CN219446972U - Rail transport vehicle for building construction - Google Patents

Rail transport vehicle for building construction Download PDF

Info

Publication number
CN219446972U
CN219446972U CN202320558320.3U CN202320558320U CN219446972U CN 219446972 U CN219446972 U CN 219446972U CN 202320558320 U CN202320558320 U CN 202320558320U CN 219446972 U CN219446972 U CN 219446972U
Authority
CN
China
Prior art keywords
track
vehicle body
frame
assembled
construction according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320558320.3U
Other languages
Chinese (zh)
Inventor
杨顺
冷正华
匡韦科
杨夏坤
霍星光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Bureau Group Co Ltd
Original Assignee
China Construction Third Bureau Group Co Ltd
China Construction Third Bureau Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Bureau Group Co Ltd, China Construction Third Bureau Construction Engineering Co Ltd filed Critical China Construction Third Bureau Group Co Ltd
Priority to CN202320558320.3U priority Critical patent/CN219446972U/en
Application granted granted Critical
Publication of CN219446972U publication Critical patent/CN219446972U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T30/00Transportation of goods or passengers via railways, e.g. energy recovery or reducing air resistance

Landscapes

  • Handcart (AREA)

Abstract

The utility model provides a track transport vehicle for building construction, which comprises a vehicle body (1) and an assembled track (2), wherein the vehicle body (1) moves on the assembled track (2); the vehicle body (1) comprises a frame (101) and four wheels (102), wherein the four wheels (102) are fixedly arranged on the frame (101); the assembled track (2) comprises a plurality of track sections (201) and splicers (202), and each adjacent track section (201) is fixedly connected through each splicer (202). The scheme of the utility model can support constructors to freely assemble the assembled track (2) according to the actual condition of a construction site, and the vehicle body (1) moving on the assembled track (2) is utilized to carry materials efficiently and safely.

Description

Rail transport vehicle for building construction
Technical Field
The utility model relates to the technical field of building construction equipment, in particular to a track transport vehicle for building construction.
Background
Often, the construction site needs to carry more materials, such as cement, sand and stone, and the traditional manual carrying mode is low in efficiency and easy to cause injury to workers, and meanwhile, many construction sites cannot accommodate the entry of large carrying machinery. Therefore, how to solve the problem of efficient material handling in the building construction scene with limited space is the technical problem to be solved by the utility model.
Disclosure of Invention
In order to at least solve the technical problems in the background art, the utility model provides a track transport vehicle for building construction.
The rail transport vehicle for building construction comprises a vehicle body and an assembled rail, wherein the vehicle body moves on the assembled rail; wherein,,
the vehicle body comprises a frame and four wheels, and the four wheels are fixedly arranged on the frame;
the assembled track comprises a plurality of track sections and splicers, and each adjacent track section is fixedly connected through each splicer.
Further, the track section comprises a transverse supporting rod and a vertical supporting rod, and the vertical supporting rod is vertically and fixedly connected with the transverse supporting rod.
Further, the track section further comprises a base, and the base is fixedly connected with the vertical support rod vertically.
Further, the assembled track further comprises a cross rod and a track frame, wherein both ends of the cross rod are vertically and fixedly connected with the cross support rods, and the track frame is connected to a plurality of the cross rods.
Further, the rail frame comprises two vertical wheel carrying rail frames.
Further, the wheel bearing rail frame is provided with a plurality of first connecting holes, two ends of the cross rod are respectively provided with a second connecting hole, and the first connecting holes and the second connecting holes are used for passing through and locking the connecting rope.
Further, the upper end of the wheel bearing rail is provided with a groove which is matched with the width of the wheel.
Further, the vehicle body further includes a traction rope provided at a rear end portion of the vehicle body.
The utility model has the beneficial effects that:
in a construction scene with limited operation space, a constructor can assemble a proper assembled track (2) according to respective positions of a storage area of building materials and a target construction area, and then place a vehicle body (1) on the assembled track (2), so that the vehicle body (1) and the assembled track (2) can be utilized to conveniently convey materials. In the conveying process, the car body (1) erected on the assembled track (2) cannot collide with construction waste, other materials and the like piled on the construction ground, so that the safety is higher.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present utility model, the drawings that are needed in the embodiments will be briefly described below, it being understood that the following drawings only illustrate some embodiments of the present utility model and therefore should not be considered as limiting the scope, and other related drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic main body structure of a rail transport vehicle for construction according to an embodiment of the present utility model;
FIG. 2 is a schematic diagram of an assembled track roof construction in accordance with an embodiment of the present utility model;
fig. 3 is a schematic view of a partial installation of a track frame and vertical supports and rails according to an embodiment of the present utility model.
Detailed Description
In order to make the objects, technical solutions and advantages of the present utility model more apparent, the present utility model will be described in further detail below with reference to the accompanying drawings, and it is apparent that the described embodiments are only some embodiments of the present utility model, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Preferred embodiments of the present utility model will be described in detail below with reference to the accompanying drawings.
Referring to fig. 1, fig. 1 is a schematic main structure of a rail transport vehicle for construction according to an embodiment of the present utility model. As shown in fig. 1, a track carrier for construction according to an embodiment of the present utility model includes a vehicle body (1) and an assembled track (2), the vehicle body (1) moving on the assembled track (2); wherein,,
the vehicle body (1) comprises a frame (101) and four wheels (102), wherein the four wheels (102) are fixedly arranged on the frame (101);
the assembled track (2) comprises a plurality of track sections (201) and splicers (202), and each adjacent track section (201) is fixedly connected through each splicer (202).
Further, the track section (201) comprises a transverse supporting rod (2011) and a vertical supporting rod (2012), and the vertical supporting rod (2012) is fixedly connected with the transverse supporting rod (2011) vertically.
Further, the track section (201) further comprises a base (2013), and the base (2013) is fixedly connected with the vertical support rod (2012) vertically.
Further, the assembled track (2) further comprises a cross rod (203) and a track frame (204), both ends of the cross rod (203) are vertically and fixedly connected with the cross rod (2011), and the track frame (204) is connected to a plurality of the cross rods (203).
Further, the track frame (204) comprises two vertical wheel carrying track frames (2041).
Further, a plurality of first connecting holes (3) are formed in the wheel bearing rail frame (2041), a plurality of second connecting holes (4) are formed in two end portions of the cross rod (203), and the first connecting holes (3) and the second connecting holes (4) are used for crossing and locking connecting ropes.
Further, the upper end of the wheel carrying rail (2041) is provided with a groove (not shown) adapted to the width of the wheel (102).
Further, the vehicle body (1) further includes a traction rope (103) provided at a rear end portion of the vehicle body (1).
When construction is required in a construction scene (e.g., indoor) where the operation space is limited, a constructor can determine the laying scheme of the assembled track (2) according to the respective positions of the storage area of the building materials and the target construction area.
1) Assembling a vehicle body (1): four wheels (102) are respectively arranged at appointed mounting positions at four corners of a frame (101). The frame (101) of the vehicle body (1) may be a plate-like structure or a frame-like structure, and the drawings of the present utility model will not be described in detail because of the conventional vehicle body structure.
2) Assembling a rail: the transverse support rods (2011), the vertical support rods (2012) and the base (2013) are sequentially and vertically installed to form a single-side track section, and the three can be movably installed in a mode of screwing, clamping and the like, and can be integrally formed or welded; and then the two ends of the cross rod (203) are respectively and fixedly installed with the two unilateral track sections (the installation mode can also adopt the conventional modes of screw connection, clamping connection and the like), and a complete track section (201) can be built at the moment. Then, the splice (202) (e.g., consisting of bolts, nuts, shims) is used to connect the individual track segments (201) to match the connection length to the lay-down scheme; two wheel bearing rail frames (2041) are respectively paved at two ends of the cross rod (203), and the space between the two wheel bearing rail frames (2041) is configured according to the space between two wheels (102) transversely arranged on the vehicle body (1); and then the connecting rope sequentially passes through the first connecting hole (3) on the wheel bearing rail frame (2041) and the second connecting hole (4) on the cross rod (203) and is locked, so that the fixed installation of the rail frame (204) and the rail section (201) can be realized.
When the vehicle body (1) with different wheel tracks is adopted, the adjustment can be realized by locking the wheel bearing rail frame (2041) and the second connecting holes (4) at different positions on the cross rod (203).
3) Carry automobile body (1) to on assembled track (2), make four wheels (102) all block into the recess of wheel bearing rail frame (2041), place the material that needs to carry on automobile body (1), can be convenient promote automobile body (1) this moment and realize transporting of material, improve material handling efficiency. In the conveying process, the car body (1) erected on the assembled track (2) cannot collide with construction waste, other materials and the like piled on the construction ground, so that the safety is higher.
In addition, one or more traction ropes (103) can be arranged at the rear end part of the vehicle body (1), the other end of the traction rope (103) can be fixed on a building near the area where the materials are located, and the maximum movement length of the vehicle body (1) is limited through the traction ropes (103) so as to prevent the vehicle body from being driven out of the assembled track (2). The effective traction length of the traction rope (103) can be set according to the length of the assembled track (2) in the actual field, and detailed description is omitted.
Note that the above is only a preferred embodiment of the present utility model and the technical principle applied. It will be understood by those skilled in the art that the present utility model is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the utility model. Therefore, while the utility model has been described in connection with the above embodiments, the utility model is not limited to the above embodiments, but may include many other equivalent embodiments without departing from the spirit of the utility model, which fall within the scope of the utility model.

Claims (8)

1. The utility model provides a track transport vechicle for construction which characterized in that: comprises a vehicle body (1) and an assembled track (2), wherein the vehicle body (1) moves on the assembled track (2); wherein,,
the vehicle body (1) comprises a frame (101) and four wheels (102), wherein the four wheels (102) are fixedly arranged on the frame (101);
the assembled track (2) comprises a plurality of track sections (201) and splicers (202), and each adjacent track section (201) is fixedly connected through each splicer (202).
2. A rail transport vehicle for construction according to claim 1, characterized in that: the track section (201) comprises a transverse supporting rod (2011) and a vertical supporting rod (2012), and the vertical supporting rod (2012) is fixedly connected with the transverse supporting rod (2011) vertically.
3. A rail transportation vehicle for construction according to claim 2, wherein: the track section (201) further comprises a base (2013), and the base (2013) is vertically and fixedly connected with the vertical support rod (2012).
4. A rail transportation vehicle for construction according to claim 3, wherein: the assembled track (2) further comprises a cross rod (203) and a track frame (204), wherein both ends of the cross rod (203) are vertically and fixedly connected with the cross support rods (2011), and the track frame (204) is connected to a plurality of the cross rods (203).
5. The track carrier for building construction according to claim 4, wherein: the track frame (204) comprises two vertical wheel carrying track frames (2041).
6. The track carrier for building construction according to claim 5, wherein: the wheel bearing rail frame (2041) is provided with a plurality of first connecting holes (3), two ends of the cross rod (203) are respectively provided with a second connecting hole (4), and the first connecting holes (3) and the second connecting holes (4) are used for crossing and locking connecting ropes.
7. The track carrier for building construction according to claim 6, wherein: the upper end of the wheel bearing rail (2041) is provided with a groove which is matched with the width of the wheel (102).
8. A rail transport vehicle for construction according to claim 1, characterized in that: the vehicle body (1) further comprises a traction rope (103) which is arranged at the rear end part of the vehicle body (1).
CN202320558320.3U 2023-03-21 2023-03-21 Rail transport vehicle for building construction Active CN219446972U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320558320.3U CN219446972U (en) 2023-03-21 2023-03-21 Rail transport vehicle for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320558320.3U CN219446972U (en) 2023-03-21 2023-03-21 Rail transport vehicle for building construction

Publications (1)

Publication Number Publication Date
CN219446972U true CN219446972U (en) 2023-08-01

Family

ID=87384486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320558320.3U Active CN219446972U (en) 2023-03-21 2023-03-21 Rail transport vehicle for building construction

Country Status (1)

Country Link
CN (1) CN219446972U (en)

Similar Documents

Publication Publication Date Title
CN108343087B (en) Prefabricated part transportation and assembly equipment system and construction method thereof
CN206680871U (en) Boom device is transported on a kind of four rail beams
CN201648969U (en) Railway T-girder bridge girder erection machine suitable for laying and erecting seamless lines for passenger and freight shared lines
CN210392614U (en) Material conveying device for roadbed high slope protection construction
CN219446972U (en) Rail transport vehicle for building construction
CN112342915B (en) Construction method for gantry hoisting beam of overhead track
CN111636914A (en) Construction method for integrating transportation and erection of straddle type monorail PC track beam in circular-section tunnel
CN106185616A (en) A kind of vehicle mounted portable unloads rail portal frame and construction method thereof
JP3991067B1 (en) Temporary bridge between railway platforms
CN114575251B (en) Large-span steel truss arch bridge construction system and construction method
CN115058957A (en) Dual-purpose trestle supporting structure
CN110565458B (en) Laying trolley and method for laying U-shaped beam track
CN113957755A (en) Medium-low speed magnetic levitation traffic combined U-shaped beam structure
CN111270577A (en) Assembly machine suitable for narrow space of subway underground line and overhead line cross-track section and construction method thereof
CN209921282U (en) Vehicle turning device capable of being used in narrow place
CN111417558B (en) String type track structure
CN113322814A (en) Construction method of cable-stayed bridge steel box girder spanning multiple obstacles
CN217027200U (en) Template operation trolley and operation system for construction of height-gradient retaining wall
CN212128685U (en) Be suitable for narrow and small space of subway underground line and overhead line track section kludge of striding line
CN114737479B (en) Protection system, dismounting device and construction method for existing traffic of upper cover of composite beam
CN112919314B (en) Device for assisting in translational transportation and installation of overweight steel column and construction method
CN215829277U (en) Frame transporting machine applied to steel-concrete composite slab combined beam bridge
CN220057500U (en) Parking structure of guide rail type rubber wheel system vehicle in parking garage
CN210195288U (en) Installation device of large-span steel member
UA71059U (en) Elevated frame system of railway transport

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant