CN218843150U - Building engineering foundation pile subassembly - Google Patents

Building engineering foundation pile subassembly Download PDF

Info

Publication number
CN218843150U
CN218843150U CN202223379944.3U CN202223379944U CN218843150U CN 218843150 U CN218843150 U CN 218843150U CN 202223379944 U CN202223379944 U CN 202223379944U CN 218843150 U CN218843150 U CN 218843150U
Authority
CN
China
Prior art keywords
fixed
foundation pile
backup pad
link
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223379944.3U
Other languages
Chinese (zh)
Inventor
宁飞
张海鹏
肖冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Village And Town Construction Service Center In Quyang Town Donghai County
Original Assignee
Village And Town Construction Service Center In Quyang Town Donghai County
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Village And Town Construction Service Center In Quyang Town Donghai County filed Critical Village And Town Construction Service Center In Quyang Town Donghai County
Priority to CN202223379944.3U priority Critical patent/CN218843150U/en
Application granted granted Critical
Publication of CN218843150U publication Critical patent/CN218843150U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a building engineering foundation pile subassembly belongs to building engineering foundation pile technical field, has aimed at the problem that foundation pile subassembly life is shorter and staff's work efficiency is lower, including the base, both ends all are fixed with stabilizing frame about the base, and equal threaded connection has the threaded rod in the middle part of two stabilizing frames, and two threaded rod close sides all are fixed with the fixed disk, and two fixed disk surfaces all rotate and are connected with the link, and the circular slot has all been seted up to two link insides, and two link close sides all are fixed with the backup pad, and two threaded rod opposite sides all are fixed with the carousel; the utility model discloses a manpower rotation hand wheel rotates, realizes that the position of foundation post sets up the effect, reaches extension foundation pile subassembly life's effect, strikes or the perk mount removes through the manpower, realizes convenient installation and dismantles the effect of foundation pile subassembly, reaches the effect that improves staff work efficiency.

Description

Building engineering foundation pile subassembly
Technical Field
The utility model belongs to the technical field of building engineering foundation pile, concretely relates to building engineering foundation pile subassembly.
Background
The building engineering is an engineering entity formed by the construction of various house buildings and their auxiliary facilities and the installation of lines, pipes and equipment matched with them, in which the house buildings are made up of top cover, beam column, wall and foundation, and can form internal space, so that it can meet the requirements of people for production, living, learning and public activities.
The comparative patent document publication numbers are: "CN 216973469U's a building engineering ground foundation pile subassembly, including bottom plate, supporting mechanism and reference column, supporting mechanism sets up in the upper surface of bottom plate, and reference column fixed connection is in the bottom of bottom plate, and supporting mechanism includes first backup pad and second backup pad. This building engineering foundation pile subassembly, with bottom plate fixed mounting on the ground through constructor, insert the foundation post between first backup pad and the second backup pad again, and pass the lower extreme of fastening hole with first backup pad fixed mounting at the foundation post through the bolt, the second backup pad is also the same, the position of foundation post is finely tuned about its constructor can removing after the completion, its first backup pad can remove along first spacing spout along the foundation post, adjust to carry out the landfill solidification design with the subassembly through cement mortar after accomplishing, be convenient for the foundation post carries out position control, the accurate nature that the foundation post position set up has been improved, above-mentioned patent is under the in-service use condition, still there is following problem: although this patent can carry out daily engineering operation, but in the in-service use process, when relying on the backup pad of bottom atress to support the operation, make the atress of whole backup pad all be used in the bottom easily, make the atress of whole backup pad not enough even, easy fracture, cause the damage, influence foundation pile subassembly life, and fixed connection's reference column is inconvenient installs and dismantles foundation pile subassembly, the installation and the dismantlement operation of giving the staff bring inconvenience, make staff's work efficiency lower.
Therefore, a need exists for a foundation pile assembly for construction engineering, which solves the problems of short service life of the foundation pile assembly and low working efficiency of workers in the prior art.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering foundation pile subassembly to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model provides a following technical scheme: the utility model provides a building engineering foundation pile subassembly, includes the base, both ends all are fixed with the steady rest about the base, two equal threaded connection in steady rest middle part has the threaded rod, two the close side of threaded rod all is fixed with the fixed disk, two the fixed disk surface all rotates and is connected with the link, two the circular recess has all been seted up to the link inside, two the close side of link all is fixed with the backup pad, two the threaded rod all is fixed with the carousel, two the carousel all is fixed with the hand wheel mutually from the side, the spout has all been seted up in base four corners, four the equal sliding connection of spout inner wall has a sliding tray, four the sliding tray middle part all is fixed with the connecting rod, four the connecting rod bottom all is fixed with the cone, four the connecting rod top all is fixed with the mount.
What need explain in the scheme is, two the threaded rod surface all rotates to be connected in the link middle part, every the fixed disk surface all rotates to be connected at every circular recess inner wall, the vertical section of fixed disk is circular setting.
It is further worth explaining that the bottoms of the two stabilizing frames are fixed in the middle of the left end and the right end of the base, the close sides of the middle parts of the two connecting frames are fixed in the middle of the two supporting plates, the cross section of each supporting plate is in a semi-arc shape, and the outer surface of the bottom of each supporting plate is in sliding connection with the outer surface of the upper end of the base.
It should be further noted that the outer surface of each sliding plate is slidably connected to the inner wall of each sliding groove, and each connecting rod penetrates through the middle of each sliding groove.
As a preferred embodiment, the middle of each fixing frame is fixed at the top end of each connecting rod, the cross section of each fixing frame is circular, the middle of each of the four cones is fixed at the bottom end of each connecting rod, and the vertical section of each cone is conical.
As a preferred embodiment, two rubber strips are fixed on the near sides of the two supporting plates, and two prepared holes are formed in the middle of each supporting plate.
Compared with the prior art, the utility model provides a pair of building engineering foundation pile subassembly includes following beneficial effect at least:
(1) Rotate the hand wheel through the manpower and rotate for hand wheel, threaded rod, carousel, fixed disk, link, circular recess, backup pad mutually support the operation, realize that the position of foundation post sets up the effect, and the backup pad setting of middle part atress makes the atress of backup pad more even, avoids the backup pad fracture, leads to ground foundation pile subassembly to damage, and then reaches extension ground foundation pile subassembly life's effect.
(2) Strike or perk the mount through the manpower and remove for mount, connecting rod, sliding tray, spout, cone work of mutually supporting realize convenient installation and dismantle the effect of ground foundation pile subassembly, facilitate for staff's work, and then reach the effect that improves staff work efficiency.
Drawings
Fig. 1 is a perspective view of the present invention;
FIG. 2 is a cross-sectional view of the stabilizer of the present invention;
FIG. 3 is a cross-sectional view of the base of the present invention;
fig. 4 is a top view of the present invention.
In the figure: 1. a base; 2. a stabilizing frame; 3. a threaded rod; 4. fixing the disc; 5. a connecting frame; 6. a circular groove; 7. a support plate; 8. a turntable; 9. a hand wheel; 10. a chute; 11. a slide plate; 12. a connecting rod; 13. a cone; 14. a fixed mount; 15. a rubber strip; 16. holes are reserved.
Detailed Description
The present invention will be further described with reference to the following examples.
Referring to fig. 1-4, the utility model provides a foundation pile assembly for building engineering, which comprises a base 1, wherein the base 1 plays a supporting role, stabilizing frames 2 are fixed at the left and right ends of the base 1, the stabilizing frames 2 play a role of stabilizing threaded rods 3, threaded rods 3 are connected at the middle parts of the two stabilizing frames 2 in a threaded manner, fixed disks 4 are fixed at the adjacent sides of the two threaded rods 3, the fixed disks 4 are driven by the threaded rods 3 to rotate and simultaneously perform a position moving effect, connecting frames 5 are rotatably connected on the outer surfaces of the two fixed disks 4, circular grooves 6 are formed in the connecting frames 5 to provide place support for the rotation of the fixed disks 4, circular grooves 6 are formed in the two connecting frames 5, supporting plates 7 are fixed at the adjacent sides of the two connecting frames 5, and the supporting plates 7 play a role of limiting the position of a foundation pile, two threaded rods 3 all are fixed with carousel 8 from the side mutually, carousel 8 and hand wheel 9 mutually support, rotation for the staff facilitates, two carousel 8 all are fixed with hand wheel 9 from the side mutually, spout 10 has all been seted up in base 1 four corners, spout 10 provides the slip place for the slip of slip disk 11, the equal sliding connection of four spout 10 inner walls has slip disk 11, four slip disk 11 middle parts all are fixed with connecting rod 12, cone 13 and mount 14's effect is connected to connecting rod 12, four connecting rod 12 bottoms all are fixed with cone 13, cone 13 is the toper setting, make things convenient for the staff to nail into in the soil, four connecting rod 12 tops all are fixed with mount 14, mount 14 makes things convenient for the staff to strike or the perk, make things convenient for the staff to carry out convenient installation and the dismantlement operation of subassembly.
Further as shown in fig. 1, 2 and 4, it is worth specifically explaining that the outer surfaces of the two threaded rods 3 are all rotatably connected to the middle of the connecting frame 5, the outer surface of each fixed disk 4 is rotatably connected to the inner wall of each circular groove 6, the vertical section of each fixed disk 4 is in a circular arrangement, the bottoms of the two stabilizing frames 2 are fixed to the middle of the left end and the right end of the base 1, the middle parts and the near sides of the middle parts of the two connecting frames 5 are fixed to the middle parts of the two supporting plates 7, the transverse section of each supporting plate 7 is in a half-arc arrangement, and the outer surface of the bottom of each supporting plate 7 is slidably connected to the outer surface of the upper end of the base 1.
As further shown in fig. 1, 3 and 4, it is worth specifying that the outer surface of each slide plate 11 is slidably connected to the inner wall of each slide groove 10, and each connecting rod 12 penetrates through the middle of each slide groove 10.
The scheme has the following working processes: when using building engineering ground foundation pile subassembly, at first rotate hand wheel 9 through the manpower and rotate, make carousel 8 with hand wheel 9 fixed connection rotate, thereby make threaded rod 3 with carousel 8 middle part fixed connection rotate, and then make threaded rod 3 surface carry out the position shift operation under the stability of threaded connection's steady rest 2, thereby make fixed disk 4 with 3 one end fixed connection of threaded rod carry out the position shift operation in the circular slot 6 inner wall pivoted that the link 5 middle part was seted up, and then make backup pad 7 with link 5 fixed connection carry out the slip operation under the stability of base 1, the position setting operation of accomplishing the foundation post, make the atress of backup pad 7 more even, support whole backup pad 7 with the middle part, the stability of support is better, base 1 is placed subaerial this moment, after the position adjustment, strike mount 14 through the manpower and move, make connecting rod 12 with mount 14 middle part fixed connection drive slide plate 11 slide operation at the spout 10 inner wall, thereby make every cone 13 with every connecting rod 12 bottom fixed connection of every connecting rod bottom move down the operation, thereby make the cone 13 insert the soil pile subassembly of accomplishing the inside the cone of foundation pile subassembly and carry out the ground through the cone removal of the mount 14, make every ground foundation pile subassembly remove the operation of carrying out the ground, make the ground foundation pile subassembly of carrying out the operation of the basic pile removal of the mount 12 and carry out the operation of the basic pile removal of the ground, it is connected with every ground.
According to the working process, the following steps are carried out: rotate hand wheel 9 through the manpower and rotate, make 8 drive threaded rod 3 with hand wheel 9 fixed connection's carousel rotate, accomplish the position control operation of backup pad 7, the position that realizes the foundation post sets up the effect, the backup pad 7 of middle part atress sets up, make the atress of backup pad 7 more even, avoid backup pad 7 fracture, lead to ground basis stake subassembly to damage, and then reach extension ground basis stake subassembly life's effect, strike or perk mount 14 through the manpower afterwards and remove, make connecting rod 12 with 14 fixed connection of mount drive cone 13 and remove, realize convenient installation and dismantle the effect of ground basis stake subassembly, facilitate for staff's work, and then reach the effect that improves staff work efficiency.
Further as shown in fig. 1, 3 and 4, it is worth specifically explaining that the middle part of each fixing frame 14 is fixed at the top end of each connecting rod 12, the cross section of each fixing frame 14 is in a circular arrangement, the middle parts of four cones 13 are fixed at the bottom end of each connecting rod 12, the vertical section of each cone 13 is in a conical arrangement, and the fixing frame 14 facilitates the installation or disassembly of the cone 13 by a worker to complete the convenient installation and disassembly operation of the basic column assembly.
Further as shown in fig. 1, fig. 2 and fig. 3, it is worth specifically explaining that two rubber strips 15 are fixed on the close sides of the two supporting plates 7, two preformed holes 16 are formed in the middle of each supporting plate 7, the preformed holes 16 provide support for the connection of the foundation columns, and the effect of conveniently fixing the foundation columns is achieved.
To sum up: make things convenient for the staff to carry out the installation or the dismantlement of cone 13 through the mount 14 that sets up to accomplish the convenient installation and the dismantlement operation of foundation column subassembly, provide the support for the connection of foundation column through the preformed hole 16 that sets up, play the effect of convenient fixed foundation pile.

Claims (6)

1. The utility model provides a building engineering foundation pile subassembly, includes base (1), its characterized in that, both ends all are fixed with steadying frame (2), two about base (1) the equal threaded connection in steadying frame (2) middle part has threaded rod (3), two the close side of threaded rod (3) all is fixed with fixed disk (4), two fixed disk (4) surface all rotates and is connected with link (5), two link (5) inside circular slot (6), two link (5) close side all is fixed with backup pad (7), two threaded rod (3) are close the side and all are fixed with carousel (8), two carousel (8) are close the side and all are fixed with hand wheel (9), spout (10) have all been seted up in base (1), four equal sliding connection in spout (10) inner wall has slide plate (11), four slide plate (11) middle part all is fixed with connecting rod (12), four connecting rod (12) bottom all is fixed with cone (13), four connecting rod (12) top all is fixed with mount (14).
2. A construction engineering foundation pile assembly as defined in claim 1, wherein: two threaded rod (3) surface all rotates to be connected at link (5) middle part, every fixed disk (4) surface all rotates to be connected at every circular slot (6) inner wall, fixed disk (4) vertical section is circular setting.
3. A construction engineering foundation pile assembly as defined in claim 1, wherein: two steady rest (2) bottom is fixed in base (1) left and right sides both ends middle part, two link (5) middle part near side all is fixed in two backup pad (7) middle parts, every backup pad (7) cross section is half arc setting, every backup pad (7) bottom surface sliding connection is at base (1) upper end surface.
4. A constructional engineering foundation pile assembly as defined in claim 1 wherein: the outer surface of each sliding disc (11) is connected to the inner wall of each sliding groove (10) in a sliding mode, and each connecting rod (12) penetrates through the middle of each sliding groove (10).
5. A construction engineering foundation pile assembly as defined in claim 1, wherein: every mount (14) middle part is all fixed on every connecting rod (12) top, every mount (14) cross section is circular setting, four cone (13) middle part is all fixed in every connecting rod (12) bottom, every cone (13) vertical section is the conical setting.
6. A construction engineering foundation pile assembly as defined in claim 1, wherein: two the similar side of backup pad (7) all is fixed with two rubber strips (15), every two preformed hole (16) have all been seted up in backup pad (7) middle part.
CN202223379944.3U 2022-12-16 2022-12-16 Building engineering foundation pile subassembly Active CN218843150U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223379944.3U CN218843150U (en) 2022-12-16 2022-12-16 Building engineering foundation pile subassembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223379944.3U CN218843150U (en) 2022-12-16 2022-12-16 Building engineering foundation pile subassembly

Publications (1)

Publication Number Publication Date
CN218843150U true CN218843150U (en) 2023-04-11

Family

ID=87306989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223379944.3U Active CN218843150U (en) 2022-12-16 2022-12-16 Building engineering foundation pile subassembly

Country Status (1)

Country Link
CN (1) CN218843150U (en)

Similar Documents

Publication Publication Date Title
CN109095278B (en) Building site uses abandonment cable coiling mechanism
CN210598071U (en) Lifting platform for interior decoration
CN111869500A (en) Agricultural tendril plant is with mount of circulated use
CN218843150U (en) Building engineering foundation pile subassembly
CN219196719U (en) Cantilever support template for water inlet tower construction
CN215407396U (en) Tall formwork support structure
CN216641353U (en) Scaffold for building construction
CN115613746A (en) Intelligent assembling method for green building curtain wall
CN113027106B (en) Basement lifting construction supporting auxiliary device
CN212957543U (en) Higher scaffold for building of security
CN109056787B (en) Temporary retaining wall for roadbed and hillside
CN218320633U (en) Lifting platform for engineering construction
CN221546497U (en) Building engineering strutting arrangement
CN221053292U (en) Arc dome station shaped steel bearing structure convenient to install and remove
CN215106568U (en) Stone column with strong supporting performance
CN216276331U (en) Steel construction curtain wall construction fixing device convenient to installation
CN219691175U (en) Supporting device for building engineering construction
CN220980491U (en) Circular pipe culvert installation construction adjusting device
CN216476523U (en) Detachable temporary supporting structure for construction engineering construction
CN110977228A (en) Manufacturing method of building beam column decorative curtain wall section steel keel frame
CN214995724U (en) Construction scaffold and construction bear frame
CN219241401U (en) Clear water artistic column masonry mold
CN218779903U (en) Novel support for construction device
CN215479456U (en) Lifting support for constructional engineering construction
CN220463890U (en) Outdoor pipeline welding robot walking track capable of being spliced rapidly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant