction method

Similar Documents

Publication Publication Date Title
CN107090975B (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN112663501B (en) Upper-span existing line steel box girder structure and construction method
CN111749140A (en) Truss integral lifting type bridge high pier creeping formwork device and construction method
CN105780922A (en) Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss
CN114876209A (en) Steel reinforced beam sectional construction method for limited hoisting
CN212582721U (en) Bearing platform of tower crane for vertical tower of top plate of foundation garage
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN103866692A (en) Novel assembling method for bent cap bearing frame
CN111809654A (en) Assembled tower crane foundation structure
CN111648611A (en) Embedded part supporting device and embedded part installation method using embedded part supporting device
CN111395183A (en) System and method for electric bridge type scaffold platform for double-column pier construction
CN216892017U (en) Tie beam integral casting template in template connecting piece and lower stand
CN217378583U (en) Crossbeam support structure with main tower column stull function
CN216040719U (en) Template support cantilever bearing structure
CN214459664U (en) Floor-free pier column bent cap template dismounting device
CN112813852B (en) Repairing and reinforcing method for bridge deck subsidence of in-service bridge
CN212249280U (en) Embedded part supporting device
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN212532065U (en) Gantry crane capable of being used in different height difference places
CN113818361A (en) Template support cantilever support system and installation method thereof
CN215857280U (en) High mound river-crossing bridge penetrating bar cantilever supporting system
CN219430545U (en) Operation platform for utilizing stiffness framework for tower column head section
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
CN211713706U (en) Large cantilever prefabricated bent cap installation lattice support device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220809